EL25-49-000 · 2025-05-07 · American Municipal Power, Inc.
Answer of American Municipal Power, Inc. in Opposition to Motion for Stay and Settlement Judge Procedures
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Large Loads Co-Located at
Generating Facilities
)
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
v.
)
)
)
)
Docket No. EL25-20-000
(Consolidated)
PJM Interconnection, L.L.C.
)
ANSWER OF AMERICAN MUNICIPAL POWER, INC.
IN OPPOSITION TO MOTION FOR STAY AND
SETTLEMENT JUDGE PROCEDURES
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”), American Municipal Power, Inc. (“AMP”) hereby submits its answer in opposition to the Joint Parties’ April 22, 2025 motion to stay the above-captioned proceedings and establish settlement judge procedures.1 The Commission should deny the Joint Motion. The Joint Parties have not
established the basis for their proposed settlement discussions. Contrary to Joint Parties’ assertions, the record supports a finding that the Open Access Transmission Tariff (“Tariff”) of PJM Interconnection, L.L.C. (“PJM”) remains just and reasonable and not unduly discriminatory or preferential, and, thus, there is no reason to convene settlement judge proceedings to develop a replacement rate. The Commission should instead confirm the justness and reasonableness of the existing Tariff, while providing guidance
1 Joint Parties, Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures, Docket Nos. EL25-49-000, et al. (April 22, 2025) (“Joint Motion”). The Joint Parties are the Electric Power Supply Association; the PJM Power Providers Group; Calpine Corporation; Cogentrix Energy Power Management, LLC; Constellation Energy Generation, LLC (“Constellation”); and LS Power Development, LLC.
PDF page 2
2
on the application of the Tariff to co-located load arrangements, as discussed in the answer filed by the Indicated PJM Transmission Owners.2 Even if the Commission were to find that the existing PJM Tariff is unjust and unreasonable, or unduly discriminatory or preferential, the best course of action would be for the Commission to provide clear guidance on the design of a replacement rate to address any identified deficiencies in the Tariff, rather than consigning the myriad participants in this proceeding (some of which are not even PJM stakeholders) to an additional round of unwieldy negotiations on issues that have long evaded resolution in prior stakeholder discussions.
I. BACKGROUND
In its February 20, 2025 order in the above-captioned proceedings,3 the
Commission preliminarily found that the PJM Tariff “appears to be unjust and unreasonable or unduly discriminatory or preferential because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements.”4 The Commission accordingly initiated a new proceeding under section 206 of the Federal Power Act (“FPA”) (“Show Cause Proceeding”) and directed PJM and the PJM Transmission Owners: (1) to show cause as to why the PJM Tariff remains just and reasonable and not unduly discriminatory or preferential; or (2) explain what Tariff changes “would remedy the Commission’s identified
2 Indicated PJM Transmission Owners, Answer, Docket Nos. EL25-49-000, et al. (March 24, 2025) (“Indicated PJM TOs Answer”).3 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).4 Show Cause Order at P 74.
PDF page 3
3
concerns if the Commission were to determine that the Tariff has in fact become unjust and unreasonable or unduly discriminatory or preferential.”5
PJM responded to the Show Cause Order on March 24, 2025.6 In addition to the answer filed by PJM, most PJM Transmission Owners (“Indicated PJM Transmission Owners”) submitted a joint answer to the Show Cause Order.7 The Indicated PJM Transmission Owners explained that the existing PJM Tariff remains just and reasonable, and not unduly discriminatory or preferential,8 and PJM took the same position.9 Numerous parties, including non-PJM stakeholders, filed responses to the PJM and Transmission Owner filings, or to the questions raised in the Show Cause Order. AMP submitted a response supporting the Indicated PJM Transmission Owners’ answer.10 AMP’s response also emphasized the continuing reasonableness of the PJM Tariff’s treatment of load served by Behind the Meter Generation (“BTMG”) and Non- Retail BTMG, as those terms are defined in the Tariff, and said that any action taken by the Commission in this proceeding should avoid prejudice to entities that have relied on the longstanding Tariff provisions allowing for netting of Network Load served by BTMG and Non-Retail BTMG.115 Id. P 87. The Commission also consolidated the Show Cause Proceeding with Docket No. EL25-20- 000, involving a complaint filed by Constellation, and with the Commission’s technical conference addressing Large Loads Co-Located at Generating Facilities in Docket No. AD24-11-000. 6 PJM, Answer, Docket Nos. EL25-49-000, et al. (March 24, 2025) (“PJM Answer”).7 See Indicated PJM TOs Answer.8 Id. at 2.9 PJM Answer at 4, 32.10 AMP, Response, Docket Nos. EL25-49-000, et al. (April 23, 2025) (“AMP Response”).11 Id. at 3-4, 10.
PDF page 4
4
Based only on the PJM and Transmission Owner submissions, Joint Parties now ask the Commission to “conclusively find the PJM Tariff to be unjust, unreasonable and unduly discriminatory and preferential.”12 Assuming such a finding, the Joint Parties argue that the Commission “should defer to the parties in this proceeding to develop a new replacement rate through a Commission-supported settlement process.”13 Specifically, Joint Parties request that the Commission stay the Show Cause Proceeding for ninety days and “appoint a settlement facilitator and/or settlement judge to actively engage, through publicly-noticed settlement conferences, with PJM, the Transmission Owners, and any other interested intervenors in a concerted, focused, and good faith effort to resolve this proceeding within a 90 day period.”14
II. ANSWER
The Commission should deny the Joint Motion. The Joint Parties have neither supported their assertion that the PJM Tariff is unjust and unreasonable or unduly discriminatory or preferential, nor shown that settlement judge procedures would be an effective way to establish a replacement rate if the Commission were to find deficiencies in the existing Tariff.
A. The record supports a finding that the PJM Tariff remains just and reasonable.
The Joint Parties’ request for a stay and settlement judge procedures is premised on the assumption that the Commission will make a “conclusive” finding that the PJM Tariff is unjust, unreasonable and unduly discriminatory and preferential.15 The record,
12 Joint Motion at 3.13 Id. at 4.14 Id. at 2.15 Id. at 3.
PDF page 5
5
however, supports the opposite conclusion. Both PJM and the PJM Transmission Owners explained in their respective answers to the Show Cause Order that the existing PJM Tariff remains just and reasonable and not unduly discriminatory or preferential.16 Given the detailed answers filed by PJM and the Indicated PJM Transmission
Owners defending the justness and reasonableness of the Tariff, there is no validity whatsoever to the Joint Parties’ assertion that “no party responding to the Co-Location Show Cause Order has demonstrated that the PJM Tariff is just, reasonable and not unduly discriminatory or preferential, or even made a meaningful effort to do so.”17 PJM and the Indicated PJM Transmission Owners each made just such a demonstration in response to the Show Cause Order, and the Joint Parties offer no meaningful rebuttal; they simply make a number of conclusory assertions reflecting their own positions on the Tariff’s alleged lack of clarity regarding co-location agreements.18
Because the record supports a finding that the PJM Tariff remains just and
reasonable, and not unduly discriminatory or preferential, there is no reason to convene settlement judge proceedings (or any other process) to develop a replacement rate under FPA section 206 as proposed by the Joint Parties.1916 PJM Answer at 4, 32; Indicated PJM TOs Answer at 2.17 Joint Motion at 4.18 See id. at 3-4.19 The Commission should reject out of hand Joint Parties’ suggestion that even if “the Commission prefer[s] not to make such a conclusive finding . . . it should still set the matter for the settlement proceedings described herein to develop a replacement rate as if it had made such a finding.” Id. at 4 n.6. Absent a predicate finding that the existing Tariff is unjust, unreasonable and unduly discriminatory and preferential, there is no reason to “develop a replacement rate.” Further, such an approach would contravene the Joint Parties’ own logic that the requested predicate finding by the Commission would “provide a clear signal for the parties to engage in meaningful discussions towards resolving their concerns.” Id. at 5.
PDF page 6
6
B. The Commission should provide guidance on application of the
existing Tariff to co-located load arrangements.
Although the existing PJM Tariff remains just and reasonable, AMP noted in its response that additional clarification and guidance concerning the treatment of co-located load could be beneficial.20 Such guidance should clarify that load co-located behind the interconnection point of an adjacent generator in PJM must be considered Network Load (or load taking Point-to-Point Transmission Service). Further, the Commission should confirm that the existing PJM Tariff provisions addressing netting of load served by BTMG and Non-Retail BTMG remain just and reasonable, which would provide assurances to entities that have relied on the longstanding provisions allowing for netting of Network Load served by BTMG and Non-Retail BTMG to support investment in numerous small generating facilities that contribute significantly to maintaining resource adequacy in PJM. The Commission can provide this guidance based on the extensive paper record that has already been developed in these dockets.
The Commission could also provide guidance regarding possible Tariff changes that PJM could propose to clarify the treatment of co-located load arrangements, particularly given the concerns expressed by the Joint Parties about the lack of such clarity. The Indicated PJM Transmission Owners, for example, suggested a reasonable definition of “Co-located Load” that would appropriately clarify how co-located arrangements fit within the existing PJM Tariff framework.21 Thus, instead of the unwarranted settlement judge procedures proposed by the Joint Parties, the Commission
20 See, e.g., AMP Response at 5; see also Indicated PJM TOs Answer at 2.21 See Indicated PJM TOs Answer at 9. AMP noted that the definition suggested by the Indicated PJM Transmission Owners would appropriately preserve the current treatment of load served by BTMG and Non-Retail BTMG. AMP Response at 6.
PDF page 7
7
should promote regulatory certainty by confirming the justness and reasonableness of the existing Tariff, while providing guidance on the application of the existing Tariff to co- located load arrangements.
C. Even if the Commission concludes that the Tariff is unjust and
unreasonable, unduly discriminatory or preferential, it should not
convene settlement judge procedures.
Even if the Commission were to conclude that the existing PJM Tariff is unjust and unreasonable, or unduly discriminatory or preferential, it should not stay these proceedings or convene a settlement judge process as proposed by the Joint Parties. Rather, given the importance of the issues relating to co-located arrangements and the need for regulatory certainty in the PJM region on these issues, the Commission should, based on the paper record developed in these dockets, provide clear instruction on the design of a replacement rate to address any deficiencies the Commission may identify in the PJM Tariff.
Simply “defer[ring] to the parties in this proceeding to develop a new replacement rate”22 would unnecessarily delay resolution of the matter while participants engage in an additional round of discussions on issues that they have thus far been unable to resolve without clear Commission guidance. As PJM has noted, for example, the PJM guidance document on co-located load arrangements – which PJM has now rescinded23 – was only “issued by PJM as an initial attempt to provide limited guidance after over a year’s worth of unfruitful stakeholder discussions.”24 There is no reason to believe that participants would now be able to reach consensus on these issues in ninety days. While a predicate
22 Joint Motion at 4.23 PJM Answer at 33.24 Id. (emphasis added).
PDF page 8
8
finding by FERC that the existing Tariff is unjust and unreasonable would require parties to focus on a replacement rate,25 such a finding would not necessarily make it any easier to resolve the competing views on how to address any Tariff deficiency absent clear direction from the Commission.
There would also be practical challenges associated with a settlement judge process. Numerous parties that are not PJM members and that do not customarily participate in PJM-related proceedings before the Commission have intervened in the Show Cause Proceeding. These participants would presumably be entitled to participate in any settlement conferences, and would have an opportunity to comment on any proposed settlement.26 These parties may have valid and legitimate interests in the Show Cause Proceeding that are not necessarily related to particular co-located load provisions in the PJM Tariff. Indeed, the Show Cause Order is not exclusively focused on the PJM Tariff. The Commission, for example, also solicited input from interested parties on jurisdictional issues related to co-located load arrangements generally.27 Non-PJM parties interested in general Commission guidance on jurisdictional and other generic issues might have limited incentive to support a non-precedential settlement limited to the PJM Tariff, all of which would likely complicate settlement discussions. Further, as PJM observed in opposing Constellation’s similar request for settlement judge procedures in consolidated Docket No. EL25-20, addressing these important co-located load issues – including issues that may impact stakeholders beyond
25 See, e.g., Joint Motion at 5 (arguing that “[t]he guidance provided by the Commission through an unjust and unreasonable and unduly discriminatory and preferential finding will provide a clear signal for the parties to engage in meaningful discussions towards resolving their concerns.”).26 18 C.F.R. § 385.602(f).27 See Show Cause Order at PP 65-73.
PDF page 9
9
PJM – through confidential settlement discussions could raise transparency concerns.28 PJM cogently observed that “there are many parties interested in these matters and the transparency demands of these parties (including state commissions) post challenges to such significant policymaking occurring through means of a contested hearing or settlement procedures.”29
Finally, the settlement judge procedures used to resolve various Winter Storm Elliott-related disputes do not provide an appropriate model for addressing any co-located load-related Tariff deficiencies that the Commission may identify.30 If the Commission were to find the existing Tariff unjust and unreasonable, or unduly discriminatory or preferential, development of a replacement rate would need to account for numerous potentially competing considerations. In contrast, the Winter Storm Elliott complaint proceedings, while raising important questions about PJM’s Capacity Performance construct and its implementation, were ultimately “just about money,” making the matters more amenable to compromise and settlement than the issues here.3128 See PJM, Answer and Motion to Dismiss, Docket No. EL25-20-000, at 4, 15-16 (Dec. 12, 2024).29 Id. at 4.30 See Joint Motion at 5 n.9 (citing Essential Power OPP, LLC v. PJM Interconnection, L.L.C., 183 FERC ¶ 61,163, at PP 19-20 (2023)); see also id. at 7 n.18 (same).31 The same can be said of the settlement process established to resolve cost allocation issues in the Greenhat matter. See Joint Motion at 5 n.9 (citing PJM Interconnection, L.L.C., 167 FERC ¶ 61,209, at PP 28-29 (2019)).
PDF page 10
10
III. CONCLUSION
WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully asks the Commission to deny the Joint Motion. Respectfully submitted,
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com
/s/ Gerit F. Hull
Gerit F. Hull
Deputy General Counsel for
Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
ghull@amppartners.org
May 7, 2025
PDF page 11
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings.
Dated at Washington, D.C., this 7th day of May, 2025.
/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com