Answer of Northern Virginia Electric Cooperative, Inc. and Northeastern Rural Electric Membership Corporation Opposing the Joint Comments and Motion to Stay…
Text extracted from the eLibrary original (SHA-256 e8f05c9b27578360…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PJM Interconnection, L.L.C.Read this passage
I. ANSWER
printed heading · Topic match: Connecting load and generation
ANSWER The Joint Parties’ Motion asks that the Commission find the PJM Interconnection, L.L.C (“PJM”) Open Access Transmission Tariff (“Tariff”) to be unjust and unreasonable, stay the consolidated proceeding, and establish settlement judge procedures to develop a replacement rate.3 The Commission…Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, NOVEC and NREMC respectfully request that the Commission deny the Motion. 7 IMM, Comments, Docket Nos.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C. this 2nd day of May, 2025. //s// Jessika Dziechciowska Jessika Dziechciowska Energy Practice Analyst Washington Energy Law LLP 900 17th Street, N.W., Suite 500-A Washington, D.C. 20006 Tel: (202) 326-9308 Email: jdziechciowska@washingtonenergylaw.comRead this passage