EL25-49-000 · 2025-06-03 · Exelon Corporation, American Electric Power Corporation and 16 others

Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners to various filings made on and after 04/23/2025

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-000

Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.
)

)

)
Docket No. EL25-20-000
(consolidated)

MOTION FOR LEAVE TO ANSWER AND ANSWER
OF THE INDICATED PJM TRANSMISSION OWNERS

Pursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”) and the Commission’s Show Cause Order,2 the Indicated PJM Transmission Owners (“Indicated TOs”)3 submit this Motion for Leave to Answer and Answer to the various filings made in the above-captioned dockets on and after

1
18 C.F.R. §§ 385.212, 385.213 (2024).
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at Ordering Paragraph (D) (2025) (“Show Cause Order”).
3 The Indicated TOs include: American Electric Power Service Corporation, on behalf of Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Duke Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.

PDF page 2

2

April 23, 2025.  Under Rule 213(a)(2)4 of the Commission’s Rules of Practice and Procedure, the Commission may authorize an answer to an answer.  There is good cause to accept this answer because it ensures a further developed record for the Commission’s decision making.5

I. The Standard Under Federal Power Act Section 206 Has Not Been Met.
The Federal Power Act (“FPA”), under section 205, requires “[a]ll rates and charges made, demanded, or received by any public utility for or in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”6  FPA section 206, on the other hand, empowers the Commission, on its own motion or upon complaint from a third party, to remedy any “rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” that is found to be “unjust [or] unreasonable.”7  The requirement that the rate or charge must be found to be unjust and unreasonable before alternatives may be considered is a necessary, real, and meaningful one.  Only after a successful showing that the existing rate is unjust and unreasonable, may the Commission order a replacement rate.8  And, “[t]he burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or the third-party complainant.”9  Neither the Commission nor any of the parties supporting the initiation of this FPA section 206 proceeding have demonstrated that the existing

4 18 C.F.R. § 385.213(a)(2).
5 See, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,112 at P 29 (2025) (accepting “answers because they . . . provided information that assisted [the Commission] in [its] decision-making process”).
6 16 U.S.C. § 824d(a).
7 Id. § 824e(a).
8 Id.  See also N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 94–95 (3d Cir. 2014) (”[U]nder § 206, FERC may change a rate in response to a complaint or on its own motion, only if the moving party demonstrates that the existing rate is unjust and unreasonable and the proposed alternative is just and reasonable.”).
9 Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).

PDF page 3

3
PJM Open Access Transmission Tariff (“PJM Tariff”) is unjust and unreasonable.  Consequently, the only action that may lawfully be taken is to terminate this proceeding.

A. The Current PJM Tariff Is Just and Reasonable and Not Unduly
Discriminatory, and No One Has Demonstrated Otherwise.
Notwithstanding proposed alternative arrangements for co-located load, no party has shown that the PJM Tariff is unjust and unreasonable.  Several parties have offered proposals that they claim would aid the development of co-located loads.  But, the Indicated TOs have explained at length why these proposals would harm, rather than help, the ability of PJM to accommodate co-located interconnection arrangements, and the attached Declaration of Danielle S. Powers (“Powers Declaration”) elaborates on those arguments.  More importantly, however, the claim— even if it were true, which it is not—that a different tariff might advantage certain load does not demonstrate that the existing tariff is unjust or unreasonable.

Some parties try to turn this process on its head.  They claim that the PJM Tariff should be changed because the Indicated TOs have not made an adequate “showing that PJM’s Tariff is just and reasonable or not unduly discriminatory, or that changes are not needed to enable progress.”10 As the Indicated TOs have also repeatedly stressed, that is not the law; indeed, it is 180 degrees off.  The burden is not on PJM or the transmission owners to show that the PJM Tariff is just and reasonable; the burden is on parties seeking a change in the rate to demonstrate the existing tariff is not just and reasonable.  The Commission may order a replacement rate under Section 206 only after a successful showing that the prevailing rate is unjust and unreasonable.11  No such showing has been made.

10  EPSA/P3 Comments at 3 (Apr. 23, 2025).
11  16 U.S.C. § 824e(a); see also Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021) (“The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—the Commission [(as in this case)] or the third-party complainant.”).

PDF page 4

4

Constellation argues that requiring all new load to become Network Load,12 like all other end use load, will cause “years of delay” and “induce[] massive and unnecessary overbuild of the system.”13  This claim is sensationalist and unsubstantiated.  No party has demonstrated that it has been unable to receive service under the existing system or that it is experiencing an undue delay for a request for service under the current PJM Tariff.  Nor has there been a coherent explanation for the claim that study processes of new large loads are unjust and unreasonable.  To the contrary, the evidence in the proceeding points to huge potential system impacts arising from contemplated city-sized loads, and a need for a reliability study regardless of how such loads propose to be connected.

Nor does the fact that some parties are complaining about the PJM Tariff show that it is unjust or unreasonable.  There are two transmission options under the existing PJM Tariff: Network Integration Transmission Service (“Network Service” or “NITS”) or Point-to-Point Transmission Service (“PTP Service”).  A preference for alternative rate structures is not evidence that the existing forms of transmission service are unjust and unreasonable.  Vistra claims the existing PJM Tariff includes “a structural bias in favor of network transmission-serviced load and against competitive, bilateral supply arrangements between sophisticated buyers and market-based rate . . . sellers.”14  However, what Vistra wants is an alternative form of service that is cheaper for it at the expense of other transmission customers.  But the fact that the cheaper-for-Vistra (and other similarly situated entities) service is unavailable does not make the existing PJM Tariff unreasonable.  As explained above, there are options for customers to obtain service.  Those

12  Capitalized terms not otherwise defined herein shall have the meanings set forth in the PJM Tariff.
13  Constellation Answer at 4 (Apr. 23, 2025).
14  Vistra Comments at 4 (Apr. 23, 2025).

PDF page 5

5

options work and are provided at rates that the Commission has found to be just and reasonable and are designed to recover the embedded costs of the PJM grid.  There is nothing unjust or unreasonable about these well-established structures.  Moreover, the establishment of tariff provisions that would grant an advantage or preference in favor of co-located loads that would take but not pay for grid services—which is what is being attempted by some in this proceeding— would result in a structural bias that benefits co-located load at the expense of other customers paying Network Service.

Talen similarly argues that the PJM Tariff is unjust and unreasonable because it “do[es] not presently outline regulatory guardrails for many of the potential configurations that co-located load arrangements may take.”15  This argument amounts to nothing more than a desire for a cheaper option, without demonstrating why the existing service is unjust and unreasonable.  The necessary guardrails are the express service definitions.  No one has alleged that they cannot get service for their customers using existing transmission services.  Nothing in the FPA requires that a tariff provide alternative, more favorable treatment for co-located load.  In fact, such “regulatory guardrails” would flout the requirement in the FPA that a tariff not grant undue preference or undue rate discrimination among customers.16

Beyond these untenable claims of harm, some parties’ arguments about the services to end- use load connecting “behind” a generator’s meter rely on a single, flawed premise: that moving the location of the meter changes the degree to which a load relies on grid services or the nature of those services.  This is fiction.  So when Constellation claims that the Indicated TOs have “conflat[ed] the benefits received from ancillary services by the co-located generator with the use

15  Talen Answer to Settlement Motion at 3 (May 13, 2025).
16  See 16 U.S.C. § 824(b).

PDF page 6

6

of the transmission system to deliver energy,”17 or Vistra states that “transmission system charges for load served by co-located generation should be based on actual use of the transmission system,”18 they are pretending that the position of the generator’s meter actually changes those services.  It does not.  Nor does it change the fact that the generator and the load continue to rely on the grid connection to function.

The Commission has rejected arguments that transmission service must be based on specific load flows because the “assessment of [Network Integration Transmission Service] is not based on actual use over a particular transmission path, but rather based on the network customer’s right to use the entire system.”19  This approach to transmission service also comports with FPA section 205(b), which prohibits an undue advantage or preference or “any unreasonable difference in rates, charges, service, facilities, or in any other respect . . . as between classes of service.”20 And this is not the first time parties have attempted to argue for a new class of service.  In one such example, Amtrak v. PPL Electric Utilities Corp.,21 the complainant attempted to argue that it made lesser use of the grid and thus should be charged under some new arrangement that differed from the charges applicable to ordinary Network Service.  The Commission, however, rejected the complaint and found in accordance with the facts that the load was served by the PJM transmission system and thus was appropriately served through the Network Service applicable to Network Load.22

17  Constellation Comments at 8 (Apr. 23, 2025) (emphasis omitted).
18  Vistra Comments at 24 (Apr. 23, 2025) (emphasis omitted).
19  Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020) (emphasis added).
20  See 16 U.S.C. § 824d(b). 21  171 FERC ¶ 61,237, reh’g denied, 173 FERC ¶ 61,043 (2020) (“Amtrak”).
22  Amtrak, 171 FERC ¶ 61,237 at PP 6–9, 39-43.

PDF page 7

7
As demonstrated by the following diagram depicting an example configuration, moving the meter does not change grid usage:

Parties supporting more favorable accommodations for co-located load under the PJM Tariff share one thing in common: their arguments are premised on the fiction that moving the location of the meter (from the example configuration at A and B to a new single meter at C) justifies a new form of service with a new rate construct.  In truth, moving placement of the meter does not change grid availability and support.  However, placement of load behind the meter can obscure load and hide information needed for system planning and grid operations.  It can result in obscured load that is not appropriately accounted for that can unpredictably move grid flows and voltages up and down, creating potentially dire circumstances if those variations were not planned for or accounted for by system operators.  Whether the meters are at C or at A and B, the grid operator and transmission owners must support and plan for both the load and the generator.

PDF page 8

8

Meter placement does not change the physics of the system—if the load suddenly increases or drops by 100 MW, the grid will experience that increase or decrease, no matter where the meter is located.  This is particularly true when the co-located unit is a nuclear plant as such plants cannot follow the load variations, so if there is an increase or decrease in load, it must be generators elsewhere on the grid that respond.  Regardless of whether a large load is behind the meter or in front of it, it impacts flows on the grid, and relies on grid services, and grid operators and transmission owners must therefore support and plan for it.  That does not justify a new form of service with a new rate construct.  The PJM Tariff in its current form allows the co-location of end-use load and generation on terms commensurate with cost-causation principles.23  And as the Indicated TOs have previously explained, “the mere presentation of potential options” does not render the existing PJM Tariff unjust and unreasonable.24  The PJM Tariff remains just and reasonable, so it cannot be changed as a result of this proceeding.

When parties claim that the PJM Tariff is unjust and unreasonable in requiring Network Service because co-located load is “fully isolated” from the grid, they are using misleading nomenclature to misrepresent the physical reality.  As the Indicated TOs have explained previously, there is no such thing as a data center load configured to be “fully isolated” behind the meter through “system protection facilities,” because co-located load that is connected to the electric grid (a) necessarily relies on essential reliability services, such as ancillary services, including black start; (b) retains the potential to draw real or reactive power from the grid at any time; and (c) relies on and benefits from its connection to the transmission system at all times.25

23  See Indicated TOs Answer at 10 (Mar. 24, 2025).
24  Indicated TOs Answer at 9 (Apr. 23, 2025).
25  Id. at 8.

PDF page 9

9

That generator and the end-use load also continue to rely on the transmission connection and investment to operate, just as if the load were “in front of the meter.”  Notably, PJM agrees that there is no such thing as “fully isolated” co-located load arrangement when there is a connection to the electric grid.26  Constellation is mistaken that a “protective relay scheme” will “prevent power flows from the PJM Transmission System . . . to the load,”27 and equally mistaken that the direction of real power flows is a sine qua non for use of, and reliance on, the transmission system. As explained by PJM,

The notion that any of the proposed co-location arrangements can
be “wholly isolated” is misleading. The load and generator are
connected to and synchronized with the multi-state bulk power
system.  It is not operating as a micro grid (nor can it if the
generating facility is a nuclear unit).  Nor is the generator delivering
power through an intermediary to a load with a breaker open.
Further, by way of example, there are obligations to ensure power
to nuclear plants to ensure safe shutdown (among other things).  The
load and generator are benefiting from ancillary services (including
but not limited to black start).  Any system protection facilities are
designed to only handle less complex N-1 conditions, and can
misoperate (and indeed have misoperated).28

There is simply no guarantee that the relay systems and protection schemes will ensure that the reliability impacts of hidden load are mitigated or eliminated.  For example, the protection schemes appear to be largely focused on dealing with situations where the co-located generation unit has an outage, but the reliability concerns are not limited to a generation outage; even while the nuclear generator is producing its full output, there could be a reliability disaster due to rapid variations in

26  See Answer of PJM Interconnection, L.L.C., at 42 (Mar. 24, 2025) (“PJM Answer”) (explaining that co-located load is not fully isolated and “object[ing] to the [Commission’s] use of the phrase ‘wholly isolated from the grid’ [in a question] as it is contrary to engineering and economic principles”); id. at 44 (“PJM is not aware of a configuration that would ‘ensure the co-located load never takes any form of transmission service.’”). 27  Constellation Answer at 78 (Apr. 23, 2025).
28  PJM Answer at 42–43.

PDF page 10

10

demand caused from hidden load unexpectedly appearing (or disappearing) on the electric grid.29 (Or to get back to the diagram, consider the situation where the meters are at A and B.  If the load at B has a relay installed so that it shuts off when the generator at A experiences an outage, that does not change the fact that the load at B impacts the grid second to second throughout the day. Putting a meter at C does not change that continual grid impact.)

Further, requiring co-located loads to obtain Network Service is consistent with bedrock principles of Order Nos. 88830 and 200331 and the PJM Tariff.  It ensures that co-located load is properly accounted for in reliability planning and pays for its share of transmission and ancillary services from the grid.  Order No. 888 codifies the Commission’s decades-long endeavor of “Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission

Services by Public Utilities.”32  It accomplishes this goal by requiring “all transmission-owning utilities to provide transmission service for electricity generated by others on the same basis that they provided transmission service of the electricity they themselves generated.”33  Consistent with this goal, co-located loads are—and should continue to be—treated like all other Network Load.

29  Powers Declaration at P 14. 30  See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, at 31,707 (1996) (cross-referenced at 75 FERC ¶ 61,080), order on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002). 31  See Standardization of Generator Interconnection Agreements and Procedure, 104 FERC ¶ 61,103 (2003) (Order No. 2003).
32  Order No. 888, 61 Fed. Reg. 21,540, 21,541 (May 10, 1996).
33  Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1363–64 (D.C. Cir. 2004) (opinion of Roberts, J.).

PDF page 11

11
Contrary to some commenters’ assertions, this treatment of co-located load does not limit competition or stifle innovation.34  Instead, it places all load, co-located or not, on a level playing field where all customers pay for the transmission services that they receive.  It is not “anti- competitive” to force everyone to play by the same rules.  Quite the opposite.  Classification as Network Load accounts for the physical reality that service to the co-located load requires Commission-jurisdictional services from the grid and should pay for those services in the same manner that all other load must pay.

Several comments argue that co-location provides “benefits” to the grid, including reducing the need for new transmission infrastructure and improving reliability, and therefore co- located load does not have to pay for its share of grid services.35  These unquantifiable benefits do nothing of the sort.  Similar benefits could be said to result from all types of load.  Indeed, as the Indicated TOs have previously explained, these benefits of efficient transmission planning and reliability are best served by treating co-located load as Network Load.36  Many loads are sited efficiently and could claim that their siting provides grid-wide benefits, but they still must pay their share of grid services because they rely on the grid for safe reliable service to keep the light on.  The current PJM Tariff enables just that.  Clarification from the Commission that co-located load is Network Load would further facilitate the benefits that these commenters emphasize.  They have failed to demonstrate that the way in which co-located load connects to the grid under the current PJM Tariff is unjust and unreasonable.  Treating co-located load in its current form under

34  See EPSA/P3 Comments at 12–13 (Apr. 23, 2025).
35  E.g., PJMCC & IECA Comments at 12–13; ENGIE Comments at 6–7; Clean Air Task Force Comments at 12.
36  Indicated TOs Answer at 7 (Apr. 23, 2025).

PDF page 12

12

the PJM Tariff (i.e., as Network Load) is essential for reliability, transmission planning, PJM’s procurement of adequate capacity, and appropriate cost allocation.

What it comes down to is this: “[t]he reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”37  The existing PJM Tariff comports with those goals.  Rather than stymy transmission planning through allowing for load to be hidden from the transmission planning process and place the electric grid at risk, the existing PJM Tariff allows for effective planning, maintains reliability of the electric grid, provides transparent outcomes, and results in an even-handed approach to cost allocation.  Nothing in the FPA requires transmission operators to offer a service more favorable to co-location arrangements when there is a service that can already accommodate these arrangements (i.e., Network Service).

Ultimately, the arguments presented by Talen, Vistra, and Constellation fail to demonstrate that the existing PJM Tariff is unjust or unreasonable. And while behind-the-meter generation arrangements have been “accommodat[ed]” in PJM for decades,38 as the Indicated TOs have previously explained and as further discussed below, behind-the-meter generation (“BTMG”) is not similarly situated to behind-the-meter co-located load.39  Different treatment of co-located load from BTMG, on account of the real differences between the two, is not unduly discriminatory. Accordingly, the existing PJM Tariff remains just and reasonable.

37  Constellation Mystic Power, L.L.C. v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022).
38  Vistra Comments at 3 (Apr. 23, 2025).
39  See Indicated TOs Answer at 5–9 (Apr. 23, 2025).

PDF page 13

13

B. There Is No Basis to Change the Existing PJM Tariff to Accommodate Co-
located Load.

Parties have lost sight of something throughout the course of this proceeding.  FERC cannot order a new type of service unless there is a finding that the existing arrangement is unlawful.  It is worth taking a moment to turn back to Order No. 888-A.  In that order, FERC stated the following:

[T]here is no dispute that the FPA does not explicitly give this
Commission authority to order, sua sponte, open access
transmission services by public utilities.  However, the fact remains
that the FPA does explicitly require this Commission to remedy
undue discrimination by public utilities.  The finding of the D.C.
Circuit in the AGD case, with regard to sections 4 and 5 of the NGA
(which parallel sections 205 and 206 of the FPA), are equally
applicable here: the Act “fairly bristles” with concerns regarding
undue discrimination and it would turn statutory construction on its
head to let the failure to grant a general power prevail over the
affirmative grant of a specific one.40

And the Supreme Court took note of this, stating that, “FERC acknowledged that it did not have the ‘authority to order, sua sponte, open-access transmission services by public utilities,’ but explained that § 206 of the FPA explicitly required it to remedy the undue discrimination that it had found.”41  This can be read to mean that, to the extent FERC required open access, FERC acknowledged that there was not express authority to do that without a finding that there was undue discrimination.  For FERC to require transmission service to accommodate certain loads, it would necessarily follow that FERC cannot order the creation of a new service under the PJM Tariff unless it makes a finding that the current treatment in the tariff constitutes undue discrimination. There is no basis to make that finding.  Under the existing PJM Tariff, Network Service is available

40  Order No. 888-A, 62 Fed. Reg. 12,274, 12,290 (Mar. 14, 1997) (footnote omitted).
41  New York v. FERC, 535 U.S. 1, 13 (2002) (citing Order No. 888–A, at 30,202; 16 U.S.C. § 824e(a)).

PDF page 14

14
to accommodate co-located loads.  There is no undue discrimination as this is the same service offered to other customers.  FERC, consequently, cannot order any of the replacement rates contemplated by parties seeking a change in the PJM Tariff solely on the basis of accommodating the type of service they would prefer for co-located load.

FERC action to the contrary would amount to an issue under the major questions doctrine. If Congress wanted to give FERC authority to order its preferred transmission service to benefit certain customers, it could have done so.42  It did not.  “Agencies have only those powers given to them by Congress, and ‘enabling legislation’ is generally not an ‘open book to which the agency [may] add pages and change the plot line.’”43  Not only does the Commission not have any authority to require a new type of transmission service to accommodate co-located load under the FPA, but any attempt by the Commission to set a replacement rate that would be a means to accommodate a narrow category of customers, such as co-located load, would run contrary to the declaration in the FPA that rates that provide an undue preference or advantage are unlawful. Specifically, FPA section 205(b) states that “[n]o public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or

42  Cf. Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”). 43  West Virginia v. EPA, 142 597 U.S. 697, 735 (2022); see also Midship Pipeline Co., L.L.C. v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly” (quoting West Virginia v. EPA, 597 U.S. at 723)).

PDF page 15

15

disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”44 Finally, any suggestion the existing PJM Tariff is unduly discriminatory45 or preferential falls flat because the same service is offered to all customers and co-located loads can move forward using the existing PJM Tariff approach.

II. There Is No Inconsistency in the Indicated TOs’ Jurisdictional Position.
Talen asserts that “the Utilities have sought to extract two holdings from the Commission:
(1) that co-located load always takes a form of FERC-jurisdictional transmission service and (2) that the interconnection of co-located load is not FERC jurisdictional.”46  Talen goes on to state that in “Exelon’s pending [petition for declaratory order] Proceeding (EL24-149), the Utilities have argued that the interconnection of end-use load is not FERC jurisdictional, supposedly because the interconnection procedures implemented by Order No. 2003 apply only to generation and not to load.”47  Talen then questions whether the utilities’ jurisdictional position is consistent within the various proceedings dealing with co-location.48  It is fully consistent.  It is the Network Service customer that is taking FERC-jurisdictional transmission service in serving the co-located load.  That is typically an LSE, but if a state allows, it may be the load itself.  The interconnection

44  16 U.S.C. § 824d(b).
45  See, e.g., Vistra Comments at 5 (Apr. 23, 2025) (claiming that “PJM has recently been implementing, and continues to implement, its tariff in an unduly discriminatory or preferential manner” and that more clarity is needed for “the rates, terms, and conditions of service associated with behind-the-meter co-location arrangements”).
46  Talen Comments at 5 (Apr. 23, 2025).
47  Id. at 8 .
48  See id. at 8 (stating that it is “odd” for “the Utilities to argue in one proceeding that FERC lacks jurisdiction over co-located load, only to turn on a dime and argue in numerous other proceedings that FERC does have jurisdiction over co-located load and should leverage that jurisdiction to approve tariff proposals that would treat co-located load as always taking FERC-jurisdictional transmission service”).

PDF page 16

16

of end-use load is not jurisdictional to FERC.  Rather, the transmission service provided by the interstate grid to the LSE is FERC-jurisdictional.

Constellation also claims that “the PJM Tariff is being interpreted in such a way as to preclude states from exercising their jurisdictional authority” and asserts that by requiring co- located load to take Network Service, “that all sales to co-located load (which is by design an end user) . . . would become subject to wholesale transmission rates,” which Constellation submits is inconsistent with the Commission’s jurisdiction.49  There is no inconsistency.  And, nothing the Indicated TOs argue suggests that service to retail load is FERC-jurisdictional.  It really is quite simple: if there is a connection to the interstate electric grid in PJM, then there is a reliance on the interstate transmission services and that service is FERC-jurisdictional.

III. The Different Treatment of BTMG and Behind-The-Meter Load Does Not Render the PJM Tariff Unjust and Unreasonable.

As an initial matter, BTMG is not similarly situated to behind-the-meter load.
Constellation states that the Indicated TOs’ position is “that anything ‘synchronized’ to the grid must take [Network Service] for their gross load and that [Network service] charges based on gross load regardless of configuration are just and reasonable” and that this position overlooks that “there already are tens of thousands of MWs of load synchronized to the grid who do not pay [Network service] based on gross billing determinants.”50  To support this statement, Constellation points to the Public Service Electric and Gas response, which describes customer reliance on BTMG.  As explained in the Indicated TOs’ prior answer, however, BTMG is different than co-located load.51

49  Constellation Answer at 27 (Apr. 23, 2025).
50  Constellation Answer at 29 (Apr. 23, 2025).
51  Indicated TOs Answer at 5–9 (Apr. 23, 2025).

PDF page 17

17
BTMG is already accounted for in the PJM Tariff, which has specific provisions on BTMG.52  This proceeding concerns behind the meter load—a different paradigm in which load is located behind a meter and avoids taking Network Service yet benefits from the services provided by the network. Although PJM plainly states that BTMG was “not intended” for large loads,53 Vistra tries to present netting as a solution for co-located load.54  Specifically, Vistra states that, under the BTMG netting framework,

[R]etail BTMG loads are currently able to avoid transmission
charges by using on-site generation or curtailing load during
expected coincident peak events.  In doing so, these loads are
permitted to net their usage of NITS to zero.  If Option 3 loads are
permitted to net in this way, it is unduly discriminatory to prohibit
behind-the-meter loads from engaging in exactly the same type of
netting.  In fact, Option 4 configurations actually use the
transmission system less than a retail BTMG configuration because
protective systems ensure that the load never draws energy from the
grid, whereas retail BTMG arrangements can draw from the grid at
the discretion of the customer.55
The PJM Tariff states, in pertinent part, that BTMG “shall refer to a generation unit that delivers energy to load without using the Transmission System.”  Unlike this definition of BTMG, co- located load arrangements use and rely upon the transmission system and therefore cannot qualify as BTMG under the PJM Tariff.  Service to co-located load using generators connected to the transmission system inherently both use and rely on the transmission system.

52 PJM OATT §§ 1 (Definition of Behind the Meter Generation), 34.2 (Netting of Behind the Meter Generation), 34.3 (Netting of Non-retail Behind the Meter Generation), and 36.1A (Behind the Meter Generation).
53 PJM Answer at 11, 76.
54 Vistra Comments at 14 (Apr. 23, 2025).
55 Id.

PDF page 18

18

IV. The Fact that Co-location Arrangements Employing Network Service Take Time Does Not Mean that the PJM Tariff Provisions for Transmission Service are Unjust and

Unreasonable.

Constellation argues that the Indicated TOs “omit the elephant in the room: it takes at least four to five years, and often seven to ten years, to complete the study process and build all the transmission upgrades necessary to provide [Network Service] to a hyperscale data center.”56 Specifically, Constellation asserts that if it is “start[ed] today, a large data center might be able to obtain service by 2030, but more likely not before 2035.”57  Omitted from this vague accusation is any explanation of how this is the fault of the existing PJM Tariff.  Nor will creating a new class of transmission service change that.  Rather, Constellation’s effort to create different reliability rules for co-located loads—perhaps pretending that problems do not exist because load is hidden behind the meter—would be unduly discriminatory to other system additions and also jeopardize system reliability.  If an interconnection creates reliability concerns requiring upgrades, the siting, design, and construction of those upgrades will reasonably take time.58  As discussed below, Constellation has consistently sought to minimize reliability concerns around co-location.  The reality is that studies have a critical purpose and circumventing them based on the fiction that co- located load cannot impact the system is not something FERC should entertain.

V. Replacement Rates that Would Not Require Network Service for Co-located Load
Could Put Grid Reliability at Risk.

Constellation minimizes the reliability concerns that would attend its proposed co-located load arrangement and states that “the necessary study process provides transparency and

56  Constellation Answer at 15 (Apr. 23, 2025). 57  Id.
58  AEP Ohio’s efforts in this regard, referenced by Constellation in its April 23, 2025 Answer at 18, footnote 49, are appropriate and necessary regardless of the litigation concerning cost allocation in this and other proceedings.

PDF page 19

19

predictability into the development of co-location arrangements.”59  As the Indicated TOs explained in their prior answer, however, when co-located load is hidden and not appropriately accounted for, there is not only a cost-allocation problem, but the study process is undermined.60 In comments in this docket, North American Electric Reliability Corporation (“NERC”) underscored some of the reliability risks: (1) “system operators may lack sufficient information to perform reliability analysis on co-located large loads”; (2) “large loads may or may not be visible to system operators depending on the load’s operation and interconnection type”; (3) “[i]f a load is connected but operating conditions are providing only partial or no generation, there is a risk of thermal overloads and voltage or stability issues”; and (4) “[f]luctuations from large loads during faults or switching can cause issues with voltage support, frequency response, stability, and protection system coordination.”61

Vistra asserts that the co-location configurations do not appear overnight and lists out the steps that would be taken that would add time to when the co-located load appears on the grid.62 The fact that these configurations take time does not at all change the fact that reliability is at risk should these configurations be treated as entities such as Vistra would prefer.  Again, when co- located load is hidden and not appropriately accounted for, a cost-allocation problem exists and the study process is undermined.  PJM may be unable to adequately procure enough capacity to serve the load because the full load will not be accounted for in the Reliability Pricing Model.  Nor

59  Constellation Answer at 47 (Apr. 23, 2025).
60  Indicated TOs Answer at 13 (Apr. 23, 2025).
61  NERC Comments at 7 (Apr. 23, 2025).
62  Id.

PDF page 20

20

would the full load be reliably and safely factored into both PJM’s transmission planning and operations processes and protocols.

Moreover, as explained in the Powers Declaration, a discounted marginal cost approach is not an appropriate replacement rate for co-located load.63  Under the existing PJM Tariff, system costs are charged to all other customers on a full embedded cost basis, independent of the marginal cost each individual customer imposes on the system and without any discount.64  The full embedded cost approach for the development of transmission rates, which is applied to all customers, including co-located customers, ensures that the PJM Tariff is not unduly discriminatory and, for that reason, should be maintained.65  Any rate discounts to a favored class of customers (i.e., co-located load) would be unduly discriminatory against existing and new load that does not fall within the proposed favored class.66  Providing discounted rates to some customers will result in other customers offsetting that discount by paying a yet higher rate.67  Such an approach to rate design (i.e., giving one group of customers a discount and charging a disproportionately higher rate to all other customers) does not comport with the FPA.  And such proposals lose sight of the fact that other customers might likewise be able to make a claim that their incremental system usage, by some metric, is lower than average.68

63  Powers Declaration at P 7.
64  Id.
65  Id.
66  Id. at P 9.  See also id. at PP 25–29 (providing examples and explaining why discounted Network Service rates for co-location arrangements would be inappropriate and unduly discriminatory); id. P 31 (“[O]ffering a discounted rate to co-located load while requiring other load customers to pay the full transmission rate contravenes the Bonbright principle of Fairness in Cost Allocation, which holds that costs should be allocated equitably and without undue discrimination among customer classes or individuals.”).
67  Id. P 32.
68  Id.

PDF page 21

21
Nor does creating a favored rate treatment for co-located load comport with NERC’s Reliability Standards.  Specifically, allowing certain transmission customers with bundled load and generation to choose their own level of transmission service, especially outside of NITS, as Constellation proposes, would represent a significant departure from NERC Reliability Standards FAC-002-2 and TPL-001-5 and would undercut transmission operators’ planning criteria and interconnection requirements that are in place to comply with those NERC requirements.69  The result would be reduced scrutiny of load, mismanagement of the transmission system, risks to reliability, and undue discrimination for other customers that take Network Service. It is also worth reiterating that, as explained in the Powers Declaration, “the interconnection of load and generation are studied separately in accordance with [NERC Reliability Standards] to ensure that the impact of a new generator on the transmission system is fully assessed, and any new load is able to be reliably served by the power system,” and therefore, any suggestion that a single study would suffice under the PJM Tariff to assess reliability impacts on an interconnection with hidden co-located load is based on a misunderstanding of the current PJM Tariff requirements.70

VI. PJM’s Options 4 and 5 Have Not Been Demonstrated to Be Just and Reasonable. As stated above, the Indicated TOs emphasize that the first step of FPA section 206 has not been satisfied and, for that reason, there is no basis to set a replacement rate.  And as the Indicated TOs explained in their April 23 Answer, the options presented by PJM are unnecessary to resolve this Show Cause proceeding.71  It is worth spending a moment on PJM’s Options 4 and 5, for

69  See Powers Declaration at PP 10–13.
70  Id. at P 5.
71  See Indicated TOs Answer at 9–12 (Apr. 23, 2025).

PDF page 22

22

which some parties are advocating.72  Options 4 and 5 are not preferred by PJM, will have a negative impact on reliability, and, most importantly, have not been demonstrated to be just and reasonable in this proceeding.  Rather, such arrangements should be treated as Network Load. First, Option 4—“Co-located load with connection to the grid with protections to avoid delivery of system energy to serve the load”—should be Network Load because it “relies on and takes grid services.”73  The load, then, is appropriately charged as Network Load because it uses wholesale transmission service.  Option 5 is identical to Option 4 “but with back-up service from PJM with permission,”74 so it too should be treated as Network Load.  This underscores that the PJM Tariff remains just and reasonable because PJM’s existing mechanisms for serving Network Load accommodate co-located loads.75

In arguing for the adoption of Options 4 and 5 as new types of service, Vistra states that “requiring all new large loads to interconnect through Options 1 or 2 increases transmission costs for consumers and creates a structural bias in favor of transmission-served load while disadvantaging competitive bilateral supply arrangements between sophisticated buyers and MBR sellers.”76  Vistra claims that Options 4 and 5 would “decreas[e] costs and enhanc[e] reliability.”77 To the extent that co-located load would be permitted to rely on wholesale transmission service, to circumvent the planning process by being hidden from the system, and to avoid costs that are applied to every other customer on the system, it cannot be said that those options would provide

72  See, e.g., Vistra Comments at 8 (Apr. 23, 2025).
73  PJM Answer at 13–14. 74  Id. at 14–15.
75  See Indicated TOs Answer at 11–12 (Apr. 23, 2025).
76  Vistra Comments at 13 (Apr. 23, 2025).
77  Id.

PDF page 23

23

decreased costs and enhanced reliability.  To the contrary, it would permit the avoidance of costs, the preferential and discriminatory treatment of customers, and significant risks to reliability of PJM’s electric grid.

Vistra seeks several revisions to the PJM Tariff to implement a replacement rate based on Options 4 and 5.  Specifically, Vistra asks the Commission,

(1) to require transmission owners to cooperate in the necessary
study process, (2) determine the transmission and ancillary service
charges that are appropriate for behind-the-meter co-located load,
(3) incorporate surgical revisions to the pro forma ISA to address
co-located load, and (4) develop a reasonable policy on the capacity
treatment of secondary generators that only serve co-located load
occasionally on an interruptible, backup basis.78

None of these changes are required.  Nor have they been shown to be just and reasonable.  First, the Commission cannot require transmission owners to participate in a study process as a prerequisite to interconnecting load, which is not FERC jurisdictional and, therefore, not subject to the PJM Tariff.  Second, for the reasons stated above, it is not appropriate to allow a unique form of service for co-located load in this proceeding because it would provide an undue advantage and preferential rate treatment because the “assessment of [Network Integration Transmission Service] is not based on actual use over a particular transmission path, but rather based on the network customer’s right to use the entire system.”79  Third, the request for a policy on the capacity treatment of secondary generators that only serve co-located load occasionally on an interruptible, backup basis is outside of the scope of this proceeding and there has not been any showing that the capacity treatment in the existing PJM Tariff is unjust and unreasonable.

78  Id. at 23.
79  Nat’l R.R. Passenger Corp., 173 FERC ¶ 61,043 at PP 13–14 (2020).

PDF page 24

24

VII. The Commission Should Reaffirm that the Existing PJM Tariff Is Just and
Reasonable to Remove Uncertainty and Should Dismiss this FPA Section 206
Proceeding.

This proceeding has fueled fire to misguided claims and uncertainty in the application of the PJM Tariff.  One such claim is that “co-location of large loads and generation facilities is not a new phenomenon in the PJM region.”80  FERC, though, acts through its orders and has never blessed a treatment of load that ignores its impact on the grid.81  Even still, Vistra goes on to state that “PJM’s own filings over the past few years—including as recently as last month— demonstrate, PJM has repeatedly applied the tariff’s necessary study provisions to facilitate behind-the-meter co-location configurations.”82  To support this, Vistra cites to the Doswell Necessary Studies Agreement (“NSA”).83  But, as the Commission explained in P 34 of that order, it was not ruling on the propriety of any arrangement, but was simply allowing PJM to conduct a study, while the proceeding plays out.

Ultimately, all concerned will benefit from a dose of clarity, if the Commission affirms that service to end-use customers, even if they are large load customers, falls under state jurisdiction. These customers are indisputably taking retail electric service, which is carved out from FERC’s jurisdiction.84  But transmission service to the Load Serving Entity is in turn governed by the

80  Vistra Comments at 3 (Apr. 23, 2025).
81  See, e.g., Californians for Renewable Energy v. Cal. Indep. Sys. Operator Corp., 175 FERC ¶ 61,213 at P 13 (2021) (“The Commission speaks through, and only through, its orders.” (emphasis added)).
82  Vistra Comments at 4 (Apr. 23, 2025).
83  Id. at 4 n. 10 (citing PJM Interconnection, L.L.C., Necessary Studies Agreement, Original Service Agreement No. 7476, Queue Position No. AA1-145, Docket No. ER25-1623-000, at Attach. 1 (filed Mar. 14, 2025)).
84  See Powers Declaration at P 20; see also 16 U.S.C. § 824(b)(1) (“The provisions of this subchapter shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce, but except as provided in paragraph (2) shall not apply to any other sale of electric energy . . . .” ).

PDF page 25

25

existing PJM Tariff rules relating to Network Service.  That divide is well-functioning, and just and reasonable.  There is no basis for those rules to change.

VIII. Motion for Leave to Answer
Although an answer to an answer is not permitted as a matter of right under the
Commission’s regulations,85 the Commission routinely permits such answers when the answer provides useful and relevant information that will assist the Commission in its decision-making process,86 corrects factual inaccuracies and clarifies the issues,87 assures a complete record in the proceeding,88 or provides information helpful to the disposition of an issue.89  The information set forth in this answer satisfies each of these criteria.  The Indicated TOs therefore respectfully request that the Commission grant leave and accept this answer.

IX. Conclusion
For the reasons stated above, and in the prior comments and answers of the Indicated TOs, the Commission should terminate this show cause proceeding, affirming that the existing PJM Tariff, and existing transmission service categories remain just and reasonable.

85  18 C.F.R. § 385.213(a)(2).
86  See, e.g., Pioneer Transmission, LLC v. N. Ind. Pub. Serv. Co., 140 FERC ¶ 61,057 at P 94 (2012) (accepting answers that “provided information that assisted us in our decision-making process”); Tallgrass Transmission, LLC, 125 FERC ¶ 61,248 at P 26 (2008) (same), order on reh’g, 150 FERC ¶ 61,224 (2015); Midwest Indep. Transmission Sys. Operator, Inc., 120 FERC ¶ 61,083 at P 23 (2007) (permitting answer to protests when it provided information that assisted the Commission in its decision-making process).
87  See, e.g., Entergy Servs., Inc., 126 FERC ¶ 61,227 at P 76, order on clarification & reh’g, 127 FERC ¶ 61,225 (2009).
88  See, e.g., Pac. Interstate Transmission Co., 85 FERC ¶ 61,378, at 62,443 (1998), order on reh’g, 89 FERC ¶ 61,246 (1999); see also Morgan Stanley Cap. Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017 at 61,036 (2000) (accepting an answer that was “helpful in the development of the record”).
89  See, e.g., CNG Transmission Corp., 89 FERC ¶ 61,100 at 61,287 n.11 (1999).

PDF page 26

26

Respectfully submitted,

/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Max Minzner

Max Minzner
Vice President and Deputy General Counsel Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com

On behalf of Exelon Corporation

/s/ Jessica Cano
Jessica Cano
Associate General Counsel – Regulatory East American Electric Power Service Corporation 1 Riverside Plaza

Columbus, OH 43215
Telephone: 614-716-2921
Email: jacano@aep.com

/s/ Lisa G. McAlister
Lisa G. McAlister
AMP Transmission, LLC
1111 Schrock Road, Suite 100
Columbus, Ohio 43229
Telephone: 614-540-6400
Email: lmcalister@amppartners.org

On behalf of American Electric Power Service Corporation

On behalf of AMP Transmission, LLC

/s/ Martin J. Keane
Martin J. Keane
Director of Public Utilities
Cleveland Public Power
1300 Lakeside Ave.
Cleveland, OH 44114
Telephone: 216-664-2444 ext. 75604
Email: martin_keane@clevelandwater.com

/s/Debra D. Roby
Debra D. Roby
Washington Energy Law LLP
900 17th Street N.W., Suite 500-A
Washington, D.C. 20006
Telephone: 703-785-9270
Email: droby@washingtonenergylaw.com

On behalf of City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power

On behalf of the City of Hamilton, OH

PDF page 27

27
/s/ Damon L. Krieger
Damon L. Krieger
Group Vice President, Legal, Strategy, and Sustainability, and Deputy General Counsel Southern Maryland Electric Cooperative, Inc. 15035 Burnt Store Road

P.O. Box 1937
Hughesville, Maryland 20637-1937
Telephone: 301-274-4323
Email: Damon.Krieger@SMECO.coop
/s/ Molly Suda
Molly Suda
Associate General Counsel
Annelise Rickert
Federal Government Affairs Director Duke Energy Corporation

1301 Pennsylvania Ave NW, Suite 200 Washington, DC 20004

Telephone: 202-824-8011
Email:  molly.suda@duke-energy.com Annelise.rickert@duke-energy.com

On behalf of Southern Maryland Electric Cooperative

On behalf of Duke Energy
/s/ Michael Brechlin
Michael Brechlin
PA Bar # 335424
Duquesne Light Company
411 7th Ave
Pittsburgh, PA 15219
Telephone: 412-393-6431
Email: mbrechlin@duqlight.com
/s/   Amanda P. Parker
Amanda P. Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OH 44308
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com On behalf of Duquesne Light Company On behalf of The FirstEnergy Transmission Companies

/s/ Denise R. Foster Cronin
Denise R. Foster Cronin
Vice President, Federal and RTO Regulatory Affairs

East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707

Winchester, KY 40392-0707
Telephone: 859-745-9615
Email: denise.cronin@ekpc.coop
/s/ Daniel E. Frank
Daniel E. Frank
Kelly Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Telephone: 202-383-0100
Email:
danielfrank@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com On Behalf of East Kentucky Power

Cooperative, Inc.

PDF page 28

28

/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C.  20006-1167
Telephone: 202-585-6900
Email: aclair@thompsoncoburn.com

/s/ Steve Nadel
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Telephone: 610-774-4775
Email: SMNadel@pplweb.com

On behalf of Old Dominion Electric Cooperative

On behalf of PPL Electric Utilities Corp.

/s/David Burns
David Burns
Senior Manager,
FERC Policy & Regulatory Affairs
Consolidated Edison Company of New York, Inc.

4 Irving Place
New York, NY 10003
Telephone: 571-678-9152
Email: burnsd@coned.com
/s/Joshua Kirstein
Joshua A. Kirstein
Senior Attorney
Law Department
Consolidated Edison Company of New York, Inc.

4 Irving Place, 18th Floor
New York, NY 10003
Telephone: 929-656-5971
Email: kirsteinj@coned.com

On behalf of Rockland Electric Company

/s/ Lindsay Berkstresser
Lindsay Berkstresser
Counsel – Energy & Regulatory
UGI Corporation
500 North Gulph Road
King of Prussia, PA 19406
Telephone: 717-504-9925
Email: berkstresserl@ugicorp.com

/s/ Richard P. Bonnifield
Richard P. Bonnifield
Husch Blackwell
1801 Pennsylvania Avenue, NW,
Suite 1000
Washington, DC 20006-3606
Telephone: 202-243-8844
Email:
richard.bonnifield@huschblackwell.com

On behalf of UGI Utilities Inc.

PDF page 29

29

/s/ Jeremy L. Fetty

Jeremy L. Fetty
Parr Richey
251 N. Illinois, Suite 1800
Indianapolis, Indiana 46204
Telephone: 317-269-2500
Email: j_fetty@wvpa.com

On behalf of Wabash Valley Power
Association, Inc.

June 3, 2025

PDF page 30

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al
)
Docket Nos. EL25-49-000
Large Loads Co-Located at Generating
Facilities
)
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
Docket No. EL25-20-000
(Consolidated)

DECLARATION OF DANIELLE S. POWERS

I. INTRODUCTION
1. My name is Danielle S. Powers. I am an engineer and Chief Executive Officer of Concentric Energy Advisors, Inc. (“Concentric”). My business address is 293 Boston Post Road West Suite 500, Marlborough, MA 01752.

2. I have over thirty-five years of direct experience in the public utility industry. I have worked for an investor-owned utility, an independent system operator, and most recently as a consultant. I have managed and/or participated in a wide variety of consulting engagements as an expert in wholesale market design and power system operations, as well as resource planning. I have provided expert testimony or reports before the Indiana Utility Regulatory Commission, the Federal Energy Regulatory Commission (“FERC”), the Illinois Commerce Commission, the Connecticut Siting Council, the Massachusetts District Court, the Regulatory Commission of Alaska, the New York Public

PDF page 31

2
Service Commission, the United States Bankruptcy Court, the Missouri House Utilities Committee, and the Indiana Senate Utilities Committee. My previous testimony has typically addressed issues related to wholesale energy market design, transmission policy, and resource planning.

3. In these proceedings, FERC directed PJM Interconnection, L.L.C. (“PJM”) and the Transmission Owners (“TOs”) to demonstrate why the PJM Open Access Transmission Tariff (“OATT”), the Amended and Restated Operating Agreement of PJM, and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (the “Tariff”) remain just and reasonable with respect to their applicability to co-location arrangements, and to explain what changes to the Tariff would remedy the concerns identified by FERC if it were to determine that the Tariff requires a replacement Tariff.

4. In the Testimony of Zachary Ming, Mr. Ming, a Partner at Energy and Environmental Economics, Inc. (“E3”) testifying on behalf of Constellation Energy Generation, LLC (“Constellation”), puts forth new tariff options for three different co-location configurations: firm, generator-contingent, and interruptible. Mr. Ming’s proposed rate options (the “E3 Proposal”) are based on his analysis of rate design principles with respect to the Tariff and his analysis of the interaction of co-location configurations and costs, including transmission costs.

II. SUMMARY
5. The E3 Proposal improperly conflates the interconnection studies for load and supply by suggesting that a single study should be conducted that recognizes

PDF page 32

3
the net impact of the addition of both the load and supply while ignoring the unique characteristics of each.  Under the current PJM tariff, and the tariffs of most

other
Independent
System
Operators/Regional
Transmission
Organizations (“ISOs/ RTOs”), the interconnection of load and generation are studied separately in accordance with North American Electric Reliability Corporation (“NERC”) standards to ensure that the impact of a new generator on the transmission system is fully assessed, and any new load is able to be reliably served by the power system.  The E3 Proposal to net the impacts of the generator and load so that the transmission system is designed to serve the reduced peak demand is inappropriate.

6. As discussed below, large loads create significant risk with respect to system reliability. Any change to the current tariff approach, that would study co- located generation and load purely on a “net” basis, cannot be reasonably considered until NERC completes its development of reliability guidelines for large load interconnection requirements by June 2026.

7. E3’s proposed replacement Network Integration Transmission Service (“NITS”) rate for co-located load reflects a discounted marginal cost approach. However, transmission system costs are charged to all other customers on a full embedded cost basis, independent of the marginal cost each individual customer imposes on the system and without any discount. A full embedded cost approach for the development of transmission rates should be maintained for all customers, including co-located customers. To do otherwise is unduly discriminatory.

PDF page 33

4
8. The E3 Proposal relies on Mr. Ming’s contention that the existing tariff does not provide price signals that incentivize co-located loads to interconnect in an economically efficient manner. Mr. Ming’s reliance on rate design principles, however, is flawed.  In addition, he conflates the manner in which transmission rates provide a price signal in a regulated utility framework with the manner in which PJM’s locational marginal prices (“LMPs”) provide a price signal in PJM’s energy market. Furthermore, Mr. Ming ignores the fact that load entities already have strong financial incentives to minimize total costs under the existing tariff. Finally, Mr. Ming ignores the fact that the primary motivation for large loads seeking co-location arrangements is not avoidance of transmission costs, but timely interconnection.

9. Ultimately, the E3 Proposal ignores the fact that the current tariff already provides most of what E3 is seeking, other than the rate discounts which are unduly discriminatory against existing load as well as new load not included in the proposed favored class. Under the current tariff, loads that are capable of actually reducing demand at the time of the system peak can do so and thereby achieve a smaller peak coincident load and a lower allocation of costs as network customers. A discount for certain customers only is not justified under this framework and would be unduly discriminatory.

PDF page 34

5
III. E3’s Proposal Does Not Consider Reliability Concerns and Operational Impacts Addressed Through the Interconnection Process.

A. Existing NERC Reliability Standards Ensure the Grid Can Reliably Serve the Full Requirement of the Load Under Both Normal and Contingency Conditions.

10. TOs and Transmission Planners must determine the reliability impact of interconnecting new loads and generation in accordance with NERC Reliability Standards FAC-002-21 and TPL-001-5.2 TOs establish their own planning criteria and interconnection requirements in compliance with these NERC Reliability Standards. They assess the reliability impacts of the full-load requirement across a range of operating conditions. If a new load presents reliability concerns, the TO collaborates with the new load and the ISO to identify and implement appropriate mitigation measures.

11. Allowing certain transmission customers with bundled load and generation to choose their own level of transmission service, especially outside of NITS, would represent a significant departure from these reliability standards. In fact, it would effectively bypass these requirements, introducing new and untested reliability risks. Without formal revisions to NERC’s Reliability Standards, TOs and ISOs are not authorized to operate under the parameters proposed by E3.

12. The NERC Large Load Task Force is currently investigating the implications of large loads interconnecting to the Bulk Power System. This work includes

1
NERC Facilities Design, Connections, and Maintenance Reliability Standards. 2

NERC Transmission Planning Reliability Standards.

PDF page 35

6
evaluating whether and how forecasting, modeling, and interconnection processes could incorporate flexible demand profiles or on-site generation while still ensuring grid reliability.

13. NERC’s study of these issues did not arise in a vacuum. There is growing experience with these new large loads and research into their power demand, and that experience and research suggest large and extreme system impacts. One regional operator, Electric Reliability Council of Texas (“ERCOT”), reported a 300 MW drop in data center demand in 24 seconds, and oscillations of 25 MW repeatedly up and down in under one second, recurring again with 50 MW oscillations three days later.3

14. It is not at all clear that the relay schemes and protection mechanisms that have been proposed by various large loads would protect the grid against such variations in data center demand. The protection schemes appear to be largely focused on dealing with situations where the co-located generation unit has an outage, but the above concerns do not relate to a generation outage and instead relate to rapid variations in demand. Given real concerns about extreme system impacts, adoption of a proposal to permit reduced scrutiny of large loads is contrary to the prioritization of reliability and system security.

15. NERC has committed to developing a reliability guideline by June 2026 that will “identify risk mitigations and improvements to planning and operations

3 ERCOT Large Load Oscillation Event, LFLTF Meeting (stakeholder presentation) (Mar. 4, 2025), https://www.ercot.com/calendar/03042025-LFLTF-Meeting (choose “LL Oscillation_LFLTF_Mar2025_Final” link under “Key Documents”).

PDF page 36

7
for large loads interconnection requirements.”4 At the very least, until NERC’s assessment is complete, it is premature for FERC to approve proposals like E3’s that assume capabilities and standards that do not yet exist.

B. E3’s Proposal Relies on a Flexible Bundled Interconnection Framework that Does Not Exist

16. E3 mapped the eight co-located configurations proposed by PJM into three different co-location configurations:

firm, generator-contingent, and
interruptible. Both the generator-contingent and interruptible options assume that large loads can interconnect to the grid without the need for full transmission service, based on their ability to use large onsite generation or load shedding to offset consumption during peak conditions. For example, according to E3’s Proposal, if a 100-MW load can reduce its draw to 40 MW during the system peak by dispatching on-site generation or potentially by shedding a portion of its load, the grid should only be planned to serve the net 40 MW load. This implies a flexible interconnection regime analogous to ERCOT’s “Connect and Manage” construct used for generation.  However, no such flexible interconnection framework currently exists for load nor for bundled load and generation anywhere in North America.

17. In considering the interconnection study to be performed for the co-located generation and load, it is instructive to contemplate the circumstance where a new generator is proposed near a large load but not formally “co-located” with that large load.  For this example, consider an aluminum smelter, which is a

4 Comments of the North American Electric Reliability Corporation at 6 (Apr. 23, 2025).

PDF page 37

8
large electrical industrial load, and assume it is in a relatively import- constrained area. In this example, the industrial load and the new generator are not co-located behind a meter point; they are physically adjacent but they are owned by different entities and have no contractual relationship.

18. In evaluating the interconnection of this hypothetical new generator, the ISO/RTO and TO will recognize the import constraint as well as the industrial load, and the analysis will account for the fact that operation of this new generator will reduce congestion on the constraint. Because of this, the interconnection requirements will generally be minimal, aside from potential secondary issues such as short circuit duty or voltage control. The proposed generator would be required to fund transmission modifications to address these issues, a point conceded in the Ming testimony,5 but otherwise the interconnection requirements are likely to be significantly less than would be the case if it were interconnected outside the import constraint.

19. Nothing changes from a reliability or electrical interconnection standpoint if this hypothetical new generator were to agree to formally co-locate with the industrial load inside the load pocket. The electrical and operational characteristics of the load and the generator are unchanged, the interconnection analysis must still account for the specific characteristics of each, and the interconnection requirement will be the same. The metering point makes no difference. Both the generator and the load do benefit from

5 See Answer of Constellation Energy Generation, LLC, at Ex. 2, Testimony of Zachery Ming, at 27:16–19 (Apr. 23, 2025).

PDF page 38

9
physically locating close together, but nothing about the contractual arrangement between the parties changes the physics of the system. Therefore, the interconnection study, the required reinforcements, and the interconnection cost are all the same whether the generation and load are contractually co-located or not.

20. Importantly, interconnection of large load customers falls under state jurisdiction because it involves the provision of retail electric service, which is not regulated by FERC. When a large load, such as a data center, seeks to interconnect to the electric grid, it does so as a retail customer of the local utility, like any other load. The interconnection process, applicable rates, and service classifications are governed by the state-approved retail tariff, which establishes the rights and obligations of both the customer and the utility. This includes determinations about interconnection requirements and whether special rate treatment, such as generator-contingent or interruptible service, is available.

C. Many Types of Large Load Have Not, Cannot, or Will Not Sign Up for these Types of Contractual Co-location Arrangements.

21. It is important to note that a substantial amount of large load has already been added to the PJM grid under the existing interconnection rules. These loads have been studied and planned as Network Loads. They are paying for transmission costs just like any other load that depends on the grid for electric service. Applying a different standard would be inconsistent and unfair to those who have followed the established process.

PDF page 39

10
22. While certain types of large loads—such as crypto mining operations—may offer meaningful load flexibility due to their ability to curtail or reduce consumption almost instantly with minimal operational impact, other large loads, such as data centers and industrial facilities, may face significant constraints that limit their flexibility.

23. For example, a large load such as a data center arranged as a tenant facility, wherein a number of different tenants contract with the owner of the data center facility, would not necessarily have the same operational characteristics as a large data center owned and operated by a single entity. In a tenant facility, portions of the facility might be able to curtail rapidly, while others might not. The provision of retail service to locations with tenant arrangements that serve customers with varying operational needs is normal. FERC rules that assume that an entire facility can be used one way or another simply do not comport with this reality.

24. Given that the majority of large loads entering the PJM footprint cannot be readily interrupted, these loads would not be suitable for generator- contingent or interruptible service. However, the types of loads capable of rapidly curtailing operation already possess the ability to minimize transmission costs through closely monitoring system conditions and curtailing whenever the system approaches its expected coincident peak. Operating in this manner may significantly reduce transmission charges since transmission costs are allocated based on the load contribution to system coincident peaks.

PDF page 40

11
IV. Role of a “Marginal Cost Discount” in Embedded Cost Ratemaking
25. E3 references rate design principles established by Bonbright, among which is the idea that rates should be non-discriminatory.6 At the same time, E3 proposes the use of marginal-cost discounted rate design for a specific class of customers while other similar transmission service customers would be charged rates that would continue to be based on full embedded costs. The application of E3’s rate design concepts leads to inequitable treatment of customer classes that is unduly discriminatory. For example, E3’s proposed treatment of customers taking “generator-contingent” service includes the idea that these customers should benefit from co-located generation to pay a discounted NITS rate for transmission service.

26. E3 proposes that the full NITS rate applies for firm interconnection service.  However, for the other service options, contingent and interruptible, E3 is proposing a discount from the full NITS rate, which seems to reflect an avoided cost concept. The calculation starts with use of the net present value of the ten-year Regional Transmission Expansion Plan (“RTEP”) incremental investment forecast. While PJM and every other RTO attempt to develop accurate forecasts, no RTO has come close to accurately forecasting transmission expansion costs and, in most cases to date, their forecasts have been substantially lower than their observed actuals.

6 See Answer of Constellation Energy Generation, LLC, at Ex. 2, Testimony of Zachary Ming, at 9:14–15.

PDF page 41

12
27. E3 then proposes to assume that only 50% of the projected incremental investment is due to load growth, so the projected marginal cost used in calculating the rate discount is only half of the projected incremental investment.  No basis is given for the use of 50%, and while some other percentage could be used, any such number would be pure speculation over a ten-year forecast period. Using E3’s example numbers, the NITS rate is $63/kW-year while the incremental investment (without the 50% load growth discount) is $52/kW-year. The 50% reduction brings this to $26/kW- year, which is how E3 generates what they refer to as a 41% discount factor to be applied to the NITS rate. None of these numbers has any basis in fact, and ultimately there is no basis in using this discount or any other discount for “as available” or interruptible transmission service. Use of the transmission system to deliver power is a use of the system, regardless of whether that use is firm, contingent, or interruptible.7

28. E3 applies the “as-available” concept only to its proposed interconnection arrangements. The “as-available” concept depends on the idea that “as- available” energy purchases do not impose any costs on the transmission system while at the same time, as stated in the Ming testimony, “withdrawing energy from the transmission system clearly reflects a ‘use’ of the transmission system.”8 Setting aside an analysis of the methodology employed by E3, the

7 See Answer of Constellation Energy Generation, LLC, at Ex. 2, Testimony of Zachary Ming, at 38:1–39:12.
8 See Answer of Constellation Energy Generation, LLC, at Ex. 2, Testimony of Zachary Ming, at 37:9–16.

PDF page 42

13
concept of “use” proposed by E3, which is the basis of the development of the “as-available” charge, is predicated on the novel idea that a charge representing a service for which there is supposedly no incremental cost should be developed on a discounted basis and applied to a limited number of customers. This disparate treatment of customer classes is unduly discriminatory.

29. The discriminatory nature of this proposal is apparent when considering otherwise similarly situated loads. For example, a ski resort operates only in winter and runs its snow guns at night. A large greenhouse also operates its lighting at night. Even though these transmission customers may or may not be firm loads, they pay the same NITS rate for transmission service that is paid by a large high load factor industrial load. However, these customers likely pay only de minimis transmission charges because most of their load occurs during off peak times. They do not impose incremental load on the transmission system and they pay the full NITS rate for whatever transmission service they do use, but because transmission charges are allocated based on contribution to coincident peak, their charges are minimized.  No additional rate discount is needed or applied. The fact that a data center with co-located generation is much larger is irrelevant to the discussion of discrimination, and discounted NITS rates for co-location are inappropriate and unduly discriminatory.

PDF page 43

14
V. Price Signals through NITS Are Neither Appropriate Nor Required to Incent Economically Efficient Siting Decisions.

A. Bonbright Rate Design Principles Do Not Support Price Signaling for Specific Commercial Arrangements.

30. E3 contends that the proposed rate designs are consistent with the Bonbright principles and are therefore just and reasonable. However, the use of price signals—specifically, a discounted transmission rate—to facilitate commercial arrangements such as a co-located business model is not among Bonbright’s criteria for sound rate design.

31. As explained previously, offering a discounted rate to co-located load while requiring other load customers to pay the full transmission rate contravenes the Bonbright principle of Fairness in Cost Allocation, which holds that costs should be allocated equitably and without undue discrimination among customer classes or individuals.

32. E3’s proposal to send price signals to facilitate the co-located business model alone, while charging undiscounted rates to all other customer classes, is misaligned with sound rate design principles. Indeed, if some customers pay discounted rates, other customers will have to make up that slack (the amount not paid on account of the discounts) by paying a yet higher rate. The Indicated PJM Transmission Owners have previously documented, in this proceeding, the material existence of unduly discriminatory cost shifting that would attend to such proposals.9 It is not sound rate design to give one group of customers a discount and charge a disproportionately high rate to all other customers, even

9 See Answer of the Indicated PJM Transmission Owners at 19 (Mar. 24, 2025).

PDF page 44

15
though many customers might be able to make a claim that their incremental system usage, by some metric, is lower than average.

B. Transmission Rates Differ Fundamentally from PJM’s LMPs.
33. E3 attempts to justify its price signal rationale by drawing a parallel to PJM’s energy market.10 However, this comparison is flawed—PJM’s energy market is in a competitive framework, whereas transmission is part of a regulated utility framework. Applying market-based pricing logic to the pricing framework of a regulated transmission system misconstrues the role and purpose of transmission rates.

34.  Among other things, the LMP energy market sends short-term price signals that allow market participants to rapidly respond to the changing need for energy. The transmission grid, however, is a fixed investment in both the short-term and intermediate-term. When one customer avoids the cost of the transmission grid, it falls to another to pay it.

C. Load Entities Already Have Strong Financial Incentives to Minimize Total Costs

35. E3 contends that without a transmission discount, load has no incentive to co- locate with generation. This is incorrect: load entities seeking interconnection already face strong financial drivers to minimize overall costs, including those associated with transmission upgrades, transmission charges, and energy procurement. Co-location often requires fewer transmission upgrades and reduces energy costs due to lower congestion and losses.

10  Answer of Constellation Energy Generation, LLC, Ex. 2, Testimony of Zachary Ming, at 23 (Apr. 23, 2025).

PDF page 45

16
36. Additionally, data center siting decisions include the consideration of other significant factors such as climate conditions, tax and regulatory incentives, fiber-optic infrastructure, and security. All transmission customers would like to pay less for their service, but billions of dollars are going to be spent on data centers, and the data centers face a broad array of cost drivers. There is no reason to believe that transmission discounts are even a primary driver in that cost portfolio.

D. Transmission Rates Are Not the Primary Driver of Co-location Decisions.
37. As noted by the Data Center Coalition, the main motivation for co-location is access to timely interconnection, not transmission costs. Their statement reads: “co-location of load with generation—whether front-of-the-meter or behind-the-meter—is a pragmatic, common, and commercially legitimate strategy to secure timely access to power as markets grapple with years-long interconnection

queue
backlogs.”11
In
short,
speed-to-power,
not
transmission pricing, is the decisive factor when large load seeks to co-locate with generation. E3’s price signaling through a discounted transmission rate is unnecessary given existing economic incentives and market behavior for co- location decisions.

VI. Conclusion
38. The E3 Proposal put forth by Mr. Ming is untenable. It is premised on a flexible interconnection framework that does not currently exist and is not applicable

11  Comments of the Data Center Coalition at 2 (Apr. 23, 2025).

PDF page 46

17
to the issue at hand. It fails to consider significant reliability and safety concerns presented by the interconnection of large loads such as data centers. These concerns are still being studied. It inappropriately utilizes a marginal cost discount in the design of transmission rates for certain customers only, an approach that is unwarranted and unduly discriminatory. Finally, it relies on an application of rate design principles that is flawed and fails to consider the primary motivation of co-location decisions (i.e., the ability to interconnect quickly).

PDF page 47

VERIFICATION

I declare under penalty of perjury that the foregoing Declaration is true and correct to the best of my information, knowledge, and belief.

Executed this 3rd day of June 2025.

/s/ Danielle S. Powers
Chief Executive Officer, Concentric Energy
Advisors, Inc.

PDF page 48

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated at Chicago, IL this 3rd day of June, 2025.

/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation