Non-Decisional: Emerald AI submits comment to FERC's Chairman and Commissioners regarding the FERC Co-Location Show Cause to PJM , (the two redactions…
PDF page 1
Thank you for the time connecting with your office at the FERC holiday festivities last month.
I am Emerald AI’s senior advisor on power and utilities strategy and was pleased to have with me at FERC, Emerald AI’s CEO Dr. Varun Sivaram. As we discussed, Emerald AI is a pioneering technology company, backed by NVIDIA, whose software makes AI data centers flexible users of power—capable of receiving dispatch signals from system operators and adjusting the power use of AI computations in tandem with utilizing any potential onsite energy resources.
Below are some takeaways from my review of the FERC Co-Location Show Cause to PJM (“Show Cause Framework and Emerald AI Validations”). The Show Cause order addresses the immediate mechanics of co-location – the information below provides a picture into the behind-the-scenes tech stack and strategy that will make this possible in reality, largely backed by orchestration solutions Emerald AI is building and deploying in the field today at AI factory GPU clusters which benefit from co-located assets, or, no co-located generation assets.
Emerald AI’s goal is to ensure that there are live projects operating in the field on US electric grids within the next two years to prove out a flexible fast track for loads with software-defined flexibility that can help balance the grid with or without 1:1 co-located generation. In 2025, Emerald AI conducted four demonstrations in partnership with EPRI, NVIDIA, utilities, and leading AI companies across the United States and United Kingdom to prove AI power flexibility across four commercial, production-grade data centers. In 2026, Emerald AI will announce with NVIDIA and Digital Realty the world’s first commercial-scale power-flexible “AI Factory”: the 96MW Aurora AI data center in Manassas, Virginia (Dominion transmission and distribution service territory). We’d be pleased to continue conversations with your office and with technical SMEs on our work to practically achieve flexibility solutions. Please do not hesitate to reach out to us for a briefing at any time.
Best Regards,
Arushi Sharma Frank
Emerald AI Senior Advisor, Power & Utilities Strategy
Arushi.sharmafrank@emeraldai.co | alt: arushisharmafrank@live.com
Ph: 571.572.9037
Attachments:
1. Emerald AI One-Year Review
2. Bios: Emerald AI CEO | Chief Scientist | Utilities Power Senior Advisor
PDF page 2
PJM Show Cause Framework and Emerald AI Validations
Takeaways
• Emerald AI’s validations in the field on live data center computation loads (training and inference) provide the physical and operational evidence that PJM’s proposed "Contract Demand" tariffs are safe. They prove that a co-located load can serve as its own "shock absorber," creating a dispatchable reliability asset that sits behind the meter but solves front-of-meter constraints with a combination of bankable flexibility solutions that include computation orchestration (shifting, slowing, pausing, calibrating while assuring required customer computational performance) and co-management of dispatch from generation and batteries.
PDF page 3
Emerald’s validations demonstrate that computation load can be a dynamic, dispatchable resource that can actively manage dispatch risk, effectively serving as its own "locational dispatch solution” baked into a larger schema for operating computation (data center) facilities in the novel ways proposed in the Show Cause order (firm contract demand transmission service; non-firm contract demand transmission service; interim network integration transmission service).
1. Operationalizing "Firm Contract Demand" (Figure 2):
Emerald’s technology allows for privatization of delivery risk to computation loads greater than what a firm grid power ceiling could provide, as proposed in Figure 2. The diagram only contemplates that if there is a 100 MW firm service limit above which the grid offers no reliability, the customer must bring 900 MW of reliable onsite generation to fill the gap. Emerald’s validations (specifically the Aurora AI Factory and Nature Energy peer-reviewed data from the Salt River Project demo with Oracle, NVIDIA, and EPRI) finesse this logic. By dynamically flexing compute power—the firm cap is a dispatch signal around which the developer of the power supply can choose to privatize the reliability risk through software controls rather than exclusively through hardware redundancy. From the grid’s perspective, the appearance of generation to match the load does not change. From the site operator’s perspective, the matching of load to generation is a shaping of generation dispatch hours and computation flexibility hours, paired together for a hyper efficient solution to meet reliability needs without compromising compute service-level agreements.
2. Figure 3: Making "Non-Firm" (Figure 3) Bankable_ Validating the "As-Available" Use Case
The Show Cause order positions Non-Firm Contract Demand as a backstop solution where the grid has no obligation to serve, potentially implying that standard data centers cannot function here without 100% redundant backup. Emerald’s platform transforms "as-available" service into a commercially viable operational mode: the AI factory can actively reshape its demand profile to match the "0 to 1000 MW" fluctuation shown in PJM’s Figure 3. An AI load can accept a Non-Firm tariff without overbuilding diesel infrastructure, effectively privatizing the curtailment risk through compute modulation that aligns with the "as-available" reality of the transmission system.
PDF page 4
3. Anti-Toggling (Guarding against unreserved use): Emerald AI’s technology platform is primed to provide an all-around virtual protection scheme to manage around regulatory anxiety that a co-located load will accidentally drift into "unreserved use" during a generator trip or system disturbance, leaning on system inertia and causing a blackout. The Salt River Project (SRP) demonstration validated that Emerald’s platform acts as a virtual "protection scheme" or governor. By successfully cutting power draw by ~25% for three hours during a peak event while meeting performance targets, the technology provides the mechanical assurance that the facility will not drift. It ensures the load physically adheres to the contracted service level, directly satisfying the FERC requirement for strict compliance with the new tariff boundaries and mitigating the "free rider" reliability concern.
4. Locational Dispatch: The AI Factory as a Nodal Asset Based on the Order on Show Cause section establishing the new Firm Contract Demand and Non-Firm Contract Demand services (Paragraphs 204–209), the Commission frames the load modeling as a static constraint at a specific point of interconnection, rather than as a dynamic, price-responsive node. This is largely the product of the capacity market construct in which these tariff changes typically live, where PJM plans transmission and procures reserve capacity for fixed blocks (sinks) of load at specific PJM buses. Emerald AI’s platform—particularly via the coming capabilities of the Aurora demonstration site (Nvidia, Digital Realty – Dominion transmission and distribution service territory, Manassas, VA)—introduces the missing variable: the ability for site-specific load to actively respond to LMPs and local congestion. While the Order discusses "curtailment" for Non-Firm service (Paragraph 209), it frames this strictly as a reliability action ("curtailed during emergency operations"), not as an economic response to Locational Marginal Pricing (LMP). The service is currently defined by reservation priority, not by an economic dispatch curve.
A core objective of the Aurora project will be to lean into the dynamic capabilities of the load, factor that capability into Dominion’s planning, and support similar outcomes for PJM review—specifically, allowing for a framework to model the site- specific load as a resource that resolves congestion or prevents it through constraint management. The core differentiator between how load is planned and “called on” for economic dispatch in PJM versus ERCOT is also the heart of the disagreement regarding the reliability contribution of flexible load between PJM and the PJM Market Monitor. This topic is explored here and arrives at where Emerald AI believes the markets must land: future iterations of these tariff designs must
PDF page 5
provide RTOs an option to utilize large electronic loads as dispatchable ISO resources, placing them on the same footing as nodal dispatchable generators.
5. Grid-Flexible AI Technology Stack - Emerald AI as the Site Orchestrator in Virginia:
The Aurora project demonstrates a technology stack where Emerald AI acts as the central orchestrator—the intelligence layer sitting between the site’s internal puzzle pieces and the utility operator.
• The Orchestration Layer: Emerald is not just providing software; it is acting as the bridge between the Site Controller (managing the facility's physical plant) and the Energy Manager (optimizing cost and dispatch). In this architecture, Emerald translates grid signals into compute actions, effectively turning the data center’s server racks into a dispatchable resource that the utility can "see" and trust.
• Grid Signal Integration: For Aurora, this means ingesting real-time signals
originating from a combination of PJM
and Dominion event calls (aggregating Dominion’s specific rider notices (often capped at 120–150 hours/year) with PJM’s broader emergency load management alerts). The site engineering team across Nvidia and Emerald are co-designing for an insurance band of curtailment hours:
(While Dominion’s retail customer tariff allows for control events of "four to six hours", the "1.6 hours" average reflects the active response required to shave the specific coincident peak, rather than the full window of the alert.) Emerald’s platform automates the response to these signals, ensuring the facility sheds load instantly without manual intervention.
• Going Beyond "Cap Flex": While Dominion’s Cap Flex program is designed for existing customers to flex around known constraints, the Aurora demo factory is a greenfield opportunity to go further, i.e., handle static curtailment, and actively
PDF page 6
manage local transmission constraints and congestion signals dynamically. This moves Cap Flex, creating the sandbox for precision tools that could expedite a new project (rather than only cap/limit an existing one looking for more transmission capacity).
• Validation via Power Quality Metering: To prove this works, the partners will install a Power Quality Meter (PQM) at the point of interconnection (a standard requirement for every new connection, including this site). This meter provides the "truth data" that validates the site's response to grid events, ensuring that when Emerald orchestrates a flex down, the grid sees the exact relief it requested.
6. Emerald Validation with National Grid UK: The National Grid live trial in London in December 2025 with Emerald’s "Conductor" platform introduces true Locational Dispatch. Because the AI factory can modulate its consumption in real-time (seconds-based guaranteed curtailment response in furtherance of numerous system strength/grid need experiments), it provides a counter-flow effect at its specific node. In a co-location scenario (Figure 2 or 3 from FERC diagram above), this means the AI factory can dispatch itself down to relieve local transmission constraints without sole reliance on generation-switching, effectively serving as a Non-Wire Alternative (NWA) solution that PJM’s static planning models fail to capture.
7. The "Interim" Bridge (Figure 4): Accelerating Interconnection
The Aurora reference design is intended to turn the "waiting room" approach described in Figure 4., into the final destination. If an AI factory is certified as "Power-Flexible" (capable of relieving grid stress), it may never need to graduate to the full "Firm Service" upgrades required in Figure 4 noted above. This challenges the baseline assumption that "Interim" is just a temporary state; Emerald’s demo projects will validate that for flexible AI loads, "Interim" (Non-Firm) coupled with intelligent compute modulation is a permanent, stable, and reliable end-state. This vision is shared by Emerald’s data center OEM partners and its core investors, including Nvidia.
[End of Takeaways Primer: Emerald AI Validations]