EL25-49-000 · 2025-06-27 · Exelon Corporation, American Electric Power Service Corporation and 15 others

Motion For Leave to Answer and Limited Answer of the Indicated PJM Transmission Owners to Constellation Energy Generation, LLC's 06/12/2025 Answer

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-000
Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
Docket No. EL25-20-000
(consolidated)
MOTION FOR LEAVE TO ANSWER AND LIMTED ANSWER
OF THE INDICATED PJM TRANSMISSION OWNERS
Pursuant to Rules 212 and 2131 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”) and the Commission’s show cause order,2 the Indicated PJM Transmission Owners (hereinafter, “Indicated TOs”)3 submit this Motion for Leave to Answer and Limited Answer to the June 12, 2025 Answer of Constellation Energy Generation, LLC (“Constellation”) made in the above-captioned dockets.  Under Rule 1

18 C.F.R. §§ 385.212, 385.213 (2025).
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at Ordering Paragraph (D) (2025).
3 The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Duke Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business Services LLC; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.

PDF page 2

2

213(a)(2)4 of the Commission’s Rules of Practice and Procedure, the Commission may authorize an answer to an answer.  Good cause exists to accept this answer because it ensures a further developed record for the Commission’s decision making.5

Constellation continues to argue points that the record does not support.  For example, the allegation that several parties would like clarifications to enable alternatives does not justify discarding the PJM Open Access Transmission Tariff (“PJM Tariff”) as unjust and unreasonable.6 The Indicated TOs have explained at length why these alternative proposals would harm, rather than help, the ability of PJM Interconnection, L.L.C. (“PJM”) to accommodate co-located interconnection arrangements.7  In response, no party has demonstrated that it has been unable to receive service under the existing PJM Tariff or that it is experiencing an undue delay for a request for service under the PJM Tariff.

Indeed, recent events plainly indicate that existing types of service can be used.  On November 1, 2024 in Docket No. ER24-2172, the Commission rejected proposed amendments to the

Interconnection
Service
Agreement
among
PJM,
Susquehanna
Nuclear,
LLC
(“Susquehanna”), and PPL Electric Utilities Corporation that would have increased the amount of

4 18 C.F.R. § 385.213(a)(2).
5 See, e.g., PJM Interconnection, L.L.C., 191 FERC ¶ 61,112 at P 29 (2025) (accepting “answers because they . . . provided information that assisted [the Commission] in [its] decision-making process”).
6 Constellation Answer at 1, 3.  Notably, Constellation’s representation that “[n]early every party in this proceeding agrees” with its position is simply false.  Constellation attempts to support this erroneous claim by citing to its own May 8, 2025 Answer in this proceeding.  Yet, Constellation’s May 8, 2025 Answer identified only seven intervenors—seven out of the more than 40 intervenors in Docket No. EL25-20 alone—that agree with Constellation’s position.
7 See Answer of the Indicated PJM TOs to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidated with Other Proceedings (Mar. 24, 2025); see also Answer of the Indicated PJM TOs (Apr. 23, 2025); see also Answer of the Indicated PJM TOs to the Motion to Stay Proceedings (May 7, 2025); see also Motion for Leave to Answer and Answer of the Indicated PJM TOs (June 3, 2025).

PDF page 3

3

co-located load at that facility from 300 MW to 480 MW.8  Susquehanna is owned by Talen Energy Corporation (“Talen”).  On June 11, 2025, after months of failure by various parties to demonstrate that the existing PJM Tariff is unjust and unreasonable, Talen announced that it has “expanded its existing nuclear energy relationship with Amazon to provide carbon-free energy from Susquehanna to Amazon Web Services (“AWS”) data centers in the region.”9  Significantly, Talen stated that

[t]he existing Susquehanna co-located load arrangement between Talen and
Amazon will transition to a “front-of-the-meter” arrangement after the completion of transmission reconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling outage.  Under the terms of the new agreement,

Susquehanna will provide its carbon-free power to the PJM grid, Talen will act as the retail electric generation supplier to Amazon, and PPL Electric Utilities (“PPL”) will be responsible for transmission and delivery.10

In this same announcement, Amazon references its $20 billion investment in data center campuses in the Commonwealth of Pennsylvania.11  The front of the meter configuration, consistent with the existing PJM Tariff, has not stopped this significant investment, “the largest private sector investment in state history,” from moving forward.12  The PJM Tariff will not stop other such investments.

Ultimately, Constellation’s preference for alternative rate structures is not evidence that the existing forms of transmission service are unjust and unreasonable.  It remains true that section

8 See Order Rejecting Amendments to Interconnection Service Agreement, 189 FERC ¶ 61,078, Docket No. ER21-2172 (Nov. 1, 2024); order on reh’g, Order Addressing Argument on Rehearing and Granting Clarification, in Part, 191 FERC ¶ 61,025 (Apr. 10, 2025).
9 See Talen Energy Expands Nuclear Energy Relationship with Amazon, Talen, June 11, 2025, available at https://ir.talenenergy.com/node/8671/pdf (“Talen Press Release”).  The Talen Press Release is appended hereto as Attachment A.
10  Id.
11  Id.
12  Id.

PDF page 4

4

206 of the Federal Power Act (“FPA”), requires a finding that the existing rate or charge is unjust and unreasonable before alternatives may be considered.13  Only after a successful showing that the existing rate is unjust and unreasonable, may the Commission order a replacement rate.14  And, “[t]he burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or the third-party complainant.”15  Even now, neither the Commission nor any of the parties supporting the initiation of this FPA section 206 proceeding have demonstrated that the existing PJM Tariff is unjust and unreasonable.  Consequently, as the Indicated TOs have consistently stated, the only action that may lawfully be taken is to terminate this proceeding.  Doing so promptly would ensure that interested stakeholders are able to continue operating under the same tariff provisions that have already successfully encouraged significant investments like the one described in the Talen Press Release.

For the reasons stated above, and in the prior comments and answers of the Indicated TOs, the Commission should terminate this show cause proceeding, affirming that the existing PJM Tariff and existing transmission service categories remain just and reasonable.

13  16 U.S.C. § 824e(a); Emera Me. V. FERC, 854 F.3d 9, 25 (D.C. Cir. 2017) (holding that “[w]ithout a showing that the existing rate is unlawful,” the Commission “has no authority to impose a new rate”).
14  16 U.S.C. § 824e(a); see also N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 94–95 (3d Cir. 2014) (“[U]nder § 206, FERC may change a rate in response to a complaint or on its own motion, only if the moving party demonstrates that the existing rate is unjust and unreasonable and the proposed alternative is just and reasonable.”).
15  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).

PDF page 5

5

Respectfully submitted,

/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Max Minzner

Max Minzner
Vice President and Deputy General Counsel Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com

On behalf of Exelon Corporation

/s/ Jessica Cano
Jessica Cano
Assistant General Counsel – Regulatory East American Electric Power Service Corporation 1 Riverside Plaza

Columbus, OH 43215
Telephone: 614-716-2921
Email: jacano@aep.com

/s/ Lisa G. McAlister
Lisa G. McAlister
AMP Transmission, LLC
1111 Schrock Road, Suite 100
Columbus, Ohio 43229
Telephone: 614-540-6400
Email: lmcalister@amppartners.org

On behalf of American Electric Power Service Corporation

On behalf of AMP Transmission, LLC

/s/ Martin J. Keane
Martin J. Keane
Director of Public Utilities
Cleveland Public Power
1300 Lakeside Ave.
Cleveland, OH 44114
Telephone: 216-664-2444 ext. 75604
Email: martin_keane@clevelandwater.com

/s/Debra D. Roby
Debra D. Roby
Washington Energy Law LLP
900 17th Street N.W., Suite 500-A
Washington, D.C. 20006
Telephone: 703-785-9270
Email: droby@washingtonenergylaw.com

On behalf of City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power

On behalf of the City of Hamilton, OH

PDF page 6

6

/s/ Damon L. Krieger
Damon L. Krieger
Group Vice President, Legal, Strategy, and Sustainability, and Deputy General Counsel Southern Maryland Electric Cooperative, Inc. 15035 Burnt Store Road

P.O. Box 1937
Hughesville, Maryland 20637-1937
Telephone: 301-274-4323
Email: Damon.Krieger@SMECO.coop

/s/ Molly Suda
Molly Suda
Associate General Counsel
Annelise Rickert
Federal Government Affairs Director Duke Energy Corporation

1301 Pennsylvania Ave NW, Suite 200 Washington, DC 20004

Telephone: 202-824-8011
Email:  molly.suda@duke-energy.com Annelise.rickert@duke-energy.com

On behalf of Southern Maryland Electric Cooperative

On behalf of Duke Energy

/s/ Jeremy L. Fetty

Jeremy L. Fetty
Parr Richey
251 N. Illinois, Suite 1800
Indianapolis, Indiana 46204
Telephone: 317-269-2500
Email: j_fetty@wvpa.com

/s/   Amanda P. Parker
Amanda P. Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OH 44308
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com

On behalf of Wabash Valley Power
Association, Inc.

On behalf of The FirstEnergy Transmission Companies

/s/ Denise R. Foster Cronin
Denise R. Foster Cronin
Vice President, Federal and RTO Regulatory Affairs

East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707

Winchester, KY 40392-0707
Telephone: 859-745-9615
Email: denise.cronin@ekpc.coop

/s/ Daniel E. Frank
Daniel E. Frank
Kelly Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Telephone: 202-383-0100
Email:
danielfrank@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com

On Behalf of East Kentucky Power
Cooperative, Inc.

PDF page 7

7

/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C.  20006-1167
Telephone: 202-585-6900
Email: aclair@thompsoncoburn.com

/s/ Steve Nadel
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Telephone: 610-774-4775
Email: SMNadel@pplweb.com

On behalf of Old Dominion Electric Cooperative

On behalf of PPL Electric Utilities Corp.

/s/David Burns
David Burns
Senior Manager,
FERC Policy & Regulatory Affairs
Consolidated Edison Company of New York, Inc.

4 Irving Place
New York, NY 10003
Telephone: 571-678-9152
Email: burnsd@coned.com
/s/Joshua Kirstein
Joshua A. Kirstein
Senior Attorney
Law Department
Consolidated Edison Company of New York, Inc.

4 Irving Place, 18th Floor
New York, NY 10003
Telephone: 929-656-5971
Email: kirsteinj@coned.com

On behalf of Rockland Electric Company

/s/ Lindsay Berkstresser
Lindsay Berkstresser
Counsel – Energy & Regulatory
UGI Corporation
500 North Gulph Road
King of Prussia, PA 19406
Telephone: 717-504-9925
Email: berkstresserl@ugicorp.com

/s/ Richard P. Bonnifield
Richard P. Bonnifield
Husch Blackwell
1801 Pennsylvania Avenue, NW,
Suite 1000
Washington, DC 20006-3606
Telephone: 202-243-8844
Email:
richard.bonnifield@huschblackwell.com

On behalf of UGI Utilities Inc.
June 27, 2025

PDF page 8

Attachment A

PDF page 9

Talen Energy Expands Nuclear Energy Relationship with Amazon
June 11, 2025
Talen enters power purchase agreement for 1,920 megawatts of carbon-free electricity at full quantity to support Amazon operations, and explore SMR technology

HOUSTON, June 11, 2025 (GLOBE NEWSWIRE) -- Talen Energy Corporation (“Talen,” “we,” or “our”) (
NASDAQ: TLN), an independent power
producer dedicated to powering the future, announced today that it has expanded its existing nuclear energy relationship with Amazon to provide carbon-free energy from Talen’s Susquehanna nuclear power plant to Amazon Web Services (“AWS”) data centers in the region. Under the terms of a new power purchase agreement (“PPA”), Talen will supply electricity to Amazon for operations that support AI and other cloud technologies at Amazon’s data center campus adjacent to Susquehanna, with the ability to deliver to other sites throughout Pennsylvania. Talen and Amazon will also explore building new Small Modular Reactors (“SMRs”) within Talen’s Pennsylvania footprint and pursue expanding the nuclear plant’s energy output through uprates, with the intent to add net-new energy to the PJM grid.

Under the expanded PPA, at the full contract quantity, Talen will provide Amazon with 1,920 megawatts of carbon-free nuclear power through 2042, with options to further extend its duration. The power delivery schedule will ramp over time, expecting to achieve the full volume no later than 2032, with the potential to meaningfully accelerate. This long-term transaction will significantly decrease Talen’s market risk and minimize its reliance on the Federal nuclear production tax credit.

“Our agreement with Amazon is designed to provide us with a long-term, steady source of revenue and greater balance sheet flexibility through contracted revenues. We remain a first mover in this space and intend to continue to execute on our data center strategy,” said Talen President and Chief Executive Officer Mac McFarland. “Talen is well-positioned to support Amazon’s energy needs as it invests further in the Commonwealth of Pennsylvania.”

“Amazon is proud to help Pennsylvania advance AI innovation through investments in the Commonwealth’s economic and energy future,” said AWS Vice President of Global Data Centers Kevin Miller. “That’s why we’re making the largest private sector investment in state history – $20B – to bring 1,250 high-skilled jobs and economic benefits to the state, while also collaborating with Talen Energy to help power our infrastructure with carbon-free energy.”

The existing Susquehanna co-located load arrangement between Talen and Amazon will transition to a “front-of-the-meter” arrangement after the completion of transmission reconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling outage. Under the terms of the new agreement, Susquehanna will provide its carbon-free power to the PJM grid, Talen will act as the retail electric generation supplier to Amazon, and PPL Electric Utilities (“PPL”) will be responsible for transmission and delivery.

“PPL Electric Utilities is investing in the resiliency of its transmission system so we can better serve our customers, meet growing energy demands, and ensure power is delivered reliably,” said Christine Martin, president of PPL Electric Utilities. “Connecting large load customers like data centers to our transmission system helps lower the transmission component of energy bills for all customers, as large load customers pay significant transmission charges on our network. We’re excited to be part of Amazon’s broader investment in Pennsylvania and look forward to the positive effects it can have for our customers and the local economy.”

Strengthening Pennsylvania’s Energy Future
The Talen and Amazon relationship will help safe, reliable nuclear energy continue to be generated at Susquehanna for years to come, maintaining its contributions to the local community and supporting Pennsylvania’s energy future while also helping to power Amazon’s AI innovation investments in the Commonwealth. Talen is a major employer and significant local taxpayer, and the agreement supports the jobs of more than 900 employees currently working at the Susquehanna facility, as well as new construction jobs.

While Pennsylvania maintains a position as a net energy exporter, producing more power than the Commonwealth requires, Talen’s strategic partnership with Amazon will help send the necessary market signals to spur new investment in additional generation and grid modernization within the Commonwealth.

Pennsylvania Policy and Stakeholder Support
The following key policymakers and stakeholders expressed their support for the transaction.
“This partnership between Talen Energy and Amazon taps into Pennsylvania’s strengths as a national energy leader and will power the largest economic development project in Commonwealth history – creating good-paying jobs, growing our economy, and ultimately adding more power to the PJM energy grid,” said Governor Josh Shapiro. “I am an all-of-the-above energy governor, and as part of my economic development plan, my Administration is working to generate even more power in the Commonwealth – with more power comes more national security, more independence, and more economic freedom. My Administration is going to continue to bring people together to attract new investment to Pennsylvania, and we stand ready to work with Talen Energy and its partners to review permits for this project as efficiently as possible.” – Pennsylvania Governor Josh Shapiro (D)

“Talen and Amazon’s expanded nuclear energy relationship not only strengthens the future of the Susquehanna plant and maintains its contributions to the community, but also helps to support the development of AI technology in Pennsylvania. Adding data centers that support AI strengthens American national security, provides a wide variety of economic opportunities, and positions the Commonwealth, and the U.S., as a leader in AI innovation.” –  U.S. Senator Dave McCormick (R-PA)

“I’m pleased about the economic development opportunities the Commonwealth and the Ninth District will receive thanks to Talen and Amazon’s long-term arrangement. Our communities will not only benefit from the economic development that will occur, but also from the contributions that the

PDF page 10

Susquehanna plant provides as a large employer within the district. Thank you, Talen, Amazon and PPL for working together to bring these benefits to Pennsylvania.” – U.S. Representative Dan Meuser (R-PA), who represents Pennsylvania’s 9 th U.S. Congressional District

“IBEW Local 1600 strongly supports the new transaction. Our members, friends, and families all benefit from the jobs and community growth this investment in Susquehanna will bring. This sets up a great career path for young students coming out of high school or college who are looking for a career in the electrical industry.” - John “Rusty” Clausius, President, IBEW Local 1600

Investor Call
Talen will host an investor call at 8:00 a.m. EDT today, Wednesday, June 11, 2025. To participate in the call, please register for the webcast via the page linked here. Participants can also join by phone by registering via the form linked here prior to the start time of the call to receive a conference call dial-in number. For those unable to participate in the live event, a digital replay will be archived for approximately one year and available on the Events page of Talen's Investor Relations website linked here.

About Talen
Talen Energy (NASDAQ: TLN) is a leading independent power producer and energy infrastructure company dedicated to powering the future. We own and operate approximately 10.7 gigawatts of power infrastructure in the United States, including 2.2 gigawatts of nuclear power and a significant dispatchable fossil fleet. We produce and sell electricity, capacity, and ancillary services into wholesale U.S. power markets, with our generation fleet principally located in the Mid-Atlantic and Montana. Our team is committed to generating power safely and reliably and delivering the most value per megawatt produced. Talen is also powering the digital infrastructure revolution. We are well-positioned to capture this significant growth opportunity, as data centers serving artificial intelligence increasingly demand more reliable, clean power. Talen is headquartered in Houston, Texas. For more information, visit https://www.talenenergy.com/.

Investor Relations:
Sergio Castro
Vice President & Treasurer
InvestorRelations@talenenergy.com
Media:
Taryne Williams
Director, Corporate Communications
Taryne.Williams@talenenergy.com
Forward Looking Statements
This communication contains forward-looking statements within the meaning of the federal securities laws, which statements are subject to substantial risks and uncertainties. These forward-looking statements are intended to qualify for the safe harbor from liability established by the Private Securities Litigation Reform Act of 1995. All statements other than statements of historical fact included in this communication, or incorporated by reference into this communication, are forward-looking statements. Throughout this communication, we have attempted to identify forward-looking statements by using words such as “anticipate,” “believe,” “continue,” “could,” “estimate,” “expect,” “forecasts,” “goal,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “seek,” “should,” “will,” or other forms of these words or similar words or expressions or the negative thereof, although not all forward-looking statements contain these terms. Forward-looking statements address future events and conditions concerning, among other things, capital expenditures, earnings, litigation, regulatory matters, hedging, liquidity and capital resources and accounting matters. Forward-looking statements are subject to substantial risks and uncertainties that could cause our future business, financial condition, results of operations or performance to differ materially from our historical results or those expressed or implied in any forward-looking statement contained in this communication. All of our forward-looking statements include assumptions underlying or relating to such statements that may cause actual results to differ materially from expectations, and are subject to numerous factors that present considerable risks and uncertainties.

PDF page 11

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated at Chicago, IL this 27th  day of June, 2025.

/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation