The Indicated PJM Interconnection, L.L.C. Transmission Owners submit Request for Rehearing of the 12/18/2025 Order
Text extracted from the eLibrary original (SHA-256 5a5e02d7122b92a7…). Download the original from the official source.
Contents · 15 sections
- I. Statement of Issues/Specification of Error.
- II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate
- A. There is No Evidence In The Record That Co-Located Loads Are Unable to
- B. The Commission Did Not Engage in Reasoned Decision Making Because It
- C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
- III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement
- A. Allowing Special Treatment For Co-Located Load Violates The FPA’s
- B. The Commission’s Emphasis On Protective Systems Is In Tension With The
- C. The 206 Order is Arbitrary And Capricious In Abandoning The Main
- D. The Commission Is Wrong In Suggesting That CD Service Will Promote
- E. The Commission’s Disregard of Reliability Considerations Underscores That
- IV. FERC Exceeded Its Jurisdiction.
- A. FERC’s Replacement Rate Violates the Major Questions Doctrine.
- B. The Commission’s New Approach Infringes On State Retail Authority.
- V. Conclusion
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
As used in Tariff, Part VI, Eligible Customer shall mean only those Eligible Customers that have submitted a Completed Application.Read this passage Filed comments: Connecting load and generation
I. Statement of Issues/Specification of Error.
printed heading · Topic match: Connecting load and generation
The Commission’s proposal that co-located load must self-fund any needed transmission upgrades is arbitrary and capricious because FERC has not explained its decision to depart from prior precedent.Read this passage Filed comments: Connecting load and generation
II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate
printed heading
The FPA requires that the rates and charges of a public utility “in connection with the transmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules and regulations affecting or pertaining to such rates or charges shall be just and reasonable.”14 “[A]ny such…Read this passage
A. There is No Evidence In The Record That Co-Located Loads Are Unable to
printed heading · Topic match: Connecting load and generation
The Commission states that “PJM’s Tariff is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to Interconnection Customers21 serving Co-Located Load and Eligible Customers taking…Read this passage Filed comments: Connecting load and generation
B. The Commission Did Not Engage in Reasoned Decision Making Because It
printed heading · Topic match: Cost allocation
As an initial matter, picking and choosing customers to receive preferential rate treatment runs contrary to the FPA’s requirement that “[n]o public utility shall, with respect to any 46 Id.Read this passage Filed comments: Cost allocation
C. The Loads Rely Upon The Entire Embedded Transmission System To Serve
printed heading · Topic match: Connecting load and generation
A nuclear facility must be interconnected to the grid as a Nuclear Regulatory Commission licensing obligation74 and it cannot follow load in any meaningful sense.75 Therefore, every swing in a load that is co-located with a nuclear plant—from zero MW to full load—will impact the grid.76 There is no…Read this passage Filed comments: Connecting load and generation
III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement
printed heading · Topic match: Connecting load and generation
All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just and…Read this passage Filed comments: Connecting load and generation
A. Allowing Special Treatment For Co-Located Load Violates The FPA’s
printed heading · Topic match: Connecting load and generation
The Commission states that “Eligible Customers taking the interim, non-firm transmission service on behalf of Co-Located Loads would avoid paying generator capacity costs in return for their willingness to curtail their withdrawals in advance of emergency conditions.”94 The Commission then sets for…Read this passage Filed comments: Connecting load and generation
B. The Commission’s Emphasis On Protective Systems Is In Tension With The
printed heading
Cir. 2014) (per curiam)) (“The cost-causation principle requires that ‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that benefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”). 98 See…Read this passage
C. The 206 Order is Arbitrary And Capricious In Abandoning The Main
printed heading · Topic match: Connecting load and generation
The Commission Also Erred In Adopting a Generator Funding Model For The Funding Of Network Upgrades For Co- Located Load With No Supporting Evidence In the 206 Order, FERC changes the PJM Tariff to “specify[] that an Interconnection Customer seeking to serve Co-Located Load using an existing…Read this passage Filed comments: Connecting load and generation
D. The Commission Is Wrong In Suggesting That CD Service Will Promote
printed heading · Topic match: Reliability and curtailment
Grid operators must plan for such eventualities to ensure system reliability.117 The Commission finds in the 206 Order that the BTMG “rules in PJM’s Tariff are no longer just and reasonable because loads with BTMG are not fully accounted for in resource adequacy planning and shift costs onto other…Read this passage Filed comments: Reliability and curtailment
E. The Commission’s Disregard of Reliability Considerations Underscores That
printed heading · Topic match: Connecting load and generation
P 200. 125 Id. 51 The Commission attempts to minimize the concerns by stating that because interconnection customers of co-located load arrangements must identify an Eligible Customer to take transmission service on behalf of co-located load, the load will be visible.126 But that does not answer…Read this passage Filed comments: Connecting load and generation
IV. FERC Exceeded Its Jurisdiction.
printed heading · Topic match: Reliability and curtailment
P 201 (setting for hearing how such emergency curtailment would be implemented and under what standards). 128 Constellation Mystic Power, LLC, 45 F.4th at 1035. 129 Cf.Read this passage Filed comments: Reliability and curtailment
A. FERC’s Replacement Rate Violates the Major Questions Doctrine.
printed heading · Topic match: Connecting load and generation
FERC, like all agencies, “ha[s] only those powers given to [it] by Congress, and ‘enabling legislation’ is generally not an ‘open book to which the agency [may] add pages and change the plot line.”131 The Commission lacks authority under the FPA to order a new type of transmission service with the…Read this passage Filed comments: Connecting load and generation
B. The Commission’s New Approach Infringes On State Retail Authority.
printed heading · Topic match: Retail and wholesale authority
FERC, 254 F.3d at 299; Tesoro Alaska Petroleum Co., 234 F.3d at 1294. 134 16 U.S.C. § 824(b). 135 Id. 54 Commission does not have authority under the FPA to dictate the terms of retail service in that fashion.Read this passage Filed comments: Retail and wholesale authority
V. Conclusion
printed heading · Topic match: Filing procedure
Conclusion Because neither the Commission nor Constellation have satisfied their burden under FPA section 206 and the Commission has not engaged in reasoned decision making in the 206 Order, the Commission should grant rehearing, revoke its directives to establish new transmission service…Read this passage Filed comments: Filing procedure
CERTIFICATE OF SERVICE
printed heading
Dated at Chicago, IL this 16th day of January, 2026. /s/ Geneva Kennedy Geneva Kennedy Exelon CorporationRead this passage