EL25-49-000 · 2025-12-08 · Old Dominion Electric Cooperative
Answer of Old Dominion Electric Cooperative in Opposition to Motion for Expedited Action of Constellation Energy Generation, LLC,
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
)
v. )
)
PJM Interconnection, L.L.C.
)
Docket No. EL25-20-000
(Consolidated)
ANSWER OF OLD DOMINION ELECTRIC COOPERATIVE
IN OPPOSITION TO
MOTION FOR EXPEDITED ACTION OF
CONSTELLATION ENERGY GENERATION, LLC
Pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.213, Old Dominion Electric Cooperative (“ODEC”) submits this Answer in opposition to the Motion for Expedited Action of Constellation Energy Generation, LLC (“Constellation”) filed in the above-captioned proceedings on November 21, 2025 (“Motion”). As discussed below, ODEC urges the Commission to reject Constellation’s Motion.1 Instead, the Commission should address the urgent need for clarity and guidance regarding large load interconnections, including co- located loads, on a generic basis in the ongoing rulemaking proceeding in Docket No. RM26-7-
1 ODEC joined the Answer of the Indicated PJM Transmission Owners to the Motion for Expedited Action of Constellation Energy Generation, LLC, filed today in this proceeding. ODEC submits this brief Answer to raise additional concerns against Constellation’s Motion.
PDF page 2
2
000.2 Such final action should allow for regional differences and be issued by the Commission no later than April 30, 2026, as expected by the Secretary of Energy.3
I. RELEVANT BACKGROUND
On November 22, 2024, Constellation filed a complaint under Federal Power Act (“FPA”) section 2064 against PJM in Docket No. EL25-20-000. In short, Constellation argued that the PJM Open Access Transmission Tariff (“Tariff”) is unjust, unreasonable and unduly discriminatory because it does not contain specific rules for interconnecting generators that will serve co-located loads. Constellation requested that the Commission grant the complaint on a fast-track basis, determine that the PJM Tariff is unjust, unreasonable and unduly discriminatory or preferential, and direct PJM to adopt in its Tariff certain portions of PJM’s Guidance on Co-Located Load. On November 1, 2024, the Commission held a technical conference in Docket No AD24- 11-000, to discuss issues related to co-location of loads at generating facilities. The Commission noted several proceedings initiated by entities in the PJM Region that involved similar issues. Initial and reply comments were filed following the technical conference.5
On February 20, 2025, the Commission issued an order in Docket No. EL25-49-000, instituting a proceeding under FPA section 206.6 The Show Cause Order followed several filings that addressed the co-location of large loads at generating facilities in PJM, as well as the Commission’s technical conference in Docket No. AD24-11-000. The Show Cause Order directed
2 Ensuring the Timely and Orderly Interconnection of Large Loads, Docket No. RM26-4-000 (“Proposed ANOPR”).
3 U.S. Dep’t of Energy, Letter from Sec’y Chris Wright to Fed. Energy Regulatory Comm’n (Oct. 23, 2025), https://www.energy.gov/sites/default/files/2025-10/403%20Large%20Loads%20Letter.pdf. See Reply Comments of Old Dominion Electric Cooperative, Docket No. RM26-4-000 at 3-6 (Dec. 5, 2025). 4 16 U.S.C. § 824e.5 Large Loads Co-Located at Generating Facilities, Notice of Request for Comments (Nov. 8, 2024). 6 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (“Show Cause Order”).
PDF page 3
3
PJM and the PJM Transmission Owners, including ODEC, to either “(1) show cause as to why the Tariff, the Amended and Restated Operating Agreement of PJM, and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region remain just and reasonable and not unduly discriminatory or preferential due to the lack of provisions specifically addressing co- location arrangements;” or (2) explain what changes to these governing documents would remedy the identified concerns if the Commission were to determine that the governing documents have become unjust and unreasonable or unduly discriminatory or preferential and, therefore, proceeds to establish a replacement Tariff.7
On October 23, 2025, the Secretary of Energy issued the Proposed ANOPR pursuant to section 403 of the Department of Energy Organization Act. The Proposed ANOPR directed FERC to initiate a rulemaking procedure and proposal regarding the interconnection of large loads. On October 27, 2025, the Commission issued a Notice Inviting Comments on the Proposed ANOPR.8 ODEC submitted Initial Comments and Reply Comments on the Proposed ANOPR on November 1, 2025 and December 5, 2025, respectively. ODEC encouraged the Commission to provide clarity and establish a durable framework for the interconnection of large loads to the transmission system in a manner that ensures reliability and resource adequacy, and ensures that large loads pay their share of the costs for the benefits they will receive.
II. ANSWER
In response to the Show Cause Order, the Indicated PJM Transmission Owners, including ODEC, demonstrated that (1) neither the Commission nor any of the parties supporting initiation of the Show Cause proceeding have met the FPA section 206 burden to demonstrate that the
7 Id. at P 2.8 By Notice issued November 7, 2025, the Commission extended the deadline for reply comments to December 5, 2025.
PDF page 4
4
existing PJM Tariff is unjust, unreasonable or unduly discriminatory and preferential; and (2) the alternatives proposed by the Show Cause supporters would actually harm PJM’s ability to accommodate co-located interconnection arrangements.9 Therefore, the Commission should confirm that the existing Tariff and governing documents are sufficient to accommodate co-located load arrangements and are just, reasonable and not unduly discriminatory or preferential. With that said, the Indicated PJM Transmission Owners agreed that clarity would be helpful, and encouraged the Commission to clarify that Network Service and Point-to-Point Service are applicable to co- located load arrangements, ensure that the Commission’s principles for open access and non- discriminatory transmission service persist, and ensure beneficiaries pay for the service they receive.10
PJM similarly demonstrated that its existing Tariff remains just and reasonable, although Commission guidance might be appropriate.11 To that end, PJM requested that if the Commission decides to take action, it would issue guidance so that PJM can work with stakeholders to develop a solution. To address timeliness, PJM suggested that the Commission could issue a compliance directive to set a deadline for future filings, such as an FPA section 205 filing by PJM consistent with the Commission’s guidance.12
As detailed in the Indicated PJM Transmission Owners’ Answer, there still has not been any demonstration that the PJM Tariff is unjust, unreasonable or unduly discriminatory. Therefore,
9 See Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidated with Other Proceedings (Mar. 24, 2025); see also Answer of the Indicated PJM Transmission Owners (Apr. 23, 2025), Answer of the Indicated PJM Transmission Owners to the Motion to Stay Proceedings (May 7, 2025), Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners (June 3, 2025).10 See Indicated PJM Transmission Owners Answer submitted March 24, 2025, at 6.11 Answer of PJM (March 24, 2025).12 Id. at 5.
PDF page 5
5
the FPA section 206 burden has not been met. Moreover, the Indicated PJM Transmission Owners’ Answer demonstrates that Constellation’s request for the Commission to make determinations regarding jurisdiction and adopt Constellation’s list of demands is both premature and raises significant concerns regarding reliability and affordability. Instead, as ODEC recommended in its Reply Comments on the Proposed ANOPR, the Commission should (1) act swiftly to provide necessary clarity, adopt generally applicable rules and/or standards, and direct compliance filings;
(2) include specific directives to ensure reliability and resource adequacy; and (3) adopt requirements to ensure that large loads pay their fair share of the costs. PJM can then work with stakeholders, as it has in its ongoing Critical Issue Fast Path (“CIFP”) process, to develop a proposal for consideration by its Board of Managers that can be submitted to the Commission in compliance with the Commission’s guidance and directives.
The Show Cause proceeding should be closed without further directive and Constellation’s complaint should be dismissed because there has been no demonstration that the existing Tariff is unjust, unreasonable or unduly discriminatory or preferential. However, even if the Commission finds that this FPA section 206 burden has been met, Constellation’s specific relief has not been shown to constitute a just and reasonable replacement rate. In addition to the issues raised in the Indicated PJM Transmission Owners’ Answer, ODEC submits that Constellation’s request for the Commission to direct that large load interconnection requests must be processed without regard to whether the load has arranged for wholesale transmission or distribution service, could lead to unreasonable cost allocation, as well as threats to reliability. In the Show Cause Order, the Commission stated that “[t]he record demonstrates that different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different
PDF page 6
6
impacts on the transmission system.”13 Further, the Commission noted that different co-location configurations can raise cost causation concerns.14 Constellation’s Motion does not resolve these concerns, nor do its Comments on the Proposed ANOPR. To the contrary, Constellation’s contentions in its Proposed ANOPR comments demonstrate the complexity of these configurations that warrants the Commission adopting general principles for PJM to address through a compliance filing.15
ODEC also takes issue with Constellation’s continued attempts to equate its co-located load arrangements with the existing PJM provisions for netting with regard to behind-the-meter generation.16 The Indicated Transmission Owners have previously explained that the two are not similar and, therefore, different treatment of co-located load from behind-the-meter generation is not unduly discriminatory.17 ODEC urges the Commission to reject Constellation’s attempt to argue otherwise.
Constellation’s request for the Commission to grant Constellation’s specific measures, for the PJM Region only, also fails to address critical issues regarding resource adequacy with co- located loads. In the Show Cause Order, the Commission advised that “the risk that co-located loads will not be reflected in resource adequacy planning mechanisms with sufficient forward notice is particularly concerning given how long it takes to add new generation capacity or upgrade transmission facilities.”18 Constellation’s request for the Commission to immediately adopt
13 Show Cause Order at P 76.14 Id.15 See Constellation’s ANOPR Comments at 32-33, citing to Constellation’s Show Cause Answer and accompanying testimony.16 See, e.g., Constellation’s Supplemental Comments at 36 (Dec. 5, 2025).17 See Indicated Transmission Owners’ Answer, June 3, 2025 in Docket No. EL25-49 at 12, 16-17; Indicated Transmission Owners’ Answer, Apr. 3, 2025 at 5-9.18 Show Cause Order at P 85.
PDF page 7
7
Constellation’s requested relief in a vacuum does not resolve this significant concern and, therefore, the Commission cannot determine that Constellation has proposed a just and reasonable replacement rate.19
III. CONCLUSION
WHEREFORE, for the foregoing reasons, ODEC urges the Commission to reject
Constellation’s Motion to Expedite, deny Constellation’s complaint and terminate the Show Cause proceeding without further action because the FPA section 206 burden has not been met, as discussed above and in the pleadings in these proceedings by the Indicated PJM Transmission Owners.
Respectfully submitted,
/s/ Adrienne E. Clair
Adrienne E. Clair
Jenna Cliatt
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
(202) 585-6900
(202) 585-6969 (fax)
aclair@thompsoncoburn.com
jcliatt@thompsoncoburn.com
Attorneys for Old Dominion Electric
Cooperative
Dated: December 8, 2025
19 Constellation contends that “existing market mechanisms should be sufficient to ensure resource adequacy even during periods of rapid demand growth” then points to a proposal that is pending in the PJM stakeholder process. See Constellation Proposed ANOPR Reply Comments at 37-38.
PDF page 8
CERTIFICATE OF SERVICE
I hereby certify that on this 8th day of December 2025, I have caused a copy of the foregoing to be served upon each party designated on the Commission’s Official Service List for this proceeding.
/s/Adrienne E. Clair