EL25-49-000 · 2025-12-15 · Virginia State Corporation Commission

Answer of the Virginia State Corporation Commission in opposition to Constellation Energy Generation, LLC's Motion to File Supplemental Comments

Text extracted from the eLibrary original (SHA-256 2c3b30efc3d2ff73…). Download the original from the official source.

Contents · 5 sections
  1. I. BACKGROUND p. 3
  2. II. ANSWER p. 4
  3. A. Constellation’s Proposal Will Create New Affordability Challenges for p. 4
  4. B. Should The Commission Choose to Act on Constellation’s Complaint p. 7
  5. III. CONCLUSION p. 8

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Retail and wholesale authority · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

If, as Constellation requests, the Commission permits existing generation assets to exit the market to serve large loads behind-the-meter, the large load customers get the benefit of partially depreciated, lower cost existing resources while the remaining customers on the system are forced to pay…
Read this passage Filed comments: Connecting load and generation

I. BACKGROUND

printed heading · Topic match: Connecting load and generation

Constellation requested that the Commission find that the PJM Tariff is unjust, unreasonable and unduly discriminatory or preferential, and direct PJM to adopt in its Tariff certain portions of PJM’s Guidance on Co-Located Load.
Read this passage Filed comments: Connecting load and generation

II. ANSWER

printed heading

II.
Read this passage

A. Constellation’s Proposal Will Create New Affordability Challenges for

printed heading · Topic match: Reliability and curtailment

Constellation proposes to take existing generation resources that are currently serving customers off the market and dedicate these resources to a data center customer.
Read this passage Filed comments: Reliability and curtailment

B. Should The Commission Choose to Act on Constellation’s Complaint

printed heading · Topic match: Cost allocation

However, these arrangements must protect existing retail customers, else the arrangement act as a wealth transfer from retail customers to generating interests like Constellation.
Read this passage Filed comments: Cost allocation

III. CONCLUSION

printed heading

Ochsenhirt Legal Advisor to the Commission – Federal Regulatory Affairs Virginia State Corporation Commission P.O.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Section 385.2010 upon each person designated on the official service list compiled by the Secretary in this proceeding. /s Frederick D.
Read this passage