EL25-49-000 · 2025-06-12 · Constellation Energy Generation, LLC

Motion for Leave and Answer of Constellation Energy Generation, LLC in response to the Indicated Transmission Owners’ fourth answer, etc

Text extracted from the eLibrary original (SHA-256 a7d257680400fb45…). Download the original from the official source.

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

NERC Reliability Standard FAC-002-2 states that “[e]ach Transmission Planner … shall study the reliability impact of: (i) interconnecting new … electricity end-user Facilities and (ii) materially modifying existing interconnections of generation.”24 No one is advocating that co-located load should…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION WHEREFORE, Constellation respectfully requests that the Commission grant leave and accept this answer and adopt its preliminary finding that the PJM Tariff is unjust and unreasonable and unduly discriminatory and preferential because it lacks clear provisions for the treatment of large…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Washington, D.C. 20004 Tel: (202) 389-3266 mack.dowiak@kirkland.com Exhibit 1 Rebuttal Testimony of Zachary Ming Rebuttal Testimony of Zachary Ming Partner Energy and Environmental Economics, Inc. (“E3”) On behalf of Constellation Energy Generation, LLC June 12, 2025 2
Read this passage

Table of Contents

printed heading · Topic match: Connecting load and generation

She 10 offers the following criticisms of my proposal for rate options for three 11 configurations of co-located load: 12 1.
Read this passage Filed comments: Connecting load and generation