Motion for Leave to Respond and Limited Response of Buckeye Power, Inc. to the 05/08/2025 Answer of Vistra Corp
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company Commonwealth Edison Company Commonwealth Edison Company of Indiana, Inc.
The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc.
AEP Kentucky Transmission Company, Inc AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc.
Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
PDF page 2
- 2 -
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission
MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000 (Consolidated)
MOTION FOR LEAVE TO RESPOND AND
LIMITED RESPONSE OF BUCKEYE POWER, INC.
Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s
(“Commission”) Rules of Practice and Procedure,1 Buckeye Power, Inc. (“Buckeye”) respectfully moves for leave to respond and submits the following brief response to the May 8, 2025 Answer of Vistra Corp. (“Vistra”).2 The Limited Response below addresses only one aspect of Vistra’s Answer: potential retail “financial commitment” requirements for new large load interconnection.3 Such retail “financial commitments” may have some benefit, but on their own they do not go far
1 18 C.F.R. §§ 385.212, 385.213.2 Motion for Leave to Answer and Answer of Vistra Corp. (May 8, 2025), eLibrary No. 20250508-5081 (“Vistra Answer”).3 Vistra Answer at 12-13.
PDF page 3
- 3 -
enough to protect other customers against unjust and unreasonable Commission-jurisdictional transmission rates. Such retail financial commitments alone fail to protect other wholesale transmission customers from the risk of unreasonably bearing substantial stranded transmission costs caused if those large loads fail to show up as expected, whether initially or after the load goes into service.
I. MOTION FOR LEAVE TO RESPOND
The Commission’s Rules prohibit answers to answers unless otherwise authorized,4 but the Commission has the authority to waive this prohibition for good cause.5 It routinely grants motions for leave to answer when doing so will assist the Commission’s decision-making process.6 The following Response will aid the Commission’s understanding of the range of risks and concerns regarding new, large load interconnections, such as large data center loads.
II. LIMITED RESPONSE
For the reasons described in our earlier comments in the now-consolidated proceedings, Buckeye disagrees with many of Vistra’s arguments on the treatment of co-location arrangements7 but responds only to Vistra’s discussion of potential requirements for “financial commitments” by new large loads.8 Vistra’s Answer regarding this issue addresses earlier comments by Americans for a Clean Energy Grid (“ACEG”),9 which “proposed to require load-serving entities and electric
4 18 C.F.R. § 385.213(a)(2).5 Id. § 385.101(e).6 See, e.g., Midcontinent Indep. Sys. Operator, Inc., 178 FERC ¶ 61,249, P 16 (2022) (accepting answers to answers “because they have provided information that assisted us in our decision-making process”).7 See Comments of Buckeye Power, Inc. (Apr. 23, 2025), eLibrary 20250423-5154 (“Buckeye April 2025 Comments”); Comments of Buckeye Power, Inc. (Dec. 9, 2024), eLibrary No. 20241209-5210 (“Buckeye December 2024 Comments”). Not addressing these other issues does not imply agreement or waiver of any argument.8 Vistra Answer at 12-13.9 Comments of Americans for a Clean Energy Grid (Apr. 23, 2025), eLibrary No. 20250423-5217 (“ACEG Comments”).
PDF page 4
- 4 -
distribution companies that request load adjustments demonstrate that any new large loads interconnections are backed by stringent financial commitments.”10 The idea behind such financial commitments is to “place the risk of customer-specific forecasting inaccuracy on the individual customer,”11 rather than the load-serving entity (“LSE”). Although “Vistra agrees that requiring such financial commitments would help improve the accuracy of PJM’s load forecasting by disincentivizing load customers from submitting multiple duplicative interconnection requests,” it argues that such reforms would need to be included in PJM’s Tariff and should be explored by the Commission in a separate proceeding.12
Buckeye agrees that retail financial commitments can play a useful role in improving forecast accuracy and protecting the host LSE and its own retail customers from the excessive transmission costs associated with overestimating new large loads.13 However, Vistra’s Answer (like ACEG’s Comments to which Vistra responds) fails to recognize that the risks of inaccurate forecasting go beyond just the allocation of risk between the host LSE and large end-use customer. As presented, the financial commitments concept omits one critically important element needed to protect other transmission customers from bearing stranded transmission costs when large loads fail to materialize as forecasted. To meet its Federal Power Act obligations, the Commission should take additional actions to fill this problematic void.
10 Vistra Answer at 12. See also ACEG Comments at 3-4 and Attachment. 11 ACEG Comments, Attach. at 2.12 Vistra Answer at 12-13.13 See Buckeye April 2025 Comments at 12 (explaining that LSEs can enter into arrangements with large end-use customers “e.g., through a minimum demand charge, and minimum contract term, backed by appropriate credit support requirement” to encourage end-use customer loads to show up as expected). Buckeye takes no position on whether the requirement for forecasted load to be backed by “financial commitments” needs to be approved through a separate Commission proceeding or can be addressed through revisions to PJM’s manuals without FERC approval.
PDF page 5
- 5 -
Specifically, as explained in Buckeye’s earlier comments in greater detail, wholesale transmission customers other than the host LSE face significant risks of stranded costs if large loads do not materialize as forecast.14 The costs of the significant transmission investments needed to serve new, large loads are shared among LSEs in the relevant PJM zone on a load-ratio share basis pursuant to transmission owner (“TO”) formula rates filed as Attachment H to the PJM OATT. If the large loads do not materialize, the host LSE’s load does not increase (or may subsequently decrease before the cost of transmission facilities built to serve the customer are fully recovered through rates, even if the large load initially went into service at planned-for levels), and a portion of the costs of transmission facilities built by the applicable transmission owner to serve the large load would thus be shifted to other LSEs in the TO Zone. Although retail “financial commitments” described by Vistra and ACEG may allow the host LSE to recover costs from the large load that failed to materialize (and potentially protect its retail customers), in the absence of further Commission action resulting in the crediting of the benefits of these financial commitments against the FERC jurisdictional wholesale transmission revenue requirement, the benefits of these “financial commitments” would be trapped at the host LSE’s retail level alone and would do nothing to protect other wholesale LSEs in the applicable TO Zone or their retail customers from these stranded transmission costs.
To ensure just and reasonable wholesale transmission rates, any costs collected under such retail “financial commitments” would need to also be credited to the wholesale transmission revenue requirement for the applicable TO Zone to ensure that the costs of any transmission facilities built by the transmission owner to accommodate such large loads, as planned and contracted for, are not shifted to other LSEs in the applicable PJM TO Zone. As Buckeye has
14 Buckeye December 2024 Comments at 4-9; Buckeye April 2025 Comments at 10-12.
PDF page 6
- 6 -
previously explained, the different approaches taken by AES Ohio and AEP Ohio illustrates how “financial commitments” at the retail level with regard to new large loads are not sufficient by themselves to ensure that other LSEs in the TO Zone are protected against unreasonable transmission cost shifts.15 Thus, additional mechanisms at the FERC-jurisdictional wholesale level, beyond the purely retail “financial commitments” describe by Vistra (and ACEG), are required to ensure just and reasonable Commission-jurisdictional transmission rates. As noted in Buckeye’s April 2025 Comments (at 10-12), and the additional details in our December 2024 Comments (at 4-9), the PJM Tariff should be revised so that each LSE is responsible, as part of the calculation of zonal transmission rates, for its large load demand.16 Such LSE responsibility will ensure that any stranded transmission costs associated with such large loads are not shifted to other LSEs through PJM transmission rates. Indeed, this approach would encourage LSEs to require financial commitments of their retail large load customers in order to backstop their wholesale responsibility, avoiding the issue of whether PJM should require retail financial commitments from large loads to host LSEs (much less the issue of where such a requirement should be located17). Critically, only the LSE where the large load is located has the ability to push stranded cost responsibility and “financial commitments” to the large retail load.
15 Buckeye December 2024 Comments at 7-9. While both AES Ohio and AEP Ohio required certain minimum demand payments, backed by credit support, from large load customers for a period of time sufficient to recover investments in transmission facilities built to accommodate such large loads as planned and contracted for, the critical difference is that “AES Ohio committed to apply any payments it receives from Amazon under this arrangement to the wholesale transmission revenue requirement to ensure that all other wholesale transmission customers would similarly be held harmless from any stranded costs caused by the retail load not showing up as expected.” Id. at 7 (footnote omitted). AEP Ohio, on the other hand, has not yet made any such commitment, “leaving other wholesale transmission customers in the AEP Zone (including Buckeye) bearing the stranded transmission costs.” Id. at 8.16 The extent of such responsibility, whether 100% or something less, the length of time such responsibility would remain in place, and other details would be subject to further Commission proceedings. 17 As noted above, Buckeye takes no position on the dispute between Vistra and ACEG on where any such “financial commitment” is located. What matters for PJM rates is LSE responsibility.
PDF page 7
- 7 -
Other LSEs that would be affected by material reduction in large loads through transmission cost- shifting at the wholesale level have no ability whatsoever to mitigate such transmission cost- shifting through the imposition of retail “financial commitments” on large loads located in the retail service territory of other LSEs.
It is therefore imperative that the Commission take steps to mitigate the potential for significant shifting of transmission costs at the wholesale level to LSEs that do not have the ability to mitigate the effects of such cost-shifting through the imposition of “financial commitments” at the retail level on the large retail loads causing such cost-shifting.18 If the Commission does not address this issue in this proceeding, the Commission should open a separate Section 206 proceeding to ensure the PJM Tariff contains sufficient provisions to mitigate transmission cost shifting caused by large loads.19 Regardless of the approach the Commission decides to take, these issues should be promptly addressed.20
III. CONCLUSION
Buckeye respectfully requests that the Commission accept and give full consideration to this Limited Response in connection with its examination of the issues in this proceeding.
18 Given the magnitude of the large, principally data center, loads currently being planned for by PJM transmission owners, and the uneven distribution of such large loads among PJM TOs and among LSEs within a PJM TO Zone, Commission inaction is not justified on the basis that the potential transmission costs shifting effects would be de minimis or that such effects, even if significant, would be evenly distributed.19 A separate Section 206 proceeding addressing standardized transmission-level load interconnection processes, as suggested by Vistra, is overly broad and not necessary to address these concerns unless such a proceeding focuses solely on interconnection processes for large loads exceeding a certain threshold.20 Buckeye April 2025 Comments at 10-13.
PDF page 8
- 8 -
Respectfully submitted,
/s/ Lija Kaleps-Clark
Kurt P. Helfrich
General Counsel
Lija Kaleps-Clark
Associate General Counsel
Buckeye Power, Inc.
6677 Busch Boulevard
Columbus, Ohio 43229
Telephone: (614) 681-5151
khelfrich@ohioec.org
lkaleps@ohioec.org
Its counsel
Dated: May 22, 2025
PDF page 9
- 9 -
CERTIFICATE OF SERVICE
I hereby certify that on this 22nd day of May, 2025, I have caused the foregoing to be served upon each person listed on the Official Service List for this proceeding.
/s/ Lija Kaleps-Clark
Lija Kaleps-Clark