EL25-49-002 · 2026-01-16 · Exelon Corporation, The FirstEnergy Transmission Companies

The Indicated PJM Interconnection, L.L.C. Transmission Owners submit Request for Rehearing of the 12/18/2025 Order

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-001

Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.
)

)

)
Docket No. EL25-20-001
(consolidated)

REQUEST FOR REHEARING OF THE INDICATED PJM TRANSMISSION OWNERS

Pursuant to Federal Power Act (“FPA”) section 3131 and Rule 7132 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), the Indicated PJM Interconnection, L.L.C. (“PJM”) Transmission Owners (“Indicated TOs”)3 request rehearing of the Commission’s order in the above-captioned dockets.4  The Commission’s 206 Order is arbitrary and capricious and not based upon reasoned decision making.  The Commission’s directive for changes to the PJM Open Access Transmission Tariff (“PJM Tariff”) exceeds the Commission’s jurisdiction and is not permitted under the FPA.

1
16 U.S.C. § 825l(a).
2
See 18 C.F.R. § 385.713.
3 This filing was prepared on behalf of the following PJM Transmission Owners:  Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company (“ComEd”), Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”).
4 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“206 Order”).

PDF page 2

2

Before turning to the problems with the Commission’s decision to impose new Contract Demand Network Service (“CD Service”)5 and a new interim non-firm transmission service (“Interim Service”), the Indicated TOs wish to express their support for certain helpful clarifications in the 206 Order: (1) An Eligible Customer6 serving a co-located load must be designated because it is the Eligible Customer that seeks and obtains transmission service and pays for it;7 (2) Transmission service to co-located loads must be metered (apart from metering of any retail energy sales or distribution services);8 (3) Existing Network Integration Transmission Service (“NITS” or “Network Service”) should be based on Gross Load; 9 and (4) Behind the Meter Generation (“BTMG”) provisions do not apply to co-located loads or provide a basis to take transmission service on a basis other than gross load.10

5 “CD Service” herein refers both to the firm and non-firm options prescribed by the 206 Order.
6 An “Eligible Customer” is defined in the PJM Tariff to mean the following:
(i) Any electric utility (including any Transmission Owner and any power marketer), Federal power marketing agency, or any person generating electric energy for sale for resale is an Eligible Customer under the Tariff.  Electric energy sold or produced by such entity may be electric energy produced in the United States, Canada or Mexico.  However, with respect to transmission service that the Commission is prohibited from ordering by Section 212(h) of the Federal Power Act, such entity is eligible only if the service is provided pursuant to a state requirement that the Transmission Provider or Transmission Owner offer the unbundled transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner.

(ii) Any retail customer taking unbundled transmission service pursuant to a state requirement that the Transmission Provider or a Transmission Owner offer the transmission service, or pursuant to a voluntary offer of such service by a Transmission Owner, is an Eligible Customer under the Tariff.  As used in Tariff, Part VI, Eligible Customer shall mean only those Eligible Customers that have submitted a Completed Application.

PJM Tariff, OATT Definitions – E-F, at 2.
7 See 206 Order, 193 FERC ¶ 61,217 at P 241.
8 See id. P 206. 9 See id. P 194.
10  See id. P 186.

PDF page 3

3

These clarifications should sufficiently answer the relevant questions presented by this proceeding.  While the Indicated TOs appreciate the Commission’s leadership in addressing this issue, the 206 Order goes beyond these clarifications and attempts to fix something that is not broken.  There are indeed issues requiring attention in the PJM wholesale markets—including resource adequacy, reliability, and affordability challenges for reasons other than transmission service offerings and rates—but the creation of new forms of transmission service does not address those challenges and instead risks making those very real problems worse.

“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”11  The existing transmission services under the existing PJM Tariff are consistent with those goals and are just and reasonable. No one has satisfied the burden under FPA section 20612 to demonstrate that the existing tariff is unjust and unreasonable.  Nor has the burden been satisfied to demonstrate that the Commission’s replacement rate is just and reasonable.  The Commission’s replacement rate that imposes new CD Service and Interim Service options could directly place at risk the reliability of PJM’s electric grid and grant an undue preference to certain categories of customers.  The new services could allow co-located load to pay for a different share of transmission system embedded costs than other customers, thereby resulting in rates that are not just and reasonable.

It appears that the primary driver of the Commission’s ruling was a desire to speed service to certain customers—those who are co-located with generators.13  The Indicated TOs support the desire to allow prompt service to all customers at locations that make efficient use of the existing

11  Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022). 12  16 U.S.C. § 824e.
13  See, e.g., 206 Order, 193 FERC ¶ 61,217 at P 200.

PDF page 4

4

system, but the CD Service and Interim Service do nothing to advance those goals.  Instead, the new services are premised on the fiction that a customer taking CD Service or Interim Service imposes different burdens on the grid than customers taking traditional network service.  From this false premise the Commission draws two conclusions.  First, the Commission concludes that, because co-located loads impose fewer burdens on the system, such facilities, and especially co- located load facilities combined with system protection commitments, should be encouraged through special incentives to minimize the need for system upgrades.  As demonstrated later herein, new load already has powerful incentives to site their facilities and utilize protective equipment to minimize the need for system upgrades and to avoid the delays attendant to system upgrades.  But the question of whether new transmission upgrades are needed to accommodate a new load must be based on engineering and technical data, such as the extent of the load, its operating characteristics, and how the system will react under various scenarios to changes in the load.  Such studies will not be based simply on theoretical net load regardless of whether imperfect protective systems are in place.

The false presumption that co-located facilities impose reduced burdens on the system drives a second Commission assumption that co-located loads should pay lower rates than other users.  This proposition violates a long-held Commission policy that all users of the transmission network should pay the same load-ratio share of network cost, regardless of claims that some users impose different burdens on the system.  As demonstrated herein, the demands on the system of co-located loads are material and no less significant than the burdens on the system of other transmission users whose demands for special rates consistently have been rejected.  Placing the meter for the load at a different location, or establishing a contractual arrangement for service thereto, does nothing to alter the physics of operating the system.  As explained in detail later, co-

PDF page 5

5

located loads derive significant operational and financial benefits from being interconnected with the grid.  These benefits significantly outweigh the cost of paying full network service rates. There has been no demonstration that the existing rate is not just and reasonable, and the Commission has not demonstrated that any replacement rate is anything other than arbitrary and capricious.  The Commission should therefore reverse its decision and reaffirm that the existing PJM tariff is just and reasonable.

I. Statement of Issues/Specification of Error.
In accordance with 18 C.F.R. § 385.713(c)(1) and (2), the Indicated TOs provide the following specification of errors and statement of issues, including citations to representative Commission and judicial precedent.

1. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has Not Been Shown to Be Unjust and Unreasonable.  See 16 U.S.C. § 824e(a); Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021) (explaining that “[t]he burden of proving” that a rate is unjust or unreasonably is placed on “the party that initiated the proceeding”).

a. There is No Evidence In the Record That Co-Located Loads Are
Unable to Obtain Reliable, Timely, and Reasonably Priced Service
Using the Existing Network Service Construct.  Therefore, the
Commission
Fails
To
Satisfy
the
Requirement
Under
the
Administrative Procedure Act That Its Decision Be Supported With
Substantial Evidence.
i. The Administrative Procedure Act (“APA”) requires the
Commission to “examine the relevant data and articulate a
satisfactory explanation for its action including a ‘rational
connection between the facts found and the choice made,’” and
to base its decision on substantial evidence; because FERC has
failed to do so, its decision is arbitrary and capricious.  Motor
Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co. (“State
Farm”), 463 U.S. 29, 43 (1983) (citation omitted); see Fla. Gas
Transmission Co. v. FERC (“Florida Gas”), 604 F.3d 636, 639
(D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate
that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y. v. NLRB, 305 U.S. 197, 229 (1938) (explaining that substantial

PDF page 6

6

evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

ii. The PJM Tariff provides two transmission service options (Network Integration Transmission Service and Point-to-Point Transmission Service) and includes provisions to explain how those services work and how Network Customers will be Served. See PJM Tariff at §§ 31.1, 31.2, 31.3, 31.6 and 32; see also generally PJM Tariff , OATT Definitions.

iii. To the extent that parties have argued they are unable to interconnect or are experiencing delays, that is false and any delay is of their own making.  See, e.g., Exelon Dec. 8, 2025 Comments at 3-4; Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20, at Ex. 5 Attach 1 (providing Exelon’s Nov. 12, 2024 Letter).  FERC arbitrarily and capriciously disregarded evidence in the record that Network Service under the current tariff is feasible and has been used for co-location arrangements.  Compare PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) and PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule F, Part F.4 (June 1, 2024), with Press Release, Talen Energy, Talen Energy Expands Nuclear Energy

Relationship
with
Amazon
(June
11,
2025),
https://ir.talenenergy.com/news-releases/news-release- details/talen-energy-expands-nuclear-energy-relationship-amazon. See also Exelon Dec. 8, 2025 Comments at 6.

iv. Ignoring data in the record regarding the ability of co-located load to interconnect to the transmission system violates the APA and renders FERC’s decision arbitrary and capricious.  See State Farm, 463 U.S. at 43.

v. There is no evidence in the record that the cost of Network Service impacts the development of data centers.  Nor is there evidence to support that Network Service imposes unnecessary upgrades on all customers.  Nor is there evidence that new forms of transmission service will allow for faster interconnection.  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

vi. The Commission has not met its burden under FPA section 206 because it acknowledges that the existing transmission services

PDF page 7

7

remain just and reasonable options.  See 206 Order, 193 FERC ¶ 61,217 at P 195 (finding Network Service charged on a gross demand basis to be “one just and reasonable transmission service option”).

b. The Commission Did Not Engage in Reasoned Decision Making Because It Did Not Explain its Departure from FERC Precedent or Refute that, Because the Existing PJM Tariff Provides Service on the Same Basis for All Customers, the Existing PJM Tariff Does Not Grant an Undue Preference.  See F.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); New England Power Generators Ass’n v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.”); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ and Commission cases are no exception.”) (citations omitted); Cal. Pub. Utils. Comm’n v. FERC, 879 F.3d 966, 977 (9th Cir. 2018) (“FERC departed from this policy without acknowledgment or explanation.  This departure was arbitrary and capricious.”); Sw. Airlines Co. v. FERC, 926 F.3d 851, 856 (D.C. Cir. 2019) (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . . [FERC] must at least ‘acknowledge’ its seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (most alterations in original) (citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a public utility from making or granting an “undue preference or advantage” or from maintaining “any unreasonable difference in rates, charges, service, facilities, or in any other respect, . . . as between classes of service”); TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12–13 (D.C. Cir. 2015) (remanding because FERC did not adequately explain its position).

i. The Commission has a long-standing policy of rejecting
attempts by network transmission customers to avoid paying
their load ratio share of system cost.  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237 at PP 40–41, denying clarification & addressing arguments raised on reh’g, 173 FERC ¶ 61,043 at PP 13–14 (2020); see Promoting

Wholesale Competition Through Open Access Non-Discriminatory

PDF page 8

8

Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888- A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,324 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002); see also, e.g., Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005); Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam); Idaho Power Co., 106 FERC ¶ 61,329 (2004); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015); Preventing Undue

Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890- C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).

c. The Loads Rely Upon the Entire Embedded Transmission System to Serve Their Full Gross Load.  Therefore, FERC’s Decision is Arbitrary and Capricious Because the Embedded Transmission System Costs Should Be Charged For Those Transmission Services.  See Decl. of David Weaver, PE, Attachment 1 to Exelon Comments, Docket No. EL25- 20 (Dec. 12, 2024); see also PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of Danielle S. Powers, at P 29.

i. The Commission’s failure to consider the benefits of grid interconnection makes the 206 Order arbitrary and capricious. See State Farm, 463 U.S. at 43.

ii. The Commission’s 206 Order is arbitrary and capricious because it failed to consider the unique issues that attend co- location with nuclear plants.  See id.; Decl.  of David Weaver, PE, Attachment 1 to Exelon Comments, Docket No. EL25-20 (Dec. 12, 2024).

2. The Burden Has Not Been Met Under FPA Section 206: FERC’s Replacement Rate is Not Just and Reasonable.  See 16 U.S.C. § 824e(a); Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. 2017) (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate ... and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just

PDF page 9

9

and reasonable rate.”) (alterations in original) (citation omitted); Emera Maine v. FERC, 854 F.3d 9, 21 (D.C. Cir. 2017); Atl. City Elec. Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002).  The 206 Order failed to address the fact that reliability is relevant to the inquiry of whether a rate is just and reasonable.  See Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022) (“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”); NAACP v. FPC, 425 U.S. 662, 669–70 (1976) (“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”).

a. Allowing Special Treatment For Co-Located Load Violates the FPA’s Requirement That There Be No Undue Preference Or Unreasonable Difference In Rates Between Classes of Service.  See 16 U.S.C. § 824d(b).

i. To the extent that the Commission suggests that the
transmission provider may move forward with interconnection before studies are completed, such course of action would jeopardize reliability and would be in tension with NERC reliability standards.  See, e.g., See NERC, FAC-002-4 – Facility Interconnection

Studies
(2022), https://www.nerc.com/globalassets/standards/reliability- standards/fac/fac-002-4.pdf; NERC, 181 FERC ¶ 61,126 (2022) (approving FAC-002-4).

ii. There is no lawful basis to require tariff changes to impose new forms of service that give certain customers a reduced share of embedded costs compared to all other users when they receive the same benefits.  See Coal. of MISO Transmission Customers v. FERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022).

b. The Commission’s Emphasis on Protective Systems Is In Tension With the Commission’s Open Access Policies and Therefore Is Arbitrary and Capricious.  The Commission Also Erred In Minimizing the Fact that Protective Systems Can and Have Failed.  See NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at

13
(July
2025),
https://www.nerc.com/globalassets/who-we-
are/standing-committees/rstc/whitepaper-characteristics-and-risks-of- emerging-large-loads.pdf.

i. The Commission erred in adopting a policy in tension with its open access policies.  See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order

PDF page 10

10

No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

c. The 206 Order is Arbitrary and Capricious in Abandoning the Main Construct of Service to Load, Which is That Customers Share In the Embedded Costs of the System.  The Commission Also Erred in Adopting a Generator Funding Model for The Funding of Network Upgrades for Co-Located Load with No Supporting Evidence.  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

i. FERC’s order is arbitrary and capricious in abandoning the main construct of service to load, which is that customers share in the embedded costs of the system.  See State Farm, 463 U.S. at 43; Coal. of MISO Transmission Customers, 45 F.4th at 1009 (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)).

ii. The Commission’s proposal that co-located load must self-fund any needed transmission upgrades is arbitrary and capricious because FERC has not explained its decision to depart from prior precedent.  See F.C.C. v. Fox Television Stations, Inc., 556 U.S. at 515 (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); New England Power Generators Ass’n, 881 F.3d at 211 (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.”); W. Deptford Energy, LLC, 766 F.3d at 20 (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ and Commission cases are no exception.”) (citations omitted); Cal. Pub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this policy without acknowledgment or explanation.  This departure was arbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . . [FERC] must at least ‘acknowledge’ its seemingly inconsistent precedents and either

PDF page 11

11

offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (most alterations in original) (citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a public utility from making or granting an “undue preference or advantage” or from maintaining “any unreasonable difference in rates, charges, service, facilities, or in any other respect, . . . as between classes of service”); TransCanada Power Mktg. Ltd., 811 F.3d at 12–13 (remanding because FERC did not adequately explain its position).

iii. The 206 Order departs from traditional cost causation principles and fails to explain or justify its departure.  See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020); see also Fox Television Stations, Inc., 556 U.S. at 515 (“[T]he requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”) (citation omitted).

iv. The Commission provides no record evidence nor a reasoned explanation for why co-located load should not be charged like other load, i.e., with the upgrade cost recovered as part of the transmission rates charged to all customers.  Transmission owners are permitted to earn a reasonable return on the investments necessary to construct, operate, and maintain transmission facilities, including those network upgrades required to serve co-located load.  See, e.g., Fed. Power Comm’n

v. Hope Nat. Gas Co., 320 U.S. 591 (1944); Bluefield Water Works & Improvement Co. v. Pub. Service Comm’n of W. Va., 262 U.S. 679 (1923).

d. The Commission is Wrong in Suggesting That CD Service Will Promote Efficiency or Change Siting.

i. The Commission’s decision to require options for CD Service does not change how the study process or the regional planning process should work.  See PJM Tariff §§  31.1-31.3, 31.6, 32.

ii. The Commission’s decision against the netting of behind the meter generation and the stated reasons for that decision cannot be logically reconciled with the structure it proposed for the new transmission services and its decision is therefore arbitrary and capricious.  See State Farm, 463 U.S. at 43.

PDF page 12

12

e. The
Commission’s
Disregard
of
Reliability
Considerations
Underscores that the Replacement Rate is Not Just and Reasonable. See Constellation Mystic Power, LLC, 45 F.4th at 1035 (“The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”); NAACP v. FPC, 425 U.S. at 669–70 (“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”).

3. FERC Exceeded Its Jurisdiction.  See 16 U.S.C. § 824(b). a. FERC’s Replacement Rate Violates the Major Questions Doctrine.  See West Virginia v. EPA, 597 U.S. 697, 723 (2022); Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”); see also Midship Pipeline Co., v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly”) (quoting West Virginia v. EPA, 597 U.S. at 723); see Atl. City Elec. Co. v. FERC, 295 F.3d 1, 8 (D.C. Cir. 2002) (As a federal agency, “FERC is a ‘creature of statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted).

b. The Commission’s New Approach Infringes on State Retail Authority.
i. The Commission’s new approach infringes on state jurisdiction and is distinguishable from wholesale demand response

programs.  See 16 U.S.C. § 824(b); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 270, 278–79 (2016); FERC, Energy Primer: A Handbook for Energy Market Basics, at 41 (Jan. 17, 2024),

https://www.ferc.gov/news-events/news/ferc-staff-issues-
2024-energy-primer-handbook-energy-market-basics.
ii. The Commission is unable to do indirectly what it cannot do directly.  Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909

F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this directly were established, the existence of power to achieve the same end indirectly through the conditioning power might well be doubted” (quoting Sunray Mid-Continent Oil Co. v. FPC, 364

U.S. 137, 152 (1960) and citing Richmond Power & Light v.
FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve indirectly through conditioning power of Federal Power

PDF page 13

13

Act what it is otherwise prohibited from achieving directly)); Am.
Gas Ass’n v. FERC, 912 F.2d 1496, 1510 (D.C. Cir. 1990) (“[T]he
Commission may not use its § 7 conditioning power to do
indirectly . . . things that it cannot do at all.”); see also FERC v. Elec.
Power Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room
either for direct state regulation of the prices of interstate
wholesales’ or for regulation that ‘would indirectly achieve the same
result.’”) (citation omitted).
II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate
Has Not Been Shown To Be Unjust And Unreasonable.

The FPA requires that the rates and charges of a public utility “in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”14 “[A]ny such rate or charge that is not just and reasonable is . . . unlawful.”15  Under FPA section 206, the Commission may, by its own motion or upon complaint from a third party, remedy any “rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” found to be “unjust [or] unreasonable.”16  “The burden of proving an unjust or unreasonable rate rests with the party that initiated the proceeding—that is, the Commission or the third-party complainant.”17  In other words, a respondent to a FPA section 206 complaint is not required to make an affirmative showing that its existing rate is still just and reasonable. For the reasons below, complainants in the above-captioned dockets (i.e., the Commission and Constellation) have failed to meet their burden of demonstrating that PJM’s current rate is unjust and unreasonable.

14  16 U.S.C. § 824d(a).
15  Id.
16  Id. § 824e(a).
17  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021).

PDF page 14

14

A. There is No Evidence In The Record That Co-Located Loads Are Unable to
Obtain Reliable, Timely, And Reasonably Priced Service Using The Existing
Network Service Construct.  Therefore, the Commission Fails To Satisfy The
Requirement Under The APA That Its Decision Be Supported With
Substantial Evidence.

Under the APA, the Commission “must examine the relevant data and articulate a
satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made’”18 and must base its decision on substantial evidence in the record.19  Substantial evidence means “more than a mere scintilla,” that is, “such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.”20  The Commission’s 206 Order does not satisfy this requirement.

The Commission states that “PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to Interconnection Customers21 serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.”22  The Commission also states that “the absence of such provisions leaves entities unable to determine what steps they must take to effectuate Co-Location Arrangements of various configurations.”23

This finding has no citation to evidence.  There is none.  Under the current PJM Tariff, there are two transmission service options: (1) Network Integration Transmission Service (“NITS”

18  State Farm, 463 U.S. at 43 (citation omitted).
19  See, e.g., Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’” (quoting Pac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004))); see also 5 U.S.C. § 706.
20  Consol. Edison Co. of N.Y., 305 U.S. at 229.
21  PJM’s Tariff defines “Interconnection Customer” to “mean a Generation Interconnection Customer and/or a Transmission Interconnection Customer.” PJM Tariff, OATT Definitions – I – J - K, at 4.
22  206 Order, 193 FERC ¶ 61,217 at P 175.
23  Id.

PDF page 15

15

or “Network Service”);24 and (2) Point-to-Point Transmission Service.25  There is no inability to determine how to serve load in PJM, whether or not co-located; the PJM Tariff already has provisions explaining how Network Service works and how loads of Network Customers will be served.  The starting point is Section 31.1 of the PJM Tariff, which (mirroring the Commission’s own pro forma Open Access Transmission Tariff (“OATT”)) requires that Network Loads are to be specified in the Service Agreement.  The PJM Tariff sets forth in Sections 31.2 and 31.3 the procedures for identifying new Network Loads that will be served by the Network Customer.  If, and to the extent that, study is required of the request, the requirements of that study are spelled out in Section 32 of the PJM Tariff.  And, in recognition of the fact that loads change after commencement of service, Section 31.6 provides the process by which to report on changing loads. These tariff provisions have been in place for decades, and are not even mentioned in the 206 Order, which does not begin to explain how the Network Service construct and existing PJM Tariff rules and precedent fail to provide a mechanism for reasonable service to loads of all sorts. The Commission cites the Constellation Complaint and comments submitted by

Constellation in support of its claim that there is “uncertainty.”26  But the actual situation described in the Constellation Complaint giving rise to the purported uncertainty revealed that any delay resulted from a decision made by Constellation in its attempt to bypass retail service requirements

24  Under the PJM Tariff, “Network Transmission Service” “mean[s] transmission service provided pursuant to the rates, terms and conditions set forth in Tariff, Part III, or transmission service comparable to such service that is provided to a Load Serving Entity that is also a Transmission Owner.”  PJM Tariff, OATT Definitions – L – M – N, at 13-14.  The PJM Tariff defines “Network Integration Transmission Service” as “the transmission service provided under Tariff, Part III.  There are two types of firm Network Integration Transmission Service:  Regional Network Integration Transmission Service and firm Cross-Border Network Integration Transmission Service. Non-firm Network Integration Transmission Service includes Secondary Service.”  Id. at 12–13.
25  Under the PJM Tariff, “Point-To-Point Transmission Service” “mean[s] the reservation and transmission of capacity and energy on either a firm or non-firm basis from the Point(s) of Receipt to the Point(s) of Delivery under Tariff, Part II.”  Id., OATT Definitions – O – P – Q, at 10.
26  206 Order, 193 FERC ¶ 61,217 at P 175.

PDF page 16

16

and to obtain service in violation of Illinois law.  This can be seen in Attachment 1 of Exhibit 5 to Constellation’s November 22, 2024, Complaint filed in Docket No. EL25-20-000.27  That attachment is a November 12, 2024, letter from ComEd to Constellation concerning interconnection requests at the LaSalle and Byron nuclear facilities.  In that letter, ComEd details certain design issues with Constellation’s proposal and then explains that the “end use load is retail load under both Illinois and federal law and cannot be interconnected solely through amendments to the LaSalle or Byron [interconnection service agreements].”28  ComEd went on to explain its continued belief that,

there is no lawful path to interconnect end use load at LaSalle and
Byron without that load taking service as a retail customer of
ComEd and we cannot continue to review proposals for co-location
of end use load at LaSalle and Byron on some other basis.29

ComEd suggested that Constellation make the requested design changes and submit “an application for retail service.”30  Instead, Constellation decided to disregard Illinois law and existing tariff mechanisms that apply to entities requesting to serve retail customers. Existing retail and transmission services were and still are available to Constellation, just not at Constellation’s preferred arrangement—that is, an arrangement that tried to excuse the co- located load from paying for Network Service.  To the extent clarification was needed, the Commission has now clarified (in portions of the 206 Order that the PJM Indicated Transmission Owners support) that these arrangements must be properly metered and must designate and involve

27  See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, at Ex. 5 Attach. 1, Declaration of James R. McCoskey (filed Nov. 22, 2024).

28  Id. at Ex. 5 Attach. 1, at 2.
29  Id.
30  Id.

PDF page 17

17

transmission service to an Eligible Customer.  Constellation’s retail bypass attempt was an effort to evade exactly those rules.  With the Commission’s clarification that those rules cannot be evaded, service can proceed in an orderly fashion.  No uncertainty exists and thus the allegation of uncertainty does not support finding the PJM Tariff unjust and unreasonable and fixing a new rate with new interim service and CD Service based upon net load of a co-located load customer. Indeed, when customers do not attempt to evade metering and take service instead through an Eligible Customer, their load service requests proceed on a timely basis.  For example, as Exelon explained in recent comments, in 2025, ComEd received more than 25 customer service applications for large load service, representing new load in excess of 20 GW.31  There is no suggestion in the record that any customer is encountering problems with those requests (and if there was a problem, it would no doubt have been raised).  The Commission ignored this data, and its decision is therefore arbitrary and capricious and not reasoned decision making.  By ignoring the record evidence, the Commission violated the requirement that an “agency must examine the relevant data and articulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the choice made.’”32

The recently revised co-location arrangements involving Talen Energy and its subsidiary Susquehanna Nuclear, LLC demonstrate that the current PJM Tariff works and needs no improvements.  In Docket Nos. ER24-2172-000 and ER24-2172-001 (“Susquehanna ISA Proceeding”),33 there was a proposal to allow co-located load to avoid purchasing Network Service

31  See Exelon December 8, 2025 Comments at 6. 32  State Farm, 463 U.S. at 43 (citation omitted).
33  See Susquehanna ISA Order, 189 FERC ¶ 61,078.

PDF page 18

18

through the use of a behind-the-meter arrangement.34  The Commission correctly rejected the proposed interconnection service agreement (“ISA”) in the Susquehanna ISA Proceeding. 35  Talen subsequently announced that “[t]he existing Susquehanna co-located load arrangement between Talen and Amazon will transition to a ‘front-of-the-meter’ arrangement after the completion of transmission reconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling outage.”36  Talen effectively conceded that PJM Network Service works, which is to say that Network Service under the existing PJM Tariff provides for timely service, and is a service upon which all customers may rely.  There is simply no evidence suggesting otherwise. In its 206 Order, the Commission also found that “PJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the transmission system under certain conditions.”37  The point here seems to be that, under the existing PJM Tariff, some large load/data center customers will be deterred from taking service because they have to pay too much in circumstances in which they are “willing and able to limit [their] energy withdrawals from the transmission system,” but again there is no evidence that the cost of paying for Network Service deters service or has any impact whatsoever on development of data centers.38  Clearly, there is not a lack of data center development in the PJM Region—quite

34  See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule F, Part F.4 (June 3, 2024). 35  Susquehanna ISA Order, 189 FERC ¶ 61,078.
36  Press Release, Talen Energy, Talen Energy Expands Nuclear Energy Relationship with Amazon (June 11, 2025), https://ir.talenenergy.com/news-releases/news-release-details/talen-energy-expands-nuclear-energy- relationship-amazon.
37  206 Order, 193 FERC ¶ 61,217 at P 159.
38  See id.

PDF page 19

19

the opposite is true.  The data center development interest in PJM is overwhelming.39  As shown in the Exelon example, data center applications have been flowing in across PJM under the existing PJM Tariff rate structure.

The Commission also states that “[r]equiring [Network Service] could necessitate
inefficient and costly transmission buildout and costs paid by transmission customers that may not be necessary if Eligible Customers taking transmission service on behalf of Co-Located Loads are willing to limit their energy withdrawals and take a transmission service that requires fewer Network Upgrades to provide.”40  Again, this is unsupported by evidence.  Any suggestion that traditional Network Service imposes unnecessary transmission upgrade costs on all existing customers41 ignores the fact that network studies are based on physics and engineering—not the ratemaking applicable to a particular service request.  For example, if a 500 MW load with various operating characteristics locates on the grid, its impact must be studied or reliability will be threatened.  If, under various operating conditions (including the potential failure of protection systems that seek to enforce a “net load” commitment), it could cause voltage collapse or other reliability concerns, those risks must be addressed.  Charging the load on a CD Service basis does not change the physical and engineering impacts of the load.  Certainly, if the load installs systems aimed at limiting its use of the grid, those might change the system impacts and need for upgrades,

39 See Exelon, Investor Meetings, at 18 (Winter 2026), https://investors.exeloncorp.com/static-files/0cd39e2e- ea59-432b-afd7-b432025fe649 (reporting a projected 18+ GW and growing data center pipeline in Exelon’s territory); FirstEnergy, 3Q 2025 Strategic & Financial Highlights, at 6 (Oct. 22, 2025), https://investors.firstenergycorp.com/investor-materials/webcasts-and-presentations/presentation-details/2025/Third- Quarter-2025-Strategic-and-Financial-Highlights/default.aspx (projecting cumulative data center demand to be 15,450 MW for 2035 based on both contracts and pipeline, i.e., “customers with reasonable level of confidence of construction”); PJM, RTEP 2024 Regional Transmission Expansion Plan, at 17 (Apr. 17, 2025), https://www.pjm.com/-/media/DotCom/library/reports-notices/2024-rtep/2024-rtep-report.pdf (“PJM is experiencing significant load growth driven primarily from the proliferation of data centers . . . .”).
40  See 206 Order, 193 FERC ¶ 61,217 at P 199.
41  See id. at P 67 (summarizing Constellation’s arguments).

PDF page 20

20

but the same can be said for similar systems applied to other loads.  Nothing in the record says that such systems are more beneficial for co-located load projects than for any other load.  Nothing in the record supports the use of different ratemaking principles when such installations are in place. To the contrary, as discussed below, the Commission has consistently rejected arguments that different ratemaking should be applied even where there are physical limits to the amount of transmission system use.42

Ultimately, in the study process, if the customer’s co-located load site is the one that requires the least transmission upgrades compared to other sites suggested by the customer, using the customer’s gross load, then that can be determined during the study process.  The fact that a load is located near a generator may well reduce system impacts—a good thing—but that holds true regardless of whether the load has contracted with the generator it abuts, or with remote generation.

The Commission states that “[p]arties further argue that Co-Located Loads may be able to receive transmission service faster with use of a new, limited transmission service product than they would if they selected NITS, to the extent that providing NITS would require Network Upgrades that the limited transmission service would not.”43  There is simply no evidence relied upon to support this assertion.  Good siting decisions, for co-located arrangements or otherwise, can lead to speedier service, with less need for system upgrades, but there is no support in the record for the notion that a new ratemaking arrangement (CD Service) will alter what must be studied in assessing the physics and engineering of any proposed new configuration.  Further, the suggestion that an agreement to limit net power withdrawals from the system to zero should permit

42  See Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam).
43  206 Order, 193 FERC ¶ 61,217 at P 205.

PDF page 21

21

fast-track interconnection again flatly ignores physical and engineering reality.  There is no question that, even when no net power is being withdrawn from the system (i.e., when the load is less than the capacity of the co-located generator), the transmission system is affected and needed by the load – indeed, the Commission agreed with this proposition when it found that co-located loads do utilize load-following based on gross rather than net load.44  Load following means that the ups and downs of the load cause flows on the grid in synchrony with those ups and downs. Even in a case where there are no net draws, load fluctuations of hundreds of MW could occur and could impact the grid, even with protective systems in place to prevent net power withdrawals.  By suggesting that the loads in such circumstances can be interconnected with a fast-track approach without studying physical impacts that threaten system integrity, the 206 Order is endorsing an unsound approach that is contrary to the public interest and based on absolutely no discernible evidence.  It is therefore not supported by substantial evidence.45

Arrangements to reduce load under peak or emergency conditions might be beneficial—or might not, if the potential concern is instabilities that arise due to the characteristics of the load itself rather than issues elsewhere on the system.  Further, such arrangements will have the same potential benefit regardless of whether there is a contractual supply arrangement with a nearby generator and regardless of whether it pays for transmission service based on net or gross load. Further, if there was doubt in anyone’s mind that Network Service is both feasible and a just and reasonable option, the Commission’s 206 Order removes such doubt by admitting that Network Service remains just and reasonable.  The Commission states that,

44  See, e.g., id. P 160.
45  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.

PDF page 22

22

it continues to be just and reasonable for an Eligible Customer
taking transmission service on behalf of Co-Located Load to elect,
as one of the required transmission services from which the Eligible
Customer must choose, to take NITS. . . .  NITS provides significant
benefits because a NITS customer gains the right to be served from
the transmission system at any time, and PJM and the transmission
owners incorporate NITS load into their transmission planning.46

The Commission also states that, “[w]hile [it] find[s] that NITS charged on a gross demand basis is one just and reasonable transmission service option for Eligible Customers taking transmission service on behalf of Co-Located Loads, it is not the only option.”47  The Commission, thus, acknowledges that the existing service options are feasible and just and reasonable, but the Commission merely wants more options.  That, however, is not a permissible basis to take action under FPA section 206.  Having found the tariff just and reasonable under the first prong of section 206, there is no second prong remedy stage for the Commission to initiate.  Giving certain customers preferential treatment for cost allocation is not an appropriate means to exercise the Commission’s FPA section 206 powers.

In short, the 206 Order is fatally flawed because it does not adhere to the requirements of Section 206 and provides no evidentiary support for the building-block assumptions upon which it purports to stand.

B. The Commission Did Not Engage in Reasoned Decision Making Because It
Did Not Explain its Departure from FERC Precedent or Refute that, Because
the Existing PJM Tariff Provides Service on the Same Basis for All
Customers, the Existing PJM Tariff Does Not Grant an Undue Preference.

As an initial matter, picking and choosing customers to receive preferential rate treatment runs contrary to the FPA’s requirement that “[n]o public utility shall, with respect to any

46  Id. P 195 (footnote omitted).
47  Id.

PDF page 23

23

transmission or sale subject to [FERC’s] jurisdiction . . . (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”48

The Commission has a long-standing policy of rejecting attempts by network transmission customers to avoid paying their load ratio share of system cost.  As the Commission recognized in the 206 Order, citing the Amtrak case, the Commission “has rejected cost causation arguments made by network customers that sought to lower their load ratio share based on actual use of the transmission system.”49  This policy has long persisted for very good reason.  The “assessment of [Network Integration Transmission Service] is not based on actual use over a particular transmission path, but rather based on the network customer’s right to use the entire system” and its effects on that system.50

The Amtrak case, which rejected an attempt by a network customer in PJM to pay for less than its full gross load, was not an outlier, but instead reflected decades of Commission precedent, rejecting challenges to uniform application of the rule that Network Service would be based on the entire gross load of the network customer, regardless of arguments (such as those advanced by Amtrak) that the customer could purportedly limit use of the system.  For example, this exact issue was addressed in Order No. 888-A and resulting appeals.  In Order No. 888-A, the Commission

48  16 U.S.C. § 824d(b).
49  206 Order, 193 FERC ¶ 61,217 at P 196 & n.412 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp, 171 FERC ¶ 61,237, at P 41 (2020), denying clarification and addressing reh’g, Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 (2020) (“Amtrak”); PJM Interconnection, L.L.C., 169 FERC ¶ 61,041, at P 60 (2019)).
50  Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020).

PDF page 24

24

held that customers cannot “split” their load at a delivery point—if some of the load takes Network Service, all of the load must be designated for Network Service:

The concept of allowing a “split system” or splitting a discrete load
is antithetical to the concept of network service.  A request for
network service is a request for the integration of a customer’s
resources and loads.  Quite simply, a load at a discrete point of
delivery cannot be partially integrated—it is either fully integrated
or not integrated.  Furthermore, such a split system creates the
potential for a customer to “game the system” thereby evading some
or all of its load-ratio cost responsibility for network services.51
That ruling was expressly upheld on appeal by the U.S Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”), which accepted the Commission’s reasoning, finding that objections were “not well-taken.”52  Application of the ruling in Order No. 888-A is dispositive: Because the Commission has recognized that these customers use the transmission system for some services (such as load following and black start), the notion that the customer can use the system for those services but not others, that it is “partially integrated,” flies in the face of the Commission’s Order 888-A ruling.

The issue was likewise addressed in a long series of cases involving Florida Municipal Power Agency (“FMPA”) and transmission service it was taking from Florida Power and Light. As recounted by the D.C. Circuit in 2005, years of litigation in that case involved the attempt by FMPA to avoid paying for Network Service based on its overall gross load, with the Commission consistently rejecting all arguments by FMPA against such load splitting.53  In the 2005 decision,

51  Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, 78 FERC ¶ 61,220 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
52  Transmission Access Pol’y Study Grp., 225 F.3d at 726.
53  Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005) (describing history of case back to 1993).

PDF page 25

25

the court remanded one argument by FMPA, which is that physical constraints on the transmission system made it physically impossible for its entire load to be served by the FPL system.54  On remand, the Commission found that even in the case of physical impossibility of serving the entire load, the gross load construct was most appropriate, rejecting arguments that a network customer should pay for any less than its entire system load.55

The Commission has consistently followed this precedent.56  For example, in Idaho Power,
the Commission rejected Bonneville Power Administration’s (“BPA”) attempt to remove certain of its load from its load ratio share.57  The Commission explained that, contrary to Order No. 888, “BPA’s proposal would essentially leave the behind the meter loads . . . as part of BPA’s network load served by Idaho Power’s transmission service, but eliminate the requirement that such loads be metered, i.e., included in BPA’s load ratio share, because Idaho Power’s transmission service may only be needed in rare instances.”58  Similarly, in Order No. 890,59 commenters complained that assigning transmission-related costs to customers that reduce their use of the transmission

54  Id. at 292 (remanding because “FERC . . . failed to explain why network customers should be charged by the transmission provider for network service that the provider is physically constrained from offering and, relatedly, why physical impossibility should not be recognized as an exception to the general rule against permitting partial load ratio pricing for network customers”).
55  Fla. Power & Light, 113 FERC  ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, 264 F. App’x 4 (D.C. Cir. 2008).
56  See, e.g., Idaho Power Co., 106 FERC ¶ 61,329 (2004) (“Idaho Power”); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010) (finding that network customer failed to comply with the tariff by not designating its total load as network load); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015) (finding that a network customer's request to designate less than its entire load as network load violated both the transmission provider’s OATT and long standing Commission policy, which require network customers to designate their entire load as network load to receive network service).
57  Idaho Power, 106 FERC ¶ 61,329 at P 14.
58  Id. 59  Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh'g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh'g, Order No. 890- B, 123 FERC ¶ 61,299 (2008), order on reh'g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009).

PDF page 26

26

provider’s system to serve load is inconsistent with the Commission’s cost-causation principles. The Commission rejected such arguments, stating that its existing policy already provides customers with the opportunity to reduce network service costs to the extent a customer is not relying on the transmission system to meet its energy needs (i.e., by taking point-to-point transmission service instead of network service).60

In the 206 Order, the Commission now has departed from these decades of precedent and,
contrary to the APA, has failed adequately to explain its departure.61  The Commission’s prior determinations of the fairness of load ratio allocation (based on gross load—even in the case of purported physical impossibility of service to full load) of embedded costs hold true.  If the new data center load is one third of the load in a PJM zone, it should pay one third of embedded costs of providing service in that zone.  If it pays less, other customers pay a disproportionate share of costs of the system.  There is no reasoned basis for these distinctions.

The Commission justifies its decision to depart from precedent (i.e., to base CD Service rates on net rather than gross load) with the assertion that co-located loads impose less burden on the grid compared to other customers, and presumably receive fewer benefits.  But prior attempts to create a new third type of transmission service have relied on the exact same argument— customers have made fact-based arguments that their uses of the transmission system are somehow different from, and less impactful than, the uses of the system by other customers.  The

60  See Order No. 890, 119 FERC ¶ 61,119.
61  See  Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position. An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”).  At paragraph 211 of the 206 Order, the Commission says that the current load-splitting proposal is different from prior situations because PJM need only plan for the specified contract demand rather than the full load, but this argument is not a difference from prior cases at all, such as the FPL case where there was no contention that FPL was redesigning its system to serve the full load of FMPA, or the Amtrak case where the entire premise of the argument was that Amtrak made only rare and limited use of the system.

PDF page 27

27

Commission consistently has rejected these requests for special rates.  The Declaration of Danielle S. Powers (“Powers Declaration”), submitted by the Indicated TOs, explains why the assessment of Network Service is not based on actual use over specific transmission paths.62  All customers have different usage of the grid.  Many customers’ reliance upon the grid varies during different times of the year and can be distinguished from other customers’ uses.  As the Powers Declaration explained, there may be a ski resort that operates only in winter and runs its snow guns at night or a large greenhouse that operates its lighting at night.63  These customers may have distinct load shapes or load factors, but they pay the same rate for Network Service as do high load factor customers.  Such customers pay the full Network Service rate, but because Network Service charges are allocated based on contribution to the system coincident peak, some customer charges may be lower on average than others if their operations occur disproportionately outside of the peak hours.  No additional rate discount is necessary or given.  Up until now, the Commission has consistently applied this approach of not carving out special rates for different customer classes for good reason—every customer can attempt to make arguments why their usage should result in a decrease of their share of the embedded costs of the transmission system.  Utilities have an obligation to serve load and that load needs to be able to call on service regardless of whether they actually utilize the system to the maximum allowable extent since weather and other factors are unpredictable.  Hence, actual usage does not reflect the benefit.  Entertaining such arguments

62  See PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of Danielle S. Powers at P 29.
63  Id.

PDF page 28

28

would frustrate the rate design that the Commission has applied across the board and that was put in place following Order No. 888.64

The existing PJM Tariff allows end-use load and generation to co-locate in a timely manner and on terms that are fair to all other users of the grid and commensurate with cost causation principles.  The existing PJM Tariff effectuates the principle that those that benefit from the transmission system should contribute to the embedded costs of the system and is consistent with the pro forma OATT in providing for Network Service and Point-to-Point Service, an important component of Order No. 888.65  Under the existing rate design, the PJM Tariff provides for transmission owners to recover on a postage stamp basis the embedded costs of their respective portions of the transmission grid from network customers.

Although the Commission disagrees that Network Service on a gross demand basis should be required for co-located load, the Commission, in the same breath, recognizes that such an option is “one part of a just and reasonable . . . rate.”66  The Commission states that because the “record demonstrates that Eligible Customers taking transmission service on behalf of Co-Located Loads are willing and able to limit their energy withdrawals from the transmission system under certain conditions,” “[i]t would be inconsistent with cost causation principles to require Eligible Customers taking transmission service on behalf of Co-Located Loads that limit their energy withdrawals to take NITS on a gross demand basis.”67  These findings are entirely disconnected

64  See, e.g., Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, 75 FERC ¶ 61,080 (1996), order on reh’g, Order No. 888-A, 78 FERC ¶ 61,220, order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000) (TAPS), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

65  See, e.g., id.
66  206 Order, 193 FERC ¶ 61,217 at P 199.
67  Id.

PDF page 29

29

from prior FERC precedent discussed above, where the Commission rejected cost-causation
arguments by the likes of Amtrak, FMPA, and BPA, who made essentially identical arguments that they would limit use of the provider’s system.  The 206 Order makes no attempt to explain why it departed from that precedent.68  The Commission has also not explained why co-located load should be treated any differently, much less preferentially.  The 206 Order is therefore deficient.69 Under the APA, the Commission must explain why circumstances have changed such that

this proceeding requires departure from past efforts by customers to pay for less than gross load.70 The Commission made no serious attempt to do so.  Nor has the Commission distinguished why other existing customers will not qualify for discounts—many of whom can argue that they impose lesser demand on the grid by some measure.  Furthermore, the 206 Order makes no effort to explain the decision to change that rule in PJM and only in PJM.  That failure to provide explanation renders FERC’s decision arbitrary and capricious and violates the APA.71  Ultimately, this is not

68  See id. P 196 & n.412 (citing Amtrak, 171 FERC ¶ 61,237 at P 41; PJM Interconnection, L.L.C., 169 FERC ¶ 61,041 at P 60 (2019)).
69  TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12-13 (D.C. Cir. 2015) (remanding because FERC did not adequately explain its position).
70  See Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation for its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, for example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); see also Constellation Mystic Power,  45 F.4th at 1057 (finding the Commission’s decision to be arbitrary and capricious and that “the Commission’s ‘failure to provide an intelligible explanation . . . amounts to a failure to engage in reasoned decisionmaking’”) (citation omitted); New England Power Generators Ass’n, Inc. v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that seem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned explanation of why those facts matter.” (citing BP Energy Co. v. FERC, 828 F.3d 959, 968 (D.C. Cir. 2016) (vacating finding of no undue discrimination where Commission identified differences between two natural-gas companies but failed to adequately explain why they provide a rational basis for the difference in treatment))); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an agency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations differently,’ . . . and Commission cases are no exception . . . .”) (alteration in original) (citations omitted).
71  See, e.g., Cal. Pub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this policy without acknowledgment or explanation. This departure was arbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A full and rational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ administering a program. . . .  [FERC] must at least ‘acknowledge’ its (cont'd)

PDF page 30

30

reasoned decision making and will create a nightmare as other customers in PJM and beyond raise a host of similar arguments that their transmission rates should be modified based on their allegedly different use of the system, which is a reason why the Commission never mandated this in the past. The Commission’s provision of an option for CD Service in the replacement tariff is based on a false presumption that co-located loads rely differently on the grid than other loads and therefore should pay different rates.  As discussed above, the Commission repeatedly has found that different usage patterns should not exempt loads from paying a gross load-ratio share.  As demonstrated in the next section, the very assertion that co-located projects impose fewer burdens on the grid, and receive fewer benefits from being interconnected, is itself unsupported and untrue.

C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
Their Full Gross Load.  Therefore, FERC’s Decision is Arbitrary and
Capricious Because The Embedded Transmission System Costs Should Be
Charged For Those Transmission Services.
Notwithstanding well-established Commission policy and judicial precedent to the contrary, the 206 Order establishes a new preferential transmission rate available only for co- located loads.  Not only is this new rate unduly discriminatory (as discussed herein), but it is based on a false premise that the combination of transmission system burdens and user benefits of co- located loads are so insignificant as to justify the establishment of a lower, preferential rate.  The Commission is wrong, with respect to both the actual burdens on the system and the benefits to co-located projects of being interconnected to the grid.

As for benefits, the Commission has recognized that co-located loads benefit from black start and load following service,72 and that such service properly should be charged based on gross

seemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection of their approach’ . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or swerve[ ] from prior precedents without discussion.’”) (alterations in original) (citation omitted).

72  See 206 Order, 193 FERC ¶ 61,217 at PP 209, 219 (3), (4).

PDF page 31

31

load.  Load following services are supplied from a diverse range of the interconnected generation facilities located throughout the system.  These services cannot be provided without use of all the transmission system’s resources and personnel.  Moreover, because it is a universal rule that generators cannot operate every hour of every year and that unexpected outages can and do occur, transmission interconnections provide an avenue for data center loads to readily acquire back-up power when co-located generation facilities are not available.  Based solely on these uses of the transmission system, co-located loads have no greater claim to preferential rates than other, similarly situated transmission customers who have been denied such preferences. In addition to diminishing the not-unique burdens imposed on the grid by co-located load, the Commission fails to consider the many advantages to co-located loads when they connect to the transmission system.  These advantages become apparent when one compares islanded co- location projects to similar projects that are interconnected to the transmission grid.  Islanded projects require extensive back-up generation to assure reliable sources of power for data center loads.  It is very difficult and expensive to supply islanded generation with black start capabilities or instantaneous load following.  All back-up generation on an islanded project will sit idle when not needed to serve the islanded load, thereby forgoing significant revenues from selling the surplus power into the wholesale market.  These lost opportunity sales revenues alone could likely cover the fully embedded costs of Network Service.  Ultimately, islanded generation projects are more risky and therefore more difficult to finance.  Grid interconnection is valuable, which is why the pending proposals do not just create isolated islands.  In determining that traditional Network Service without the option of additional services mandated by the Commission is unjust and unreasonable, the Commission considered none of these benefits of grid interconnection.  Failure

PDF page 32

32

to consider the benefits of grid interconnection makes the 206 Order arbitrary and capricious and unreasoned.73

Additionally, the 206 Order’s finding that the existing PJM Tariff is not just and reasonable is arbitrary and capricious because the Commission failed to consider the unique issues that attend co-location with nuclear plants.  A nuclear facility must be interconnected to the grid as a Nuclear Regulatory Commission licensing obligation74 and it cannot follow load in any meaningful sense.75 Therefore, every swing in a load that is co-located with a nuclear plant—from zero MW to full load—will impact the grid.76  There is no question that a nuclear co-location arrangement is dependent on the grid because the nuclear unit serving the load is not permitted by its license to operate without a robust grid interconnection.77  Further, load that is co-located with a nuclear unit depends on services such as load following, voltage support, black start, and other ancillary services that will be and can only be delivered over the grid.78  Because nuclear units cannot provide these services, there is full dependence on the transmission system because the nuclear unit lacks the ability to increase and decrease output in response to the demand from the co-located load.79  The transmission system services are used every second of every hour—not just when the generator fails or the load exceeds the output of the connected nuclear unit.80  Because the nuclear

73  See State Farm, 463 U.S. at 43.
74  See, e.g., Decl. of David Weaver, PE at PP 11-12, Attachment 1 to Exelon Comments, Docket No. EL25-20 (Dec. 12, 2024).
75  See, e.g., id. at P 18.
76  See id. at PP 18-19.
77  See id. at PP 11-13, 16.
78  See id. at PP 14-19.
79  See id.
80  See id.

PDF page 33

33

unit runs full out all the time (aside from refueling and other equipment-related outages), from an engineering and physics perspective, a load served by a co-located nuclear plant uses the system in the same way as a load that is served by remote resources.  In both cases the nuclear plant’s output remains constant, and all needs of the load are addressed by remote generation that moves up and down to follow the load.81  The Commission’s failure to respond to these arguments concerning the unique aspects of nuclear generation in its decision is a violation of the APA.82

III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement
Rate is Not Just and Reasonable.

Whatever the 206 Order is, the one thing it is not is a viable FPA Section 206 action.  Under FPA section 206,83 there are two steps: only after the Commission finds a rate to be unjust and unreasonable, may it set a replacement rate.84  No one has met the burden at either step. As discussed above, the Commission and complainants fail at the first step of FPA section 206 because the PJM Tariff provides for two transmission services (i.e., Network Service and Point-to-Point Service) that the Commission continues to recognize as just and reasonable and

81  See id. at PP 2, 24.  While we describe this as a nuclear issue, renewable resources are often in the same position, unable to alter their output in the short-term and thus leaving all load and voltage fluctuation to the broader grid. Most thermal resources can alter their output, but often not instantaneously.  Whether they can “absorb” sudden load fluctuations of an abutting load so that the grid is not impacted remains to be studied, but in any case they would not absorb the load fluctuations absent installation of control systems that provide for such absorption, which is a different thing from systems that protect against net withdrawals of power.
82  See New England Power Generators Ass’n, Inc., 881 F.3d at 211 (finding “that FERC did not engage in the reasoned decisionmaking required by the Administrative Procedure Act” because it “failed to respond to the substantial arguments put forward by Petitioners and failed to square its decision with its past precedent”); Canadian Ass’n of Petroleum Producers, 254 F.3d at 299 (“Unless the Commission answers objections that on their face seem legitimate, its decision can hardly be classified as reasoned.”) (citations omitted); Tesoro Alaska Petroleum Co. 234 F.3d at 1294 (“The Commission’s failure to respond meaningfully to the evidence renders its decisions arbitrary and capricious.”). 83  16 U.S.C. § 824e(a).
84  See id; see also Advanced Energy Mgmt. All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just and reasonable rate.”) (alterations in original) (citation omitted); Emera Maine, 854 F.3d at 21; Atl. City Elec. Co., 295 F.3d at 10.

PDF page 34

34

those two services are offered to all customers without undue preference.  The 206 Order also fails at the second step of FPA section 206 because the proposed replacement rate is not just and reasonable, would grant an undue preferential rate for co-located loads, and would exacerbate the resource adequacy, reliability constraints, and affordability concerns in PJM—all contrary to the FPA.

“[T]he principal purpose of [the FPA is] to encourage the orderly development of plentiful supplies of electricity . . . at reasonable prices.”85  “The reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies.”86  It necessarily follows that reliability is relevant to the inquiry of whether a rate is just and reasonable.  Yet, the Commission’s proposed replacement rate was directed without any examination of the reliability and resource adequacy implications.  The Indicated TOs maintain that co-located load using transmission grid services should be required to be in front-of-the-meter to ensure reliability, transparency, and appropriate cost allocation.

In the 206 Order, FERC directed revisions to the PJM Tariff to

clarify that an Interconnection Customer seeking to serve a Co-
Located Load with a newly interconnecting generating facility may:
(1) request interconnection service at a level below its maximum
facility output; (2) use existing procedures in the PJM Tariff to
accelerate the study of the interconnection service request if the
request has no cost allocation for Network Upgrades and does not
require further studies; (3) request provisional interconnection
service; and (4) request Surplus Interconnection Service.87

As part of the replacement rate, PJM was also directed to revise the PJM Tariff to establish three new transmission services that “reflect that Eligible Customers taking service on behalf of Co-

85  NAACP v. FPC, 425 U.S. 662, 669–70 (1976).
86  Constellation Mystic Power, LLC, 45 F.4th at 1035.
87  206 Order, 193 FERC ¶ 61,217 at P 176.

PDF page 35

35

Located Loads are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”88  The three options directed by the Commission are as follows:

(1) Eligible Customers seeking to take Network Service on behalf
of Co-Located Load may take a new interim, non-firm
transmission service until all Network Upgrades necessary to
provide the requested Network Service are complete;

(2) a Firm Contract Demand transmission service that an Eligible
Customer can choose to take on behalf of a Co-Located Load
instead of taking Network Service; and

(3) a Non-Firm Contract Demand transmission service that an
Eligible Customer can choose to take on behalf of a Co-Located
Load instead of taking Network Service.89

For the new Interim Service, FERC states that Eligible Customers “would avoid paying generator capacity costs in return for their willingness to curtail their withdrawals in advance of emergency conditions (i.e., it will be curtailed before existing firm transmission services and the new Firm Contract Demand Transmission Service).”90

There is no basis for the Commission to direct these new services, and the Commission has not pointed to any other regional transmission organization, independent system operator, or public utility where such transmission services are used or required.  These three service options provide preferential treatment for certain customers in one region of the country where their rates are subsidized by all other customers, and the Commission has required these tariff changes without regard to the reliability implications.

88  Id. P 178.
89  Id.
90  Id. P 201.

PDF page 36

36

A. Allowing Special Treatment For Co-Located Load Violates The FPA’s
Requirement That There Be No Undue Preference Or Unreasonable
Difference In Rates Between Classes Of Service.
As explained above, FPA section 205 prohibits any public utility charging transmission rates from “mak[ing] or grant[ing] any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage” or “maintain[ing] any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”91  The Commission, by requiring the new forms of service discussed above, would establish rates that grant an undue preference or advantage to co-located loads.  As an initial matter, for all of the new services, the Commission has not pointed to any example in any other regional transmission organization’s, independent system operator’s, or public utility’s tariff where these types of transmission services have been required by the Commission. The Commission fails to demonstrate that these changes are just and reasonable.  The 206 Order claims that “PJM’s Tariff is unjust and unreasonable because it does not include transmission services that reflect an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the transmission system under certain conditions.”92  But there already exist mechanisms (such as demand response at the state and retail levels) to address when customers can scale back their load or bring other generation to bear in order to reduce their withdrawals when called upon.  If co-located loads would like to be compensated for being interruptible, then they should rely upon PJM’s demand response rules, and the 206 Order fails to explain why those rules are inadequate here. Indeed, the Commission

91  16 U.S.C. § 824d(b).
92  206 Order, 193 FERC ¶ 61,217 at P 159.

PDF page 37

37

maintains that those rules are just and reasonable for co-located loads taking Network Service.93 The point of FPA section 206 is not for the Commission to declare what it thinks would be better tariff options—it is to ensure that the tariff on file is just and reasonable.  The services imposed by the 206 Order run into tension with foundational goals of the FPA—to ensure just and reasonable rates that do not provide an unreasonable difference among classes of customers or an undue preference.

For the new Interim Service, there is no basis for the Commission to require this new form of service prior to the completion of necessary network upgrades and studies to ensure reliability of the system.  The Commission states that “Eligible Customers taking the interim, non-firm transmission service on behalf of Co-Located Loads would avoid paying generator capacity costs in return for their willingness to curtail their withdrawals in advance of emergency conditions.”94 The Commission then sets for hearing and asks for “briefing on an appropriate point in emergency operations at which to curtail Eligible Customers taking this new interim, non-firm transmission service on behalf of Co-Located Loads.”95  Which is to say that the Commission has not accounted for reliability risks, not knowing how or when these curtailments would be implemented, or how they would protect reliability.  Furthermore, even assuming emergency conditions were clearly defined, additional inconsistencies amongst co-located load in different states could be created by future State legislation.  For example, a State could require all retail large loads be curtailable under similar emergency conditions, which would effectively cause some retail customers to pay NITS while other co-located counterparts would pay a discounted rate.

93  Id. P 242.
94  Id. P 201.
95  Id.

PDF page 38

38

As discussed earlier in this rehearing request, system impacts are not limited to situations where there are net withdrawals from the system—load following and sudden load fluctuations potentially impact reliability regardless of whether there are net withdrawals from the system.96 Further, the Commission fails to explain why system protection schemes installed in non-co- located load configurations would not provide similar benefits and be deserving of preferential rates.  Accordingly, the new service grants an undue preference for co-located loads. Second, the only issue that CD Services resolve is the level of embedded system costs to be allocated to co-located load.  The entire point of Constellation’s complaint was to allow loads with co-location arrangements to pay a smaller share of the embedded costs of the grid—leaving those costs to other customers and creating an economic benefit for the co-located generator and/or load, depending on their commercial arrangements.  The 206 Order implements a solution to a problem that does not exist—there is no evidence in the record to this proceeding that data centers are being slowed down by paying full transmission rates, which are a tiny portion of overall data center costs and not an impediment to data center expansion.  Co-located load and generation projects care about transmission costs economics but most of all seek one thing: reliable power.  That is why it makes sense to interconnect and synchronize with the transmission grid rather than resorting to islanded microgrid arrangements.

As previously discussed, interconnecting to the grid burdens the system by adding new loads and operating contingencies that must be addressed by system operators.  Grid interconnections also bring significant project benefits such as the ability to sell on-site back-up generation into the

96  If the Commission suggests that the transmission provider move forward with interconnection before such study, that jeopardizes reliability and flies in the face of NERC reliability standards, such as FAC002-4, which imposes strict requirements to study the system impacts of all proposed new interconnections, or modifications to existing interconnections, in order to protect system reliability.  See NERC, FAC-002-4 – Facility Interconnection Studies (2022), https://www.nerc.com/globalassets/standards/reliability-standards/fac/fac-002-4.pdf; NERC, 181 FERC ¶ 61,126 (2022) (approving FAC-002-4).

PDF page 39

39

wholesale markets when it otherwise would sit idle, and the ability to receive load following service from off-site generation.  The totality of these burdens and benefits—benefits which no doubt exceed the cost of Network Service based on gross load—easily justify charging co-located loads the same rate as all other transmission customers.  To allow for preferential rate treatment for co-location arrangements would allow those customers to rely upon the grid and its benefits at a price that is subsidized by all other customers.  That cannot be said to be just and or reasonable. Accordingly, there is no lawful basis for requiring tariff changes to impose this new form of service that gives these customers a reduced share of embedded costs compared to all other users when they receive the same benefits.97  Such a decision is not grounded in reasoned decision making and is not supported by substantial evidence.98

B. The Commission’s Emphasis On Protective Systems Is In Tension With The
Commission’s Open Access Policies And Therefore Is Arbitrary And
Capricious.  The Commission Also Erred In Minimizing The Fact That
Protective Systems Can And Have Failed.

As the Indicated TOs have explained, protective systems can provide value, but they are no panacea.  They can protect against net withdrawals from the grid (where the load exceeds the co-located generation), but do not protect the grid from real impacts that occur even when there is consumption by a co-located customer but no net withdrawal, such as the impacts of load and voltage spikes and oscillations.99  Further, the emphasis on protective systems to prevent backflows

97  See Coal. of MISO Transmission Customers, 45 F.4th at 1009 (alterations in original) (quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)) (“The cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”).
98  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706.
99  This follows directly from the Commission’s acknowledgement that these arrangements need load following for the entire gross load, regardless of the absence of net withdrawals.

PDF page 40

40

ignores an important issue: other providers may want to compete to serve these customers.  The generators have an interest in designing captive arrangements where the customers cannot access alternative supply, but that is not something the Commission should endorse.  To the contrary, it flouts the core proposition behind Order No. 888,100 where the Commission established its open access policies.  Transmission asset owners cannot create barriers that inhibit the ability of other generation on the grid to compete to serve load.  As the Supreme Court recognized, a key motivation behind the open access requirements is that owners’ “control of transmission facilities gives them the power either to refuse to deliver energy produced by competitors or to deliver competitors’ power on terms and conditions less favorable than those they apply to their own transmissions.”101  But that is exactly what generators like Constellation propose.  Their argument is that they will convert their generator interconnection facilities into transmission assets and then install relay systems that make the load captive to its generation.102  In addition to its other flaws, that proposal should be rejected because it is an illegal effort to stifle competition. Moreover, the Commission puts too much faith in protective systems operating

instantaneously and without failure.  Co-located loads “can pose reliability risks if their generation unexpectedly trips off-line and appropriate protection or ride-through systems are not in place [because] [t]he operational visibility and controllability of [behind-the-meter] loads are limited,

100  See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,323 (Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).

101  New York v. FERC, 535 U.S. 1, 8–9 (2002).
102  See, e.g., Aff. of Steven Herling at P 23, Exhibit 4 to Constellation Reply, Docket No. EL25-20 (Apr. 23, 2025) (“The protection system, discussed above, is fully redundant and, while it cannot be guaranteed to never fail, it is unreasonable to treat the failure of both primary and secondary relay system facilities following the loss of a generator as anything other than a third contingency.”).

PDF page 41

41

making it more challenging to predict system impacts, especially during uncontrolled transitions between on-site generation and grid supply that may arise due to protection system failures.”103  If, after co-located generation fails, the load unexpectedly shifts to drawing supply from the grid, for even a moment, the transmission system sees a rapid demand spike, which may stress and harm the system.104  Moreover, as the Commission acknowledged, “PJM maintains that it is always possible that any protection system in an isolated (but not islanded) Co-Location Arrangement could mis-operate, be disabled, or degrade, and that, in the few instances where such schemes exist on the PJM system, PJM has observed these schemes fail, and the load has taken grid service.”105 As the Commission recognizes from PJM’s comments, “if the protection system fails, the large load would instantly take significant energy from the system” and “though a few such configurations may seem tolerable, the risk increases with large quantities of such configurations.”106  To address this risk, the Commission “direct[s] PJM to apply a penalty rate.”107 Assessing penalties, however, only addresses the issue after the fact and does not remediate the reliability implications of faulty protective systems.

As previously discussed, because the Commission has not addressed these issues, it has not engaged in reasoned decision making and fails to satisfy the APA requirements.

103  NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July 2025), https://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics- and-risks-of-emerging-large-loads.pdf.
104  Id.
105  206 Order, 193 FERC ¶ 61,217 at P 44.
106  Id. P 17.
107  Id. P 212.

PDF page 42

42

C. The 206 Order is Arbitrary And Capricious In Abandoning The Main
Construct Of Service To Load, Which Is That Customers Share In The
Embedded Costs Of The System.  The Commission Also Erred In Adopting a
Generator Funding Model For The Funding Of Network Upgrades For Co-
Located Load With No Supporting Evidence

In the 206 Order, FERC changes the PJM Tariff to “specify[] that an Interconnection Customer seeking to serve Co-Located Load using an existing generating facility must bear the costs of all Network Upgrades that PJM finds are necessary to preserve transmission system reliability for existing transmission customers, and that an existing generating facility cannot begin service to a Co-Located Load until all required Network Upgrades are in service.”108  The reasoning that the Commission provides is solely that “[t]his requirement will protect existing transmission customers from transmission reliability risks and from bearing the cost of Network Upgrades required for an Interconnection Customer to begin serving Co-Located Load.”109 As explained above, the Commission’s policy for decades has been that the embedded costs of the transmission system are shared by all customers.  To that end the costs of network upgrades are shared by all customers.  This makes sense because “[t]he cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”110

The Commission’s proposal that co-located load must self-fund any needed transmission upgrades is arbitrary and capricious because FERC has not explained its decision to depart from prior precedent. This particularly includes the Commission’s prior decisions to “reject[] cost

108  Id. P 176.
109  Id. 110  Coal. of MISO Transmission Customers, 45 F.4th at 1009 (second and third alterations in original) (quoting S.C. Pub. Serv. Auth., 762 F.3d at 53).

PDF page 43

43

causation arguments made by network customers that sought to lower their load ratio share based on actual use of the transmission system.”111

Under the PJM Tariff, load pays all transmission costs, except when the transmission system requires upgrades to accommodate requests by generators to interconnect.  Charging load for the embedded costs of the system, including upgrades, makes sense because all loads benefit from the transmission network.  Co-located load likewise benefit from the transmission network as a whole.  The Commission acknowledges as much by finding that the co-located load rely on the network (based on gross load) for load following and black start.112  But load following and black start cannot be delivered in isolation—they depend on diverse resources around the grid being able to transmit power over functioning stable transmission lines, which is to say that they depend in turn on the network itself, on other operating reserves and voltage support services that keep the grid stable and working, and on network upgrades that allow the grid to support all of the diverse uses of the grid that are simultaneously occurring.

Because co-located load relies upon and reaps significant benefits from the transmission system and imposes new costs on the system, co-located load should be charged for the benefits it receives from the grid and for the burdens it places upon the grid just like other load.  The Commission provides no record evidence nor a reasoned explanation for why co-located load should not be charged like other load, i.e., with the upgrade cost recovered as part of the transmission rates charged to all customers.113

111  206 Order, 193 FERC ¶ 61,217 at P 196 & n.412 (citing Amtrak, 171 FERC ¶ 61,237 at P 41; PJM Interconnection, L.L.C., 169 FERC ¶ 61,041 at P 60 (2019)).
112  See id. PP 159-160.
113  See State Farm, 463 U.S. at 43.  Of course, transmission owners must be permitted to earn a reasonable return on the investments necessary to construct, operate, and maintain transmission facilities, including those network upgrades required to serve co-located load.  See, e.g., Fed. Power Comm’n., 320 U.S. 591; Bluefield Water Works (cont'd)

PDF page 44

44

The FERC approach to incremental costs differs from the approach taken in the PJM Tariff, and the Commission’s own OATT, which assign cost responsibility to all network customers (based on their respective load ratio shares) for incremental investments needed to reliably serve load expansion (in addition to making all network loads responsible for their share of pre-existing embedded system costs).  The 206 Order’s shifting of cost responsibility departs from traditional cost causation principles and is randomly applied only to cases where the added load is served through an existing generator interconnection facility (and even then not fully served, as explained above), as opposed to new loads being served through the broader transmission system.  The 206 Order notably preserves Network Service as a just and reasonable approach, but the Network Service funding model is in direct conflict with the proposed assignment of costs to co-located loads.  The simultaneous existence of conflicting funding models is discriminatory, internally inconsistent with the 206 Order’s retention of Network Service, and contrary to FERC’s cost- causation principles.  The 206 Order fails to explain or justify this departure and therefore is arbitrary and capricious and not the product of reasoned decision making.114

The Commission should not erode its rolled-in rate policy by making exiting incumbent generators solely responsible for transmission upgrade costs they cause by serving co-located load.

& Improvement Co., 262 U.S. 679.  For decades, the Commission has recognized this principle by rolling the costs of load-driven network upgrades into transmission rates.  The 206 Order, however, departs from this longstanding approach without substantial record evidence or justification.  Eliminating this opportunity for capital recovery with a reasonable rate of return not only creates regulatory uncertainty that undermines investor confidence, but further discourages investment in the transmission system at a time when such investment is critical.  Since the 2003 blackout, the electric industry has faced persistent challenges in attracting private capital. Abrupt policy shifts—such as narrowing rolled-in rate treatment—exacerbate these challenges, weaken financial performance, and deter investors who rely on stable, predictable returns.

114  See New England Power Generators Ass’n, Inc., 881 F.3d at 211.

PDF page 45

45

Erosion of the Commission’s rolled-in rate policy is apt to create several issues.  This can be seen in several considerations:

First, in some (if not most) cases, it will be a benefit to other customers to include new co- located loads in the pool of payers for the existing transmission network rather than setting them apart and assigning them only the incremental cost for specific upgrades.  By spreading the revenue requirement for the transmission system generally over an increasing number of billing units— a.k.a. “increasing the denominator”—it reduces what other customers pay for transmission. The

undeniable fact is that large loads—not only because of their size, but also their high load factors, impose significantly upon the overall transmission (and distribution) revenue requirement needs now, and new co-located loads would do the same.  By contributing to paying the cost of the overall system on which they depend, these customers, like other customers, equitably, could help address overall concerns about affordability as the national energy grid transforms.  But, if they are required to pay only for incremental investment, they avoid paying for the broader system upon which they depend and that public benefit is lost.  The more co-located loads are carved out to pay separately for certain transmission infrastructure, the less they will pay for the overall grid and the more other customers will pay as a forced subsidy.

While cost shift outcomes can play out in more than one way in the near term, over the long term the calculus of requiring co-located loads to fund certain upgrades but not pay otherwise for their use of the existing system, can play out in just one way: it is worse for other customers while it significantly and unduly benefits co-located load customers.  Once a co-located load has fulfilled its responsibility (whether immediately or over time) for funding certain upgrades, prohibitions on “and” pricing would draw one to the conclusion that they would, immediately or

PDF page 46

46

eventually, not be responsible for any further payments for transmission service.115  But the transmission system is not a one-and-done investment.  The system evolves and requires maintenance to ensure reliability, resilience, and quality of service, all of which comes at a cost. Allowing a model where initial investment absolves co-located loads from financial contributions associated with the ongoing use of the system leaves other customers holding the bag and creates obvious and problematic inequities.

Second, such an approach creates challenging dynamics like those we have seen in the generator interconnection space. For example, this approach likely benefits earlier loads that identify favorable interconnection points, only for later co-located load customers to trigger significant upgrades, which once completed may lower costs for future load interconnection requests.  Furthermore, transmission system upgrade needs can be very sensitive to other large loads modifying their requests or withdrawing, as well as overlapping issues with other aspects of transmission planning.  Not only do these dynamics threaten to create inequities, they create incentives for speculative behavior and point of interconnection “shopping,” with associated unpredictable requests and withdrawals.  This is precisely the kind of behavior that became so problematic, resource-intensive, and delay-inducing in the generator interconnection queue. Third, co-located loads may not all be AI data centers.  Allocating transmission system upgrade costs up-front to those customers runs counter to the policy objective of promoting economic development by imposing too many near-term financial hurdles.  While some co-located loads may have substantial access to capital, significant up-front requirements could hinder

115  See Standardization of Generator Interconnection Agreements and Procedures, 104 FERC ¶ 61,103 at P 694 & n.111 (2003).

PDF page 47

47

economic development, particularly for many commercial and industrial customers that find themselves included in a new paradigm designed to support AI data center interconnections. It also bears emphasis that large loads, co-located or otherwise, will not always trigger significant transmission upgrades.  The expectation is data centers, which are sophisticated parties, will make every effort to choose sites where the upgrades will be minor, and the harmful impact of their future exemption from transmission costs on other customers will not be offset at all.  In short, it should not be assumed that large loads will trigger system upgrades with costs in excess of what they would otherwise contribute to the system if they paid traditional network rates based on their load-share ratio, and the 206 Order erred in adopting a funding model around such a false premise.116

D. The Commission Is Wrong In Suggesting That CD Service Will Promote
Efficiency Or Change Siting.
To be clear, under any circumstance, project development teams for new load, whether that load is co-located or not, already have a strong incentive to site their facilities on the grid at a location that minimizes the need for transmission upgrades.  Project developers understand that additional work can add cost, increase complexity, risk project delay, and result in lost opportunity. In addition, and as discussed above, wise siting decisions will minimize the need for system upgrades, which will hasten interconnection.  That benefit is real.  But it has nothing to do with the proposed CD Service.  This is because the impacts to the grid are based on physics and

116  The Commission also lacked evidence to eliminate rolled-in rate treatment as an option for network upgrades. Here again, the Commission failed to satisfy its burden under the APA.  By replacing rolled‑in rate treatment with direct assignment to the co-located generator, without at least providing customers the option to select rolled-in rate treatment, the 206 Order is arbitrary and capricious.  In the 206 Order, the Commission failed to (a) address material comments demonstrating system-wide benefits of transmission upgrades required by exiting generation, or (b) consider the alternative of permitting both rolled‑in rate treatment and direct assignment.

PDF page 48

48

engineering.  Whether the service paid for is based on net load or gross load does not change that planning and siting depend on the physics and engineering of the grid.

The Commission’s decision to require options for CD Service does not change how the study process should work.  Regardless of cost-allocation, ensuring there is a reliable grid is essential and understanding what load amount the system needs to support is necessary.  If transmission providers are forced to pretend a 500 MW load is only 50 MW, or even that it is zero, and pretend away the physics and engineering impacts, it will threaten reliability and resource adequacy and therefore cannot be said to be just and reasonable.

While protective systems can be beneficial, any suggestion that regional planning needs are automatically reduced by the establishment of CD Service is also not supported by evidence. No loads should be taken out of the broader planning process—to do so would only threaten reliability of the system.  Grid operators must plan for such eventualities to ensure system reliability.117

The Commission finds in the 206 Order that the BTMG “rules in PJM’s Tariff are no longer just and reasonable because loads with BTMG are not fully accounted for in resource adequacy planning and shift costs onto other transmission customers contrary to the Commission’s cost causation principles.”118  In other words, the netting of BTMG against load for calculating network cost responsibilities effectively shifts transmission costs.  Therefore, in the context of BTMG, FERC determined that BTMG should be considered to ensure resource adequacy and that BTMG output should not be netted against load.  The Commission’s decision against the netting of BTMG and the stated reasons for that decision cannot be logically reconciled with the structure it proposed

117  See PJM Tariff §§ 31.1-31.3, 31.6, 32.
118  206 Order, 193 FERC ¶ 61,217 at P 2.

PDF page 49

49

for the new transmission services.  The very reasons that the Commission made this BTMG change are the same reasons that the new transmission services are not just and reasonable.  On this basis, the requirement for PJM to offer these services cannot be said to be reasoned decision making and the Commission’s decision is arbitrary and capricious.119

E. The Commission’s Disregard of Reliability Considerations Underscores That
The Replacement Rate Is Not Just and Reasonable.
The new transmission service options reflect that the Commission overlooked important reliability concerns.  The Commission claims everything will be fine due to protective systems and the potential penalties for violating CD Service limits on the part of co-located load.  This simply ignores that loads impact the system even when there is no net power draw on the system.  The Commission acknowledges as much when it finds that the loads use the grid for load following based on gross load, not net load.120  Protective systems, even when fully functioning, are intended to keep net load at zero or below, but as the Commission has held, it is the gross load that is being followed by resources elsewhere on the grid every minute of the day, and thus using and impacting the system every minute of the day.121  The suggestion that protective systems that only address net load obviate reliability concerns ignores physical reality.

Further, the Commission in the 206 Order does not squarely address flaws in that reasoning even though they were directly raised in the record regarding risks associated with protective system failures or removal.  Even if protective systems operated perfectly (and they do not necessarily work perfectly) and penalties addressed any residual risk (again, they do not, especially, and indeed, because the penalties are currently unknown), large loads may have an

119  See State Farm, 463 U.S. at 43.
120  See 206 Order, 193 FERC ¶ 61,217 at P 209.
121  See id.

PDF page 50

50

incentive to exceed their contract limitations for transmission service in some circumstances.  The Commission has not explained how reliability planning may proceed in the face of that prospect. Additionally, the Commission acknowledges that it previously submitted that “the speed at which Co-Located Load can be added to the transmission system may pose particular resource adequacy challenges, especially if Co-Location Arrangements are not adequately and transparently reflected in existing resource adequacy planning mechanisms.”122  At the same time, the Commission states that it does not have “sufficient evidence to conclude that additional Tariff changes regarding Interconnection Customers electing to use their generating facilities to serve Co-Located Load are needed with respect to capacity market rules, reliability, and resource adequacy.”123  The Commission’s decision to direct Interim Service be offered until all Network Upgrades necessary to provide the requested Network Service are completed overlooks potential resource adequacy risks.  This service is, by definition, offered before needed transmission upgrades are completed and it is unclear from the 206 Order how it will be determined whether the load may be reliably served.  The purpose of this interim service is “more rapid interconnection and operation of Co-Located Loads” and the only reliability check is a determination by PJM that it can provide “some level of interim service reliably.”124  The Commission’s decision is arbitrary and capricious.  There are no guideposts whatsoever for how PJM should determine that it can provide “some level of interim service reliably.”125

122  Id. P 243.
123  Id.
124  Id. P 200.
125  Id.

PDF page 51

51

The Commission attempts to minimize the concerns by stating that because interconnection customers of co-located load arrangements must identify an Eligible Customer to take transmission service on behalf of co-located load, the load will be visible.126  But that does not answer the question of how and by what standards loads would be curtailed to protect reliability, or whether curtailment is even an adequate response to the need to follow gross load on a moment-by-moment basis.  Indeed, as noted above, the Commission set for hearing how that should work—currently, it is unknown.127  Because “[t]he reasonableness of a rate is assessed in light of the FPA’s goals of promoting reliable service at reasonable rates and developing plentiful energy supplies,”128 and given the foregoing, it cannot be said that these transmission service options are just and reasonable.129  The Commission did not conduct assessment of the reliability risks from either a generation or a transmission perspective in this proceeding.  Accordingly, the Commission failed to seriously take into account reliability implications in setting a replacement rate, and its decision is therefore not reasoned decision making and is arbitrary and capricious.

IV. FERC Exceeded Its Jurisdiction.

126  See id. P 241.
127  Id. P 201 (setting for hearing how such emergency curtailment would be implemented and under what standards). 128  Constellation Mystic Power, LLC, 45 F.4th at 1035.
129  Cf. Ameren Servs. Co. v. FERC, 880 F.3d 571, 580–81 (D.C. Cir. 2018) (finding that FERC “ma[de] no real attempt to holistically assess all of the various risks and benefits to the transmission owner caused by the addition of the upgrade facilities,” that “FERC inadequately considered [the] argument that all costs, and risks, are not baked in—that, in fact, shareholders are forced to accept incremental exposure to loss with no corresponding benefit” and therefore, that FERC’s “failure to meaningfully respond to it makes FERC’s decision arbitrary and capricious”) (footnote omitted); Advanced Energy Mgmt. All., 860 F.3d at 664–65 (explaining the Commission’s rationales that “support[ed] the Commission’s finding that the energy market rules were unjust and unreasonable,” which included a rationale that “existing generator outage provisions ‘impede PJM’s ability to ensure reliability’ because they do not give PJM the authority to rescind approval for a planned outage when there is an emergency”) (citation omitted); Cent. Hudson Gas & Elec. Corp. v. FERC, 783 F.3d 92, 111 (2d Cir. 2015) (explaining that FERC, in creating the Lower Hudson Zone, considered long-term benefits that would follow accurate price signals, including that it would “alleviate the risk of reliability problems in the long run”).

PDF page 52

52

A. FERC’s Replacement Rate Violates the Major Questions Doctrine.
As the Indicated TOs previously explained, there is no basis to change the PJM Tariff under FPA section 206 when the purpose of the change is to provide preferential treatment or a preferred service to a certain category of customers.  Such action would violate the major questions doctrine. Only Congress can carve out federal preemption over state regulation.  If Congress wanted to give the Commission authority to direct its preferred transmission service to benefit certain categories of customers, it could have done so.130  It did not do so.  FERC, like all agencies, “ha[s] only those powers given to [it] by Congress, and ‘enabling legislation’ is generally not an ‘open book to which the agency [may] add pages and change the plot line.”131  The Commission lacks authority under the FPA to order a new type of transmission service with the sole purpose to benefit co-located load and to treat it differently from other loads that have similar system impacts and usage. Accordingly, the replacement rate directed by FERC—because it favors a narrow category of customers (i.e., co-located load) without reasoned explanation—violates the requirement in the FPA that no rate by a public utility grants an undue preference or advantage or unreasonable

130  Cf. Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the fundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, hide elephants in mouseholes.”); see Atl. City Elec. Co., 295 F.3d at 8 (As a federal agency, “FERC is a ‘creature of statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred upon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted).

131  West Virginia v. EPA, 597 U.S. 697, 723 (2022) (third alteration in original) (citation omitted); see also Midship Pipeline Co. v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding the remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore erroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ to make such a determination indirectly”) (second alteration in original) (quoting West Virginia v. EPA, 597 U.S. at 723).

PDF page 53

53

difference in rates.132  The Commission never responded to this argument—another violation of the APA.133

B.  The Commission’s New Approach Infringes On State Retail Authority.

The states, not the Commission, have jurisdiction to decide when and in what
circumstances retail load will be curtailed, and how utilities should charge and treat retail customers in those circumstances.  The Commission has jurisdiction over “the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce,” and over “all facilities for such transmission or sale of electric energy.”134  Except as otherwise provided in the FPA, the states retain jurisdiction over “any other sale of electric energy” and “over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.”135

Public utilities have a retail obligation to serve.  And the states decide how that obligation should be met.  For example, states might require the provision of backup service to retail customers who lose supply from their contracted supplier, would regulate the distribution system costs associated with such service that would be charged to the retail customer, and would regulate the costs and terms of the backup service.  Rather than honoring the states’ freedom and flexibility to exercise their jurisdiction over such questions, the Commission’s new rule appears to create a new federal construct that defines the extent and terms of service in such situations.  The

132  16 U.S.C. § 824d(b).
133  See New England Power Generators Ass’n, Inc., 881 F.3d at 211; Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d at 299; Tesoro Alaska Petroleum Co., 234 F.3d at 1294.
134  16 U.S.C. § 824(b).
135  Id.

PDF page 54

54

Commission does not have authority under the FPA to dictate the terms of retail service in that fashion.

Notably, the approach adopted by the Commission in the form of new transmission services is not similar to wholesale demand response programs where the courts have found that the Commission appropriately acted.136  “Wholesale demand response . . . pays consumers for commitments to curtail their use of power, so as to curb wholesale rates and prevent grid breakdowns,” and “wholesale market operators employ demand response bids in competitive auctions that balance wholesale supply and demand and thereby set wholesale prices.”137  “The operators accept such bids if and only if they bring down the wholesale rate by displacing higher- priced generation.  And when that occurs (most often in peak periods), the easing of pressure on the grid, and the avoidance of service problems, further contributes to lower charges.”138 Unlike the wholesale demand response programs, which “allow[] any state regulatory body to prohibit consumers in its retail market from taking part in wholesale demand response programs,” thereby “not requir[ing] any “‘action[ ] that would violate State laws or regulations,’” the Commission’s new forms of transmission services provide no such limitation.139  As the Supreme Court has explained, however, “if indirect or tangential impacts on wholesale electricity rates sufficed, FERC could regulate now in one industry, now in another, changing a vast array of

136  See FERC, Energy Primer: A Handbook for Energy Market Basics, at 41 (Jan. 17, 2024), https://www.ferc.gov/news-events/news/ferc-staff-issues-2024-energy-primer-handbook-energy-market-basics (“Demand response is the reduction in consumption of electricity by customers from their expected consumption levels, in response to either reliability needs or price signals.  Customers will forego power use for short periods, shift some energy use from peak periods to other times, or use on-site generation in response to price signals or incentives for load reduction.”).
137  FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 270, 278–79 (2016).
138  Id. at 279.
139  Id. at 275 (third alteration in original) (citation omitted).

PDF page 55

55

rules and practices to implement its vision of reasonableness and justice,” a result that the Court could not “imagine . . . was what Congress had in mind.”140  That is the problem here with FERC’s replacement rate.

As the Supreme Court explained, the FPA
“limit[s] FERC’s sale jurisdiction to that at wholesale,” reserving
regulatory authority over retail sales (as well as intrastate wholesale
sales) to the States.  FERC cannot take an action transgressing that
limit no matter how direct, or dramatic, its impact on wholesale
rates.  Suppose, to take a far-fetched example, that the Commission
issued a regulation compelling every consumer to buy a certain
amount of electricity on the retail market.  Such a rule would
necessarily determine the load purchased on the wholesale market
too, and thus would alter wholesale prices.  But even given that
ineluctable consequence, the regulation would exceed FERC’s
authority, as defined in § 824(b), because it specifies terms of sale
at retail—which is a job for the States alone.141
FERC’s CD Services similarly interfere with States’ regulation of the terms of sale at retail, dictating the terms and circumstances of service to end use customers who lose their contracted retail power supplier—an area that is directly within the States’ domain.  The Commission is unable to do indirectly what it cannot do directly, which is what it does when it intrudes on state regulatory authority over retail service in this fashion.142

140  Id. at 278.
141  Id. at 279–80 (alteration in original) (citations omitted).
142  Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909 F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this directly were established, the existence of power to achieve the same end indirectly through the conditioning power might well be doubted”) (quoting Sunray Mid-Continent Oil Co. v. FPC, 364 U.S. 137, 152 (1960) and citing Richmond Power & Light v. FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve indirectly through conditioning power of Federal Power Act what it is otherwise prohibited from achieving directly)); Am. Gas Ass’n, 912 F.2d at 1510 (“[T]he Commission may not use its § 7 conditioning power to do indirectly . . . things that it cannot do at all.”); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room either for direct state regulation of the prices of interstate wholesales’ or for regulation that ‘would indirectly achieve the same result.’”) (citation omitted).

PDF page 56

56

If one takes away the Commission’s intrusion into the terms of retail service (such as the issue of what distribution charges and responsibilities should be borne by the load, the terms of and charges for backup service to the load, and the terms by which the load might avoid paying for such service) nothing is left of CD Service.  The Commission should encourage transmission providers to treat an Eligible Customer who takes transmission service to serve these loads like all other such providers, i.e.,  on the basis of their load ratio share of embedded network costs and leave the retail service questions to the retail regulator.  The imposition of CD Service rates to usurp these questions exceeds the Commission’s lawful authority.

PDF page 57

57

V. Conclusion
Because neither the Commission nor Constellation have satisfied their burden under FPA section 206 and the Commission has not engaged in reasoned decision making in the 206 Order, the Commission should grant rehearing, revoke its directives to establish new transmission service offerings, and instead, take no action pursuant to section 206 and find that the existing PJM Tariff is just and reasonable.

Respectfully submitted,
/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Bradley R. Perkins
Bradley R. Perkins
Vice President and Deputy General Counsel
Exelon Corporation
Chase Building
10 S. Dearborn, 52nd Floor
Chicago, IL 60603
Telephone: 312-394-2632
Email: bradley.perkins@exeloncorp.com

On behalf of Exelon Corporation

/s/ Amanda P. Parker
Amanda P. Parker
Corporate Counsel
FirstEnergy Service Company
341 White Pond Drive
Akron, OH 44320
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com

On behalf of The FirstEnergy
Transmission Companies

PDF page 58

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in the above captioned dockets. Dated at Chicago, IL this 16th day of January, 2026.

/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation