EL25-49-000 · 2025-05-09 · Constellation Energy Generation, LLC
Errata to the 5/8/2025 Motion for Leave and Answer of Constellation Energy Generation, LLC
PDF page 1
Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Avenue, NW
Suite 760
Washington, DC 20001
Seth.Lucia@constellation.com
May 9, 2025
Via eFiling
Honorable Debbie-Anne A. Reese, Secretary
Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, DC 20426
Re: PJM Interconnection, L.L.C., et al., Docket Nos. EL25-49, AD24-11, and EL25-20 Errata to Motion for Leave and Answer
Dear Secretary Reese:
On May 8, 2025, Constellation Energy Generation, LLC (“Constellation”) filed a Motion for Leave and Answer in the above-captioned proceedings (Accession No. 20250508-5131) (“May 8 Answer”). It has come to Constellation’s attention that footnote 27 in our May 8 Answer did not include language Constellation intended for filing. Attached is a clean version of Constellation’s corrected May 8 Answer reflecting the following correction to footnote 27 shown in redline below:
Other than the above change to footnote 27, the rest of Constellation’s May 8 Answer remains the same. Please contact the undersigned with any questions.
Respectfully submitted,
/s/ Seth Lucia
Seth Lucia
Constellation Energy Generation, LLC
PDF page 2
CERTIFICATE OF SERVICE
I hereby certify that I have on this 9th day of May 2025, caused to be served a copy of this filing upon all parties on the service list in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2024).
/s/ Shawn Whites
Shawn Whites
Constellation Energy Generation, LLC
PDF page 3
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
MOTION FOR LEAVE AND ANSWER OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation Energy Generation, LLC (“Constellation”) moves for leave and submits this answer1 in support of the Commission’s preliminary finding that the PJM Tariff is unjust and unreasonable and unduly discriminatory and preferential2 because, as recent filings plainly show, no one knows the rules for the co-location of large loads and generation. That lack of clarity is allowing certain transmission owners to erect discriminatory roadblocks to safe and reliable interconnection configurations that would reduce the need for costly transmission upgrades and preserve each state’s jurisdiction to decide how to regulate sales to end-use customers. The need for clarity in the tariff cannot wait any longer. President Trump has emphasized that the United States’ competitiveness with other nations depends on the development of Artificial Intelligence (“AI”) infrastructure and that co-location enables such development “on a very rapid basis.”31 Constellation submits this answer and motion for leave pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213, and respectfully submits there is good cause for the Commission to accept the motion for leave. See Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised[] and will ensure a complete record”).2 See PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115, at P 74 (2025) (“Show Cause Order”).3 The White House, Remarks by President Trump at the World Economic Forum, January 23, 2025, 11-12, https://www.whitehouse.gov/remarks/2025/01/remarks-by-president-trump-at-the-world-economic-forum/.
PDF page 4
2
Accordingly, the Commission should affirm its preliminary finding and fix a replacement rate by adopting rules for a variety of co-location configurations as already fully supported in the record.
THE RECORD CONCLUSIVELY DEMONSTRATES THAT THE PJM TARIFF
IS UNJUST AND UNREASONABLE
This is “a show cause proceeding pursuant to section 206” of the Federal Power Act
(“FPA”)4 which includes “a two-step procedure that requires … an explicit finding that the existing rate is unlawful before setting a new rate.”5 Thus, as a threshold matter, the Commission must first “determine whether an existing [rule] is ‘unjust, unreasonable, unduly discriminatory or preferential….’”6 The Commission initiated this proceeding with a preliminary finding under section 206 of the FPA that
the existing PJM Tariff appears to be unjust and unreasonable or unduly
discriminatory or preferential because it does not contain provisions addressing
with sufficient clarity or consistency the rates, terms, and conditions of service that
apply to co-location arrangements. The absence of such provisions may leave
entities unable to determine what steps they can or must take to effectuate co-
location arrangements of various configurations and how to do so in a manner that
is just and reasonable.7
The approximately fifty filings submitted in response to the Show Cause Order conclusively demonstrate the correctness of the Commission’s preliminary finding.
4 Show Cause Order at P 2; see 16 U.S.C. § 824e.5 Emera Me. v. FERC, 854 F.3d 9, 24 (D.C. Cir. 2017); see also MISO Transmission Owners v. FERC, 45 F.4th 248, 253 (D.C. Cir. 2022) (“At step one, FERC decides if the old rate is unjust and unreasonable. … If so, then FERC proceeds to step two and sets a new rate.”) (citing 16 U.S.C. § 824e(a)). 6 Emera Me., 854 F.3d at 21 (quoting 16 U.S.C. § 824e(a)). In determining whether the existing rate is unreasonable, the evidence must be “assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.” Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022) (per curiam) (citing Consol. Edison Co. v. FERC, 510 F.3d 333, 342 (D.C. Cir. 2007); NAACP v. FPC, 425 U.S. 662, 669–70 (1976)).7 Show Cause Order at P 74 (emphasis added); see also id. at P 75 (“In addition, we preliminarily find that this lack of applicable Tariff provisions raises the potential for undue discrimination or preferential treatment,” citing “allegations in the record that [an Indicated Transmission Owner] has delayed work on … requests to co-locate load with … generation at certain facilities”).
PDF page 5
3
First, numerous parties agreed with the Commission’s preliminary finding that the PJM
Tariff is unjust and unreasonable because it lacks clear co-location provisions, and advocated the adoption of replacement rates pursuant to section 206 of the FPA:8
• Antora Energy LLC
• Electric Power Supply Association and the PJM Power Providers, and individually,
• Calpine Corporation
• Cogentrix Energy Power Management, LLC
• Constellation Energy Generation, LLC
• LS Power Development, LLC
• Vistra Corp.
• Enchanted Rock, LLC
• Independent Market Monitor for PJM9
• Mainspring Energy, Inc.
• Solar Energy Industries Association.108 Motion to Intervene Out of Time and Comments of Antora Energy LLC in Response to the Commission’s Co- location Order at 1-2 (filed Apr. 23, 2025); Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures of the Electric Power Supply Association, the PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS Power Development, LLC at 1-2 (filed Apr. 22, 2025); Response of Enchanted Rock, LLC at 2 (filed Apr. 23, 2025); Comments of the Independent Market Monitor for PJM at 2, 13-14 (filed Apr. 23, 2025) (explaining that it “agrees that the current [Tariff] rules are not clear” and because “[t]hese are issues that require a review process and decision by the Commission,” the IMM “recommends that the Commission decide the questions based on submissions by the parties and a hearing at the Commission’s discretion.”); Comments of Mainspring Energy, Inc. Regarding Co-located Generation and Data Center Integration at 1 (filed Apr. 23, 2025); Comments of the Solar Energy Industries Association at 6 (filed Apr. 23, 2025); see also Comments of the Electric Power Supply Association and the PJM Power Providers (filed Apr. 23, 2025) (separate comments); Answer of Constellation Energy Generation, LLC (filed Apr. 23, 2025) (“Constellation First Answer”) (individual company comments); Comments of Vistra Corp. at 4 (filed Apr. 23, 2025) (individual company comments). 9 The Independent Market Monitor for PJM “agrees that the current [Tariff] rules are not clear” and because “[t]hese are issues that require a review process and decision by the Commission,” the IMM “recommends that the Commission decide the questions based on submissions by the parties and a hearing at the Commission’s discretion.” Comments of the Independent Market Monitor for PJM at 2, 13-14 (emphasis added). In this FPA section 206 proceeding, this is equivalent to asking the Commission to fix a replacement rate. Under FPA section 206, no replacement rate is established until the Commission makes the step one finding that the existing rate is unjust and unreasonable, in this case because—as the IMM agrees—the “current rules are not clear.” Id. at 2.10 Two additional parties, Clean Air Task Force and Public Interest Organizations, did not appear to assert that the lack of clear co-location rules rendered the Tariff unjust and unreasonable, but argued that numerous other aspects of the current PJM Tariff are unjust and unreasonable under FPA section 206. See Comments of Clean Air Task Force at 5-6 (filed Apr. 23, 2025) (asserting FERC jurisdiction under section 206 “[w]here, as here, the evidence demonstrates that the existing tariff provisions are inadequate, unjust, and unreasonable” “to properly plan for and
PDF page 6
4
Second, another large group of parties agreed with the Commission that the PJM Tariff lacks clear co-location rules and advocated for further clarity in the Tariff, but did not specify how they thought the Commission should proceed under the FPA:
• Bloom Energy Corporation (“urg[ing] the Commission to provide detailed guidance to PJM … to implement co-location tariff rules”).11
• BrightNight Power Marketing, LLC (“Because PJM’s current open access transmission tariff is not sufficiently clear about the rules that apply to co-located load arrangements, BrightNight supports the Commission establishing pro forma rules….).12
• Data Center Coalition (urging the Commission to “affirm the legitimacy of co-location,” “direct PJM to provide Tariff clarity,” and “reject one-size-fits-all treatment of network load”).13
• Delaware Public Service Commission (“The DEPSC is inclined to support these types of frameworks” [PJM Options 6-8]).14
• EDF Renewables, Inc. (“The Commission should act expeditiously to encourage flexible co- location structures that will enable speedy and reliable interconnection for large loads.”).15
• Electricity Consumers Resource Council (“the Commission should focus on facilitating co- location and other flexible arrangements” and “should reject the overarching premise in the comments of the Indicated PJM Transmission Owners that only Network Service or Point-to- Point Transmission Service arrangements should be permitted, and that no other flexibility should be allowed”).16
• ENGIE North America Inc. (“The Commission should provide clear guidance on co-location arrangements.”)17
• Office of the Federal Energy Advocate of the Public Utilities Commission of Ohio (“The Ohio FEA supports further consideration of these options [PJM Options 6-8].”).18
allocate costs pertaining to … large co-located loads”) (emphasis added); Comments of Public Interest Organizations, passim (filed Apr. 23, 2025) (asserting numerous aspects of the PJM Tariff are unjust and unreasonable as applied to co-location).
11 Comments of Bloom Energy Corporation at 1-2, 13 (filed Apr. 23, 2025).12 Comments of BrightNight Power Marketing, LLC at 3 (filed Apr. 23, 2025).13 Comments of the Data Center Coalition at 12 (filed Apr. 23, 2025) (initial capitalization omitted).14 Comments and Intervention of the Delaware Public Service Commission at 6 (filed Apr. 23, 2025).15 Comments of EDF Renewables, Inc. at 6 (filed Apr. 23, 2025) (initial capitalization omitted).16 Motion to Intervene and Comments of the Electricity Consumers Resource Council to PJM Interconnection, L.L.C.’s Answer to the Section 206 Show Cause Order at 4, 6 (filed Apr. 23, 2025) (emphasis in the original).17 Comments of ENGIE North America Inc. at 5 (filed Apr. 23, 2025).18 Comments of the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate at 4 (filed Apr. 23, 2025).
PDF page 7
5
• Pennsylvania Public Utility Commission (“PJM’s Tariff must be revised to require that PJM conduct long-term scenario analyses on the potential cumulative reliability and cost impacts of behind-the-generator-meter co-located load arrangements”).19
• PJM Industrial Customer Coalition and Industrial Energy Consumers of America
(“wholeheartedly agree[ing]” with the Commission’s concerns about the lack of “a common
and consistent understanding” of the co-location rules and “urg[ing] the Commission to
provide sufficient guidance to PJM to enable a clear, cost-based structure, and understandable study process, and the ability to expedite projects that do not require transmission updates”).20
• Public Service Electric and Gas Company (“PSE&G proposes a principle-based approach to
address the Commission’s issues and concerns and suggests a path forward to obtain timely
and needed clarity with respect to co-located load rules”).21
• Talen Energy Corporation (“Talen respectfully requests that the Commission direct PJM to submit Tariff modifications to address the five [new] co-location configuration options
proposed by PJM”).22
Third, the American Council on Renewable Energy and Advanced Energy United both
called for a process under section 205 of the FPA to clarify the PJM Tariff.23
Finally, several other parties apparently took no position on the PJM Tariff’s lack of clarity regarding the treatment of co-location, but still advocated prompt Commission guidance or other possible reforms on an expedited timeline.2419 Comments of the Pennsylvania Public Utility Commission at 6-7 (filed Apr. 23, 2025).20 Joint Comments of PJM Industrial Customer Coalition and Industrial Energy Consumers of America at 14 (filed Apr. 23, 2025) (emphasis in the original).21 Response of Public Service Electric and Gas Company to the Order to Show Cause (filed March 24, 2025) at 2.22 Comments of Talen Energy Corporation on Answer of PJM Interconnection L.L.C. to Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings at 12 (filed Apr. 23, 2025).23 Comments of the American Council on Renewable Energy at 1 (filed Apr. 23, 2025); Response of Advanced Energy United at 3 (filed Apr. 23, 2025).24 Comments of Americans for a Clean Energy Grid at 5 (filed Apr. 23, 2025) (supporting adoption of “commitment- backed load forecasting proposal”); Comments of the Business Council for Sustainable Energy at 2 (filed Apr. 23, 2025) (“BCSE supports FERC taking action as soon as is practicable to address the issues related to the co-location of large loads”); Comments of Invenergy Renewables LLC and Invenergy Thermal LLC at 6 (filed Apr. 23, 2025) (during the “interim” while PJM is “completing its interconnection queue transition process … PJM’s Tariff should be amended to include at least co-located loads in the standard generator interconnection procedures”); Comments of Natural Resource Defense Council at 9 (filed Apr. 23, 2025) (“urg[ing] the Commission to examine the extent to which RTO load forecasts apply appropriate rigor to exclude speculative data center projects”); Comments of the Organization of PJM States, Inc. at 3 (filed Apr. 23, 2025) (“OPSI continues to call on the Commission to require that transmission providers conduct transparent, publicly reviewable reliability studies pursuant to a PJM tariff for large co-located load arrangements to preserve system reliability.”); Comments of RMI at 3-5 (filed April 29, 2025) (“PJM should rectify the current lack of a ‘tariffed study process for load’” and “require earlier standardized information
PDF page 8
6
The preceding lists of parties expressing the lack of clarity in the PJM Tariff comprise an
extensive record in support of the Commission’s preliminary finding that the Tariff is unjust and unreasonable because it lacks clear co-location rules. But even among the parties professing opposition to the Commission’s preliminary section 206 finding, most (including PJM itself) still either expressly support clarification of the PJM Tariff or highlight Tariff provisions that could be clarified.25 PJM took the lead on suggesting possible clarifications, cataloguing eight co-location configuration options in its response to the Show Cause Order.26 This greatly facilitated efforts by
sharing between itself, large load customers, and transmission owners”); Letter from Paul Stockton, Former Assistant Secretary of Defense for Homeland Defense and America’s Security Affairs, John B. Hashem, Major General, US Army (Ret.), Robert G. F. Lee, Major General, US Army (Ret.), Joseph L. Lengyel, General, USAF (Ret.), Craig R. McKinley, General, USAF (Ret.), Darryll D. M. Wong, Major General, USAF (Ret.), Chuck Wald, General, USAF (Ret.), and Benny M. Paulino, Major General, US Army (Ret.) to Mark C. Christie, Chairman, and Judy W. Chang, Willie L. Phillips, David Rosner, and Lindsay S. See, Commissioners at 1 (Apr. 22, 2025) (“We urge that the Federal Energy Regulatory Commission act to ensure that data centers can meet their growing power requirements as quickly as possible.”) (emphasis added); see also Answer of Allegheny Electric Cooperative, Inc. to Show Cause Order Issued in Connection with the Treatment of Co-located Load within PJM Interconnection, L.L.C. (filed March 24, 2025) at 2 (Allegheny “remains uncommitted as to whether the current PJM Tariff sufficiently addresses Co-Located Load” but “Allegheny is certain that the need for clarity from the Commission is both essential and urgent.”).
25 Answer of PJM Interconnection, L.L.C. (filed March 24, 2025) at 4, 32 (“What PJM and the industry need now is Commission guidance on a path forward based on the record developed in this proceeding” and “clarifications and enhancements could well be in order given that this is an evolving area and Tariff provisions did not contemplate the type of arrangements at issue in this docket or their implications”); Answer of the Indicated PJM Transmission Owners at 2 (filed Apr. 23, 2025) (“to the extent FERC believes it would provide helpful clarity, the Indicated TOs recommend adopting a proposed definition of co-located load” in the Tariff); Comments of Buckeye Power, Inc. at 9 (filed Apr. 23, 2025) (“Buckeye supports the Commission providing additional clarity or guidance to support” PJM Options 6- 8); Answer of The Dayton Power and Light Company d/b/a AES Ohio to Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (filed March 24, 2025) at 2 (“AES Ohio is open to working with PJM and stakeholders to explore alternative transmission service arrangements for certain co- located load configurations that may be appropriate to reflect specific co-located load circumstances and associated system needs”); Response of American Municipal Power, Inc. at 2-3 (filed Apr. 23, 2025) (“additional clarification concerning the treatment of co-located load may be beneficial”); Comments of the Maryland Office of Joint Consumer Advocates at 7 (filed Apr. 23, 2025) (“the Commission should … clarify that co-located load should be classified as network service under the PJM Tariff”). At least one of the Indicated Transmission Owners also filed separate comments. See Answer of PPL Electric Utilities Corporation at 2 (filed Apr. 23, 2025) (“there are clearly areas where the PJM Tariff … could benefit from increased clarity and FERC guidance” and “it is appropriate to set these rules of the road directly in the tariffs…. PPL Electric believes that these rules can, and should, accommodate behind-the- meter load where required by state law”).26 PJM has also initiated further stakeholder discussions on some of these options, which would be unnecessary if the Tariff were clear. See Tim Horger, Senior Dir., Forward Market Operations & Performance Compliance, PJM, Large Load Additions Workshop (May 9, 2025), https://www.pjm.com/-/media/DotCom/committees- groups/workshops/llaw/2025/20250509/20250509-item-02---large-load-additions-workshop---presentation.pdf.
PDF page 9
7
parties to develop the record (which they have), so the Commission can fix an appropriate
replacement rate, as discussed below.27
Of the remaining filing parties who addressed the issue whether the PJM Tariff is just and
reasonable, only two parties and two individuals are outliers that did not advocate for any Tariff change or clarification.28 And no party pointed to any Tariff prohibition on co-location because there is none.29
In sum, the record in this proceeding unequivocally supports the Commission’s preliminary
finding that the PJM Tariff lacks clear co-location rules and is unjust and unreasonable. Again,
27 The Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures of the Electric Power Supply Association, the PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS Power Development, LLC (filed Apr. 22, 2025) (“Joint Motion”) included as a foundation that the Commission’s preliminary FPA section 206 showing has been met, but this argument was made before additional overwhelming support was filed in the record that the PJM Tariff needs clarification (as established herein). Four of the same parties opposing an FPA section 206 finding in this case also filed comments in opposition to the 206 arguments in the Joint Motion, but all of them failed to cite to any record evidence or selectively cited only to conclusory statements in a few filings in the extensive record in this proceeding in support of a finding that the Tariff is just and reasonable. See Answer of American Municipal Power, Inc. in Opposition to Motion for Stay and Settlement Judge Procedures at 4-5 (filed May 7, 2025) (citing only PJM’s and the Indicated Transmission Owners’ filings in the record); Answer of the Indicated PJM Transmission Owners to the Motion to Stay Proceedings at 3-4 (filed May 7, 2025) (failing to cite any filings in the record); Answer of Northern Virginia Electric Cooperative, Inc. and Northeastern Rural Electric Membership Corporation Opposing the Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures at 3 (filed May 2, 2025) (citing only the Indicated Transmission Owners’ Answer); Answer of PJM Interconnection, L.L.C. to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures at 3 & n.3 (filed May 5, 2025) (claiming “the ever-growing record in this proceeding reflects substantial support for a finding that PJM’s existing Tariff is just and reasonable in regards to co-location arrangements” and citing its own answer, the Indicated Transmission Owners’ answer, AMP’s answer, and—erroneously—Talen Energy’s answer) (Talen has requested the Commission to direct PJM to submit tariff modifications and believes that all eight options proposed by PJM, when implemented into the tariff and taken as a whole, will result in PJM’s tariff being just and reasonable).
28 See Comments of Northeastern REMC on the Order Instituting the Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (filed Apr. 23, 2025); Comments of Northern Virginia Electric Cooperative (filed Apr. 23, 2025). Two individuals also assert that the existing PJM Tariff is just and reasonable but also state that the “current pro forma interconnection agreements do not contain sufficient [reliability] protections and should, at a minimum, be updated accordingly if it is [sic] to be used for connecting co-located large loads.” See Reply Comments of Suzanne Glatz and Abraham Silverman at 14-16 (filed Apr. 23, 2025).29 For the sake of a full accounting of the record, several entities—most not PJM members—offered comments in the record without addressing the justness and reasonableness of the PJM Tariff, nor specifically requesting prompt Commission guidance. See Response of the Center for Biological Diversity (filed Apr. 23, 2025); Comments of Chevron U.S.A. Inc. (filed Apr. 23, 2025); Comment of Consumers’ Research (filed Apr. 23, 2025); Comments of the Edison Electric Institute (filed Apr. 23, 2025); Comments of the North American Electric Reliability Corporation (filed Apr. 23, 2025); Reply Comments of Southern California Edison Company and Pacific Gas and Electric Company (filed Apr. 23, 2025); Comments of the Union of Concerned Scientists (filed Apr. 23, 2025).
PDF page 10
8
even the transmission interests clinging to a one-size-fits-all30 firm Network Integrated
Transmission Service (“NITS”) approach based on gross load billing determinants admit that
“there are clearly areas where the PJM Tariff … could benefit from increased clarity and FERC guidance” and argue that “it is appropriate to set these rules of the road directly in the tariffs.”31 One of the most fundamental elements of just and reasonable rates is that customers must
know the rate in advance.32 “Predictability” is a “central purpose of the filed rate doctrine.”33 Review of the filings in this case highlights nearly universal acknowledgement that the PJM Tariff lacks “predictable” co-location rules. Accordingly, and consistent with Commission precedent, the Commission must find that the PJM Tariff is unjust and unreasonable because, first and
foremost, no one knows the rules.34
The Commission also preliminarily found in the Show Cause Order that the “absence of
[clear co-location] provisions may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations” and this “raises the
30 Except—according to Indicated Transmission Owners—existing Behind-the-Meter Generation loads and generators, which would be grandfathered and allowed to net. See Answer of the Indicated PJM Transmission Owners at 5 (filed Apr. 23, 2025).31 Answer of PPL Electric Utilities Corporation at 2 (filed Apr. 23, 2025). Again, PPL Electric Utilities Corporation is an “Indicated Transmission Owner.”32 See, e.g., FPA section 205, 18 U.S.C. § 824d(d) (“No change shall be made by any public utility in any such rate, ... rule, regulation, or contract relating thereto, except after sixty days’ notice to the Commission and to the public.”) (emphasis added); see also PJM Power Providers Group v. FERC, 96 F.4th 390 (3d Cir. 2024) (rejecting retroactive change to PJM Base Residual Auction rules because parties were not on notice that Tariff rules could change).33 See PJM Power Providers Group, 96 F.4th 390, 401-02 (describing “predictability” as “a central purpose of the filed rate doctrine”).34 See Dominion Energy Marketing, Inc., et al., v. ISO New England Inc., 155 FERC ¶ 61,121 at P 17 (2016) (“We find that ISO-NE’s existing Tariff is unclear as to whether new incremental capacity and existing capacity at the same generation station must submit a composite offer to participate in the [forward capacity auction]” and “[a]s a result of this lack of clarity the Tariff fails to provide adequate notice of what the requirement is and, thus, we find the Tariff is unjust and unreasonable.”); see also, e.g., New York Independent Sys. Operator, Inc., 162 FERC ¶ 61,107 at PP 160, 173 (2018) (finding NYISO’s tariff revisions “unclear and, therefore, unjust and unreasonable” and finding that differences in definitions were also “unclear and, therefore, unjust and unreasonable”); Tennessee Gas Pipeline Co., 123 FERC ¶ 61,217 at P 14 (2008) (finding that the pipeline’s revised tariff language “is ambiguous and, accordingly [] unjust and unreasonable” and conditioning acceptance of the tariff revisions on a compliance filing to clarify the language at issue).
PDF page 11
9
potential for undue discrimination or preferential treatment.”35 Substantial unrebutted evidence in the record confirms this is the case, including some Indicated Transmission Owners refusing to “work on … requests to co-locate load with … generators at certain facilities.”36 In response to the Show Cause Order, Constellation included extensive record evidence supported by sworn expert testimony of the significant injury the lack of clear co-location rules and delays in service to data centers are causing to economic and national security, and the host of other injuries inflicted by the current de facto NITS-only approach (including billions of dollars of unnecessary transmission upgrades, intrusion on state jurisdictional authority and flexibility, and violation of cost-causation and other rate design fundamentals).37 No expert rebuttal to any of this evidence was filed by the Indicated Transmission Owners or any other opponent in response to the Show Cause Order, and argument in pleadings without an evidentiary basis is insufficient to rebut record evidence.38 Many parties not only failed to submit any expert analysis to demonstrate why the current PJM Tariff is just and reasonable but also failed to respond to the Commission’s briefing questions contained in the Show Cause Order.
Based on the record, the Commission should affirm its preliminary finding under section 206 of the FPA that the PJM Tariff is unjust and unreasonable because it lacks “provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements.”3935 Show Cause Order at PP 74-75.36 Id.37 See Constellation First Answer at Section I (pp. 13-36); see also id., Exh. 1, Declaration of Dr. Paul Stockton; Exh. 2, Testimony of Zachary Ming. Mr. Ming is the only rate design expert in the record to discuss the issue whether a NITS-only approach is unjust and unreasonable.38 See, e.g., San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs. Into Mkts. Operated by the Cal. Indep. Operator Corp., 153 FERC ¶ 61,144, at P 32 (2015) (“general arguments will not suffice to rebut the specific . . . evidence presented by [parties]”).39 Show Cause Order at P 74.
PDF page 12
10
THE RECORD SUPPORTS THE COMMISSION’S ADOPTION OF A
REPLACEMENT RATE OF CO-LOCATION CONFIGURATION OPTIONS
With the step one showing made under section 206 of the FPA, the Commission must move to step two and fix a replacement rate. Under the plain terms of the FPA, the Commission has no discretion to do otherwise. The record in this proceeding already does the heavy lifting and provides substantial evidence and support for adopting new “generator-contingent” options (PJM Options 4 and 5) and a provisional “interruptible” option (PJM Option 7), as well as clarifying the Tariff to allow a “firm” co-location configuration based on net generation and load at a point of interconnection (PJM Option 2, which essentially would clarify that the same rules for PJM Option 3 should be available at the co-located load and generator’s election). With appropriate rate treatment as demonstrated in the record, these three categories of potential co-location configurations collectively provide a just and reasonable rate that maximizes efficient use of existing energy infrastructure and minimizes expansive transmission upgrades and other costs. Each type of configuration also appropriately allocates costs commensurate with the level of transmission service being used by the load. Constellation introduced extensive record support for the configurations and the proposed rate treatment for each option, and Vistra Corp. and Enchanted Rock, LLC, also provided expert support for the generator-contingent configuration.40 While many of the proponents of a NITS-only approach—including the Indicated
Transmission Owners—chose not to put forward any expert evidence in response to the Show Cause Order or even meaningfully address PJM’s eight options in their March submittals, their steadfast refusal to engage on the key issues, despite the overwhelming record evidence identifying
40 See Constellation First Answer, Exh. 2, Testimony of Zachary Ming; Comments of Vistra Corp., Att. A, Affidavit of Dr. Roy J. Shanker (filed Apr. 23, 2025) (primarily addressing PJM Options 4 and 5); Response of Enchanted Rock, LLC, Att. A, Affidavit of Dr. Albert W. Bremser (filed Apr. 23, 2025) (addressing a new “as-available” transmission service, which shares features with PJM Option 5).
PDF page 13
11
the problems with their proposed approach, does not prevent the Commission from ruling on the record before it.41 Constellation previously moved for settlement discussions on a replacement rate, and while Constellation is willing to engage in good faith settlement talks on a replacement rate, there already is substantial evidence in the record for the Commission to adopt a replacement rate without providing the Indicated Transmission Owners another means to delay resolution. In reviewing the record, the Commission should be wary of conclusory statements and
unsupported policy posturing as opposed to expert evidence. For example, Constellation offered extensive record expert evidence about why resource adequacy and reliability concerns—which always are present with any large new load—nevertheless are not affected by co-location unless we assume contrary to the law that new data center load does not need to be served.42 There is no expert support in the record for the oft-repeated assertion that co-location jeopardizes resource adequacy.
The Commission also must distinguish facts from half-truths. Some parties highlight
recent voltage drops on the grid caused by data centers in Virginia,43 which in this proceeding that is focused on co-location may create the impression that co-located behind-the-meter data centers cause reliability problems. But the full truth is that the Virginia data centers were connected to the grid and taking service from remote generators using the exact same front-of-the-meter approach that Indicated Transmission Owners advocate. The voltage issue had nothing to do with co-
41 The Commission provided notice to PJM and the Transmission Owners that it intended to “be able to issue our [final] decision within approximately three months of the filing of Tariff revisions.” Show Cause Order at P 90. The Commission thus should not countenance sandbagging by parties that demonstrably benefit from delay in adopting clear co-location rules. The Commission should reject any late-filed answers by the Indicated Transmission Owners or others attempting to introduce rebuttal evidence when these parties chose not to present a case in chief with supporting evidence in their initial filings. Such delay is prejudicial to the parties like Constellation being refused access to wholesale services to accommodate co-located loads under the Indicated Transmission Owners’ erroneous interpretation of the PJM Tariff.42 Constellation First Answer at Section II.B. (pp. 58-64); see also id., Exh. 3, Affidavit of Aaron Patterson.43 See, e.g., Comments of the Union of Concerned Scientists at 11, 14.
PDF page 14
12
location. Had the data centers been co-located behind-the-meter, PJM’s former head of operations suggests that the voltage drops might not have occurred.44 The Commission should reject the conjectural narrative that co-location jeopardizes resource adequacy and reliability. If anyone had evidence that co-location risks resource adequacy or reliability any more than any other service to new load, they would have—and should have—provided it by now.
A similarly inapt argument is that “[c]o-location arrangements involving existing generators can heighten concerns … by exacerbating certain market participants’ incentives to abuse market power and engage in market manipulation.”45 There is absolutely no support for this statement, and to the extent this is a legitimate concern, it would be equally applicable to any scenario when supply and demand conditions are tightening. Like the resource adequacy “concerns” discussed above, it has nothing to do with co-location. Regardless, PJM, the IMM and the Commission are well-equipped with rules and tools to screen and mitigate market power. And existing generators are not withholding power by selling it to co-located load. Load is load, and you cannot withhold supply while at the same time using that supply to serve load. While there already is full record support to adopt these co-location configurations (PJM Option 2 with a netting option, Options 4 and 5 for generator-contingent service, and Option 7 for provisional interruptible service), we provide the following brief additional comments: First, for the “firm” co-location configuration (PJM Option 2), the correct rate treatment is to allow the load the choice whether to net the generation and the load, just as with PJM’s existing Behind-the-Meter Generation (“BTMG”) rules (PJM Option 3). The Indicated Transmission
44 See Constellation First Answer at 22; id., Exh. 5, Affidavit of Michael Kormos at ¶ 7 (“Large generators also typically provide significant inertia that can help the local grid avoid or minimize the impact of many anomalies. Given the reduced likelihood of a voltage drop in the first place for load co-located with a generator, it is less likely that such load will sense a voltage anomaly that will lead it to drop.”).45 Comments of Public Interest Organizations at 32-33 (filed Apr. 23, 2025).
PDF page 15
13
Owners assert that co-located load should pay gross NITS while BTMG load should continue to net. But as the PJM Industrial Customer Coalition and Industrial Energy Consumers of America argue, the Indicated Transmission Owners “do not dispute the fact that the configurations between BTMG and co-located load can be identical … yet [they] advocate for a radically different approach for all similarly situated customers that are defined as co-located load.”46 “This is unduly discriminatory.”47 It “would create an unreasonable preference for one type of users over another. It would create dramatically different costs for different users with identical impact to the transmission grid.”48 There is no principled way to sustain the Indicated Transmission Owners’ arguments.
Second, for the “generator-contingent” co-location configurations (PJM Options 4 and 5), it is telling that the primary argument against this type of service is that protective relays—and their backup protective relays—all may suddenly fail, and that the transmission system allegedly must be planned accordingly.49 No expert subscribes to this self-serving conjecture, as confirmed in affidavits in the record by two former senior PJM operators and planners.50
The other leading argument against generator-contingent service is that co-located loads allegedly are attempting to avoid paying for ancillary services. As the Commission is aware, every load interest at the technical conference and since has stated that it will pay any appropriate charges for any services they use, including ancillary services. The focus on ancillaries also is a distraction from the main issue, which is whether loads should be forced to take front-of-the-meter NITS
46 Joint Comments of PJM Industrial Customer Coalition and Industrial Energy Consumers of America at 9 (filed Apr. 23, 2025).47 Id.48 Id. (emphasis in the original).49 For a full discussion of this issues, see Constellation First Answer at 48-49.50 See id., Exh. 4, Affidavit of Steven R. Herling at ¶ 23; Exh. 5, Affidavit of Michael Kormos at ¶¶ 6-7.
PDF page 16
14
service on a gross basis, even though other configurations and rate structures better encourage efficient use of the grid, minimize cost to current customers, and more promptly connect data center load critical to our national security. The cost of these ancillary services is only a small fraction of the costs of NITS. To eliminate any debate and move past what always has been a peripheral issue, Constellation would support generator-contingent co-location rules that included ancillary service charges as part of a replacement rate.
With red herrings about relays and ancillary service charges cast aside, generator-
contingent service can be seen for what it is: an option to efficiently and promptly serve large loads without socializing upgrade costs or increasing resource adequacy or reliability risks. While the Indicated Transmission Owners spill much ink about their desire to protect customers, nothing about a rate design that encourages billions of dollars of transmission overbuild is in customers’ best interests. Customers already are shouldering the burden of massive transmission rate increases,51 while supply costs have essentially held steady since PJM’s Reliability Pricing Model (“RPM”) was implemented.52
Third, for provisional “interruptible” service for co-located loads (PJM Option 7 with
Constellation’s proposed rate treatment),53 the Commission should clarify that the provisional service ends once the network upgrades are built. However, some additional details regarding
51 See Md. Office of People’s Counsel, Motion for Leave to File Answer and Answer, Docket No. ER24-843-000, at 15 (Mar. 20, 2024) (protesting allocation of over $500 million in costs to Maryland customers for transmission upgrades primarily needed to serve data centers located in Virginia).52 See Constellation First Answer, Exh. 3, Affidavit of Aaron Patterson at ¶ 19 (explaining that “[i]n real terms, combined energy, ancillary services, and capacity costs have fallen by about 34% over the period simply comparing 2008 and 2025/26. And even ignoring the high prices in 2008, [these] costs have on average remained essentially flat in real terms from 2009 onward. Over the same period transmission costs in PJM, which are not subject to competition but continue to be determined using traditional cost-based ratemaking, have more than tripled in real terms…”).53 See Constellation First Answer at 55-57.
PDF page 17
15
when the service will be interrupted still need to be provided. The Commission should require PJM to make a compliance filing with these details within 60 days.
Finally, the Commission should reject PJM’s Option 6 (Interconnection Preferences for
BYOG) as unduly discriminatory and preferential for the reasons Constellation previously
addressed.54 It creates risks of “vintaging” where new resources are paid out-of-market and then used to suppress market prices to all existing resources. The Commission has long rejected such schemes after an initial failed foray into contract vintaging in the natural gas markets.55 Moreover, this proposal will not achieve the apparent objective to address resource adequacy concerns: it provides preferential treatment to resources regardless of their capacity attributes simply because they have a contract. This approach would undermine the investment signal sent by PJM’s
centralized capacity market, which explicitly values capacity resources according to their Effective Load Carrying Capability. The Commission should resist the siren call of extra-market BYOG incentives. This is the precise time that the Commission should be staying the course with respect to RPM and providing for regulatory certainty.
54 See id. at 52-55.55 See id. at 53-54, citing Re Area Rate Proceeding for Rocky Mountain Area, 49 FPC 924, 942 (1973) (citing Opinion No. 468, Permian I, 34 FPC 159, 185 (1965) (“vintaging by contract date is an anachronism which should be eliminated”); PJM Interconnection, L.L.C., 126 FERC ¶ 61,275, at P 149 (2009) (finding that PJM’s proposal to increase the RPM’s New Entry Price Adjustment provision from three years to seven years would “further bifurcate capacity markets by giving new suppliers longer payments and assurances unavailable to existing suppliers providing the same service”), order on reh’g, 128 FERC ¶ 61,157 (2009). For more recent examples, see PJM Interconnection, L.L.C., 175 FERC ¶ 61,084, at PP 17 (2021) (rejecting an effective load carrying capability (“ELCC”) class rating floor “transition mechanism” because “it would discount the accredited capacity value of some ELCC Resources below their actual capacity value in order to value other ELCC Resources above their actual capacity value” and because PJM would “unreasonably discount the capacity value of ELCC Resources that enter the market at a later date”); id. at P 108 (further finding that the transition mechanism “would discriminate between resources in a class based on vintage despite the fact that all resources in a class bear equal responsibility for the decrease in the capacity contribution of their ELCC Class;” ISO New England Inc., 173 FERC ¶ 61,198 at PP 68, 73-74 (2020) (eliminating seven-year new entrant price lock because it “result[s] in unreasonable price distortion” by “reduc[ing] the price paid to all capacity suppliers” in the capacity auction).
PDF page 18
16
CONCLUSION
WHEREFORE, Constellation respectfully requests that the Commission grant leave and accept this answer and adopt its preliminary finding that the PJM Tariff is unjust and unreasonable and unduly discriminatory and preferential because it lacks clear provisions for the treatment of large loads co-located with generation, and this lack of clarity has caused undue discrimination against large loads seeking to co-locate. The Commission should fix replacement rates as set forth herein.
Respectfully submitted,
/s/ Paul F. Wight
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel
Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW, Suite 760
Washington, D.C. 20001
(202) 347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Kirkland & Ellis LLP
1301 Pennsylvania Ave., NW
Washington, D.C. 20004
(202) 389-3321
paul.wight@kirkland.com
Counsel for Constellation Energy
Generation, LLC
May 8, 2025
PDF page 19
17
CERTIFICATE OF SERVICE
I hereby certify that I have on this 8th day of May, 2025, caused to be served a copy of the foregoing upon all parties on the service list in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2024).
/s/ Shawn Whites
Shawn Whites
Constellation Energy Generation, LLC