EL25-49-000 · 2025-12-08 · Exelon Corporation, AMP Transmission and 8 others

Answer of Indicated PJM Interconnection, L.L.C. Transmission Owners to the 11/21/2025 Motion for Expedited Action filed by Constellation Energy Generation, LLC

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-000

Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.
)

)

)
Docket No. EL25-20-000
(consolidated)

ANSWER OF THE INDICATED PJM TRANSMISSION OWNERS TO THE MOTION
FOR EXPEDITED ACTION OF CONSTELLATION ENERGY GENERATION, LLC

Pursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy
Regulatory Commission (“FERC” or “Commission”), the Indicated PJM Interconnection, L.L.C. (“PJM”) Transmission Owners (“Indicated TOs”)2 submit this Answer to the Motion for Expedited Action that was filed by Constellation Energy Generation, LLC (“Constellation”) on November 21, 2025 (“Constellation’s Motion”).3

1
See 18 C.F.R. § 385.213(d)(1) (“Any answer to a motion or to an amendment to a motion must be made within 15 days after the motion or amendment is filed, except as described below or unless otherwise ordered.”).

2 This filing was prepared on behalf of the following PJM Transmission Owners: AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.
3 Constellation attached its comments filed in Docket No. RM26-4-000 to its motion in this proceeding.  The Indicated TOs are not addressing all of the issues with the RM26-4-000 filing in the instant filing—those issues will instead be addressed where they belong in Docket No. RM26-4-000.

PDF page 2

2

For the reasons discussed herein, the Commission should reject Constellation’s Motion, which if granted would result in affordability concerns for customers, market uncertainty, reliability risks, and a jurisdictional overreach on the part of the Commission.  Should the Commission decide to act in this proceeding prior to resolution of Docket No. RM26-4-000, the only action that should be taken, as the Indicated TOs have previously explained, is to terminate the above-captioned complaint dockets because the PJM Open Access Transmission Tariff (“PJM Tariff”) has not been shown to be unjust and unreasonable.4

I. BACKGROUND
On October 23, 2025, the Secretary (“Energy Secretary”) of the U.S. Department of Energy (“DOE”) “direct[ed] [FERC] to initiate rulemaking procedures and [to] consider [an] Advance Notice of Proposed Rulemaking (ANOPR) presenting potential reforms to ensure the timely and orderly interconnection of large loads to the transmission system.”5  The Energy Secretary submitted the proposal through his authority under section 403 of the Department of Energy Organization Act6 and asked that the Commission act on the proposal “no later than April 30, 2026.”7  On October 27, 2025, the Commission issued a notice inviting comments on the ANOPR in a new rulemaking docket, Docket No. RM26-4-000.8  Among other things, the ANOPR is exploring the possibility of standardizing interconnection procedures and agreements for “hybrid

4 See Answer of Indicated TOs at 24–25 (June 3, 2025).
5 Secretary Chris Wright, DOE, Ensuring the Timely and Orderly Interconnection of Large Loads: Advance Notice of Proposed Rulemaking (“ANOPR”), Docket No. RM26-4-000,  at P 1 (Oct. 27, 2025) (footnote omitted) (“DOE ANOPR Filing”).
6 See 42 U.S.C. § 7173(a) (“The Secretary and the Commission are authorized to propose rules, regulations, and statements of policy of general applicability with respect to any function within the jurisdiction of the Commission under section 7172 of this title.”). 7 DOE ANOPR Filing, Transmittal Letter at 2. 8 Interconnection of Large Loads to the Interstate Transmission System, Docket No. RM26-4-000, Notice Inviting Comments (Oct. 27, 2025).

PDF page 3

3

facilities,” which the ANOPR defines as loads, “seeking to share a point of interconnection with new or existing generation facilities.”9  Hundreds of comments and reply comments were submitted by numerous parties on the ANOPR.

Constellation’s Motion asks that FERC quickly move forward and rule on co-located load issues in PJM, rather than waiting until it has considered and ruled in the aforementioned rulemaking proceeding.10

II. ANSWER
A. Constellation’s Desire for a PJM-Specific Outcome Is Inappropriate
Where the Commission Is Evaluating These Issues at a National Level in
the Pending ANOPR Proceeding.
PJM’s existing tariff is just and reasonable and should be upheld for that reason.  Further, it would cause confusion and unwarranted expense and upheaval for the Commission to modify the PJM Tariff in this proceeding on an interim basis before addressing issues nationwide in Docket No. RM26-4-000.  Would an early ruling in PJM mean that PJM will have different rules from the rest of the country?  Or would the rules be changed again once a ruling is issued in RM26- 4-000?  Any changes to the PJM Tariff should be informed by the principles or rules established through the ANOPR process, to adhere to the policy direction and solutions, which FERC is now contemplating on a national basis.  A patchwork of rules that may or may not change in the near- term is a recipe for market uncertainty that could stifle rather than assist sensible forward movement on data center development, including investment delays in energy infrastructure

9 DOE ANOPR Filing at P 12.
10  Constellation’s Motion suggests transmission owners are delaying large load interconnections.  See Constellation’s Motion at 2.  Nothing could be further from the truth.  The Indicated TOs are fully supportive of interconnecting large loads, co-located or otherwise, as quickly, safely, equitably, and reliably as possible, consistent with the existing just and reasonable PJM Tariff and with applicable state laws.  Concurrently with this answer, Exelon is filing a separate answer to correct any misapprehension regarding the ability of large loads and their load serving entities to receive transmission services in the Exelon service territories.

PDF page 4

4

needed to support increasing demand.  The expedited action in this docket that Constellation seeks would potentially pre-judge issues to be decided in the ANOPR proceeding without adequate consideration of the full record being developed there and potentially result in conflicting outcomes.

Constellation argues that an early ruling for PJM is supported by the fact that the DOE ANOPR Filing explains that it “is not intended in any way to discourage public utilities from making filings to address these and similar issues under [Federal Power Act (“FPA”)] section 205.”11  But allowing filings under FPA section 20512 is simply a reflection of the statute—public utilities have a right under FPA section 205 “to file rates and terms for services rendered with [their] assets.”13  This reservation of rights to transmission owners to modify tariffs at any time for service provided with their assets does not alter the far stricter rules applicable to FPA section 20614 actions, which can only proceed when the rate is found “unjust [and] unreasonable.”15  That burden has not been met, nor would it be appropriate to make such a finding while the hundreds of comments on the ANOPR are in the midst of their review.  Should the Commission decide to act in this proceeding prior to action in the ANOPR docket, as the Indicated TOs have explained in prior filings, the appropriate course of action would be to terminate the complaint and show cause proceedings for failure to meet the burden established under FPA section 206.16

11  DOE ANOPR Filing at P 32.
12  16 U.S.C. § 824d.
13  Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002) (citing 16 U.S.C. § 824d). 14  16 U.S.C. § 824e.
15  Id. § 824e(a). 16  See, e.g., Answer of Indicated TOs at 2–3 (June 3, 2025) (“Neither the Commission nor any of the parties supporting the initiation of this FPA section 206 proceeding have demonstrated that the existing [PJM Tariff] is unjust and unreasonable.  Consequently, the only action that may lawfully be taken is to terminate this proceeding.”).

PDF page 5

5

B. Constellation Would Have the Commission Improperly and Prematurely
Make a Broad Jurisdictional Determination in this Proceeding.
Under FPA section 201(b)(1), FERC has jurisdiction over “the transmission of electric energy in interstate commerce and . . . the sale of electric energy at wholesale in interstate commerce.”17  Except as otherwise provided for under the FPA, carved out from FERC’s jurisdiction are “facilities used for the generation of electric energy[,] . . . facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, . . . [and] facilities for the transmission of electric energy consumed wholly by the transmitter.”18 The National Association of Regulatory Utility Commissions (“NARUC”) recognizes in a recent resolution that “the ANOPR asserts FERC jurisdiction over the interconnection of large loads to the transmission system” and asks FERC to “make clear that it is affirmatively not asserting jurisdiction over end-use sales, which falls squarely within the exclusive jurisdiction of state retail energy regulatory authorities.”19

In the Show Cause Order in this proceeding, FERC explained that,
[T]he Commission has exercised authority over the terms of certain
interconnections to the transmission system as “an essential element
of [t]ransmission [s]ervice.”  Although the Commission reached that
conclusion based on the nature of interconnection to the
transmission system generally, not the purpose for such
interconnection (i.e., to make a wholesale sale or to make a
wholesale or retail purchase), it has not historically exercised

17  16 U.S.C. § 824(b)(1).
18  Id.
19  NARUC, EL-1 Resolution Urging the Federal Energy Regulatory Commission to Preserve and Affirm State Retail Regulatory Jurisdiction in its Large Load Interconnection Proceeding, Substantive Resolutions Passed by the NARUC Board of Directors, at 6, https://pubs.naruc.org/pub/97FE08D1-CF4D-9199-BA7F- 5884DD427E55?_gl=1*1cgs1pd*_ga*MTEwMTgwNTA4OS4xNzUxNTQ3Nzc0*_ga_QLH1N3Q1NF*czE3 NjI5NTMxNTAkbzExJGcxJHQxNzYyOTUzMTY4JGo0MiRsMCRoMA (adopted by the NARUC Board of Directors on Nov. 11, 2025).

PDF page 6

6

jurisdiction over any and all transmission-level interconnections of
retail load.20

The Commission further explained that it has “examine[d] whether certain facilities had a ‘dual use,’ (i.e., the facilities were used for both wholesale and retail purposes), but the Commission limited its assertion of jurisdiction to distribution level interconnections.”21  And in another recent proceeding, FERC declined to address “jurisdiction over the process of interconnecting loads to the Commission-jurisdictional transmission system.”22

Constellation would have the Commission decide in this proceeding that co-located load interconnections should be treated as entirely FERC-jurisdictional, disregarding the fact that retail service to the loads is definitely not subject to FERC authority.  Consistent with their prior comments,23 the Indicated TOs reiterate that it is the Network Integration Transmission Service (“Network Service”) customer that is taking FERC-jurisdictional transmission service in serving the co-located load, which is typically a load serving entity, but if a state allows, it may be the load itself.  The only part of such an arrangement that is FERC jurisdictional is the transmission service provided by the interstate grid to the load serving entity.

The Commission may decide, to the extent it has jurisdiction, how transmission costs associated with large load customer interconnections will be recovered in FERC Docket No. RM26-4-000.  In the context of this proceeding, for FERC to determine what transmission costs

20  PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 72 (2025) (alterations in original) (footnotes omitted) (“Show Cause Order”); see also id. PP 66–72.
21  Id. P 72 n.224 (citation omitted).
22   Tri-State Generation and Transmission Ass’n, Inc., 193 FERC ¶ 61,070, at P 50 (2025)  (“Because it appears that Tri-State’s proposal before us sets the terms of retail sales, we need not elaborate in this order on other matters raised by parties regarding the extent of the Commission’s jurisdiction, such as jurisdiction over the process of interconnecting loads to the Commission-jurisdictional transmission system.”).
23  See Answer of Indicated TOs at 15–16 (June 3, 2025).

PDF page 7

7

should appear on a particular retail customer’s (including a large load customer’s) bill would have FERC tread into questionable jurisdictional territory that would have broad national implications. Notably, Network Service addresses many of the jurisdictional issues raised by NARUC and others.  That is, there are no jurisdictional complications if loads are served by a state- authorized load serving entity that procures Network Service to serve that load and, perhaps, other loads.  Affirmation by FERC that this is Network Service, and that FERC has jurisdiction over that service, will clarify the contentious jurisdictional debate.  Once it is made clearer that this service is Network Service, the process for seeking service is unambiguous under the existing PJM Tariff and has not been shown to be a problem.  Of course, network customers have to pay for embedded costs of transmission—something Constellation objects to—but that has not been shown to be unjust and unreasonable.

C. Constellation’s Preferred Outcome Raises Significant Affordability and
Reliability Concerns.
What Constellation proposes would result in large loads avoiding their share of the cost of the transmission services that they rely upon.  But the services are not free.  If the large loads do not pay for the transmission system and related services that they use, someone else must pay instead.  Constellation’s continued push to subsidize co-located load would result in significant cost-shifts to other customers.24

While transmission and ancillary service charges are the primary issue in this proceeding, load impacts should certainly be taken into consideration.  PJM’s independent market monitor, Monitoring Analytics, LLC, warned in its recent 2025 Quarterly State of the Market Report that rapid data center growth is driving tight supply-demand conditions, higher capacity prices, and

24  See Exelon Comments in Opposition to Complaint, Docket No. EL25-20, at Attach. 2, Declaration of John J. Reed & Danielle S. Powers (filed Dec. 12, 2024).

PDF page 8

8

increased transmission and energy costs for all customers.25  The Market Report asserts that proposals to let data centers remove existing capacity from the market and dedicate it to themselves would create cost shifts and reliability risks until new generation is built.26  Constellation’s Motion not only evades this issue entirely but attempts to sidestep regulatory and PJM oversight of the issue by not measuring the actual consumption of large loads that the grid must be prepared to support.

Increased transmission investment will be needed to ensure continued reliability of the grid when massive and diverse new loads become connected to the system.  The lack of visibility into the operation of these loads, as discussed further below, could adversely affect grid stability and prevent adequate planning on the part of PJM.  This underscores the proposition that new large loads, whether or not co-located with generation, should pay their share of the embedded cost of the transmission system.

As PJM’s independent market monitor explained, it would be inappropriate to “shift the costs of serving data center load to all other customers.”27  But that is exactly what would happen if Constellation’s plan were to go forward, permitting data centers to receive the benefits of the electric grid without bearing their fair share of costs for that service.  Constellation’s proposal to allow certain categories of customers to avoid paying for transmission service would only frustrate the purpose of the FPA, which is “to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”28

25  Monitoring Analytics, LLC, Q3 State of the Market Report for PJM: January Through September, at 1–3 (Nov. 13, 2025), https://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025q3-som-pjm.pdf (“Market Report”).
26  See id.
27  Id. at 3.
28  NAACP v. FPC, 425 U.S. 662, 669–70 (1976).

PDF page 9

9

Affordability should remain top of mind for the Commission.  In PJM, demand has
outpaced the development of supply.29  The transmission system requires maintenance to ensure reliability, resilience, and quality of service.  Maintenance comes at a cost, and all customers that benefit from that maintenance and that rely upon the transmission system should bear that cost. Doing otherwise would place disproportionate financial risks on an ongoing basis to other customers and unduly benefit large loads that avoid paying for Network Service.

Another problem is visibility by transmission system operators and planners into critical information and operating conditions that bear on system stability and reliability.  When co-located load is hidden and not appropriately accounted for in transmission planning and operations, it creates reliability risks by undermining accurate system modeling and resource adequacy assessments.  North American Electric Reliability Corporation (“NERC”) has explained in this proceeding that (1) “system operators may lack sufficient information to perform reliability analysis on co-located large loads”; (2) “large loads may or may not be visible to system operators depending on the load’s operation and interconnection type”; (3) “[i]f a load is connected but

29  NERC, 2025–2026 Winter Reliability Assessment, at 8 (Nov. 2025), https://www.nerc.com/globalassets/our- work/assessments/nerc_wra_2025.pdf (“Winter electricity demand is rising at the fastest rate in recent years, particularly in areas where data center development is occurring. . . . Most assessment areas are projecting an increase in peak demand.  SaskPower, PJM, the U.S. Southeast, and parts of the U.S. West have the largest increase in peak demand forecasts.”); see PJM, PJM Auction Procures 134,311 MW of Generation Resources; Supply Responds to Price Signal, at 1 (July 22, 2025), https://www.pjm.com/-/media/DotCom/about- pjm/newsroom/2025-releases/20250722-pjm-auction-procures-134311-mw-of-generation-resources-supply- responds-to-price-signal.pdf (explaining that PJM’s 2026/2027 Base Residual Auction “cleared volume was just over (by 139 MW UCAP) the projected reliability requirement, underscoring the region’s tightening supply- demand balance”); NERC, 2024 Long-Term Reliability Assessment Report, at 16 (Dec. 2024, corrected July 11, 2025), https://www.nerc.com/globalassets/our-work/assessments/2024-ltra_corrected_july_2025.pdf (“PJM’s projections for generator additions in 2025 and 2026 are scaled back dramatically from the 2023 LTRA while demand forecasts continue to rise.”); id. at 92 (“Overall, new generation is coming on-line slower than anticipated. Generator retirements are outpacing the new generation replacing them.  As a result, PJM could face future resource adequacy challenges, impacting system reliability and PJM’s ability to serve load. PJM could be at risk of facing resource adequacy challenges if these trends continue.  PJM has applied an 11% reduction to the nameplate value of Tier 1 resources to reflect the historical rate of slower-than-anticipated addition of new generation.”); id. at 93 (“Driven by discrete and localized load growth, like Data Center Alley in Loudoun County, Virginia, in 2022, PJM and stakeholders conducted a review of data center load growth and identified growth rates of over 300% in some instances.”).

PDF page 10

10

operating conditions are providing only partial or no generation, there is a risk of thermal overloads and voltage or stability issues”; and (4) “[f]luctuations from large loads during faults or switching can cause issues with voltage support, frequency response, stability, and protection system coordination.”30

In other words, behind-the-meter loads “can pose reliability risks if their generation unexpectedly trips off-line and appropriate protection or ride-through systems are not in place [because] [t]he operational visibility and controllability of [behind-the-meter] loads are limited, making it more challenging to predict system impacts, especially during uncontrolled transitions between on-site generation and grid supply that may arise due to protection system failures.”31  “If the load unexpectedly shifts to expecting grid supply after the co-located generation fails, the utility supply sees a rapid demand spike, which may stress the transmission system.”32 Increased demand without appropriate planning due to hidden load will result in

transmission and generation constraints.  Large loads that are not visible as part of the PJM planning process can very well deplete transmission and generation capacity in times of increased demand.  The effect will be increased costs and decreased quality of service for other customers. The way to mitigate this is by maintaining the requirement for these large co-located loads to be subject to Network Service and the costs that should attend that service.

30  NERC Comments at 7 (Apr. 23, 2025).
31  NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July 2025), https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics- and-risks-of-emerging-large-loads.pdf.
32  Id.

PDF page 11

11

D. Nothing Has Changed: The Standard Under Federal Power Act Section
206 Has Not Been Met.
As a legal matter, nothing has changed since the commencement of this proceeding.  As discussed in the prior submissions of the Indicated TOs, the existing forms of transmission service in PJM—Network Service and Point-to-Point Transmission Service (“PTP Service”)—continue to be just and reasonable methods of providing transmission service to loads in PJM, including loads co-located with generation facilities.

Constellation continues to ignore a fundamental part of FPA section 206:33 only after a successful showing that the existing rate is unjust and unreasonable can the Commission order a replacement rate.34  No such showing has been made.  The PJM Tariff remains just and reasonable, and nothing in the record of this proceeding proves otherwise.  “The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or the third-party complainant.”35  Neither the Commission nor any of the parties supporting the initiation of this FPA section 206 proceeding have demonstrated that the existing PJM Tariff forms of transmission service are unjust and unreasonable.  The indisputable fact is that there is a path under the existing PJM Tariff for all customers to get service in a timely fashion at reasonable, non-preferential rates.

The two options for transmission service under the PJM Tariff—Network Service and PTP Service—allow for recovery of the embedded costs of the PJM grid.36  Constellation seeks to

33  16 U.S.C. § 824e(a).
34  Id.  See also N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74, 94–95 (3d Cir. 2014) (“[U]nder § 206, FERC may change a rate in response to a complaint or on its own motion, only if the moving party demonstrates that the existing rate is unjust and unreasonable and the proposed alternative is just and reasonable.”).
35  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).
36  See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, 81 FERC ¶ 61,257 (1997) (adopting PJM pricing proposal to allow recovery of embedded transmission revenue requirement from network customers), corrected (cont'd)

PDF page 12

12

exempt large co-located loads from these costs, granting undue preference at the expense of other customers, contrary to the FPA’s mandate that all rates be just and reasonable and free from undue discrimination.37

Co-located loads rely on the transmission system for essential services and impose
reliability challenges.  As the Indicated TOs have previously explained,38 the “assessment of [Network Integration Transmission Service] is not based on actual use over a particular transmission path, but rather based on the network customer’s right to use the entire system”39 and its effects on that system.  Preferential treatment cannot be justified under the guise of national security, as similar critical facilities that contribute to our national security already pay under the existing PJM Tariff.  The real issue here is cost allocation and the attempt by some to shift to other customers the embedded costs of the transmission system.

The outcome in Docket Nos. ER24-2172-000 and ER24-2172-001 (“Susquehanna ISA
Proceeding”) illustrates this point.40  The proposal in that case was to avoid Network Service

by 82 FERC ¶ 61,103 (1998), and clarified in part by 92 FERC ¶ 61,282 (2000), and review granted in part, vacated in part by 295 F.3d 1 (D.C. Cir. 2002); PJM OATT, Section 34.1 (providing for payment by network customers of load ratio share of embedded cost of their zone); PJM OATT Attachments H-1, H-1A, H-2, H-2A, H-3, H-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the Exelon Utilities based on the embedded costs of their respective transmission systems).

37  16 U.S.C. § 824d(a) (“All rates and charges made, demanded, or received by any public utility for or in connection with the transmission or sale of electric energy” must “be just and reasonable.”); id. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”).
38  See Answer of Indicated TOs at 6, 23 (June 3, 2025) (quoting Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020)).
39  Nat’l R.R. Passenger Corp., 173 FERC ¶ 61,043 at P 14.
40  See PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (“Susquehanna ISA Order”).

PDF page 13

13

through a behind-the-meter arrangement.41  That proposal sought essentially what Constellation seeks here, an exemption from responsibility for embedded costs.  The Commission rejected the proposal in the Susquehanna ISA Proceeding.42  What happened next is most instructive: the data center development continued anyway, and it did so under the existing Network Service option available under the PJM Tariff.43  Which is to say that nothing about the arrangement or the current PJM Tariff required the behind-the-meter form of service.  Constellation’s claim that the PJM Tariff is unjust and unreasonable is misplaced; no basis exists for creating a new service or replacement rate.44

No matter how quickly any party prefers action in this proceeding, the Commission cannot order any replacement rates merely to accommodate the type of service some customers would prefer.  Again, FPA section 206 only permits action when the existing rate is unjust and unreasonable—which has not been shown.  Additionally, as the Indicated TOs have previously explained,45 Commission action to attempt to set a replacement rate that would accommodate a narrow category of customers, such as co-located load, would conflict with the major questions

41  See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule F, Part F.4 (June 1, 2024).
42  Susquehanna ISA Order, 189 FERC ¶ 61,078.
43  See Press Release, Talen Energy, Talen Energy Expands Nuclear Energy Relationship with Amazon (June 11, 2025), https://ir.talenenergy.com/news-releases/news-release-details/talen-energy-expands-nuclear-energy- relationship-amazon (“The existing Susquehanna co-located load arrangement between Talen and Amazon will transition to a ‘front-of-the-meter’ arrangement after the completion of transmission reconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling outage.”).
44  Constellation’s range of concerns at times go beyond the issue of the types of transmission service provided by PJM and instead relate to operation and timing of the interconnection queue and study process.  Undoubtedly, there continues to be room for reform of the interconnection queue, but that is not a reason to revise transmission services and charges that have proven to work for all customers.
45  See Answer of Indicated TOs at 14–15 (June 3, 2025).

PDF page 14

14

doctrine46 and the declaration in the FPA that rates that provide an undue preference or advantage are unlawful.47  Congress could have given FERC authority to require preferred transmission service to benefit certain wholesale (or retail) customers, but it did not do so.

III. Conclusion
There are important issues to consider such as possible reforms to the interconnection queue process to minimize unjustified delays.  That is where the problem is—not with the type of transmission services offered.  Constellation wants to avoid paying for Network Service and asks for quick action to establish a new form of service in PJM to accommodate its desires while the Commission simultaneously considers related national policy direction and solutions.  There is no basis for that and the standard under FPA section 206 has not been met to require such a change to the PJM Tariff.  For the reasons stated above, FERC should reject Constellation’s Motion. Should FERC decide to act in this proceeding prior to resolution of the ANOPR proceeding, the complaint and show cause proceedings should be terminated, and FERC should find that the PJM Tariff remains just and reasonable.

46  See West Virginia v. EPA, 597 U.S. 697, 723 (2022) (“Agencies have only those powers given to them by Congress, and ‘enabling legislation’ is generally not an ‘open book to which the agency [may] add pages and change the plot line.’” (alteration in original (citation omitted))); see also Midship Pipeline Co., L.L.C. v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such  authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly” (second alteration in original (quoting West Virginia v. EPA, 597 U.S. at 723))).
47  See 16 U.S.C. § 824d(b).

PDF page 15

15

       Respectfully submitted,

/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs Exelon Corporation

701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Max Minzner

Max Minzner
Senior Vice President & Deputy General Counsel - Corporate

Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com

On behalf of Exelon Corporation

/s/ Lisa G. McAlister
Lisa G. McAlister
AMP Transmission, LLC
1111 Schrock Road, Suite 100
Columbus, Ohio 43229
Telephone: 614-540-6400
Email: lmcalister@amppartners.org

/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C.  20006-1167
Telephone: 202-585-6900
Email: aclair@thompsoncoburn.com

On behalf of AMP Transmission, LLC

On behalf of Old Dominion Electric
Cooperative
/s/ Martin J. Keane
Martin J. Keane
Director of Public Utilities
Cleveland Public Power
1300 Lakeside Ave.
Cleveland, OH 44114
Telephone: 216-664-2444 ext. 75604
Email: martin_keane@clevelandwater.com

/s/Debra D. Roby
Debra D. Roby
Washington Energy Law LLP
900 17th Street N.W., Suite 500-A
Washington, D.C. 20006
Telephone: 703-785-9270
Email: droby@washingtonenergylaw.com

On behalf of City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power

On behalf of the City of Hamilton, OH

PDF page 16

16

/s/ Michael Brechlin
Michael Brechlin
PA Bar # 335424
Duquesne Light Company
411 7th Ave
Pittsburgh, PA 15219
Telephone: 412-393-6431
Email: mbrechlin@duqlight.com
/s/ Amanda P. Parker
Amanda P. Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OH 44308
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com

On behalf of Duquesne Light Company On behalf of The FirstEnergy Transmission Companies

/s/ Denise R. Foster Cronin
Denise R. Foster Cronin
Vice President, Federal and RTO Regulatory Affairs

East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707

Winchester, KY 40392-0707
Telephone: 859-745-9615
Email: denise.cronin@ekpc.coop

/s/ Daniel E. Frank
Daniel E. Frank
Kelly Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Telephone: 202-383-0100
Email:
danielfrank@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com

On Behalf of East Kentucky Power
Cooperative, Inc.

/s/ Steve Nadel
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Telephone: 610-774-4775
Email: SMNadel@pplweb.com

/s/ Jeremy L. Fetty

Jeremy L. Fetty
Parr Richey
251 N. Illinois, Suite 1800
Indianapolis, Indiana 46204
Telephone: 317-269-2500
Email: j_fetty@wvpa.com

On behalf of PPL Electric Utilities Corp.

On behalf of Wabash Valley Power
Association, Inc.

PDF page 17

17

/s/ Damon L. Krieger
Damon L. Krieger
Group Vice President, Legal, Strategy, and Sustainability, and Deputy General Counsel Southern Maryland Electric Cooperative, Inc. 15035 Burnt Store Road

P.O. Box 1937
Hughesville, Maryland 20637-1937
Telephone: 301-274-4323
Email: Damon.Krieger@SMECO.coop

/s/Joshua Kirstein
Joshua A. Kirstein
Senior Attorney
Law Department
Consolidated Edison Company of New York, Inc.

4 Irving Place, 18th Floor
New York, NY 10003
Telephone: 929-656-5971
Email: kirsteinj@coned.com

On behalf of Southern Maryland Electric Cooperative

On behalf of Rockland Electric Company

/s/ Lindsay Berkstresser
Lindsay Berkstresser
Counsel – Energy & Regulatory
UGI Corporation
500 North Gulph Road
King of Prussia, PA 19406
Telephone: 717-504-9925
Email: berkstresserl@ugicorp.com

/s/ Richard P. Bonnifield
Richard P. Bonnifield
Husch Blackwell
1801 Pennsylvania Avenue, NW,
Suite 1000
Washington, DC 20006-3606
Telephone: 202-243-8844
Email:
richard.bonnifield@huschblackwell.com

On behalf of UGI Utilities Inc.

December 8, 2025

PDF page 18

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated this 8th day of December, 2025.

/s/Alejandro Bautista
Alejandro Bautista
Assistant General Counsel
Exelon Corporation
2301 Market Street
Philadelphia, PA 19101
Telephone: 267-533-0120
Email: Alejandro.Bautista@exeloncorp.com