Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners to various filings made on and after 04/23/2025
Text extracted from the eLibrary original (SHA-256 4bb94b43218b8ce4…). Download the original from the official source.
Contents · 24 sections
- I. The Standard Under Federal Power Act Section 206 Has Not Been Met.
- A. The Current PJM Tariff Is Just and Reasonable and Not Unduly
- B. There Is No Basis to Change the Existing PJM Tariff to Accommodate Co-
- II. There Is No Inconsistency in the Indicated TOs’ Jurisdictional Position.
- III. The Different Treatment of BTMG and Behind-The-Meter Load Does Not Render the
- IV. The Fact that Co-location Arrangements Employing Network Service Take Time Does
- V. Replacement Rates that Would Not Require Network Service for Co-located Load
- VI. PJM’s Options 4 and 5 Have Not Been Demonstrated to Be Just and Reasonable.
- VII. The Commission Should Reaffirm that the Existing PJM Tariff Is Just and
- VIII. Motion for Leave to Answer
- IX. Conclusion
- I. INTRODUCTION
- II. SUMMARY
- III. E3’s Proposal Does Not Consider Reliability Concerns and Operational Impacts
- A. Existing NERC Reliability Standards Ensure the Grid Can Reliably Serve the
- B. E3’s Proposal Relies on a Flexible Bundled Interconnection Framework that
- C. Many Types of Large Load Have Not, Cannot, or Will Not Sign Up for these
- IV. Role of a “Marginal Cost Discount” in Embedded Cost Ratemaking
- V. Price Signals through NITS Are Neither Appropriate Nor Required to Incent
- A. Bonbright Rate Design Principles Do Not Support Price Signaling for Specific
- B. Transmission Rates Differ Fundamentally from PJM’s LMPs.
- C. Load Entities Already Have Strong Financial Incentives to Minimize Total
- D. Transmission Rates Are Not the Primary Driver of Co-location Decisions.
- VI. Conclusion
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage
I. The Standard Under Federal Power Act Section 206 Has Not Been Met.
printed heading
The Federal Power Act (“FPA”), under section 205, requires “[a]ll rates and charges made, demanded, or received by any public utility for or in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or…Read this passage
A. The Current PJM Tariff Is Just and Reasonable and Not Unduly
printed heading · Topic match: Connecting load and generation
Classification as Network Load accounts for the physical reality that service to the co-located load requires Commission-jurisdictional services from the grid and should pay for those services in the same manner that all other load must pay.Read this passage Filed comments: Connecting load and generation
B. There Is No Basis to Change the Existing PJM Tariff to Accommodate Co-
printed heading · Topic match: Connecting load and generation
Specifically, FPA section 205(b) states that “[n]o public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or 42 Cf.Read this passage Filed comments: Connecting load and generation
II. There Is No Inconsistency in the Indicated TOs’ Jurisdictional Position.
printed heading · Topic match: Connecting load and generation
It is the Network Service customer that is taking FERC-jurisdictional transmission service in serving the co-located load.Read this passage Filed comments: Connecting load and generation
III. The Different Treatment of BTMG and Behind-The-Meter Load Does Not Render the
printed heading · Topic match: Connecting load and generation
Constellation states that the Indicated TOs’ position is “that anything ‘synchronized’ to the grid must take [Network Service] for their gross load and that [Network service] charges based on gross load regardless of configuration are just and reasonable” and that this position overlooks that…Read this passage Filed comments: Connecting load and generation
IV. The Fact that Co-location Arrangements Employing Network Service Take Time Does
printed heading
The Fact that Co-location Arrangements Employing Network Service Take Time Does Not Mean that the PJM Tariff Provisions for Transmission Service are Unjust and Unreasonable.Read this passage
V. Replacement Rates that Would Not Require Network Service for Co-located Load
printed heading · Topic match: Connecting load and generation
Specifically, allowing certain transmission customers with bundled load and generation to choose their own level of transmission service, especially outside of NITS, as Constellation proposes, would represent a significant departure from NERC Reliability Standards FAC-002-2 and TPL-001-5 and would…Read this passage Filed comments: Connecting load and generation
VI. PJM’s Options 4 and 5 Have Not Been Demonstrated to Be Just and Reasonable.
printed heading · Topic match: Connecting load and generation
Specifically, Vistra asks the Commission, (1) to require transmission owners to cooperate in the necessary study process, (2) determine the transmission and ancillary service charges that are appropriate for behind-the-meter co-located load, (3) incorporate surgical revisions to the pro forma ISA…Read this passage Filed comments: Connecting load and generation
VII. The Commission Should Reaffirm that the Existing PJM Tariff Is Just and
printed heading · Topic match: Connecting load and generation
ER25-1623-000, at Attach. 1 (filed Mar. 14, 2025)). 84 See Powers Declaration at P 20; see also 16 U.S.C. § 824(b)(1) (“The provisions of this subchapter shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce,…Read this passage Filed comments: Connecting load and generation
VIII. Motion for Leave to Answer
printed heading
Motion for Leave to Answer Although an answer to an answer is not permitted as a matter of right under the Commission’s regulations,85 the Commission routinely permits such answers when the answer provides useful and relevant information that will assist the Commission in its decision-making…Read this passage
IX. Conclusion
printed heading
Conclusion For the reasons stated above, and in the prior comments and answers of the Indicated TOs, the Commission should terminate this show cause proceeding, affirming that the existing PJM Tariff, and existing transmission service categories remain just and reasonable. 85 18 C.F.R. §…Read this passage
I. INTRODUCTION
printed heading
I am an engineer and Chief Executive Officer of Concentric Energy Advisors, Inc. (“Concentric”).Read this passage
II. SUMMARY
printed heading · Topic match: Connecting load and generation
E3’s proposed replacement Network Integration Transmission Service (“NITS”) rate for co-located load reflects a discounted marginal cost approach.Read this passage Filed comments: Connecting load and generation
III. E3’s Proposal Does Not Consider Reliability Concerns and Operational Impacts
printed heading
E3’s Proposal Does Not Consider Reliability Concerns and Operational Impacts Addressed Through the Interconnection Process.Read this passage
A. Existing NERC Reliability Standards Ensure the Grid Can Reliably Serve the
printed heading
TOs and Transmission Planners must determine the reliability impact of interconnecting new loads and generation in accordance with NERC Reliability Standards FAC-002-21 and TPL-001-5.2 TOs establish their own planning criteria and interconnection requirements in compliance with these NERC…Read this passage
B. E3’s Proposal Relies on a Flexible Bundled Interconnection Framework that
printed heading
The electrical and operational characteristics of the load and the generator are unchanged, the interconnection analysis must still account for the specific characteristics of each, and the interconnection requirement will be the same.Read this passage
C. Many Types of Large Load Have Not, Cannot, or Will Not Sign Up for these
printed heading · Topic match: Retail and wholesale authority
The provision of retail service to locations with tenant arrangements that serve customers with varying operational needs is normal.Read this passage Filed comments: Retail and wholesale authority
IV. Role of a “Marginal Cost Discount” in Embedded Cost Ratemaking
printed heading
E3 proposes that the full NITS rate applies for firm interconnection service.Read this passage
V. Price Signals through NITS Are Neither Appropriate Nor Required to Incent
printed heading
Price Signals through NITS Are Neither Appropriate Nor Required to Incent Economically Efficient Siting Decisions.Read this passage
A. Bonbright Rate Design Principles Do Not Support Price Signaling for Specific
printed heading · Topic match: Cost allocation
As explained previously, offering a discounted rate to co-located load while requiring other load customers to pay the full transmission rate contravenes the Bonbright principle of Fairness in Cost Allocation, which holds that costs should be allocated equitably and without undue discrimination…Read this passage Filed comments: Cost allocation
B. Transmission Rates Differ Fundamentally from PJM’s LMPs.
printed heading
Transmission Rates Differ Fundamentally from PJM’s LMPs. 33.Read this passage
C. Load Entities Already Have Strong Financial Incentives to Minimize Total
printed heading
Load Entities Already Have Strong Financial Incentives to Minimize Total Costs 35.Read this passage
D. Transmission Rates Are Not the Primary Driver of Co-location Decisions.
printed heading
Their statement reads: “co-location of load with generation—whether front-of-the-meter or behind-the-meter—is a pragmatic, common, and commercially legitimate strategy to secure timely access to power as markets grapple with years-long interconnection queue backlogs.”11 In short, speed-to-power,…Read this passage
VI. Conclusion
printed heading
It is premised on a flexible interconnection framework that does not currently exist and is not applicable 11 Comments of the Data Center Coalition at 2 (Apr. 23, 2025). 17 to the issue at hand.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Chicago, IL this 3rd day of June, 2025. /s/ Geneva Kennedy Geneva Kennedy Exelon CorporationRead this passage