EL25-49-000 · 2025-05-23 · Public Service Electric and Gas Company
Motion for Leave to Answer and Answer of Public Service Electric and Gas Company to the initial and reply comments re FERC's 02/20/2025 Show Cause Order
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, LLC et al.
)
)
Docket Nos. EL25-49
Large Loads Co-Located at Generating
Facilities
)
)
AD24-11
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
EL25-20
(Consolidated)
)
MOTION FOR LEAVE TO ANSWER AND ANSWER OF
PUBLIC SERVICE ELECTRIC AND GAS COMPANY
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and 213 (2025), Public Service Electric and Gas Company (“PSE&G”)1 hereby submits this Motion for Leave to Answer and Answer to the initial and reply comments that have been filed in response to the Commission’s Show Cause Order issued on February 20, 2025 (the “Show Cause Order”).2
In response to the Show Cause Order, a number of comments have been filed. Based on those comments, as well as the comments submitted in other dockets regarding co-located load arrangements over the past year, the Commission now has a very comprehensive, robust record before it upon which to establish just and reasonable rules
1 PSE&G serves 2.4 million electric customers in its franchised service territory in New Jersey, including a number of large load customers who have onsite or Behind the Meter Generation (“BTMG”) to meet some or all of their power requirements.2 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 at P 2 (2025) (“Show Cause Order”) (making a preliminary finding that the PJM Tariff may be “unjust and unreasonable or unduly discriminatory or preferential because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions that apply to co-location arrangements.”).
PDF page 2
2
under the PJM Tariff governing co-located load arrangements. As the Commission evaluates the issues and issues a decision, it should be guided by three key principles to ensure compliance with the requirements of the Federal Power Act and longstanding precedent and policies.
• First, any new rules governing co-location arrangements, including those regarding transmission pricing, must comply with the basic ratemaking principle of cost causation. This means that charges for wholesale grid services, if any, must reflect the customer’s actual use of the system. For instance, PJM’s Show Cause filing identifies two behind the meter (“BTM”) co-located load options (Options 4 and 5) under which the load uses the transmission system to a lesser degree than other configurations; PJM reasonably proposes cost responsibility reflecting the actual use of the transmission system, consistent with cost causation. On the other hand, a gross load transmission methodology that does not consider the customer’s actual use of the transmission system would not comport with cost causation principles.
• Second, rules adopted by the Commission should not adversely impact existing customers in PJM who have BMTG and who have long relied upon the netting provisions under the PJM Tariff for purposes of paying wholesale grid services (as set forth in Option 3 in PJM’s Show Cause filing). Here, there is no material distinction between BTMG and BTM load arrangements as both configurations result in a reduced use or impact on the power grid in the same way, and should be allowed to net their co- located generation against their load in a comparable manner; any disparate treatment of similarly-situated customers would be unjustified and unduly discriminatory under the Federal Power Act; and
• Third, in recognition of the vital importance of data centers to the United States, the Commission should endeavor to remove barriers and provide regulatory flexibility for customers to select the configuration that best suits their circumstances.
Now is the time for the Commission to act and provide needed certainty to the industry – including data center developers, utilities, generation owners, existing customers and other relevant stakeholders. The lack of clarity and certainty over the past year has had a chilling effect on data center development, and we respectfully urge the Commission to act in a timely manner to establish new rules on co-location.
PDF page 3
3
I. MOTION FOR LEAVE TO ANSWER
While Rule 213 of the Commission’s Practice and Procedure does not provide for answers to answers, the Commission permits such pleadings where, as here, the information provided will facilitate the Commission’s decision-making process and aid in the resolution of issues.3 There is good cause for the Commission to accept this Answer because it will clarify certain issues and assist the Commission with its decision-making.
II. ANSWER
In response to the Show Cause Order, over fifty sets of comments presenting a wide range of views and positions have been filed with the Commission. Most parties agreed with the Commission’s preliminary finding that there is a gap in the PJM Tariff governing co-located loads and urged the Commission to expeditiously establish rules governing co-location arrangements. PJM, while maintaining that the Tariff remains just and reasonable, acknowledges that “clarifications” to the PJM Tariff may be warranted, and has identified eight options for the interconnection of large co-located load. And as relevant to this proceeding, PJM has proposed that the “participants involved in the co- location arrangement should pay the costs of any grid services they consume,” including a reduced level of charges for certain configurations that result in a lesser use of the transmission system. On the other hand, certain parties, continue to argue that the existing PJM Tariff is just and reasonable, no revisions are needed, and all co-location arrangements (regardless of the physical configuration used) should be required to take
3 See, e.g., Green Island Power Auth. & Albany Eng’g Corp., 168 FERC ¶ 61,033 at P 37 (2019); Carolina Power & Light Co., 97 FERC ¶ 61,048 at 61,278 (2001) (finding good cause to waive Rule 214 when a pleading helped to ensure a complete and accurate record).
PDF page 4
4
network transmission service (or point-to-point transmission service) and pay wholesale grid charges based a gross load basis.4 As the Commission evaluates the various arguments presented and make rulings in this proceeding, PSE&G respectfully urges the Commission to keep several key principles in mind, as discussed below.
A. Any Transmission Pricing Rules Governing Co-Location
Arrangements Must Comply With Well-Established Cost Causation
Principles.
A bedrock ratemaking principle that the Commission and the courts have
articulated and applied under the Federal Power Act over a number of decades is that “rates and charges must reflect to some degree the costs actually caused by the customer who must pay for them,”5 and that costs must be allocated in a manner that is “roughly commensurate” with benefits that entity receives.6 This is such a core ratemaking principle that is well understood and accepted such that the Court of Appeals for the Seventh Circuit has characterized it as really an “unremarkable principle.” In a 2009 decision, the Seventh Circuit instructed that under this cost causation principle, “FERC is not authorized to approve a pricing scheme that requires a group of utilities to pay for facilities from which its members derive no benefits, or benefits that are trivial in relation
4 These parties take this position even though the Commission is looking to establish transmission pricing rules under which the imposition of charges is commensurate with the use of the transmission system, as required by cost causation. In the Show Cause Order, the Commission stated that “different co-location arrangements are likely to use or benefit from the transmission system in different ways” and any charges must be consistent with cost causation principles as well the Commission’s recent actions in other related proceedings. See also Atlantic City Electric Co, et al., 190 FERC ¶ 61,109 (2025) (rejecting Section 205 filings proposing that all co-located load arrangements pay full network transmission service and ancillary services on a gross load basis).
5 KN Energy, Inc. v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992).
6 Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009) (“2009 ICC Decision”) (emphasis added).
PDF page 5
5
to the costs sought to be shifted to its members.”7 According to the court, compliance with cost causation is a simple exercise –i.e., comparing of the “costs assessed against a party to the burdens imposed or benefits drawn by that the party.”8 And the court warned that a “claim of generalized system benefits” is not enough to justify the imposition of charges upon a market participant.9
Adherence to cost causation is clearly on the Commission’s mind in this proceeding. Throughout the Show Cause Order, the Commission repeatedly emphasized the importance of compliance with cost causation principles in establishing what wholesale grid charges, if any, should be imposed on co-location arrangements. For instance, the Commission stated that “the record demonstrates that different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different impacts on the transmission system.”10 This observation indicates that the Commission is looking for a calibrated and reasonable transmission pricing methodology for the allocation of costs to co-located load based on its actual level of usage or benefits.
To date, none of the comments submitted in this proceeding warrant a change to the Commission’s preliminary finding that co-located load should pay for the grid services
7 2009 ICC Decision, 576 F.3d at 476 (emphasis added).8 2009 ICC Decision, 576 F.3d at 476 (citing Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004).9 Id. (emphasis added).10 Order at P 76.
PDF page 6
6
that it uses or from which it benefits. PJM’s March 24, 2025 filing identifies eight options; for each option, PJM proposes varying levels of charges for transmission and/or ancillary services depending upon the use of the grid. Specifically, PJM’s filing proposes two BTM/co-location load arrangements: (i) Option 4 (co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load); and (ii) Option 5 (co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load or receive back-up service from PJM with permission). For both options, because the load would not be designated as Network Load (and if there is no withdrawal of energy during coincident peak), PJM proposes that “traditional NTS charges” would not apply but that certain ancillary services should apply.11 This appears to be a reasonable approach to assess charges based on the load’s actual use of the system. Similarly, Option 3 (BTMG with netting) appropriately recognizes the load’s actual use of the transmission system and assesses charges based on netting.
In this proceeding, to resolve the principal controversy pending before the Commission over the past year, the Commission needs only to apply what the Seventh Circuit characterized as the “unremarkable principle” of cost causation; this means that any transmission pricing methodology must reflect the customer’s actual use of the transmission system and allocate costs based on the customer’s usage to ensure that each customer pays for the costs it imposes on the system. This is the same netting principle that the Commission approved for BTMG arrangements under the PJM Tariff more than
11 See PJM’s March 24, 2025 Filing, Exhibit A, New Option 4 and New Option 5 (Options for Service to Large Loads).
PDF page 7
7
twenty years ago.12 By contrast, it is clear that a transmission pricing methodology that is based the customer’s gross load without any consideration for actual use of the transmission system would be unjust and unreasonable and violative of cost causation principles.
B. The Commission Should Ensure That Any Ruling Should Not Adversely
Impact BTMG Customers, And Any Disparate Treatment of BTM Load
Would Be Unjustified and Unduly Discriminatory.
As PSE&G explained in its initial comments, there are a number of customers in PSE&G’s service territory and across the PJM region that have BTMG to meet a portion or all of their power needs, including universities, industrial customers, pharmaceutical companies and rooftop solar customers.13 Under the PJM Tariff, those customers are allowed to net their BTMG against their Network Load for purposes of paying transmission and other charges. In approving these BTMG provisions, the Commission applied cost causation principles by recognizing that BTMG customers use the PJM grid to a lesser degree and should be responsible for paying transmission charges based on their actual or net use of the system.14 Importantly, the Commission explained that the
12 In approving the BTMG provisions in the PJM Tariff, the Commission found emphasized that the BTMG tariff provisions would “encourage qualifying entities with behind the meter generation to reduce their use of the PJM transmission system” and would allocate costs based on the customer’s “actual use of the PJM’s system . . .” and this is “consistent with the principle of cost causation.” See PJM Interconnection, L.L.C., 107 FERC 61,113 at P 17 (emphasis added).13 See PSE&G’s March 24, 2025 Show Cause Response at 2, 18.14 See PJM Tariff, 34.22 and 34.33. See also PJM Manual 14D, Appendix A at p. 179 (allowing BTMG customers to benefit from their reduced usage of the transmission system by “allowing such generation to net for the purposes of calculating transmission, capacity, ancillary services, and administrative fee charges.”). To reflect that there is no use of the transmission system by BTMG arrangements and that customers do not need to pay transmission charges for load served by BTMG arrangements (either in whole or in part), the PJM Tariff specifically provides that the load of a network customer “does not include the load served by operating Behind the meter Generation.”
PDF page 8
8
BTMG provisions in the PJM Tariff (and the netting approach) would encourage loads to reduce their use of the PJM transmission system and consequently the need for new transmission facilities. The Commission’s longstanding policy is to encourage BTMG co- location arrangements to reduce use of the transmission system and the need for new transmission facilities to be constructed. This paradigm benefits all transmission customers. In this proceeding, the Commission should ensure that customers who have BTMG or onsite generation are not negatively impacted by any new rules that the Commission may require.
In addition, as relevant to this proceeding, co-located BTM load arrangements use the transmission system in the same way as BTMG customers. Specifically, both arrangements involve load and generation co-locating at the same site. This results in a similar reduced use of the transmission system and a reduced need for transmission upgrades.15 As such, based on the Commission’s comparability principles, both arrangements should be treated in the same manner and pay for transmission services based on their actual system usage (i.e., based on net use of the transmission system). To treat BTM co-located load and BTMG differently would be improper, unjust and unreasonable and unduly discriminatory under the Federal Power Act.
C. The Commission Should Provide Flexibility and Optionality to Support Future Co-Location Arrangements
There is universal recognition of the importance of data centers to the economic development and national security in the United States. Data centers are part of today’s
15 See PSE&G’s March 24, 2025 Show Cause Answer at 14-16 (discussing that co-located loads and BTMG have similar reduced power flow or impact on transmission in the same way).
PDF page 9
9
modern life, and virtually everyone is using services provided by data centers.16 During the November 1, 2024 Technical Conference, Chairman Christie stated that the “reality” is that “we all live life online” and “data center load growth is just part of modern life, and we have to deal with it.”17 Chairman Christie added “we want to serve data centers,” and “data centers under the principle of universal service have a right to be served.”18 To foster data center development and to maintain U.S. leadership in this transformative industry, it is paramount that the Commission take action to reduce any regulatory barriers within its jurisdiction that may hinder their development.19 Importantly, the Commission should provide data centers with the flexibility and optionality to select a configuration that best fits their particular circumstances and needs. PSE&G appreciates PJM’s efforts and thoughtfulness in identifying and developing a menu of options that may be available to data centers (there could be more), including two BTM/co-location load arrangements (Option 4 and Option 5). Importantly, for both BTM options, to reflect a reduced use of the grid, PJM reasonably proposes that the load pays
16 Routine, everyday uses of data centers include internet searches, social media, streaming services, email services, and on-line shopping/e-commerce transactions.17 November 1, 2024 Technical Conference, Transcript at 11.18 Id.19 The Commission’s longstanding policy is to remove regulatory barriers and to promote customer choice and competition. See, e.g., Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission Organizations and Independent System Operators, Order No. 2222, 172 FERC ¶ 61,247 (2020) (the Commission amending its regulations to remove barriers to the participation of distributed energy resource aggregations in the capacity, energy, and ancillary service markets operated by Regional Transmission Organizations and Independent System Operators.”).
PDF page 10
10
for ancillary services, but not NITS.20 On the other hand, PSE&G does not agree with PJM’s view that Option 3 (Existing BTMG with netting) does not or should not apply to co-located load arrangements. As discussed above, there is no meaningful distinction between BTMG and BTM load given that both configurations involve generation and load co-located and adjacent to one another, resulting in a reduced use or impact on the power grid in a comparable manner.21
D. The Commission Should Expeditiously Complete this Proceeding and
Establish a Concrete Time Frame for the Implementation of Final Rules
Governing Co-Location Arrangements.
Over the past year, there has been significant uncertainty with respect to the rules that would apply to co-location arrangements, with multiple dockets pending before the Commission. While there have been a significant number of comments submitted expressing a wide range of perspectives, the key issue before the Commission comes down to a basic transmission ratemaking question – i.e., to what extent do co-located load arrangements use or benefit from the transmission system, and if so, what level of transmission or ancillary charges should apply?22 In the Show Cause Order, the
20 See PJM’s March 24, 2025 Filing, Exhibit A, New Option 4 and New Option 5 (Options for Service to Large Loads).21 See November 1 Technical Conference Transcript at 14 (Commissioner Rosner stating that “siting generation near load reduce system costs” and the “physics” of BTMG and BTM load “are kind of – they kind of work the same.”).22 To resolve this issue, the Commission simply needs to apply the well-established and “unremarkable” principle of cost causation. Even though certain other issues have been raised in this proceeding (such as reliability and resource adequacy), those issues apply equally to both co- location and front of the meter large load additions. For instance, at Paragraph 85 of the Show Cause Order, the Commission stated, “we recognized, as does PJM, that these concerns, are not necessarily unique to co-location arrangements and that significant load growth more generally may generally raise many of the same concerns.”
PDF page 11
11
Commission established an accelerated schedule for the submission of initial and reply comments, as well as a commitment to issue a decision promptly.23 The time has come for the Commission to act to provide clarity and guidance as the “rules of the road” with respect to co-location arrangements. Here, PSE&G agrees with PJM that “[w]hat PJM and the industry need now is Commission guidance on a path forward based on the record developed in this proceeding.” 24 Accordingly, PSE&G urges the Commission to complete its analysis and issue an order as soon as possible.
23 See Show Cause Order at P 90 (“we estimate that we would be able to issue our decision within approximately three months of the filing of Tariff revisions.”).
24 PJM’s March 24 Answer at 4-5.
PDF page 12
12
III. CONCLUSION
For the reasons discussed herein, the Commission should expeditiously issue a decision that provides timely and needed clarity with respect to co-located load rules and that leads to a result that is (i) consistent with cost causation principles; (ii) avoids harming impacting existing BTMG customers in PJM and treats BTM load in a non- discriminatory manner; (iii) provides for regulatory flexibility and optionality to support data center development; and (iv) establishes a concrete schedule for the implementation of final co-location rules.
Respectfully submitted,
Jodi L. Moskowitz
Vice President, Regulatory, Deputy
General Counsel and RTO Strategy
Officer
PSEG Services Corp.
80 Park Plaza, T-20
Newark, NJ 07102
(973) 430-6409
Jodi.Moskowitz@pseg.com
/s/ Viet H. Ngo
Viet H. Ngo
Associate Counsel – Federal Regulatory
PSEG Services Corporation
601 New Jersey Ave, NW Suite 310
Washington, DC 20001
(202) 460-9356
Viet.Ngo@pseg.com
PDF page 13
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in the proceeding. Dated at Newark, New Jersey this 23rd day of May, 2025.
/s/ Robert Gardinor
Robert Gardinor