Answer of American Municipal Power, Inc. in Opposition to Motion for Stay and Settlement Judge Procedures
Text extracted from the eLibrary original (SHA-256 f432bd6c043e903a…). Download the original from the official source.
Contents · 6 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage Filed comments: Connecting load and generation
I. BACKGROUND
printed heading
AMP submitted a response supporting the Indicated PJM Transmission Owners’ answer.10 AMP’s response also emphasized the continuing reasonableness of the PJM Tariff’s treatment of load served by Behind the Meter Generation (“BTMG”) and Non- Retail BTMG, as those terms are defined in the Tariff, and…Read this passage
II. ANSWER
printed heading
ANSWER The Commission should deny the Joint Motion.Read this passage
A. The record supports a finding that the PJM Tariff remains just and
printed heading
The record supports a finding that the PJM Tariff remains just and reasonable.Read this passage
B. The Commission should provide guidance on application of the
printed heading · Topic match: Connecting load and generation
Although the existing PJM Tariff remains just and reasonable, AMP noted in its response that additional clarification and guidance concerning the treatment of co-located load could be beneficial.20 Such guidance should clarify that load co-located behind the interconnection point of an adjacent…Read this passage Filed comments: Connecting load and generation
C. Even if the Commission concludes that the Tariff is unjust and
printed heading · Topic match: Connecting load and generation
As PJM has noted, for example, the PJM guidance document on co-located load arrangements – which PJM has now rescinded23 – was only “issued by PJM as an initial attempt to provide limited guidance after over a year’s worth of unfruitful stakeholder discussions.”24 There is no reason to believe that…Read this passage Filed comments: Connecting load and generation
III. CONCLUSION
printed heading
CONCLUSION WHEREFORE, for the foregoing reasons, American Municipal Power, Inc. respectfully asks the Commission to deny the Joint Motion.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 7th day of May, 2025. /s/ John McCaffrey John McCaffrey Stinson LLP 1775 Pennsylvania Avenue NW Suite 800 Washington, DC 20006 (202) 728-3026 john.mccaffrey@stinson.comRead this passage