EL25-49-000 · 2025-05-08 · Vistra Corp.

Motion for Leave to Answer and Answer of Vistra Corp. to the 04/23/2025 comments filed by North American Electric Reliability Corporation, et al

Text extracted from the eLibrary original (SHA-256 9a9bbdadde625f87…). Download the original from the official source.

Contents · 12 sections
  1. I. MOTION FOR LEAVE TO ANSWER p. 3
  2. II. ANSWER p. 3
  3. A. The Reliability Concerns Raised in Comments Apply to All New Large Loads, p. 6
  4. B. Generation Asset Owners Should Not Be Prohibited from Maximizing the Use of p. 10
  5. C. Reforms to Load Forecasting Are Warranted, But Should Occur Through a p. 12
  6. III. Conclusion p. 13
  7. Attachment A p. 16
  8. I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT p. 17
  9. II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS p. 19
  10. III. RELIABILITY ISSUES RAISED BY PJM AND NERC p. 20
  11. IV. OBSERVATIONS AND CONCLUSIONS p. 22
  12. Attachment B p. 26

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. MOTION FOR LEAVE TO ANSWER

printed heading

MOTION FOR LEAVE TO ANSWER Although the Commission’s procedural rules generally do not allow answers to answers, the Commission may permit them for good cause.4 The Commission frequently accepts answers that clarify the issues before the Commission, ensure a complete record, or otherwise assist the…
Read this passage

II. ANSWER

printed heading · Topic match: Connecting load and generation

In particular, ACEG’s proposal to require new large loads to make substantial financial commitments before they can be included in PJM’s load forecast would help prevent the inclusion of duplicative load interconnection requests in the load forecast.
Read this passage Filed comments: Connecting load and generation

A. The Reliability Concerns Raised in Comments Apply to All New Large Loads,

printed heading · Topic match: Connecting load and generation

Any new requirements must apply to all new large loads, not just those that are co-located with a generator.
Read this passage Filed comments: Connecting load and generation

B. Generation Asset Owners Should Not Be Prohibited from Maximizing the Use of

printed heading · Topic match: Cost allocation

Shanker explained that in an Option 4 case, Network Integration Transmission Service (“NITS”) costs for other ratepayers remain the same where the parties to the co-location arrangement pay for all necessary upgrades; to contrast, in an Option 1 configuration, NITS costs for other ratepayers could…
Read this passage Filed comments: Cost allocation

C. Reforms to Load Forecasting Are Warranted, But Should Occur Through a

printed heading · Topic match: Retail and wholesale authority

Rather, ACEG’s proposal contemplates that these reforms occurring primarily through retail tariffs, with “[m]inimal changes to BPM Manual 19.”43 Vistra agrees that requiring such financial commitments would help improve the accuracy of PJM’s load forecasting by disincentivizing load customers from…
Read this passage Filed comments: Retail and wholesale authority

III. Conclusion

printed heading · Topic match: Connecting load and generation

Conclusion Responses to PJM’s Answer to the Show Cause Order provide a strong record for the Commission to act quickly to implement a replacement rate that ensures PJM accommodates behind-the-meter co-located load in a just and reasonable and not unduly discriminatory manner.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated: May 8, 2025 Washington, D.C. /s/ Sarah Greenberg Sarah Greenberg Wilson Sonsini Goodrich & Rosati 1700 K Street NW Fifth Floor Washington, DC 20006 (202) 431-5231 sgreenberg@wsgr.com
Read this passage

Attachment A

printed heading

Herling 1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al.
Read this passage

I. QUALIFICATIONS AND PURPOSE OF AFFIDAVIT

printed heading · Topic match: Reliability and curtailment

While at PJM, I contributed to or led initiatives that resulted in a wide range of milestone achievements in PJM’s evolution and growth as a regional transmission organization (“RTO”), including the creation of the RTEP process, the development of procedures 2 and standard terms and conditions for…
Read this passage Filed comments: Reliability and curtailment

II. DESCRIPTION OF CO-LOCATION PROJECT OPTIONS

printed heading · Topic match: Connecting load and generation

There are a number of potential options for the interconnection of co-location projects to the grid, involving different physical configurations and different means by which the co-located load will interact with the grid.
Read this passage Filed comments: Connecting load and generation

III. RELIABILITY ISSUES RAISED BY PJM AND NERC

printed heading · Topic match: Connecting load and generation

In their response to FERC question D. iii., PJM states “In response to this question’s specific prompt about dynamic response models, today, PJM conducts dynamic studies for co-located load projects.
Read this passage Filed comments: Connecting load and generation

IV. OBSERVATIONS AND CONCLUSIONS

printed heading

Coordination of study efforts between PJM and the PJM transmission owners has always been a foundational element of the PJM planning process and must continue for the grid to remain reliable and for customer needs to be met in a timely, fair and non-discriminatory manner.
Read this passage

Attachment B

printed heading · Topic match: Cost allocation

June 2016. o Panelist at FERC’s PJM Solution-Based DFAX Technical Conference related to the assignment of cost allocation using PJM’s solution-based distribution factor (DFAX) cost allocation method.
Read this passage Filed comments: Cost allocation