Order on Show Cause Proceeding, Directing Compliance Filings, etc. re Allegheny Electric Cooperative, Inc. et al. v. PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 3aacfda4d681b088…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
EL25-20 involving Co-Located Load.[fn:4] As discussed below, we find that PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and…Read this passage Filed comments: Connecting load and generation
Background
printed heading · Topic match: Connecting load and generation
PSE&G argues that the Commission should establish ancillary services charges for Co-Located Load configurations based on actual use consistent with cost causation principles.[fn:130] Reply Comments General Several commenters urge the Commission to ensure any cost allocation to Co-Location…Read this passage Filed comments: Connecting load and generation
Discussion
printed heading · Topic match: Connecting load and generation
As the Commission explained in Order No. 845, Interconnection Customers may seek provisional interconnection service when available studies or additional studies as necessary indicate that there is a level of interconnection service that can occur without any additional Interconnection Facilities…Read this passage Filed comments: Connecting load and generation
Conclusion
printed heading · Topic match: Cost allocation
As we establish new transmission services, it cannot come at the expense of other ratepayers.Read this passage Filed comments: Cost allocation
Footnotes
Word notes · Topic match: Connecting load and generation
Tariff clarity is essential to reduce unnecessary disputes, avoid case-by-case confusion, and enable transmission providers to process interconnection and load addition requests efficiently and predictably.”). [fn:378] PJM March 24 Response at 32 (“Nevertheless, clarifications and enhancements…Read this passage Filed comments: Connecting load and generation