EL25-49-000 · 2025-05-13 · Talen Energy Corporation
Answer of Talen Energy Corporation to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-Located at Generating
)
Docket No. AD24-11-000
Facilities
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
)
(consolidated)
v. )
)
PJM Interconnection, L.L.C.
)
ANSWER OF TALEN ENERGY CORPORATION
TO JOINT COMMENTS AND MOTION TO
STAY PROCEEDINGS AND REQUEST TO ESTABLISH
SETTLEMENT JUDGE PROCEDURES1
Talen Energy Corporation (“Talen”) asserts and reiterates that all eight options
presented by PJM Interconnection, L.L.C. (“PJM”) for the co-location of large load in its Answer2 to the Show Cause Order3 are, when taken as a whole, just and reasonable and not unduly discriminatory. Therefore, there is no need for a 90-day period of settlement judge procedures. Time is of the essence. The Commission already has before it a record to find that the PJM solutions to the issues presented by large load co-location are just and
1 This answer is submitted pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”). To the extent this answer may be considered an answer to the Answer of PJM Interconnection, L.LC. to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures filed in by PJM Interconnection, L.L.C., in Docket No. EL25-49-000 on May 5, 2025, Talen requests that the Commission consider this answer as a Request for Leave to Answer and Answer.
2 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Answer of PJM Interconnection, L.L.C. (filed Mar. 24, 2025). (“Answer to the Show Cause Order”)3 PJM Interconnection, L.L.C, et al., Docket No. EL25-49-000, Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (filed Feb. 20, 2025) (“Show Cause Order”).
PDF page 2
2
reasonable. Once PJM makes all changes necessary to implement the latter five options in its Open Access Transmission Tariff (“OATT” or “Tariff”), to the extent necessary, its Tariff will be just and reasonable. Accordingly, Talen respectfully requests that the Commission deny the Motion to Stay Proceedings and Request Settlement Judge Procedures4 and instead order PJM to revise its OATT and file amended Tariff language no later than thirty (30) days after such a Commission order.
I. ANSWER
A. PJM’s Tariff Will Become Just and Reasonable Once it Incorporates
Language Effectuating All Eight Co-Located Load Configuration Options
Presented in its Answer to the Show Cause Order.
Talen does not agree that PJM’s Tariff is just and reasonable as it currently stands today. PJM presented eight options for co-located load configurations in its Answer to the Show Cause Order.5 The eight options presented by PJM include both front-of-the-meter and behind-the-meter arrangements, including options that allow for co-located load to not be network load and/or not take any FERC-jurisdictional services. Taken together, the eight configuration options permit entities seeking to enter into co-located load arrangements to select the configuration that best meets their needs from a considerable variety of configuration options. Thus, this framework, when adopted as a whole, will result in PJM’s Tariff being just and reasonable and not unduly discriminatory. There is an ample record of evidence already to support this finding.
4 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures of the Electric Power Supply Association, the PJM Power Providers Group, Calpine Corporation, Cogentrix Energy Power Management, LLC, Constellation Energy Generation, LLC, and LS Power Development, LLC (filed April 22, 2025). (“Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures”)5 Answer to the Show Cause Order.
PDF page 3
3
However, PJM’s current Tariff language only allows entities pursuing large load arrangements to configure these arrangements in three ways: as network load with its own point of interconnection (“POI”) to the grid (Option 1); as network load that shares the same POI with the generator but is separately metered (Option 2); or as network load that has a behind-the-meter generation agreement with a co-located generator (Option 3).6 These three options do not presently outline regulatory guardrails for many of the potential configurations that co-located load arrangements may take, despite there being an immediate need for such guidelines. The absence of any tariff language that outlines how these loads may interconnect under other configurations results in the current PJM Tariff being unjust and unreasonable.
PJM’s Tariff will be just and reasonable only if the Commission orders PJM to make all necessary Tariff modifications to effectuate the selection of all eight configuration arrangements it presented in its Answer to the Show Cause Order, including those arrangements where: co-located load is non-network load connected directly to a generator connected to the PJM transmission system with various protections in place to avoid the potential of delivery of system energy to serve the load (Option 4); co-located load is configured the same as Option 4 and also has conditional approval from PJM to take back- up power from the grid if necessary (Option 5); co-located load is network load and it brings additional generation to the PJM transmission system that could serve as a capacity resource for PJM (Option 6); co-located load is network load but it uses a new transitional non-capacity backed service offering until any resource adequacy issues associated with
6 PJM Answer at 9-13; see PJM Answer Ex. A.
PDF page 4
4
its load addition are addressed (Option 7); or co-located load is network load and participates in PJM’s demand response programs (Option 8).7
Once the Commission orders PJM to modify its Tariff to provide for the additional five co-located load configuration options, and PJM submits a compliance filing effectuating such changes, the Tariff will be just and reasonable.
B. The Commission Should Deny the Motion to Stay Proceedings and Request for Settlement Judge Procedures and Order PJM to Modify its Tariff Within 30 Days.
Time is of the essence for the Commission to act. PJM and its diverse stakeholders rely on the Commission to support to PJM in administering its transmission system in a reliable and stable way that also promotes economic growth. As Talen has previously explained, it is essential for the Commission to provide clarity and regulatory certainty on the critical issues presented by the co-location of large load as quickly as possible.8 Talen does not agree that the Commission should establish a 90-day period of settlement judge procedures to further discuss the issues. The record already before the Commission has eight strong, viable options for co-located load configuration proposed by PJM which are just and reasonable and not unduly discriminatory. A 90-day settlement period will only further delay crucial regulatory certainty for all stakeholders involved. Instead of establishing a 90-day period of settlement judge procedures, the Commission should order PJM to file amended Tariff language no later than thirty (30) days after the order is issued.
7 Id. at 13-20; see PJM Answer Ex. A.8 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Comments of Talen Energy Corporation on Answer of PJM Interconnection, L.L.C. To Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (filed April 23, 2025); Large Loads Co-Located at Generating Facilities, Docket No. AD24-11-000, Comments of Talen Energy Corporation on Issues Related to Co-Location of Large Loads at Generating Facilities (filed Dec. 9, 2024).
PDF page 5
5
II. CONCLUSION
For the aforementioned reasons, Talen respectfully requests that the Commission deny the Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures, and order PJM to make all necessary Tariff modifications to effectuate the selection of configuration Options 4 through 8 within 30 days of FERC’s order in this proceeding.
Respectfully submitted,
/s/ William S. Scherman
William S. Scherman
Melinda J. Warner
Vinson & Elkins LLP
2200 Pennsylvania Avenue, NW
Suite 500 West
Washington, DC 20037
Jennifer Mansh
Talen Energy Corporation
Senior Vice President, Regulatory and
External Affairs
600 Hamilton St., Suite 600
Allentown, PA 18101
Jennifer.Mansh@TalenEnergy.com
Counsel for Talen Energy Corporation
May 13, 2025
PDF page 6
6
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings.
Dated at Washington, DC, this 13th day of May 2025.
/s/ Melinda J. Warner
Melinda J. Warner
Vinson & Elkins LLP