EL25-49-000 · 2025-12-15 · Virginia State Corporation Commission
Answer of the Virginia State Corporation Commission in opposition to Constellation Energy Generation, LLC's Motion to File Supplemental Comments
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Large Loads Co-Located at Generating
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
)
v.
)
Docket No. EL25-20-000
)
(consolidated)
PJM Interconnection, L.L.C.
)
ANSWER TO MOTION OF THE VIRGINIA STATE
CORPORATION COMMISSION
Pursuant to Rule 213 of the Federal Energy Regulatory Commission’s (“FERC” or the “Commission”) Rules of Practice and Procedure, 18 C.F.R. § 385.213, the Virginia State Corporation Commission (“VSCC”) submits this Answer in opposition to the Motion to File Supplemental Comments of Constellation Energy Generation, LLC (“Constellation”) filed in the above-captioned consolidated proceedings on November 21, 2025 (“Motion” and “Supplemental Comments”).
This proceeding pits two groups with entrenched corporate interests against one another. On one side is Constellation, which insists that the PJM Interconnection, L.L.C. (“PJM”) tariff is unjust and unreasonable because it does not explicitly permit the type of co-located generation and data center arrangement Constellation prefers and financially benefits from. On the other side are transmission owners, who seek (according to Constellation) to prohibit such arrangements in service of their own corporate interest of selling transmission service to generators and interconnected load.
PDF page 2
2
Caught in the middle are existing customers. If, as Constellation requests, the Commission permits existing generation assets to exit the market to serve large loads behind-the-meter, the large load customers get the benefit of partially depreciated, lower cost existing resources while the remaining customers on the system are forced to pay for higher cost new generation. That is, new generation built to meet resource adequacy challenges caused almost exclusively by the large load customers that benefit from Constellation’s proposed arrangement. This scenario, where data center customers get lower-cost existing generation while everyone else pays for higher cost new facilities, is the exact opposite of requiring the data centers paying their “fair share” for the costs they impose. If the Commission permits such a paradigm, it is unequivocally choosing the corporate interests of a select few over the affordability of electric rates for everyday consumers. This complaint, although phrased as a dispute over interconnection, is at its heart a dispute over retail service arrangements, as data center customers are unquestionably end-use customers taking retail electric service. Before taking any action regarding co-located load generally or Constellation’s complaint specifically, the Commission should ensure that the solution to the problem alleged by Constellation does not make matters worse for retail customers, who are already facing unprecedented affordability issues posed by large load additions. Given that issues related to large load interconnection are under consideration by the Commission in Docket No. RM26-7-000, that is the appropriate proceeding for the Commission to carefully consider and craft a solution that enables expeditious large load interconnections without unfairly burdening consumers with a disproportionate share of the infrastructure costs. In that proceeding, the VSCC proposed a framework that would address issues related to large load interconnections, including co-located load, that would obviate the need to take specific PJM action in this proceeding.
PDF page 3
3
I. BACKGROUND
On November 22, 2024, Constellation filed a complaint under Federal Power Act (“FPA”) section 206 against PJM in Docket No. EL25-20-000. Constellation asserted in the complaint that the PJM Open Access Transmission Tariff (“Tariff”) is unjust, unreasonable and unduly discriminatory because it does not contain rules for governing interconnection of co-located loads. Constellation requested that the Commission find that the PJM Tariff is unjust, unreasonable and unduly discriminatory or preferential, and direct PJM to adopt in its Tariff certain portions of PJM’s Guidance on Co-Located Load.
On November 1, 2024, the Commission held a technical conference in Docket No AD24- 11-000, to discuss issues related to co-located load. The Commission noted several proceedings in the PJM Region that involved similar issues. On February 20, 2025, the Commission issued an order in Docket No. EL25-49-000 (the “Show Cause Order”), instituting a proceeding under FPA section 206. The Show Cause Order directed PJM and its Transmission Owners to either “(1) show cause as to why the Tariff, the Amended and Restated Operating Agreement of PJM, and Reliability Assurance Agreement Among Load Serving Entities in the PJM Region remain just and reasonable and not unduly discriminatory or preferential due to the lack of provisions specifically addressing colocation arrangements;” or (2) explain what changes to these governing documents would remedy the identified concerns if the Commission were to determine that the governing documents have become unjust and unreasonable or unduly discriminatory or preferential and, therefore, proceeds to establish a replacement Tariff.
On October 23, 2025, the Secretary of the Department of Energy (“Secretary”) directed the Commission to consider an Advance Notice of Proposed Rulemaking (“ANOPR”) regarding the interconnection of large loads to the interstate transmission system and issue a final action by April
PDF page 4
4
30, 2026.1 On October 27, 2025, the Commission issued a Notice Inviting Comments on the proposed ANOPR. The VSCC submitted Initial Comments and Reply Comments on the ANOPR on November 15, 2025 and December 5, 2025, respectively.
In its comments in Docket No. RM26-4-000, the VSCC requested that the Commission develop a set of Commission-mandated minimum standards for large load interconnections, while allowing transmission owners to continue to manage large load interconnection queues with direct oversight of their state regulatory commissions. The VSCC noted that these guidelines could permit the accelerated interconnection of large loads that are willing to bring their own generation or to be co-located with generation by creating a fast-track generator interconnection queue for those verified generation resources. In its Reply Comments, the VSCC included a specific proposed set of guidelines that would address large load interconnection (including co-located load), while respecting state regulatory authority.
II. ANSWER
A. Constellation’s Proposal Will Create New Affordability Challenges for
Retail Ratepayers and Necessarily Raises Questions of Federal Versus
State Jurisdiction Better Suited for Careful Consideration in the
Existing ANOPR Docket.
While Constellation argues that the PJM Tariff is unjust and unreasonable because it does not properly accommodate the specific co-located arrangement Constellation prefers and financially benefits from, the VSCC is unaware of any evidence indicating that the PJM tariff, specifically, is unjust and unreasonable necessitating a PJM-specific solution. Rather, to the extent
1 Secretary of Energy, Secretary of Energy’s Direction that the Federal Energy Regulatory Commission Initiate Rulemaking Procedures and Proposal Regarding the Interconnection of Large Loads Pursuant to the Secretary’s Authority Under Section 403 of the Department of Energy Organization Act (Oct. 23, 2025) (“ANOPR”).
PDF page 5
5
Constellation raises a legally cognizable issue for the Commission to resolve, it is how co-located load should be accommodated generally.
In its Supplemental Comments, Constellation asserts that the Commission can avoid jurisdictional arguments by “assert[ing] jurisdiction over hybrid facilities at a shared point of interconnection. The Commission’s jurisdiction is over the interconnection facilities, not any retail sale.”2 The actual reality is far more complicated than Constellation asserts, and obviously implicates state authority over retail sales. For example, Constellation urges the Commission to reject the argument that its jurisdiction over large load interconnection is limited to where transmission service is provided to customers as an unbundled product,3 directly asking the Commission to exercise jurisdiction over a retail sale (that also includes bundled transmission service).
In addition, Constellation claims that by only exercising jurisdiction over interconnections, the Commission need not concern itself with the retail wheeling prohibition in FPA section 212(h).4 Taking this argument to its logical conclusion reveals the absurdity of Constellation’s argument. Obviously, customers seeking interconnection are generally seeking such interconnection to take transmission service. If the customer is not requiring or taking transmission service, the co-location arrangement can be islanded from the grid. Yet, that is not what Constellation proposes. If, instead, the large load customer is permitted to take any service from the transmission system, the interconnection is by its very nature enabling retail wheeling as the data center is an end-use customer. Moreover, PJM does not have the ability to monitor whether
2 Supplemental Comments at 13.3 Id. at 18.4 Id. at 17-18; 18 U.S.C. § 824k(h).
PDF page 6
6
large load customers served via co-location arrangements are taking retail electric service from a non-utility provider, even if such sales are prohibited by state law.
Constellation acknowledges that PJM faces a significant reliability problem. It suggests that the Commission deal with this problem by “fix[ing] the market so it is better able to respond to the resource adequacy issue and … fix the load forecast.”5 Constellation is simultaneously requesting relief in this proceeding that would exacerbate resource adequacy and reliability issues before the Commission can try to fix the dysfunctional market. In the interim, Constellation and its co-locating data center customers benefit, while everyone else loses. Constellation reaps an additional windfall as a co-locating generator and owner of a generation portfolio that will benefit from a market that is both short of resources and expensive, as the recent PJM capacity auctions have demonstrated.
The relief requested by Constellation, which would have the Commission change the PJM tariff to accommodate the business arrangement Constellation prefers, will have real impact on non-data center customers at a time those customers are facing significant affordability issues. Constellation proposes to take existing generation resources that are currently serving customers off the market and dedicate these resources to a data center customer. These existing resources are depreciated, and thus significantly cheaper than the new facilities the remaining customers would have to pay for to replace the departing resource. At a time when state and federal regulators alike are endeavoring to ensure that data center customers pay their “fair share” of the costs they impose on the system, Constellation proposes that the Commission do the exact opposite. The ANOPR frames these issues, asking whether and, if so, how hybrid loads (including co-located loads) should be interconnected in all regions. Taking action specific to the PJM region
5 Supplemental Comments at 31.
PDF page 7
7
thus appears to be both premature and potentially harmful, to the extent it conflicts with later guidance through the NOPR process. The Commission should, therefore, reject Constellation’s request and focus its efforts on the ANOPR.
As the VSCC noted in its ANOPR comments, by promulgating a set of guidelines for all large load interconnections to be applied by transmission owners in their state tariffs, the Commission could remove barriers to all such interconnections, including co-located load. In addition to directing expedited queues for certain limited types of interconnection (including hybrid loads), the Commission should act within its existing jurisdiction to accelerate interconnection of generation needed to support load.
The VSCC also requested in Docket No. RM26-4-000 that the Commission schedule a technical conference to hear from all interested parties, including state commissions. To the extent Constellation has raised valid issues for Commission consideration that were not previously addressed in Docket No. AD24-11-000, these issues could be taken up in the NOPR technical conference.
B. Should The Commission Choose to Act on Constellation’s Complaint
Outside of the ANOPR Proceeding, the Commission Should Preserve
State Jurisdiction over Bundled Service and Protect Affordability by
Permitting Only New Resources to Serve Co-Located Load Absent
Sufficient Impact Studies For Existing Generation.
The VSCC is not necessarily opposed to co-located load and generator arrangements, and in the ANOPR proceeding proposed a process for such arrangements to receive expedited interconnection review. However, these arrangements must protect existing retail customers, else the arrangement act as a wealth transfer from retail customers to generating interests like Constellation. The VSCC does not believe that action now is warranted, but if the Commission chooses to act now, it must take two steps to protect existing retail customers.
PDF page 8
8
First, the Commission should make clear that co-located arrangements are not a means for data center loads to bypass restrictions on retail sales in vertically-integrated states like Virginia. With certain limited exceptions, retail customers in Virginia are required to take service from their incumbent utility, 6 and the Commission does not have jurisdictional authority to disturb these arrangements, even in the service of expanding data center interconnection. Vertically integrated states have made a policy determination that limited access to third-party generation is the best means to protect captive retail ratepayers, and the Commission should respect that policy choice. Second, if a generator proposes to remove an existing generation asset from service to dedicate the output of the generation to a co-locating data center load, the Commission should require that the generator be studied in the same manner as a retiring generator, including (if applicable) reliability must-run or similar arrangements. Otherwise, the remaining retail ratepayers (who are losing a generation asset otherwise available to them), will face retail rate increases. That these rate increases are matters of retail ratemaking is immaterial – the Commission should refrain from making the affordability issues these ratepayers face worse in the interest of protecting Constellation’s business model.
III. CONCLUSION
WHEREFORE, for the foregoing reasons, the VSCC requests that the Commission reject Constellation’s Motion to Expedite, deny Constellation’s complaint and terminate the Show Cause proceeding without further action.
6 Virginia Code § 56-577.
PDF page 9
9
Respectfully submitted,
/s Frederick D. Ochsenhirt
Frederick D. Ochsenhirt
Legal Advisor to the Commission – Federal Regulatory Affairs
Virginia State Corporation Commission P.O. Box 1197
Richmond, Virginia 23218
(804) 371-9671
Dated: December 15, 2025
PDF page 10
10
CERTIFICATE OF SERVICE
I hereby certify that the foregoing has been served in accordance with 18 C.F.R. Section 385.2010 upon each person designated on the official service list compiled by the Secretary in this proceeding.
/s Frederick D. Ochsenhirt
Frederick D. Ochsenhirt
Legal Advisor to the Commission – Federal
Regulatory Affairs
Virginia State Corporation Commission
P.O. Box 1197
Richmond, Virginia 23218
(804) 371-9671
Dated at Richmond, Virginia this 15th day of December, 2025.