Motion for Leave to Answer and Answer of Public Service Electric and Gas Company to the initial and reply comments re FERC's 02/20/2025 Show Cause Order
Text extracted from the eLibrary original (SHA-256 850f4599c90fd3e7…). Download the original from the official source.
Contents · 7 sections
- I. MOTION FOR LEAVE TO ANSWER
- II. ANSWER
- A. Any Transmission Pricing Rules Governing Co-Location
- B. The Commission Should Ensure That Any Ruling Should Not Adversely
- C. The Commission Should Provide Flexibility and Optionality to Support
- D. The Commission Should Expeditiously Complete this Proceeding and
- III. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Cost allocation · Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
As the Commission evaluates the issues and issues a decision, it should be guided by three key principles to ensure compliance with the requirements of the Federal Power Act and longstanding precedent and policies. • First, any new rules governing co-location arrangements, including those regarding…Read this passage Filed comments: Connecting load and generation
I. MOTION FOR LEAVE TO ANSWER
printed heading
MOTION FOR LEAVE TO ANSWER While Rule 213 of the Commission’s Practice and Procedure does not provide for answers to answers, the Commission permits such pleadings where, as here, the information provided will facilitate the Commission’s decision-making process and aid in the resolution of issues.3…Read this passage
II. ANSWER
printed heading · Topic match: Connecting load and generation
PJM, while maintaining that the Tariff remains just and reasonable, acknowledges that “clarifications” to the PJM Tariff may be warranted, and has identified eight options for the interconnection of large co-located load.Read this passage Filed comments: Connecting load and generation
A. Any Transmission Pricing Rules Governing Co-Location
printed heading · Topic match: Cost allocation
Specifically, PJM’s filing proposes two BTM/co-location load arrangements: (i) Option 4 (co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load); and (ii) Option 5 (co-located load with connection to the grid with protections to avoid…Read this passage Filed comments: Cost allocation
B. The Commission Should Ensure That Any Ruling Should Not Adversely
printed heading · Topic match: Cost allocation
To treat BTM co-located load and BTMG differently would be improper, unjust and unreasonable and unduly discriminatory under the Federal Power Act.Read this passage Filed comments: Cost allocation
C. The Commission Should Provide Flexibility and Optionality to Support
printed heading · Topic match: Connecting load and generation
Importantly, for both BTM options, to reflect a reduced use of the grid, PJM reasonably proposes that the load pays 16 Routine, everyday uses of data centers include internet searches, social media, streaming services, email services, and on-line shopping/e-commerce transactions. 17 November 1,…Read this passage Filed comments: Connecting load and generation
D. The Commission Should Expeditiously Complete this Proceeding and
printed heading · Topic match: Cost allocation
Even though certain other issues have been raised in this proceeding (such as reliability and resource adequacy), those issues apply equally to both co- location and front of the meter large load additions.Read this passage Filed comments: Cost allocation
III. CONCLUSION
printed heading · Topic match: Cost allocation
CONCLUSION For the reasons discussed herein, the Commission should expeditiously issue a decision that provides timely and needed clarity with respect to co-located load rules and that leads to a result that is (i) consistent with cost causation principles; (ii) avoids harming impacting existing…Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
Dated at Newark, New Jersey this 23rd day of May, 2025. /s/ Robert Gardinor Robert GardinorRead this passage