EL25-49-000 · 2025-05-13 · Talen Energy Corporation

Answer of Talen Energy Corporation to Joint Comments and Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures

Text extracted from the eLibrary original (SHA-256 b15e3b1b0653a618…). Download the original from the official source.

Contents · 4 sections
  1. I. ANSWER p. 2
  2. A. PJM’s Tariff Will Become Just and Reasonable Once it Incorporates p. 2
  3. B. The Commission Should Deny the Motion to Stay Proceedings and Request p. 4
  4. II. CONCLUSION p. 5

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

EL25-49-000 on May 5, 2025, Talen requests that the Commission consider this answer as a Request for Leave to Answer and Answer. 2 PJM Interconnection, L.L.C., et al., Docket No.
Read this passage

I. ANSWER

printed heading

I.
Read this passage

A. PJM’s Tariff Will Become Just and Reasonable Once it Incorporates

printed heading · Topic match: Connecting load and generation

PJM presented eight options for co-located load configurations in its Answer to the Show Cause Order.5 The eight options presented by PJM include both front-of-the-meter and behind-the-meter arrangements, including options that allow for co-located load to not be network load and/or not take any…
Read this passage Filed comments: Connecting load and generation

B. The Commission Should Deny the Motion to Stay Proceedings and Request

printed heading · Topic match: Connecting load and generation

The record already before the Commission has eight strong, viable options for co-located load configuration proposed by PJM which are just and reasonable and not unduly discriminatory.
Read this passage Filed comments: Connecting load and generation

II. CONCLUSION

printed heading

CONCLUSION For the aforementioned reasons, Talen respectfully requests that the Commission deny the Motion to Stay Proceedings and Request to Establish Settlement Judge Procedures, and order PJM to make all necessary Tariff modifications to effectuate the selection of configuration Options 4…