Motion for Leave to Answer and Answer of Vistra Corp. to the 04/23/2025 comments filed by North American Electric Reliability Corporation, et al
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Docket Nos. EL25-49-000
EL25-49-001
PDF page 2
-2-
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities,
Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
AD24-11-000
EL25-20-000
(Consolidated)
MOTION FOR LEAVE TO ANSWER AND ANSWER OF VISTRA CORP.
Pursuant to Rules 212 and 2131 of the Federal Energy Regulatory Commission’s (“Commission”) Rules of Practice and Procedure, Vistra Corp. (“Vistra”) hereby moves to answer and answers the comments filed on April 23, 2025, by the North American Electric Reliability Corporate (“NERC”), Americans for a Clean Energy Grid (“ACEG”), Organization of PJM States (“OPSI”), and Public Interest Organizations (“PIOs”) in response to the Commission’s February
1
18 C.F.R. §§ 385.212, 385.213 (2024).
PDF page 3
-3-
20, 2025 Order (“Show Cause Order”)2 and PJM Interconnection, L.L.C.’s (“PJM”) answer (“PJM Answer”).3
I. MOTION FOR LEAVE TO ANSWER
Although the Commission’s procedural rules generally do not allow answers to answers,
the Commission may permit them for good cause.4 The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the Commission in its decision-making.5 Vistra respectfully requests that the Commission accept this answer to clarify certain issues and assist the Commission with its decision-making.
II. ANSWER
The record in this proceeding provides strong support for the Commission to set a
replacement rate to require PJM to accommodate behind-the-meter co-located load. There is general agreement that there is a need for PJM to accommodate new, large loads to support our national security and economic growth.6 There is also a general consensus that PJM’s current
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).3 Answer of PJM Interconnection, L.L.C., Docket No. EL25-49 (filed Mar. 24, 2025) (“PJM Answer”).4 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or a request for rehearing, unless otherwise ordered by the decisional authority.”).5 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that “provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC ¶ 61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s decision- making process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised, and will ensure a complete record”).6 See, e.g., Comments of Chevron U.S.A. Inc, Docket No. EL25-49, at 2-4 (filed April 23, 2025); Answer of Constellation Energy Generation, LLC, Docket No. EL25-49, at 3 (filed April 23, 2025) (“Constellation Comments”); Comments of Advanced Energy United, Docket No. EL25-49, at 2 (filed April 23, 2025); Comments of the Data Center Coalition, Docket No. EL25-49, at 1-2 (filed April 23, 2025); Comments of the Edison Electric Institute, Docket No. EL25-49, at 3-4 (filed April 23, 2025); Comments of the Business Council for Sustainable Energy, Docket No. EL25-49, at 2 (filed April 23, 2025); Comments of Electricity Consumers Resource Council, Docket No. EL25- 49, at 10.
PDF page 4
-4-
tariff does not sufficiently accommodate the co-location of large loads behind a generator’s meter.7 The disagreement, as distilled by the filed comments, appears to be over whether that lack of accommodation of behind-the-meter co-location is lawful. Some commenters agree with PJM that the tariff remains just and reasonable even though it does not accommodate behind-the-meter co- located load.8 However, consistent with the Show Cause Order and the Susquehanna ISA
Rehearing Order,9 many commenters recognize that the existing tariff is not just and reasonable and/or that the tariff is being implemented in an unduly discriminatory manner.10
As discussed further below, there is no valid basis to discriminate against behind-the-meter co-located load. Moreover, none of the commenters that support discriminating against behind- the-meter load provide any analytic support to justify that position. Their comments rely on vague and unsupported assertions that behind-the-meter co-located load raises reliability and resource
7 See, e.g., Comments of the Independent Market Monitor for PJM, Docket No. EL25-49, at 2 (filed April 23, 2025) (“The Market Monitor agrees that clear rules governing all aspects of the addition of large loads are required.”); Constellation Comments at 3 (“The Commission was right that the existing PJM Tariff lacks requisite clarity, and this has paralyzed co-location efforts and service to data centers.”); Comments of Northern Virginia Electric Cooperative, Docket No. EL25-49, at 8 (filed April 23, 2025) (“NOVEC Comments”); Comments of Indicated PJM Transmission Owners, Docket No. EL2-49, at 4 (filed April 23, 2025) (“Indicated PJM TOs Comments”).8 See NOVEC Comments at 8; Indicated PJM TOs Comments at 4.9 Show Cause Order at P 3 (directing PJM to explain why its tariff remains just and reasonable without provisions addressing behind-the-meter co-location or to explain what changes to the tariff would remedy the absence of such provisions); PJM Interconnection, L.L.C., 191 FERC ¶ 61,025, at P 60 (2025) (“Susquehanna ISA Rehearing Order”) (“[W]e clarify that the Rejection Order does not prevent entities from filing non-conforming interconnection agreements to address matters related to a generator serving co-located load, or prejudge any such future filing.”).10 See, e.g., Constellation Comments at 3; Comments of BrightNight Power Marketing, LLC, Docket No. EL25-49, at 3; Comments of Electric Power Supply Association, Docket No. EL25-49, at 2-3 (filed April 23, 2025); Comments of Solar Energy Industries Association, Docket No. EL25-49, at 5 (filed April 23, 2025); Comments of Talen Energy Corporation, Docket No. EL25-49, at 12 (filed April 23, 2025); see also Comments of Engie North America, Inc., Docket No. EL25-49, at 4-5 (filed April 23, 2025) (explaining that the “current tools in PJM’s existing tariff” are inadequate); Comments of PJM Industrial Customer Coalition, Docket No. EL25-49, at 7 (filed April 23, 2025) (“Indicated TO’s proposed approach is also unduly discriminatory.”).
PDF page 5
-5-
adequacy concerns.11 To contrast, Vistra’s initial comments included an affidavit by Dr. Roy Shanker, which provided a robust and analytically sound assessment of the various configurations in which new large loads can be added to the system.12 Dr. Shanker found that Options 4 and 5 are “dominant” configurations, in that they provide benefits to all parties, including other market participants, when compared to other potential load configurations, such as Option 1.13 In its initial comments, Vistra suggested a specific replacement rate to ensure that the tariff accommodates Option 4 and 5 configurations in a just and reasonable and not unduly discriminatory manner.14 That proposal would ensure that co-location configurations that fit within Options 4 and 5 pay their fair share and that other customers are not harmed. The Commission can and should adopt that replacement rate quickly to remedy undue discrimination and ensure that PJM accommodates Options 4 and 5 in a just and reasonable and not unduly discriminatory manner. Vistra also continues to believe that Options 6-8 should be further explored to provide customers with flexibility to engage in other types of beneficial transactions. However, each of these configurations also appears likely to require more involved tariff modifications than those needed for Options 4 and 5. The Commission should direct PJM to engage with stakeholders to implement further reforms to facilitate Options 6-8. Beyond the general issues discussed above, this Answer addresses certain specific issues raised in the record, including the reliability concerns associated with the addition of new large
11 See, e.g., NOVEC Comments at 11 (“If co-location arrangements like the configuration advanced by the Constellation complaint are permitted, they will present reliability challenges.”); Comments of Buckeye Power, Inc., Docket No. EL25-49, at 2-3 (filed April 23, 2025) (arguing that front-of-the-meter co-located loads are “a better alternative for reliability and resource adequacy[.]”).12 Comments of Vistra Corp., Docket No. EL25-49, Attach. A, Affidavit of Dr. Roy J. Shanker, PhD on Behalf of Vistra Corp. (filed April 23, 2025) (“Dr. Shanker Aff.”). 13 Id. PP 52-70.14 See Comments of Vistra Corp., Docket No. EL25-49, at 22-31 (filed April 23, 2025) (“Vistra Initial Comments”).
PDF page 6
-6-
loads, the transparency of the necessary study process, and improvements to PJM’s load forecasting practices. As discussed below, the reliability concerns raised in the docket relate to all new large loads, not just those that are co-located with a generator. Therefore, such concerns do not justify discrimination against behind-the-meter co-located loads. Concerns about the transparency of the necessary study process are reasonable, but can be addressed in a straightforward manner, by posting necessary study results online in a manner similar to other interconnection study results (and with appropriate measures to protect confidential or sensitive information). These concerns do not justify discrimination against behind-the-meter co-located loads, nor do they require an overhaul of the necessary study process itself. Finally, Vistra agrees with the suggestions made in the record to improve PJM’s load forecasting process. In particular, ACEG’s proposal to require new large loads to make substantial financial commitments before they can be included in PJM’s load forecast would help prevent the inclusion of duplicative load interconnection requests in the load forecast. Development of such a reform would be a natural fit within a separate, broader proceeding focused on standardizing the transmission-level load interconnection process, which Vistra also suggested in its initial comments.
A. The Reliability Concerns Raised in Comments Apply to All New Large Loads,
Regardless of Whether They Are Co-Located
NERC’s comments provided insight into its recent “initiatives addressing large loads.”15 To provide further context regarding these reliability concerns, attached to this Answer is an affidavit by Steven Herling, PJM’s former VP of Planning, an electrical engineer with 30 years of experience with reliability analyses in PJM.16 As Mr. Herling explains, the reliability concerns
15 Comments of the North American Electric Reliability Corporation, Docket No. EL25-49, at 2-10 (filed April 23, 2025) (“NERC Comments”).16 Affidavit of Steven R. Herling on Behalf of Vistra Corp., Attach. A (“Herling Aff.”).
PDF page 7
-7-
that NERC flagged relate to the voltage sensitivity of new large loads.17 This voltage sensitivity, however, “is not a co-location issue,” because it is “equally, or perhaps even more appliable to front-of-the-meter interconnections of large data centers, such as contemplated in PJM’s Option 1.”18 In fact, the particular incident that NERC discussed in Attachment 2 does not appear to have involved any co-located data centers. There is no reason to believe that a behind-the-meter co- located data center would have worsened this event; in fact, co-location may actually make such events less likely because “co-located generators are, themselves, a voltage source with automatic voltage regulators, reducing the likelihood that grid disturbances will exceed the threshold associated with voltage-sensitive data center loads.”19 Nonetheless, NERC concluded that the event “did not cause significant operating issues with the grid.”20
Minimizing any reliability concerns associated with the co-location of large loads would incorporate the same processes and studies utilized to address all other reliability concerns. As Mr. Herling explains, “the modeling elements required to perform power flow, short circuit, and dynamic analysis for the various co-location options proposed by PJM are all knowable and any operational actions included in PJM’s proposed options are readily modeled.”21 The necessary study process includes all of the same models and analytic tools to evaluate contingencies that are used in RTEP studies.22 The reliability impacts of new large loads, either alone or in combination with a generator, are knowable and can be addressed by proper coordination between PJM, the
17 Id. PP 15, 21. 18 Id. P 21.19 Id.20 NERC Comments, Attach. B, at 8.21 Herling Aff. at P 19.22 Id. P 18.
PDF page 8
-8-
applicable transmission owner, and the co-located load customer. This type of coordination is not novel in managing reliability impacts of new load of all types.23 NERC recommends that PJM should ensure the availability of data and information to support reliability analysis, coordination, load balancing, and accurate modeling for co-located large loads. These recommendations are sensible, but there is nothing groundbreaking or new about them.24 Sufficient data and information sharing has always been necessary to study the reliability of any new addition on the grid. Any new requirements must apply to all new large loads, not just those that are co-located with a generator.
The existence of reliability concerns related to new, large loads in general does not justify prohibiting or delaying the addition of behind-the-meter load. In fact, as NERC explained: Proximity between large loads and power generation sources can
reduce energy loss while improving transmission reliability. This
co-location fosters improved coordination, leading to better load
management and reduced strain on the BPS . . . NERC noted that
nuclear power is a particularly advantageous resource for co-located
large loads due to its inherent high-capacity factor, load-carrying
ability, and steady performance even in extreme weather
conditions.25
While transmission owners argue against behind-the-meter co-location, despite its reliability benefits compared to Option 1 configurations, transmission owners are moving full steam ahead interconnecting new front-of-the-meter large loads. For example, Exelon utilities recently announced on an earnings call that their load interconnection queue includes 16 GW of
23 See id. P 22.24 Id.25 NERC Comments at 6.
PDF page 9
-9-
new large loads that have already paid deposits.26 Exelon expects to connect 1.6 GW of that load by 2028, 5.3 GW by 2030, and 12 GW by 2034.27 Exelon anticipates that these front-of-the-meter load interconnections will trigger up to $15 billion in transmission upgrades,28 which will go directly into Exelon’s rate base.29 Given that front-of-the-meter large loads raise similar reliability concerns as behind-the-meter co-located loads, one can infer that these reliability concerns are not insurmountable. It would be unduly discriminatory to permit front-of-the-meter arrangements and prohibit or delay co-location arrangements based on alleged reliability concerns.
Mr. Herling also provided additional detail about the necessary study process, which illustrates that it sufficiently assesses the reliability of behind-the-meter co-located loads, using the same models and analytic tools as RTEP studies.30 Some commenters, however, raised questions regarding the transparency of the necessary study process for interconnecting new large loads.31 While these concerns are reasonable, there is a straightforward solution. PJM posts other interconnection study results on a publicly available website.32 PJM could post necessary study results there as well, subject to appropriate confidentiality protections for Critical Energy/Electric Infrastructure Information and commercially sensitive information, like the identity of the co-
26 Exelon data center pipeline doubles to 36 GW since year-end, Utility Dive (May 2, 2025), https://www.utilitydive.com/news/exelon-data-center-pipeline-pjm-maryland- earnings/746971/?utm_source=Sailthru&utm_medium=email&utm_campaign=Issue:%202025-05- 02%20Utility%20Dive%20Newsletter%20%5Bissue:72830%5D&utm_term=Utility%20Dive. 27 See id.28 Id.29 See Vistra Initial Comments at 15, 37.30 Herling Aff. at PP 10-11, 18-19.31 See Comments of the Organization of PJM States, Inc., Docket No. EL25-49, at 3 (filed April 23, 2025) (“OPSI has emphasized that PJM’s current process of using interconnection modifications to accommodate behind the meter co-located load arrangements lacks transparency and public oversight noting these modifications are privately negotiated and under non-disclosure agreements.”); Comments of Public Interest Organizations, Docket No. EL25- 49, at 11 (filed April 23, 2025) (“Moreover, the Necessary Study Process occurs entirely behind closed doors.”).32 See PJM, Cycle Service Request Status, https://www.pjm.com/planning/m/cycle-service-request-status.
PDF page 10
-10-
located load customer. These concerns do not require an overhaul of the necessary study process, nor do they justify discrimination against the addition of behind-the-meter co-located load. Rather, they can be quickly adopted through surgical tariff revisions similar to those Vistra identified in its initial comments.
B. Generation Asset Owners Should Not Be Prohibited from Maximizing the Use of
Their Assets
NOVEC argued that nuclear power plants should not be permitted to serve new large loads
because they were “largely constructed by or for vertically integrated utilities who funded the projects from cost-of-service rates collected by captive retail customers.”33 NOVEC states that it “agrees in principle that owners of generation assets should be able to seek to maximize the beneficial ownership of those assets,” but asserts that the Commission should reject the co-location of large loads at these generating facilities “because the Federal Power Act is a consumer- protection statute.”34
Vistra agrees with the principle that owners of generation assets should be able to seek to maximize the beneficial ownership of those assets. PJM may not prohibit sellers from seeking beneficial bilateral arrangements in an effort to commandeer the sellers’ resources for the PJM capacity market.35 Attempts to do so may even rise to a regulatory taking.36 Moreover, NOVEC’s
33 NOVEC Comments at 15.34 Id. at 16.35 See PJM Interconnection, L.L.C., 178 FERC ¶ 61,121, at P 97 (2022) (“If a seller deems PJM’s capacity market rules undesirable, it can elect to pursue selling its capacity through other avenues, including via bilateral contracts within PJM, external sales outside of PJM, and other arrangements.”).36 See ISO New England, Inc., 135 FERC ¶ 61,029, at P 255 (2011) (rejecting regulatory takings arguments in large part because “resources are not compelled to participate in the [ISO-NE capacity market.]”); see also Palazzolo v. Rhode Island, 533 U.S. 606, 617–18 (2001) (listing factors relevant to determining whether there is a taking, including “the regulation’s economic effect on the [property owner], the extent to which the regulation interferes with reasonable investment-backed expectations, and the character of the government action.”); Hodel v. Irving, 481 U.S. 704, 716
PDF page 11
-11-
argument rests on a fundamental misunderstanding of the impacts of co-location on other consumers. As Dr. Roy Shanker previously explained, when compared to an appropriate comparison case, Option 4 and 5 configurations provide significant benefits to other market participants, both in terms of planning reliability and energy and capacity market prices.37 Specifically, Dr. Shanker explained that in an Option 4 case, Network Integration Transmission Service (“NITS”) costs for other ratepayers remain the same where the parties to the co-location arrangement pay for all necessary upgrades; to contrast, in an Option 1 configuration, NITS costs for other ratepayers could increase because the costs of transmission facilities would be socialized to the entire rate base.38 Dr. Shanker explained that LMPs would be the same in both an Option 4 and Option 1 case.39 Dr. Shanker also explained that while capacity prices increase in both Option 4 and Option 1 cases, capacity prices increase more in the Option 1 case than the Option 4 case.40 NOVEC has provided no analytic basis for its conclusions that co-location is unfair to existing ratepayers. NOVEC’s vague and analytically flawed assertions about consumer protection do not justify prohibiting owners of an asset from seeking the most beneficial use of those assets. Additionally, as Constellation explained, the premise underlying NOVEC’s argument ignores that fact that these “generating resources were sold by most utilities to merchant owners over 20 years ago,” at which point merchant owners assumed all risks associated with the
(1987) (federal regulation constituted a taking where it abrogated essential property rights, even though the property owners retained other rights, because “the right to pass on property . . . has been part of the Anglo-American legal system since feudal times.”); Yancey v. United States, 915 F.2d 1534, 1541 (Fed. Cir. 1990) (noting that regulatory taking precedent does not create “an automatic numerical barrier preventing compensation, as a matter of law, in cases involving a smaller percentage diminution in value.”).
37 Dr. Shanker Aff. at PP 52-70.38 Id. P 58.39 Id. P 61.40 Id. P 62.
PDF page 12
-12-
generating facility.41 There are many merchant generators that were once built by a vertically integrated utility. The merchant owners of these plants have always been able to choose how to operate their assets, whether that involves capacity market participation or not. Nuclear plants are no different. Moreover, even under previous the rate-base model, “consumers paid for service, not for assets.”42 There is no reason that rates paid to a vertically integrated utility over 20 years ago should prevent a private merchant generator from seeking beneficial commercial arrangements for facilities that it now owns. Nor would doing so even benefit ratepayers, as explained above.
C. Reforms to Load Forecasting Are Warranted, But Should Occur Through a
Standardized Load Interconnection Process
ACEG proposed improvements to PJM’s load forecasting process. Specifically, ACEG proposed to require load-serving entities and electric distribution companies that request load adjustments demonstrate that any new large loads interconnections are backed by stringent financial commitments. ACEG asserts that the additional financial commitments would not impose a new FERC-jurisdictional rate. Rather, ACEG’s proposal contemplates that these reforms occurring primarily through retail tariffs, with “[m]inimal changes to BPM Manual 19.”43 Vistra agrees that requiring such financial commitments would help improve the accuracy of PJM’s load forecasting by disincentivizing load customers from submitting multiple duplicative interconnection requests. However, while Vistra agrees with the overall proposal, Vistra submits that these reforms would constitute a FERC-jurisdictional rate—not a retail rate—and, under the Commission’s rule of reason, should be placed in the PJM tariff rather than a business practice
41 Constellation Comments at 107.42 Id. at 108. 43 Comments of Americans for a Clean Energy Grid, Docket No. EL25-49, at 8 (filed April 23, 2025).
PDF page 13
-13-
manual.44 As Vistra explained in its initial comments, load interconnection is within the Commission’s jurisdiction over the interstate transmission system.45 Load forecasting and the requirement to provide additional financial security in the transmission-level load interconnection process similarly fall under the Commission’s transmission jurisdiction46 and is a matter “readily susceptible of specification” that significantly affects the rates for service.47 Vistra encourages the Commission to explore this issue in a separate proceeding focused on standardized transmission- level load interconnection.
III. Conclusion
Responses to PJM’s Answer to the Show Cause Order provide a strong record for the
Commission to act quickly to implement a replacement rate that ensures PJM accommodates behind-the-meter co-located load in a just and reasonable and not unduly discriminatory manner. There is no valid basis to discriminate against behind-the-meter co-located load given that the reliability issues of new large loads apply regardless of the specific configuration in which they are added to the system. Based on Dr. Shanker’s analysis of behind-the-meter co-located loads against a proper comparison case,48 and Mr. Herling’s conclusions that the relevant reliability concerns are equally or even more applicable to non-co-located large loads,49 it is clear that co-
44 See Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 (2018) (“[P]rovisions that ‘significantly affect rates, terms, and conditions’ of service, are readily susceptible of specification, and are not generally understood in a contractual agreement must be included in a tariff, while items better classified as implementation details may be included only in the business practice manual.”).45 See Vistra Initial Comments at 38.46 Vistra asserts that the Commission has a second basis for exercising jurisdiction over load forecasting because, to the extent such forecasts are used in PJM’s markets, load forecasting is a practice directly affecting rates for the sale of electric energy.47 See supra note 44.48 Shanker Aff. at PP 52-70.49 Herling Aff. at P 21.
PDF page 14
-14-
location is part of the solution for reliably serving new loads without adversely impacting current customers. Furthermore, concerns about the transparency of the necessary study process can be addressed through narrow reforms to ensure that the results of such studies are posted in a manner consistent with other interconnection studies. None of these issues prevent the Commission from expeditiously implementing a replacement rate to remedy undue discrimination and ensure PJM facilitates Options 4 and 5 configurations. The record also indicates that the Commission should
(a) direct PJM to initiate a stakeholder process to determine what tariff revisions would be needed to accommodate Options 6-8, and (b) open a proceeding to explore standardized transmission- level load interconnection procedures, which could include reforms to improve load forecasting through financial commitments.
Respectfully submitted,
/s/ J. Arnold Quinn
J. Arnold Quinn
SVP of Regulatory Policy
Andrew Weinstein
Vice President, FERC Market Policy
Vistra Corp.
325 7th Street NW
Suite 520
Washington, DC 20004
arnie.quinn@vistracorp.com
andrew.weinstein@vistracorp.com
Nicholas M. Gladd
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(617) 598-7871
ngladd@wsgr.com
sgreenberg@wsgr.com
Counsel for Vistra Corp.
Dated: May 8, 2025
PDF page 15
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings.
Dated: May 8, 2025
Washington, D.C.
/s/ Sarah Greenberg
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K Street NW
Fifth Floor
Washington, DC 20006
(202) 431-5231
sgreenberg@wsgr.com
PDF page 16
Attachment A
Affidavit of Steven R. Herling
PDF page 17
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC.
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
AFFIDAVIT OF STEVEN R. HERLING
I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT
1. My name is Steven R. Herling. I am currently President of Herling Power Grid Consulting, Inc. (“HPGC”), which provides consulting services related to planning, operational, and regulatory issues facing the electric power industry. My business address is 513 William Salesbury Drive, Downingtown, PA 19335. Through HPGC, I have served as a subcontractor to other consulting firms, such as The Brattle Group and Charles River Associates. I have advised clients on generator and merchant transmission interconnection issues as well as a range of PJM Interconnection, L.L.C. (“PJM”) Regional Transmission Expansion Plan (“RTEP”) process issues.
2. In July 2020, I retired from PJM, where I had been employed since May 1990. At PJM, I held a number of positions in the Operations and Planning Divisions and was promoted to Vice President of Planning in May 2004. While at PJM, I contributed to or led initiatives that resulted in a wide range of milestone achievements in PJM’s evolution and growth as a regional transmission organization (“RTO”), including the creation of the RTEP process, the development of procedures
PDF page 18
2
and standard terms and conditions for generation and merchant transmission interconnections, the development of the competitive transmission process, and the reliability and resource adequacy aspects of successive integrations of additional control areas that more than doubled the size of the PJM market area. In addition to my work for PJM, I contributed to a wide range of activities for the North American Electric Reliability Corporation (“NERC”) and served on various regional industry working groups and committees addressing reliability and planning matters.
3. Prior to joining PJM, I worked for the General Public Utilities Service Corporation (“GPU”) for three years in systems operations, where I was responsible for dispatcher training and certification, operations and planning activities, and energy management system and operational support tools. Prior to GPU, I worked for the American Electric Power Service Corporation (“AEP”) for eight years in bulk transmission planning. In that position, I performed a range of power system analyses related to the AEP 765 kV transmission system, generator and circuit breaker dynamic modeling, and the mechanical behavior of turbine-generator shaft systems.
4. I hold a Bachelor of Science in Electric Power Engineering and a Master of Engineering in Electric Power Engineering, both from Rensselaer Polytechnic Institute. Please refer to my resume attached as Exhibit B.
5. I have testified on a number of occasions in proceedings before the Federal Energy Regulatory Commission (“FERC”), as well as various state commissions, and legislative task forces, on matters relating to system planning and reliability issues. I have also testified in transmission line Certificate of Public Convenience and Necessity (“CPCN”) proceedings in Pennsylvania, Maryland, West Virginia, Virginia, and New Jersey, and I have testified in a transfer of ownership case for a public utility in Kentucky.
PDF page 19
3
6. I have been asked by Vistra Corp. (“Vistra”) to provide an affidavit that discusses the concerns raised by PJM Interconnection, L.L.C. (“PJM”) and the North American Electric Reliability Organization (“NERC”) with respect to the reliability impacts of the interconnection of large co- located loads to the grid and how those concerns can reasonably be managed. This affidavit and the opinions expressed herein are based on my experience in the field of electric power system planning, operation, and regulation and my knowledge of the electric power industry. My opinions and analyses are subject to change if additional information becomes available.
II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS
7. There are a number of potential options for the interconnection of co-location projects to the grid, involving different physical configurations and different means by which the co-located load will interact with the grid. In its March 24, 2025 Answer in the above-captioned docket, PJM presents eight such options. PJM Option 1 is not, in fact, a co-location configuration, but contemplates load connected to the grid at a separate point of interconnection from any generator.
8. The remaining PJM options all involve load co-located with generation at the same point of interconnection. Two of the options include relaying that will prevent delivery of energy from the grid following the loss of the co-located generating resource. For example, Option 4 relies on a direct connection to co-located generation facility for the delivery of energy without reliance on grid transmission facilities. Some of the PJM options also contemplate the ability of the co-located load to take interruptible service or participate as a Demand Response resource, thereby serving as a tool for operators to manage operational emergencies.
PDF page 20
4
9. The design elements of these configurations and the associated operational/market behaviors are all well understood and able to be modeled in planning and operations analyses.
III. RELIABILITY ISSUES RAISED BY PJM AND NERC
10. In discussing their proposed options for co-location, PJM describes the various studies that may be performed to ensure compliance with applicable reliability criteria.1 As relevant here, PJM explained that it performs a Necessary Study when a generator is involved and the co-location project involves a modification to the generator’s interconnection. The Necessary Study is also reviewed by the applicable transmission owner.
11. PJM goes on to describe the analyses that comprise the Necessary Study as including generation deliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems review, baseline stability, and, if applicable, a nuclear plant interface requirements voltage analysis.2
12. PJM also explains the other studies used to integrate new large loads in other configurations include 1) a “Transmission Owner retail load integration study,” performed by the local transmission owner to identify local upgrades needed to reliably accommodate the load based on the planning criteria of that local transmission owner, 2) a “PJM Do No Harm study,” to evaluate whether upgrades identified by the local transmission owner will adversely impact the reliability of the Transmission System, and 3) Regional Transmission Expansion Planning (RTEP) studies when an aggregation of large load additions could possibly trigger regional transmission needs.3
13. In their response to FERC question D. iii., PJM states “In response to this question’s specific prompt about dynamic response models, today, PJM conducts dynamic studies for co-located load projects. All applicable North American Reliability Corporation (“NERC”), PJM, and Transmission
1 PJM Answer at 7.2 Id. at 49.3 Id. at 6-8.
PDF page 21
5
Owner-specific contingencies and criteria are evaluated. For such dynamic studies, co-located loads are modeled in detail within both power flow and dynamic models.”4
14. PJM raises one concern with respect to co-location projects interconnected through its Option 4 or Option 5. PJM Options 4 and 5 include relaying that will prevent delivery of energy from the grid following the loss of the co-located generating resource. PJM raises the concern that “it is possible to develop a special protection scheme that could disconnect the load if the local generator trips. This scheme could be developed with sufficient redundancy to help better ensure activation. However, it is always possible that the protection system could misoperate, be disabled, or degrade.”5
15. NERC raises reliability concerns related to the voltage sensitivity of co-location loads and the potential for disconnection from the grid and transfer to backup generation.6 As an example, NERC cites the loss of approximately 1,500 MW of load following a 230 kV transmission line fault when the line locked out after three auto-reclose attempts.7 The loss occurred when voltage-sensitive data center load at 60 different load points across 25 different substations was automatically disconnected from the grid.8 NERC refers to a Commission comment in its Show Cause Order, suggesting that system operators may lack sufficient information and transient stability models to perform reliability analysis on co-located large loads.9
16. Based on these concerns, NERC recommends “that the Commission and industry continue examining specific reliability implications of co-located large loads. NERC also recommends that the Commission and industry consider requirements for data or information sharing, to support system
4 Id. at 53.5 Id. at 44.6 NERC Comments at 3-10.7 Id. at 8.8 Id., Attach. A, at 4.9 NERC Comments at 7.
PDF page 22
6
operators in performing reliability analyses as well as coordination, load balancing, and accurate modeling for co-located large loads.”10
IV. OBSERVATIONS AND CONCLUSIONS
17. PJM and the PJM transmission owners currently perform a wide range of analyses to establish compliance of the grid with all NERC, PJM, and transmission owner planning criteria. These studies span the entire range of power flow, short circuit, and dynamics analyses and have been performed, collaboratively, for decades, since the inception of PJM as an Independent System Operator.
18. Through the Necessary Study process described above, PJM has the ability to evaluate all aspects of a co-location project to ensure that it is designed such that the grid remains reliable, consistent with all applicable criteria. The Necessary Study relies on the same transmission system, generation, and load models that PJM uses throughout all aspects of the RTEP process. It utilizes all of the same analytical tools and evaluates all of the same contingency sets to test compliance against all of the same reliability criteria.
19. The modeling elements required to perform power flow, short circuit, and dynamics analyses for the various co-location options, proposed by PJM, are all knowable and any operational actions included in PJM’s proposed options are readily modeled. PJM and the PJM transmission owners have the ability to collaborate to perform all of the analyses required to ensure the continued reliability of the PJM grid.
20. With respect to PJM’s concerns about potential failure of a special protective system, it is worth noting that PJM plans, in its RTEP analyses, for N-1 conditions followed by a single protection system failure, such as a stuck breaker. In this instance, a stuck breaker becomes a second contingency. Based on my experience with the RTEP, the solution to stuck breaker criteria violations
10 Id. at 3.
PDF page 23
7
is to add a redundant series breaker, making the failure of both breakers following an N-1 event a third contingency. PJM does not plan for or require upgrades for such third contingencies, nor would it be reasonable to do so. Assuming that the protection system associated with an Option 4 or 5 co- location project is fully redundant, it is unreasonable to treat the failure of both primary and secondary relay system facilities following the loss of a generator as anything other than a third contingency.
21. It is also important to note that the voltage-sensitivity issue underlying the 1,500 MW load loss event cited by NERC is not a co-location issue. Nothing in the NERC Comments or the attached materials suggests that any of the data centers involved in the event were co-located with generating resources. The voltage sensitivity issue at the core of the discussion is equally, or perhaps even more applicable to front-of-meter interconnections of large data centers, such as contemplated in PJM’s Option 1. Co-located generators are, themselves, a voltage source with automatic voltage regulators, reducing the likelihood that grid disturbances will exceed the threshold associated with voltage- sensitive data center loads. The loss occurred because the loads transferred from the grid to their own uninterruptible power supply (“UPS”) systems in order to protect data center cooling equipment, not because of any interaction with co-located generation.11
22. NERC’s recommendation to continue studying these issues and engage in information sharing is sensible. Coordination of study efforts between PJM and the PJM transmission owners has always been a foundational element of the PJM planning process and must continue for the grid to remain reliable and for customer needs to be met in a timely, fair and non-discriminatory manner. Consistent with NERC’s stated concerns, PJM should have access to the data and information required to support operational actions and the performance of reliability analyses. PJM as the planner and
11 NERC Comments, Attach. B, at 4.
PDF page 24
8
operator of the grid requires detailed data for large voltage-sensitive loads, whether they are co- located with generation sources or interconnected to the grid separate from any generator.
23. This concludes my affidavit.
PDF page 25
9
VERIFICATION
I declare under penalty of perjury that the foregoing Affidavit is true and correct to the best of my knowledge, information, and belief.
Executed May 8, 2025
________________________
Steve Herling
Settin
PDF page 26
Attachment B
Resume of Steven R. Herling
PDF page 27
Page 1
Steven R. Herling
PROFESSIONAL EXPERIENCE
Herling Power Grid Consulting, Inc. (2020 – Present)
President
Provide expertise to support strategic decision making related to the development of planning processes and the integration with electric power grid market structures.
Provide expertise to support strategic decision making related to the integration of renewable technologies onto the electric power grid.
Provide expert witness services in transmission line siting proceedings.
Yoh Staffing Services (2020 – 2021)
Executive Consultant (2020 – 2021)
Provide expert witness services in transmission line siting proceedings.
PJM Interconnection, LLC (1990 – 2020)
Executive Consultant, Planning (2019 – 2020)
Provide expert witness services in support of the Transource 500/230 kV IEC Project. Provide leadership to the development of planning processes related to aging infrastructure and grid resilience.
Provide leadership to the development of planning processes related to the integration of off-shore wind into the grid.
Support the transition of responsibility to the new Vice President, Planning.
Vice President, Planning (2004 – 2019)
The Vice President, Planning reports directly to the CEO.
Responsible for the oversight of System Planning division of PJM which includes Transmission Planning, Interregional Planning, Interconnection Analysis, Interconnection Projects, Infrastructure Coordination and Resources Adequacy Planning.
Position Summary:
Develop long range strategies to achieve PJM’s Planning business objectives.
Provide overarching methodology for the monitoring and analysis of Planning studies as well as the introduction of improved and emerging technologies in the Planning space.
Support the leadership of the Planning organization in large and complex engineering assignments to support present and future needs of the PJM system.
PDF page 28
Page 2
Support the activities of PJM and industry committee or task forces involved with issues related to planning and engineering.
Prepare board reports, presentations as well as expert testimony regarding Planning and Interconnection recommendations.
In conjunction with subject matter experts, coordinate delivery of all communication regarding the regional transmission expansion and enhancement plans.
Ensure the Planning division and staff can support the requests of PJM as well as external entities regarding Interconnection queue activities and feasibility studies.
Ensure relationships with the PJM community as well as other regulatory entities are productive and in alignment with the PJM strategic plan.
Various Staff and Management Positions at PJM (1990 – 2004)
General Public Utilities Service Corporation (1987 – 1990) – System Operations
American Electric Power Service Corporation (1979 – 1987) – Bulk Transmission Planning
Expert Witness Testimony:
Kentucky proceeding related to the transfer of ownership and control of Kentucky Power Company.
Pennsylvania and Maryland CPCN proceedings related to the Transource 500/230 kV IEC Project.
Pennsylvania and New Jersey CPCN proceedings related to Susquehanna – Roseland 500 kV transmission line.
Pennsylvania, West Virginia, and Virginia CPCN proceedings related to TRAIL and Meadowbrook – Loudoun 500 kV transmission lines.
West Virginia, Virginia, and Maryland CPCN proceedings related to PATH 765 kV transmission line.
Maryland CPCN proceeding related to MAPP HVDC and 500 kV transmission lines.
Virginia CPCN proceeding related to Surry – Skiffes Creek 500 kV transmission line.
Numerous FERC hearings, settlement proceedings, and technical conferences, most recently including: o Panelist at FERC’s Competitive Transmission Development Technical Conference (Docket No. AD16-
18) regarding Regional Transmission Planning and Other Transmission Development Issues relative to Order No. 1000 implementation and compliance. June 2016.
o Panelist at FERC’s PJM Solution-Based DFAX Technical Conference related to the assignment of cost allocation using PJM’s solution-based distribution factor (DFAX) cost allocation method. January 2016
o Panelist at FERC’s Technical Conference related to the NIPSCO Complaint (Docket No. EL13-88) on two panels: (i) Transmission Planning Cycles: Whether the Commission should require the PJM- MISO cross-border transmission planning process to run concurrently with the RTOs regional planning cycles as opposed to after the regional transmission planning cycles; and (ii) Lower Voltage Transmission Projects: Whether the Commission should require the RTOs to have a process for joint planning and cost allocation of lower voltage and lower cost cross-border upgrades. June 2015 o IMO Potomac-Appalachian Transmission Highline LLC and PJM Interconnection, L.L.C. (Docket No. ER09-1256-002 and ER12-2708-003). Offered expert testimony relative to the PATH Abandonment Costs matter. April 2015
o Duquesne Light Company (Docket No. ER13-90-002). Provided Declaration in support of PJM Transmission Owners’ compliance filing with the March 22, 2013 Order to add more detail regarding
PDF page 29
Page 3
how the solution-based DFAX values will be used to calculate assignments of cost responsibility. July 2013
o Public Service Electric and Gas Company (Docket No. ER13-90). Provided expert testimony on behalf of the PJM Transmission Owners revisions to the PJM Tariff to modify the cost allocation methodology describing PJM’s current use of distribution factors (DFAX) in allocating the costs of certain transmission upgrades and expansions and discuss how PJM would implement the solution-based DFAX proposed by the PJM Transmission Owners. October 2012
o Panelist at FERC’s Review of Small Generator Interconnection Agreements and Procedures Technical Conference (Docket No. AD12-17) on a panel entitled: Review of Required Upgrades, which explored improving the small generator interconnection process for identifying upgrades to support interconnection including whether interconnection customers should have the opportunity to engage in an expedited independent third-party expert review of upgrade requirements that are perceived as excessive by the interconnection customer. July 2012
Most Recent Publications:
Before the United States District Court for the Middle District of Pennsylvania, Case No. 1:21-cv-01101- JPW, Expert Report of Steven R. Herling in Transource Pennsylvania, LLC, vs. Pennsylvania Public Utility Commission, January 20, 2023.
“New Jersey State Agreement Approach for Offshore Wind Transmission: Evaluation Report (with H. Pfeifenberger, J.M. Hagerty, J. DeLosa, M. Kaplin, D. Sullivan, C. Peacock, E. Bennett, and E. Snyder), prepared for the New Jersey Board of Public Utilities, October 6, 2022
“The Sponsorship Model” – IEEE Power & Energy Magazine – July/August 2016
Education:
MEEPE, Rensselaer Polytechnic Institute, (1979)
BSEPE, Rensselaer Polytechnic Institute, (1978)
Senior Member of the Institute of Electrical and Electronics Engineers