EL25-49-000 · 2025-06-12 · Constellation Energy Generation, LLC
Motion for Leave and Answer of Constellation Energy Generation, LLC in response to the Indicated Transmission Owners’ fourth answer, etc
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
MOTION FOR LEAVE AND ANSWER OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation Energy Generation, LLC (“Constellation”) moves for leave and submits this
answer1 in response to the Indicated Transmission Owners’ fourth answer in this proceeding, and the belated claims of their new witness, Danielle S. Powers.2 Nearly every party in this proceeding agrees that the PJM Tariff is unclear and confusing and requires clarification.3 The Indicated Transmission Owners do not contend otherwise. Nor do they offer any evidentiary rebuttal to Constellation’s expert testimony on (1) the critical national interest in expediting the efficient interconnection and co-location of data center loads,4 (2) the lack of any resource adequacy
1 Constellation submits this answer and motion for leave pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213, and respectfully submits there is good cause for the Commission to accept the motion for leave. See Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised[] and will ensure a complete record”).2 See Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners (filed June 3, 2025) (“Indicated TOs’ Fourth Answer”) and Declaration of Danielle S. Powers (“Powers Decl.”), attached thereto; see also Answer of the Indicated PJM Transmission Owners (filed Mar. 24, 2025) (“Indicated TOs First Answer”); Answer of the Indicated PJM Transmission Owners (filed Apr. 23, 2025) (“Indicated TOs’ Second Answer”); Answer of the Indicated PJM Transmission Owners to the Motion to Stay Proceedings at 3-4 (filed May 7, 2025) (“Indicated TOs’ Third Answer”).3 See Motion for Leave and Answer of Constellation Energy Generation, LLC (filed May 8, 2025) (“Constellation’s Second Answer”), at 2-9 (summarizing the parties’ positions on this core point).4 See Answer of Constellation Energy Generation, LLC (filed April 23, 2025) (“Constellation’s First Answer”), Exh. 1, Declaration of Dr. Paul Stockton; see also Exh. 1 hereto, Rebuttal Testimony of Zachary Ming (“Ming Rebuttal”)
PDF page 2
2
concerns caused by co-location versus load growth generally,5 (3) the much higher transmission upgrade costs caused by large loads not locating near generation,6 (4) the use of the transmission system under co-location configurations from an expert electrical engineering perspective and how that use differs from front-of-the-meter configurations,7 and (5) the broad system benefits of the co-location of large loads and generation.8
Instead, several weeks after the deadline for timely filings in this proceeding, based on the schedule outlined by the Commission in its Show Cause Order,9 the Indicated Transmission Owners recently submitted a pleading full of misstatements of the record and a few new but irrelevant arguments. The only accompanying evidence was the Powers Declaration, which purports to respond to the Testimony of Zachary Ming, Constellation’s witness on the rate design issues associated with large loads. Consistent with PJM’s eight co-location configuration options, Mr. Ming advocated for three classes of transmission service for large loads: firm, generator- contingent, and interruptible, with corresponding transmission rates reflecting actual use of the transmission system.10 The objective is to reliably utilize the transmission system most fully at lowest overall cost. Instead of addressing the merits of Constellation’s rate arguments, Ms. Powers misstates the record, makes flawed assumptions, and propounds numerous erroneous arguments.
at 13 (citing Energy and Environmental Economics, Inc. report that “even under a ‘moderate’ data center growth scenario, electric demand could double in [Virginia] over a 25-year period. Under an ‘unconstrained’ scenario, the time to double is reduced to 10 years”).
5 See, e.g., Constellation’s First Answer, Exh. 3, Affidavit of Aaron Patterson.6 Id.7 Id., Exh. 4, Affidavit of Steven Herling (“Herling Aff.”).8 Id., Exh. 5, Affidavit of Michael Kormos (“Kormos Aff.”).9 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”) at P 87 (PJM and the Transmission Owners filings were due 30 days after the Show Cause Order, with responses due 30 days thereafter). The Commission’s process did not provide for Transmission Owners to file their initial expert testimony 103 days after the Show Cause Order. (The Show Cause Order issued on February 20, 2025; the Indicated Transmission Owners filed their initial expert testimony on June 3, 2025—103 days later.)10 Constellation’s First Answer, Exh. 2, Testimony of Zachary Ming (“Ming Testimony”).
PDF page 3
3
To ensure an accurate record, Constellation attaches hereto as Exhibit 1 the Rebuttal Testimony of Zachary Ming.
In addition to Mr. Ming’s rebuttal of Ms. Powers’ declaration, Constellation—rather than responding to points it previously covered—instead offers the following brief clarifications to the record:
First, the Indicated Transmission Owners claim that “[p]arties have lost sight of something throughout the course of this proceeding,” which according to the Indicated Transmission Owners, is that “FERC cannot order a new type of service unless there is a finding that the existing arrangement is unlawful.”11 But it is the Indicated Transmission Owners who appear to “have lost sight” of the detailed explanation in Constellation’s comments—comprising 23 pages, with additional supporting expert testimony—that the existing rate is unjust and unreasonable because it lacks sufficient clarity about the rules for co-location.12 The Indicated Transmission Owners have no answer. Constellation also submitted a separate answer itemizing the positions of every party in this proceeding on this issue, listing the parties supporting the Commission’s preliminary finding that the PJM Tariff does not contain “provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements” and “[t]he absence of such provisions may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations.”13 Indeed, nearly every party in this proceeding agrees that the existing PJM Tariff requires clarification about how to serve large loads.1411 Indicated TOs’ Fourth Answer at 13 (emphasis added).12 Constellation’s First Answer at 13-36 (citing statute, cases, and supporting evidence); see also Ming Testimony at 19-24 (providing expert testimony on the same showing); Ming Rebuttal at 5-6 (repeating showing in initial testimony).13 Constellation’s Second Answer at 2-3; see Show Cause Order at PP 74-75.14 See Constellation’s Second Answer at 2-9.
PDF page 4
4
Second, the Indicated Transmission Owners belatedly trot out the “major questions
doctrine” to argue that the Commission does “not have any authority to require a new type of transmission service” and “cannot order any of the replacement rates contemplated by the
parties.”15 This smacks of desperation. In at least six rounds of prior filings in these proceedings, the Indicated Transmission Owners never previously raised this argument.16 And it is no wonder why: it is meritless. Confirming that existing behind-the-meter generation rules in PJM apply to large loads, and adopting generator-contingent or interruptible forms of transmission service with accompanying rates, is well within the Commission’s statutory authority to ensure just and reasonable and non-discriminatory rates for transmission service, and is far narrower in its scope than, for example, the Commission’s recent transmission reforms in Order No. 1920, let alone Order No. 888.17 Ironically, if any party’s position implicates the “major questions doctrine,” it is the Indicated Transmission Owners’: Congress expressly left to the states jurisdiction over retail power sales, yet the Indicated Transmission Owners ask the Commission to override a state’s choice to allow co-location and direct retail service by mandating that all large loads must be wholesale Network Integrated Transmission Service customers and pay on a gross basis.1815 Indicated TOs’ Fourth Answer at 14 & nn. 42, 43 (citing cases).16 See Indicated TOs’ First, Second, and Third Answers (all failing to raise “major questions” issue); see also Exelon Comments in Opposition to Complaint, Docket No. EL25-20-000 (filed Dec. 12, 2024); Exelon Answer and Motion for Leave to Answer Constellation and Vistra Answers, Docket No. EL25-20-000 (filed Jan. 7, 2025); Comments of David Weaver, PE on Behalf of Exelon (Docket No. AD24-11-000) (all also failing to raise “major questions” issue). 17 See, e.g., Bldg. for the Future Through Elec. Reg’l Transmission Plan. & Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068 (2024), order on reh’g & clarification, Order No. 1920-A, 189 FERC ¶ 61,126 (2024), order on reh’g & clarification, Order No. 1920-B, 191 FERC ¶ 61,026 (2025); Promoting Wholesale Competition Through Open Access Nondiscriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, [Regs. Preambles 1991-1996] FERC STATS. & REGS. ¶ 31,036 (1996), 61 Fed. Reg. 21,540 (1996), order on reh’g, Order No. 888-A, FERC STATS. & REGS. ¶ 31,048 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248, 62 Fed. Reg. 64,688 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., New York v. FERC, 535 U.S. 1 (2002).18 See Constellation’s First Answer at 26-28 (explaining that requiring co-located loads to always take Network Integrated Transmission Service unduly limits state jurisdiction and flexibility contrary to law) (citing cases).
PDF page 5
5
Third, the Indicated Transmission Owners repeat allegations that “BTMG [Behind-the-
Meter Generation] is not similarly situated to behind-the-meter load” because “co-located load arrangements use and rely upon the transmission system and therefore cannot qualify as BTMG.”19 The Indicated Transmission Owners continue to simply assume the premise of this argument
without any expert evidentiary support for the claim. Ms. Powers does not address it. Instead, the Indicated Transmission Owners leave unrebutted the only expert engineering testimony that is in the record on this point by Steven R. Herling, a former Vice President of Planning for PJM with over 30 years’ experience in the operations and planning of the transmission system. He explained that these two configurations (BTMG and co-located loads and generation) can be designed “in exactly the same manner.”20
In addition, the Indicated Transmission Owners’ new diagram purporting to show that the
location of the meter has no effect on the amount of grid services used by a configuration in fact confirms that there is no meaningful difference between BTMG and co-located loads: simply
remove the word “large” throughout the Indicated Transmission Owners’ illustration and the same diagram depicts BTMG.21 As Mr. Ming already testified, “[t]here is no physical, technical, or
19 Indicated TOs’ Fourth Answer at 16-17.20 Constellation’s First Answer, Exh. 4, Affidavit of Steven R. Herling at ¶ 30 (“BTMG arrangements and co-located load arrangements can be designed from an engineering perspective in exactly the same manner. In one, the load is typically greater in magnitude than the generating facility. In the other, the load is typically lesser in magnitude than the generating facility.”); see also id. (“The physics of energy delivery are the same in both arrangements and are not related to contractual arrangements or rate structures.”).21 Indicated TOs’ Fourth Answer at 7 (illustration of “Large” Load Meter Scenarios, depicting a “Large” Load and a “Large” Generator). Note also that the Indicated Transmission Owners’ diagram also fails to depict protective relays—the electrical equipment that does change usage of the transmission grid (meters do not). See Constellation’s First Answer at 46 (showing a generator-contingent (behind-the-meter) configuration with protective relays); see also id. 48-49 (relying on expert engineering testimony to refute the Indicated Transmission Owners’ and others’ unsupported and erroneous assertions that protective relays cannot be relied upon to prevent power flows). The Indicated Transmission Owners and their sponsored witness both repeat these false claims that protective relays cannot work. See Indicated TOs’ Fourth Answer at 9-10; Powers Decl. at ¶ 14 (“It is not at all clear that the relay schemes and protection mechanisms … would protect the grid”). However, Ms. Powers could have, but did not, challenge the testimony of Steven Herling or Michael Kormos, which specifically affirmed the widespread use and efficacy of relay schemes and protection mechanisms in PJM operations and designs. See Herling Aff.at ¶ 23; Kormos Aff. at ¶ 7.
PDF page 6
6
economic reason why a netting construct should apply differently for customers with behind-the- meter generation or co-located generation.”22
Fourth, Indicated Transmission Owners claim that any form of transmission service other than full Network Integrated Transmission Service “would represent a significant departure from NERC Reliability Standards FAC-002-2 and TPL-001-5” and “[t]he result would be reduced scrutiny of load” and “mismanagement of the transmission system,” among other reliability allegations.23 They are incorrect. NERC Reliability Standard FAC-002-2 states that “[e]ach Transmission Planner … shall study the reliability impact of: (i) interconnecting new … electricity end-user Facilities and (ii) materially modifying existing interconnections of generation.”24 No one is advocating that co-located load should be connected without a study. Worse still, unrebutted record evidence shows that some Indicated Transmission Owners are refusing to “work on … requests to co-locate load with … generators at certain facilities,” which appears to be a plain violation of FAC-002-2.25
Ms. Powers, for her part, cites recent load drops in ERCOT as proof that large loads jeopardize reliability.26 But as Mr. Ming testifies, the dropped load in ERCOT was not co-located; it was grid-connected.27 The Indicated Transmission Owners previously raised the same type of
22 Ming Testimony at 55.23 Indicated TOs’ Fourth Answer at 21.24 NERC Reliability Standard FAC-002-2 R1. NERC Reliability Standard TPL-001-5 is about Transmission Planners maintaining system models for performing planning assessments. The Indicated Transmission Owners do not explain how all other potential types of transmission service necessarily violate this Reliability Standard. 25 See Show Cause Order at PP 74-75 (the Commission preliminarily finding that the “absence of [clear co-location] provisions [in the PJM Tariff] may leave entities unable to determine what steps they can or must take to effectuate co-location arrangements of various configurations” and this “raises the potential for undue discrimination or preferential treatment”).26 Powers Decl. at ¶ 13.27 Ming Rebuttal at 17.
PDF page 7
7
reliability concerns about grid-connected large load drops in Virginia.28 It is misleading for the Indicated Transmission Owners to keep repeating claims that co-location jeopardizes reliability but then citing load drops by grid-connected loads. For reasons that Constellation already fully explained, it also is misleading to claim that co-location jeopardizes resource adequacy when co- location has no effect on it whatsoever—load is load that must be served, whether it is co-located or grid-connected.29
CONCLUSION
WHEREFORE, Constellation respectfully requests that the Commission grant leave and accept this answer and adopt its preliminary finding that the PJM Tariff is unjust and unreasonable and unduly discriminatory and preferential because it lacks clear provisions for the treatment of large loads co-located with generation, and this lack of clarity has caused undue discrimination against large loads seeking to co-locate. The Commission should fix replacement rates as set forth in Constellation’s First and Second Answers. The Commission should not order a stakeholder or other process that relies on the good faith and cooperation of the Indicated Transmission Owners to resolve the issues raised in this proceeding.
28 See Constellation’s First Answer at 22 (pointing out that Virginia load drops were of grid-connected load, not co- located load).29 See id. at 58-63 (explaining misplaced resource adequacy concerns).
PDF page 8
8
Respectfully submitted,
/s/ Paul F. Wight
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Paul F. Wight
Kirkland & Ellis LLP
1301 Pennsylvania Ave., NW
Washington, D.C. 20004
(202) 389-3321
paul.wight@kirkland.com
Counsel for Constellation Energy
Generation, LLC
June 12, 2025
PDF page 9
9
CERTIFICATE OF SERVICE
I hereby certify that I have on this 12th day of June, 2025, caused to be served a copy of the foregoing upon all parties on the service list in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2024).
/s/ Mack Dowiak
Mack Dowiak
Kirkland & Ellis LLP
1301 Pennsylvania Ave., N.W.
Washington, D.C. 20004
Tel: (202) 389-3266
mack.dowiak@kirkland.com
PDF page 10
Exhibit 1
Rebuttal Testimony of
Zachary Ming
PDF page 11
Rebuttal Testimony of Zachary Ming
Partner
Energy and Environmental Economics, Inc. (“E3”)
On behalf of
Constellation Energy Generation, LLC
June 12, 2025
PDF page 12
2
Table of Contents
1
Introduction … 3 2
Responses to Criticisms … 8 3
Recommendation … 21
PDF page 13
3
Constellation Energy Generation, LLC
1
2
Rebuttal Testimony of Zachary Ming, Partner, Energy and Environmental 3
Economics, Inc. (“E3”)
4
1 Introduction
5
Q1.
PLEASE STATE YOUR NAME, OCCUPATION, BUSINESS ADDRESS.
6
A1.
My name is Zachary Ming. My current position is Partner at Energy and 7
Environmental Economics (“E3”). My business address is 44 Montgomery Street 8
Suite 1500, San Francisco, California 94104.
9
Q2.
PLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY.
10
A2.
I am filing this testimony as an independent expert, and it represents my own 11
positions and perspectives. This testimony was funded by Constellation Energy 12
Generation, LLC (“Constellation”).
13
Q3.
ARE YOU THE SAME ZACHARY MING WHO FILED DIRECT
14
TESTIMONY IN THIS PROCEEDING?
15
A3.
Yes. I filed direct testimony on behalf of Constellation in this proceeding on April 16
23, 2025.
17
Q4.
PLEASE PROVIDE A SUMMARY OF YOUR DIRECT TESTIMONY.
18
A4.
My testimony demonstrated that there are three fundamental configurations of co- 19
located load: firm, generator-contingent, and interruptible. For each configuration, 20
I outlined an ideal rate structure that adheres to accepted rate design principles 21
including fair apportionment of costs and economic efficiency. Finally, I 22
PDF page 14
4
demonstrated how each of the eight rate design options proposed by PJM can 1
generally be mapped to one of these three fundamental configurations and how they 2
can be modified to align with ideal rate structures.
3
Q5.
WHAT IS THE PURPOSE OF THIS REBUTTAL TESTIMONY?
4
A5.
This testimony responds to the declaration of Danielle S. Powers, who submitted a 5
rebuttal to my direct testimony. Ms. Powers’ rebuttal was submitted on behalf of 6
the Indicated PJM Transmission Owners.
7
Q6.
PLEASE PROVIDE A SUMMARY OF MS. POWERS’ REBUTTAL TO
8
YOUR TESTIMONY.
9
A6.
Ms. Powers asserts that the existing NITS tariff is adequate in its current form. She 10
offers the following criticisms of my proposal for rate options for three 11
configurations of co-located load:
12
1. Ms. Powers describes my proposal as unduly discriminatory and 13
inequitable because it results in a different rate for co-located loads 14
compared to NITS customers;
15
2. Ms. Powers argues that because many large loads will lack flexibility to 16
respond, additional tariff options are not needed;
17
3. Ms. Powers argues that the more flexible approach for interconnection that 18
my proposal enables is unprecedented;
19
4. Ms. Powers argues that some loads may site efficiently (e.g. close to 20
generators) even in the absence of a rate design that encourages them to do 21
so;
22
PDF page 15
5
5. Ms. Powers expresses concern that my proposal does not consider
1
reliability concerns and operational impacts; and
2
6. Ms. Powers asserts that the true motivation of large loads is to secure faster 3
interconnection – not to avoid transmission costs – so no alternative options 4
or discounts are needed.
5
Q7.
DOES MS. POWERS’ AFFIDAVIT ADDRESS YOUR ARGUMENTS AS
6
TO WHY THE CURRENT PJM TARIFF IS NOT JUST AND
7
REASONABLE WITH RESPECT TO CO-LOCATED LOADS?
8
A7.
No. While Ms. Powers declares the existing tariff to be sufficient, she fails to 9
respond to the most fundamental deficiency with the current tariff: the ambiguity 10
and lack of clarity it provides regarding co-located loads – a topic I discussed in my 11
direct testimony. In fact, this deficiency is the entire underlying reason that FERC 12
ordered this show-cause proceeding in the first place, finding that the PJM Tariff 13
does not contain “provisions addressing with sufficient clarity or consistency the 14
rates, terms, and conditions of service that apply to co-location arrangements” and 15
“[t]he absence of such provisions may leave entities unable to determine what steps 16
they can or must take to effectuate co-location arrangements of various 17
configurations.”1 While PJM’s stance is that the existing tariff remains just and 18
reasonable, it concedes that “clarification and enhancements could well be in order 19
given that this is an evolving area and Tariff provisions did not contemplate the 20
type of arrangements at issue in this docket or their implications.”2 PJM asserts that 21
1 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at PP 74-75 (2025).2 Answer of PJM Interconnection, L.L.C., Docket No. EL25-49-000, et al., (filed Mar. 24, 2025) (“PJM Answer”) at 32.
PDF page 16
6
the current tariff allows for multiple options for co-located loads – including one 1
option where load and generation are physically co-located but metered separately 2
(Existing Option #2) and another where load and generation are located behind the 3
same meter (Existing Option #3).
4
Q8.
PLEASE
SUMMARIZE
YOUR
RESPONSE
TO
MS.
POWERS’
5
CRITICISMS.
6
A8.
In general, Ms. Powers misrepresents many of my arguments and in some cases 7
asserts positions that I simply do not take. In other cases, her rebuttals are flawed. 8
Specifically:
9
1. The assertion that my proposal is discriminatory and inequitable is 10
unfounded: under my proposal, co-located customers are provided with a 11
discount in exchange for imposing fewer costs on the transmission system 12
than NITS customers. Further, the level of the discount is proposed in a 13
manner that ensures these customers still equitably contribute to the 14
embedded costs of the system to create positive impacts for all customers. 15
2. Ms. Powers’ assertion that many loads will not have the flexibility to curtail 16
is entirely compatible with my proposal; such customers would have the 17
opportunity to elect firm service. My proposal expands the number of 18
options available so that loads that do have the flexibility to curtail can 19
select a rate option that simultaneously lowers their own cost and the 20
overall cost of the electric system.
21
3. The argument that there are few similar parallels for flexible transmission 22
service in North America neglects to recognize the significance of this 23
PDF page 17
7
moment: the number and magnitude of new large loads seeking
1
interconnection has no historical precedent. Simply assuming the existing 2
tariff is adequate to address the scale, scope, and pace of change occurring 3
because it has been deemed just and reasonable in the past misses the point. 4
4. The argument that some loads may site efficiently even in the absence of a 5
rate design that encourages them to do so ignores the theoretical and 6
empirical benefits of efficient rate design.
7
5. Ms. Powers’ concern that my proposal does not consider reliability 8
concerns or operational impacts is either a misunderstanding or 9
misrepresentation of my proposal. I propose that PJM account for all 10
unique load and supply characteristics and fully comply with all NERC 11
standards.
12
6. Nothing in my testimony claims insight over the motivation of large loads 13
looking to interconnect nor does it “ignore” the potential motivation of 14
speed-to-market. The goals of my proposed rate designs are to ensure that 15
loads are charged fairly and efficiently. The prospect of faster 16
interconnection as a potential benefit to large loads is aligned with – not 17
opposed to – the potential for reductions in transmission cost relative to 18
firm service.
19
I elaborate on each of these responses in subsequent sections.
20
PDF page 18
8
2 Responses to Criticisms
1
2.1 Ms. Powers’ arguments that my proposed tariff options would be 2
“discriminatory” and “inequitable” are unfounded.
3
Q9.
MS.
POWERS
ARGUES
THAT
YOUR
PROPOSED
TARIFF
4
STRUCTURES ARE “DISCRIMINATORY” AND “INEQUITABLE”
5
BECAUSE ONE CLASS OF CUSTOMERS (CO-LOCATED LOADS)
6
WOULD
BE
CHARGED
A
“DISCOUNTED
MARGINAL
COST
7
APPROACH” BASED PRICE WHILE ALL OTHERS WOULD PAY NITS
8
CHARGES BASED ON A “FULL EMBEDDED COST APPROACH.” DO
9
YOU AGREE WITH THIS ASSESSMENT?
10
A9.
No. Ms. Powers characterizes the generator-contingent and interruptible options I 11
present as discriminatory and inequitable solely on the basis that they are provided 12
with a discounted transmission rate. There are multiple fundamental flaws with this 13
argument.
14
First, the ideal rate structures that I propose can only be characterized as a 15
“discount” when compared to full “gross” billing for co-located loads. 3 When 16
compared to “net” billing (a structure supported by multiple parties in this 17
proceeding), the rate structures I propose result in increased costs. 18
Second, my proposal is fully consistent with a “full embedded cost 19
approach.” In fact, the entire point of calculating marginal costs in my proposal is 20
to determine the residual (i.e. embedded cost) contribution that all loads make to 21
the system to ensure that co-located customers contribute equivalently. 22
3 The differences between “gross” and “net” billing are discussed in more detail in my direct testimony.
PDF page 19
9
Finally, what Ms. Powers fails to acknowledge in asserting that differently 1
priced rate options are discriminatory is that these different options also provide 2
different standards of service from traditional NITS customers. A co-located load 3
on a generator-contingent or interruptible tariff would be subject to curtailment by 4
PJM based on on-site generator capability and/or grid conditions – a reduced 5
service level compared to conventional NITS. Providing a discount for inferior 6
service is neither discriminatory nor inherently inequitable.
7
Q10. TO
SUPPORT
HER
CLAIM
THAT
YOUR
PROPOSAL
IS
8
DISCRIMINATORY AND INEQUITABLE, MS. POWERS ASSERTS
9
THAT “IF SOME CUSTOMERS PAY DISCOUNTED RATES, OTHER
10
CUSTOMERS WILL HAVE TO MAKE UP THAT SLACK” AND “[W]HEN
11
ONE CUSTOMER AVOIDS THE COST OF THE TRANSMISSION GRID,
12
IT FALLS TO ANOTHER TO PAY FOR IT.”4 DO YOU AGREE?
13
A10. No. This claim rests upon a flawed premise that the costs of the transmission system 14
are fixed and fails to acknowledge that customers’ behavior may also reduce the 15
total costs to the system. If the cost reductions to the system are equivalent to the 16
discount provided to the customer, then other customers will see no incremental 17
costs. If the cost reductions to the system are greater than the discount provided to 18
the customer (as is the case in my proposed ideal rate designs), then other customers 19
will see lower costs.
20
4 See Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners (filed June 3, 2025), Declaration of Danielle S. Powers (“Powers Decl.”) at 14.
PDF page 20
10
Q11. HOW DOES YOUR PROPOSED APPROACH FOR DESIGNING
1
GENERATOR-CONTINGENT
AND
INTERRUPTIBLE
TARIFFS
2
ACCOUNT FOR EQUITY BETWEEN THESE CUSTOMERS AND NITS
3
CUSTOMERS?
4
A11. The frameworks for ratemaking presented in the generator-contingent and 5
interruptible arrangements are designed to ensure an equitable contribution of all 6
customers toward system embedded costs. For all of these customers, the 7
contribution toward system embedded costs is equal to the full NITS rate minus 8
marginal cost. The difference is that full NITS customers also impose marginal cost 9
on the system and therefore pay additionally. Under my proposed construct, there 10
are aligned incentives between co-located customers and NITS customers. All 11
customers contribute to the embedded costs of the system and therefore reduce rates 12
for other customers.
13
2.2 Ms. Powers’ position that many large loads are not flexible is 14
entirely compatible and consistent with my proposed options for
15
service.
16
Q12. REGARDING
THE
GENERATOR-CONTINGENT
AND
17
INTERRUPTIBLE SERVICES YOU PROPOSE, MS. POWERS ALSO
18
ASSERTS THAT “[M]ANY TYPES OF LARGE LOAD HAVE NOT,
19
CANNOT, OR WILL NOT SIGN UP FOR THESE TYPES OF
20
PDF page 21
11
CONTRACTUAL CO-LOCATION ARRANGEMENTS.”5 WHAT IS YOUR
1
RESPONSE?
2
A12. The fact that large loads “have not” opted for these types of contractual co-location 3
arrangements is hardly a useful observation, as those options have not historically 4
been available to new load loads under the PJM tariff, and their consideration is the 5
very reason for this proceeding. For loads that “cannot” and “will not” agree to such 6
arrangements, Ms. Powers herself observes that “these loads would not be suitable 7
for generator-contingent or interruptible service,” nearly reaching the logical 8
conclusion that those types of loads could elect to receive firm service under my 9
proposal.
10
In her focus on lack of flexibility among a subset of large loads, Ms. Powers 11
seems to suggest that because some loads may not be flexible, the same tariff should 12
apply to all co-located loads, flexible or not. What my proposed framework 13
provides is options: if a load is not flexible, as Ms. Powers expects, they can elect 14
to take firm service; if a load is flexible, it can opt for a service that better meets its 15
needs rather than be forced into a “one-size-fits-all” agreement.
16
2.3 Ms. Powers’ arguments that such tariff options lack precedent
17
ignores the fact that the current dynamics for load growth are
18
unprecedented and require a novel approach.
19
Q13. MS. POWERS CHARACTERIZES YOUR PROPOSAL AS RESEMBLING
20
A “CONNECT AND MANAGE” APPROACH FOR LOADS, AND CLAIMS
21
5 Id. at 9.
PDF page 22
12
THAT
THERE
ARE
NO
FRAMEWORKS
FOR
LOAD
1
INTERCONNECTION IN NORTH AMERICA. IS THIS CORRECT?
2
A13. No. As discussed in my direct testimony, the Alberta Electric System Operator 3
(“AESO”)’s Demand Opportunity Service (“DOS”) for transmission customers 4
bears many similarities to the interruptible example I proposed.6 AESO’s rate is 5
one that allows existing customers to use electricity beyond a contracted capacity 6
subject to the following conditions:
7
• AESO’s service of this additional load is subject to transmission 8
availability, and the load can be interrupted with limited notice; 9
• The customer must be capable of curtailing its load within 10 minutes of 10
notification from AESO; and
11
• Customers using the system under a DOS agreement are subject to a 12
transmission charge denominated in $/MWh, providing a mechanism for 13
some recovery of embedded costs corresponding to their use of the system. 14
Q14. NONETHELESS, THERE ARE RELATIVELY FEW EXAMPLES OF
15
OPTIONS FOR LOADS TO INTERCONNECT IN THIS MANNER. IS
16
THAT A REASON THAT PJM/FERC SHOULD NOT CONSIDER IT
17
HERE?
18
A14. No. The absence of comparable tariffs in other jurisdictions is hardly a sound 19
justification to dismiss its potential usefulness in the present circumstance in PJM. 20
The bulk electric system is in a state of rapid and unprecedented transformation, 21
6 See, generally, materials on Rate Demand Opportunity Service, available at https://www.aeso.ca/rules- standards-and-tariff/tariff/rate-demand-opportunity-service-dos
PDF page 23
13
driven both by changes in the generation mix and significant new loads. In such an 1
environment, it is incumbent upon grid operators and regulators to critically 2
reassess how well market design and tariffs are suited to handle the changing needs 3
of the grid – especially as PJM acknowledges that “[t]ariff provisions did not 4
contemplate the type of arrangements at issue in this docket or their implications.”7 5
Dismissing that opportunity simply because it may differ from how things have 6
been done in the past is short-sighted and narrow.
7
As it pertains to the specific matter at hand – tariff design for large co- 8
located loads – it is worth recognizing that the nature of prospective load growth 9
driven by data centers and large industrial customers has no historical parallel. E3’s 10
recent report to Virginia’s Joint Legislative Audit and Review Commission 11
(“JLARC”) indicated that even under a “moderate” data center growth scenario, 12
electric demand could double in the state over a 25-year period. Under an 13
“unconstrained” scenario, the time to double is reduced to 10 years. Today’s 14
electric system is the cumulative product of more than a century of steady growth, 15
and serving new loads at that scale would require nearly doubling the scale of the 16
electric grid in a fraction of the time. In such a period of dramatic change, it is 17
essential that PJM and FERC consider improvements and innovations to supply 18
new customer segments – while continuing to adhere to sound ratemaking 19
principles – particularly if those services could mitigate the need for new 20
infrastructure.
21
7 PJM Answer at 32.
PDF page 24
14
Q15. ARE OTHER JURISDICTIONS CURRENTLY EXAMINING SPECIAL
1
RATE TREATMENTS FOR LARGE CUSTOMERS ON ACCOUNT OF
2
THESE DYNAMICS?
3
A15. Yes. The Texas legislature has recently examined a novel approach for loads that 4
allows for faster interconnection under the premise that these loads will curtail if 5
the system is unable to serve them. 8 Additionally, many utilities are currently 6
considering special tariffs for large loads that are designed to balance enabling 7
growth with the need to protect existing customers from cost increases.9 8
2.4 Ms. Powers’ argument that some loads may site efficiently even in 9
the absence of a rate design that encourages them to do so is
10
economically unfounded.
11
Q16. MS. POWERS STATES THAT “PRICE SIGNAL THROUGH NITS ARE
12
NEITHER
APPROPRIATE
NOR
REQUIRED
TO
INCENT
13
ECONOMICALLY EFFICIENT SITING DECISIONS.”10 WHAT IS YOUR
14
RESPONSE TO THIS?
15
A16. This position contradicts one of the, if not the, core tenets of economics – that the 16
role of prices serves as an “invisible hand” to guide the action of individual 17
producers and consumers. Just because a consumer can do something without a 18
price incentive does not mean that they will. When loads do not see a price signal 19
8 For example see Senate Bill 6 from the 2025/2026 legislative session https://legiscan.com/TX/bill/SB6/2025, whose concepts are explained more by Goff Policy https://www.linkedin.com/pulse/texas-way-trust-market-fix-queue-eric-goff-f4q3c/9 See, generally, Berkeley Lab Energy Markets & Policy Technical Brief, available at https://eta- publications.lbl.gov/sites/default/files/2025- 01/electricity_rate_designs_for_large_loads_evolving_practices_and_opportunities_final.pdf .10 Powers Decl. at 14.
PDF page 25
15
that reflects transmission costs, they will not consider these costs in their siting and 1
configuration, which will almost certainly result in large loads in aggregate 2
configuring in higher cost-manner than they would otherwise.
3
Q17. MS. POWERS STATES THAT “THE USE OF PRICE SIGNALS –
4
SPECIFICALLY, A DISCOUNTED TRANSMISSION RATE – TO
5
FACILITATE COMMERCIAL ARRANGEMENT SUCH AS A CO-
6
LOCATED BUSINESS MODEL IS NOT AMONG BONBRIGHT’S
7
CRITERIA FOR SOUND RATE DESIGN.”
11 WHAT IS YOUR
8
RESPONSE?
9
A17. This statement misrepresents my testimony. The purpose of my proposal is to 10
encourage economic efficiency – both through load’s decisions of where to locate 11
physically on the grid and through their operational decisions in response to 12
availability of co-located generation and the conditions on the grid – while 13
providing for fair apportionment of costs among co-located loads and other 14
customers. The fact that a commercial agreement between a co-located load and 15
generator may also exist is not relevant and is certainly not the purpose of my rate 16
proposal.
17
Q18. MS. POWER STATES THAT “APPLYING MARKET-BASED PRICING
18
LOGIC TO THE PRICING FRAMEWORK OF A REGULATED
19
11 Id.
PDF page 26
16
TRANSMISSION SYSTEM MISCONSTRUES THE ROLE AND PURPOSE
1
OF TRANSMISSION RATES.”12 WHAT IS YOUR RESPONSE?
2
A18. What my testimony highlights is that both sound market design and sound rate 3
design should both be economically efficient. This means getting an outcome that 4
yields the most value for the least cost. The principle of economic efficiency is 5
included in Bonbright's Principles of Public Utility Rates that was originally 6
published in 1961, long before the restructuring of the electricity system and the 7
advent of electricity markets. This principle is absolutely applicable in the context 8
of a regulated transmission utility.
9
2.5 Ms. Powers mischaracterizes the impact of co-located loads on grid 10
reliability and my position on the topic.
11
Q19. MS. POWERS ASSERTS THAT YOUR TESTIMONY “IMPROPERLY
12
CONFLATES THE INTERCONNECTION STUDIES FOR LOAD AND
13
SUPPLY BY SUGGESTING THAT A SINGLE STUDY SHOULD BE
14
CONDUCTED THAT RECOGNIZES THE NET IMPACT OF BOTH THE
15
LOAD
AND
SUPPLY
WHILE
IGNORING
THE
UNIQUE
16
CHARACTERISTICS OF EACH.”13 IS HER CHARACTERIZATION OF
17
YOUR TESTIMONY ACCURATE?
18
A19. No. Nowhere in my testimony do I assert that the study process should be conducted 19
using a simplistic net framework. A single study is eminently capable of 20
simultaneously capturing the "unique characteristics" of both load and supply. 21
12 Id. at 15.13 Id. at 2.
PDF page 27
17
Nothing in my testimony suggests that PJM would not rigorously do so or that the 1
outcome would not be compliant with NERC standards.
2
Q20. MS. POWERS RAISES GENERAL CONCERNS WITH THE ABILITY OF 3
THE GRID TO PROTECT AGAINST THE CHALLENGES OF
4
INTEGRATING LARGE LOADS – FOR EXAMPLE BY STATING THAT
5
“IT IS NOT AT ALL CLEAR THAT THE RELAY SCHEMES AND
6
PROTECTION MECHANISMS THAT HAVE BEEN PROPOSED BY
7
VARIOUS LARGE LOADS WOULD PROTECT THE GRID AGAINST
8
SUCH VARIATIONS IN DATA CENTER DEMAND.”14 WHAT IS YOUR
9
RESPONSE TO THIS CONCERN?
10
A20. This concern appears to be wholly unrelated to co-location. In fact, the data center 11
incident in ERCOT that Ms. Powers cites in paragraph 13 is specifically not a co- 12
located load. Therefore, this concern should have no bearing on the decision to 13
facilitate co-location in PJM.
14
2.6 Faster interconnection – which Ms. Powers describes as the primary 15
motive behind large loads’ desire to co-locate – is a co-benefit with 16
avoided transmission costs enabled by my proposal, not a competing 17
objective.
18
Q21. MS. POWERS ASSERTS THAT YOUR TESTIMONY “…IGNORES THE 19
FACT THAT THE PRIMARY MOTIVATION FOR LARGE LOADS
20
SEEKING CO-LOCATION ARRANGEMENT IS NOT AVOIDANCE OF
21
14 Id. at 6.
PDF page 28
18
TRANSMISSION COSTS, BUT TIMELY INTERCONNECTION.” 15 DO
1
YOU VIEW THIS AS INCONSISTENT WITH THE POSITIONS YOU’VE
2
TAKEN?
3
A21. No, I do not. First, taken at face value, this statement appears to suggest that 4
principled ratemaking for co-located loads is unnecessary because transmission 5
costs are a small portion of the costs borne by data centers.
6
Second, it is inaccurate to say that my proposal focuses solely on cost rather 7
than speed. For example, I state that “unnecessary and inefficient costs may slow 8
down - or even discourage - the interconnection of new beneficial load." 16 9
Additionally, I discuss how allowing large loads to take service under generator- 10
contingent or interruptible service on an interim basis could facilitate more timely 11
interconnection of these loads.17
12
Third, Ms. Powers’ comments seem to suggest that the motivation to 13
interconnect more quickly should be a reason not to include additional tariff 14
options. Indeed, she elaborates: “In short, speed-to-power, not transmission pricing, 15
is the decisive factor when large load seeks to co-locate with generation. E3’s price 16
signaling through a discounted transmission rate is unnecessary given existing 17
economic incentives and market behavior for co-location decisions.” This position 18
is problematic for multiple reasons: (1) because it fails to recognize that faster 19
interconnection is a co-benefit that is aligned with, rather than opposed to, 20
customers that impose fewer costs on the transmission system and; (2) because it 21
15 Id. at 4.
16 See Answer of Constellation Energy Generation, LLC (filed April 23, 2025), Exh. 2, Testimony of Zachary Ming (“Ming Direct Testimony”), at 22.
17 Id. at 48.
PDF page 29
19
suggests that it is appropriate to price discriminate by charging the same tariff rates 1
to customers receiving a lower standard of service because of their willingness to 2
pay.
3
Q22. PLEASE
ELABORATE
ON
THE
IDEA
THAT
FASTER
4
INTERCONNECTION
FOR
CO-LOCATED
LOADS
SEEKING
5
GENERATOR-CONTINGENT AND INTERRUPTIBLE SERVICE IS A
6
CO-BENEFIT TO REDUCED TRANSMISSION COSTS.
7
A22. My testimony focused on the benefit of avoided transmission investments because 8
the rate design proposals I offer are directly linked to that value. The ability to 9
interconnect more rapidly to the system if transmission investments are not needed 10
is a potential additional benefit to the co-located load that is independent of the 11
costs of the electric system. Two things are simultaneously true of transmission 12
investments: (1) they result in incremental costs to the system, and (2) their 13
planning and construction require long periods of time – often five to ten years. To 14
the extent a co-located load seeking interconnection can do so in a manner that 15
avoids the need for the transmission cost, two benefits result: (1) the transmission 16
costs are avoided, and (2) the load can be interconnected more quickly. In other 17
words, these are co-benefits, not competing priorities, and the fact that loads may 18
be motivated to seek alternative service arrangements by the prospect of faster 19
interconnection should be understood as an added benefit of my proposal, not a 20
drawback.
21
PDF page 30
20
Q23. DOES THE CURRENT NITS TARIFF PROVIDE CUSTOMERS WITH A
1
MEANS OF SEEKING FASTER INTERCONNECTION?
2
A23. No. Under the current tariff, if the interconnection study process identifies new 3
transmission upgrades as required to meet a load, the new load has no opportunity 4
to seek faster interconnection, even if it is willing to accept a lower standard of 5
reliability.
6
PDF page 31
21
3 Recommendation
1
Q24. IN LIGHT OF THE RESPONSES YOU MAKE, DO YOU HAVE A
2
RECOMMENDATION?
3
A24. Yes. Based on the arguments I make above, I recommend that FERC disregard the 4
declaration of Ms. Powers.
5
Q25. DOES THIS CONCLUDE YOUR TESTIMONY?
6
A25. Yes.
7
PDF page 32
VERIFICATION
I declare under penalty of perjury that the foregoing Rebuttal Testimony is true and correct to the best of my knowledge, information, and belief.
Executed this 12th day of June 2025.
________________________
Zachary Ming