EL25-49-000 · 2025-05-22 · Buckeye Power, Inc.

Motion for Leave to Respond and Limited Response of Buckeye Power, Inc. to the 05/08/2025 Answer of Vistra Corp

Text extracted from the eLibrary original (SHA-256 d875379fb6328ddc…). Download the original from the official source.

Contents · 3 sections
  1. I. MOTION FOR LEAVE TO RESPOND p. 3
  2. II. LIMITED RESPONSE p. 3
  3. III. CONCLUSION p. 7

Read topic-matched comments in EL25-49

Topics in the text: Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. MOTION FOR LEAVE TO RESPOND

printed heading

MOTION FOR LEAVE TO RESPOND The Commission’s Rules prohibit answers to answers unless otherwise authorized,4 but the Commission has the authority to waive this prohibition for good cause.5 It routinely grants motions for leave to answer when doing so will assist the Commission’s decision-making…
Read this passage

II. LIMITED RESPONSE

printed heading · Topic match: Cost allocation

As Buckeye has 14 Buckeye December 2024 Comments at 4-9; Buckeye April 2025 Comments at 10-12. - 6 - previously explained, the different approaches taken by AES Ohio and AEP Ohio illustrates how “financial commitments” at the retail level with regard to new large loads are not sufficient by…
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading

Helfrich General Counsel Lija Kaleps-Clark Associate General Counsel Buckeye Power, Inc. 6677 Busch Boulevard Columbus, Ohio 43229 Telephone: (614) 681-5151 khelfrich@ohioec.org lkaleps@ohioec.org Its counsel Dated: May 22, 2025 - 9 -
Read this passage

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that on this 22nd day of May, 2025, I have caused the foregoing to be served upon each person listed on the Official Service List for this proceeding. /s/ Lija Kaleps-Clark Lija Kaleps-Clark