EL25-49-002 · 2026-01-20 · Earthjustice

Public Interest Organizations submit Limited Request for Clarification of the 12/18/2025 Order

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

)
PJM Interconnection, et al.
)
Docket No. EL25-49-000, et al.

)

LIMITED REQUEST FOR CLARIFICATION OF PUBLIC INTEREST
ORGANIZATIONS

Pursuant to Section 313 of the Federal Power Act (“FPA”),1 and Rules 212 and 713 of the Commission’s Rules of Practice and Procedure,2 Earthjustice, Environmental Defense Fund, and Sierra Club (Public Interest Organizations) request clarification of the Commission’s December 18, 2025 order in the above- captioned proceeding, 193 FERC ¶ 61,217 (2025) (“Order”), pursuant to the reasons more fully described below.

I. Background

Last February, the Commission took on the tough task of prompting PJM to revisit its processes for addressing large load arrangements.3  As part of the show cause proceeding, the Commission sought feedback from PJM and stakeholders on over thirty comprehensive briefing questions covering topic areas that required further clarity to support colocation arrangements, including cost allocation for transmission service4 and resource adequacy concerns, such as whether PJM should consider changes to its “planning processes” or “load forecasting methods” to “better plan for and address resource adequacy and reliability impacts of co-location arrangements.”5

The Commission’s Show Cause Order specifically asked whether PJM should “consider changes to load forecasting methods, informational postings, or the reserve margin study process to better plan for and address the resource adequacy and reliability impacts of co-location arrangements.”6 As further detailed below, on

1 16 U.S.C. § 825l.
2 18 C.F.R. §§ 385.212, 385.713.
3 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 (2025) (Show Cause Order).
4 Show Cause Order P 88, b.i – b.iv.
5 Id. P 88, e.v.  In addition, the Commission consolidated with this proceeding the record from the technical conference in Docket No. AD24-11-000 and Constellation’s complaint in Docket No. EL25-20-000.
6 Show Cause Order P 88 (e)(v).

PDF page 2

2

April 23, 2025, Public Interest Organizations (PIOs) filed comments that comprehensively responded to, among other things, this question.7 On September 18, 2025, Commissioner Rosner issued a follow-up letter to PJM specifically requesting information relating to PJM’s existing process and future expectations regarding its load forecasting process.8 PJM responded to that letter on October 17, 2025.9

Based on the responses to its Show Cause Order, the Commission issued a decision on December 18, 2025.10  While we agree that the Order takes several measures to ensure that rates are just and reasonable for consumers,11 it is unclear how the timing and format of some of the measures will serve their stated purpose, and if so, whether they will be implemented in a timely manner.  As explained in our response, certain prerequisite revisions to PJM’s planning processes, like reformed load forecasting procedures, are necessary before PJM can serve large loads using its existing transmission services and its processes for forecasting capacity market demand and planning regional transmission projects (RTEP) while maintaining rates that are just and reasonable.12

II. Limited Request for Clarification

A. We request clarification on how the rates for PJM’s
Commission-jurisdictional services will be just and
reasonable during the interim period before PJM
implements procedures to avoid using speculative load
information

1. Accurate demand forecasts are needed to support imminent
phases of PJM’s next capacity market and RTEP processes
PJM’s RTEP and capacity market processes are in the midst of using PJM’s load forecasts to plan system needs that will drive energy infrastructure investments and impact wholesale electricity rates.  PJM is preparing to hold the

7 See generally Public Interest Organizations, Comments, Docket No. EL25-49-000, at 15-24 (filed Apr. 23, 2025) (hereinafter “PIO Comments”).
8 See Commissioner Rosner, Letter to PJM, Docket Nos. EL25-49, et al. (Sept. 18, 2025) (“Rosner Letter”). 9 See Asthana, Manu, Letter in Response, Docket No. EL25-49, et al., (Oct. 17, 2025), available at: https://www.ferc.gov/media/pjm-response-chairman-david- rosners-09192025-letter-re-large-load-forecasting-americas. (“PJM October Letter”). 10 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (Order).
11 Order P 162; see also Rosner Concurrence P 1.
12 PIO Comments at 6, 20.

PDF page 3

3

next Base Residual Auction in June 2026.13  The auction will rely in part on PJM’s demand forecast.  With respect to the RTEP, PJM will use data that it gathers from November 2025 through March 2026 to build base case modeling assumptions and perform initial case reviews.14  And from March 2026 to June 2026, PJM expects to perform its RTEP baseline studies,15 which will inform the transmission projects that will be available in the competitive bidding window that PJM expects to open in July 2026.

2. Without a specific directive, PJM is not likely to resolve the issues with its forecasting process in a timely manner

In the Order, the Commission did not directly address the load forecasting issues raised in the record; however, the Commission did require PJM to provide an informational filing that includes, among other things, an update regarding the development of “enhanced load forecasting.”16 Here, we request clarification regarding how the Commission intends to respond to, or otherwise use, the information provided in the record, and any additional information provided by PJM pursuant to the Commission’s request in any subsequent order related to this series of dockets.17 The issues raised by PIOs merit immediate consideration because of the way in which large load forecasting impacts whether the outcome of the newly proposed colocation transmission service pathways ultimately result in rates that are just and reasonable.

Specifically, in our comments we noted that, “PJM’s Tariff is unjust and unreasonable because it lacks sufficient controls and standards to ensure large load forecast accuracy and to protect against speculative large load forecast estimates.”18 We argued that “PJM’s large load forecasting process does not substantively account for speculative load additions, thus rendering the process and resulting forecast, as well as everything that relies on that forecast, unjust and

13 PJM Interconnection, L.L.C., News Release, at 4 (Dec. 17, 2025), https://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2025-

releases/20251217-pjm-auction-procures-134479-mw-of-generation-resources.pdf.
14 Yiming Mao, PJM Interconnection, L.L.C., Review of 2026 RTEP Assumptions, at 3 (Jan. 6, 2026), https://www.pjm.com/-/media/DotCom/committees- groups/committees/teac/2026/20260106/20260106-item-08---2026-rtep- assumptions.pdf.
15 Id.
16 Order P 238.
17 Note the Commission has stated that it “will not act on or notice this informational Filing.” Order P 238, n.486.
18 PIO Comments at 15.

PDF page 4

4

unreasonable,” and also that PJM’s failure to include the provisions governing large load forecasting in the PJM Tariff violates the Commission’s Rule of Reason.19 PJM’s load forecasting procedure can largely be found on three pages in PJM Manual 19, attachment B.20 We identified four primary problems with PJM’s current process. First, the LSE/EDCs in PJM report their large load forecasts in completely different ways, posing a substantial gradient in uncertainty based on the standards and criteria each participant uses in submitting its forecast to PJM.21 Second, PJM has no way to cross-check whether a data center in, for example, Exelon’s service territory has also made the same proposal in Dominion’s territory, and both proposals end up in PJM’s forecast even though only one will be built.22 Third, PJM’s process has no way to timely ensure that large data center cancellations are quickly identified and incorporated into PJM’s forecasts.23 Lastly, we contend that because PJM’s large load forecasting processes are not codified in PJM’s Tariff, and they directly and significantly affect rates for jurisdictional Commission services, their omission violates the Commission’s Rule of Reason.24 We predicted that the combination of these four problems will necessarily result in highly uncertain, and likely inflated load forecasts that will result in unjust and unreasonable rates.

In addition to the question posed in the Show Cause Order, as noted above, Commissioner Rosner submitted a letter to PJM on September 18, 2025, noting that “we cannot efficiently plan the electric generation and transmission needed to serve new customers if we don’t forecast how much energy they will need as accurately as possible.”25 Commissioner Rosner then posed a series of questions for PJM to answer that are largely consistent with the issues raised in PIOs’ comments:

(1) How do you, the utilities in your footprint, and state regulators obtain information that verifies when and whether prospective large loads in your region will reach commercial operation?

(2) To what extent are prospective large load requests subject to consistent, objective screening criteria before they are included in the load forecast?

(3) How do you forecast how the actual electricity consumption of a large load will compare to its requested level of interconnection service?

19 Id. 20 PJM Manual 19, Attach. B, at 26-28.
21 PIO Comments at 17.
22 Id.
23 Id. at 18-19.
24 Id. at 20.
25 Rosner Letter at 1.

PDF page 5

5

(4) How do you coordinate with utilities at the regional or interregional level to share best practices on large load forecasting and ensure that large load interconnection requests are not double-counted?26

On October 17, 2025, PJM responded to Commissioner Rosner’s letter.27 PJM also indicated that it has adopted a Load Adjustment Request Implementation document that “offers enhanced transparency about PJM’s load adjustment request submission process in PJM Manual 19, Attachment B.”28 With regard to PIOs’ comments, while the document specifies generally what types of information PJM desires from forecast submitters and explains a basic weighting criteria, it expressly does not require or “specify a particular methodology for forecasting large loads.”29 Without a clear methodology, LSE/EDCs will continue to report data with widely varying accuracy, which will necessarily result in uncertain forecasts. Commissioner Rosner also asked PJM to respond to the concern of double-counting of data centers; however, PJM’s response does not identify a concrete way in which it is currently, or plans to in the future, address this issue. Instead, it merely concludes that PJM “looks forward to continued collaboration with its stakeholders . . . to pursue additional enhancements and opportunities for consistency across the region.”30 This response is not sufficient to address this well-known issue across the industry.31 Additionally, nothing in PJM’s response addresses the need for more timely updates to the load forecasting process in PJM. Considering the way in which significant load proposals are dropped, or added, PJM needs a more dynamic approach for updating the load forecasts to reflect the current state of demand.32 Thus, it is unclear how the informational report on PJM’s activities that the Commission directed in the Order will ensure PJM implements needed improvements to its process in a timely manner.

3.  The inaccuracy of PJM’s demand forecasting was recently
demonstrated

26 Id. at 2.
27 See generally PJM October Letter. 28 Id. at 2.
29 PJM Interconnection, L.L.C., Load Adjustment Request Implementation, PJM Resource Adequacy Planning Department (July 1, 2025; revised Aug. 26, 2025), available at: https://www.pjm.com/-/media/DotCom/committees- groups/subcommittees/las/postings/load-adjustment-request-implementation.pdf.
30 PJM October Letter at 6.
31 PIO Comments at 17-18.
32 Id. at 18.

PDF page 6

6

Unfortunately, PIOs’ concerns regarding the accuracy of PJM’s load forecasts have recently been actualized. PJM’s recent announcements call into question the accuracy of the inputs to PJM’s most recent capacity market auction and related wholesale electricity market rates as well as its transmission planning models. Shortly after PJM’s 2027/2028 Base Residual Auction, Stu Bresler, PJM’s former Executive Vice President of Market Services and Strategy, indicated during a press conference that the 2026 Forecast would likely reflect a decrease in forecasted load for that time period since PJM is revising its process for implementing load adjustments.33  However, that course correction came too late for ratepayers. As a reminder, the 2027/2028 auction resulted in a capacity shortfall and “record [high] prices” in part due to the projected demand, which included 5,100 MW for data centers.  Regarding the next auction, PJM Chief Operating Officer Stu Bresler said that “PJM’s overall power demand forecast for the year beginning in mid-2027 will be ‘appreciably lower’ than current projections.”34  According to PJM’s most recent 2026 PJM Load Forecast Report, its most recent analysis has “brought large load adjustments down in the near-term forecast years compared to the 2025 Long-Term Load Forecast.”35

State representatives and industry experts are also sounding the alarms.36 Former NARUC President, Travis Kavula, has stated that despite PJM now “applying a scintilla of judgment,” its forecast “remains a colossal act of speculation.”37 Considering that PJM uses its load forecasts to essentially set the demand curve for capacity obligations, for reliability studies, and to support the

33 Devin Leith-Yessian, PJM Capacity Auction Clears at Max Price, Falls Short of Reliability Requirement, (December 17, 2025), https://www.rtoinsider.com/121911- pjm-capacity-auction-clears-max-price-falls-short-reliability-requirement/.
34 Behr, Peter, PJM to ratchet down projected AI power demand for eastern US, Energy Wire, available at: https://subscriber.politicopro.com/article/eenews/2026/01/06/pjm-to-ratchet-down- projected-ai-power-demand-for-eastern-us-00711947.
35 PJM Load Forecast Report, PJM (January 14, 2026), at 4, available at: https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026- load-report.pdf.
36 John D. Wilson, et al, Energy Systems Integration Group Large Load Task Force, Forecasting for large Loads, Current Practices and Recommendations, at 2-5 and 68 https://gridstrategiesllc.com/wp-content/uploads/ESIG-Large-Loads-Forecasting- report-2025.pdf (“The massive scale of anticipated large load growth—for individual facilities and collectively  within and across regions—increases the reliability  and financial consequences of load forecast errors.”
37 See https://x.com/TKavulla/status/2011885773663191205?s=20

PDF page 7

7

RTEP,38 and those forecasts have been shown to be “appreciably,” and possibly “colossally” inaccurate, how can the resulting rates from these processes be just and reasonable without significant revisions to PJM’s process?

We request clarification regarding how the Commission intends to use the informational report directed in its Decision,39 and further request that any subsequent order from the Commission address the issues raised in the record regarding the continuing and ongoing deficiencies in PJM’s large load forecasting process.

B. Evaluating whether the status quo transmission rate design
for large load customers is still just and reasonable
Given the unprecedented volume and scale of large-load requests, the Commission should evaluate whether existing transmission rate designs remain just and reasonable. In the Order, the Commission determined that co-located load paying for NITS service would be responsible for costs that are at least "roughly commensurate" with benefits because zonal NITS rates include upgrades and operations and maintenance costs.40 However, this rate design relies on a standard that assumes load growth is incremental and widely distributed.

The practical reality is that discrete large-load pockets trigger multi-million- dollar reliability solutions. Because customers pay only in proportion to billing determinants (usage shares) rather than incremental costs triggered, a significant “payer gap” can emerged. Under Schedule 12 of the PJM Tariff, a substantial share of the revenue requirement for RTEP projects are allocated regionally through the Transmission Enhancement Charge.41 For example, the Mars-Golden-Lockridge Complex (2022 RTEP Window 3) is now estimated at $725.3M following April 2025 scope updates. Under a 7% load-share illustrative, the triggering load pays only $50.8M, leaving $674.5M to be socialized among other customers.

The gap is even more pronounced in the Southern Cluster / “Kraken” package—a $5.08B portfolio centered on a 185-mile undergrounded HVDC line approved in the 2024 RTEP Window 1 to serve “Data Center Alley.”42 If a 1,000 MW

38 PJM Manual 19, at 12, available at https://www.pjm.com/- /media/DotCom/documents/manuals/m19.pdf.
39 Order P 238, n.486 (noting the Commission “does not intend to act on or notice this informational filing”).
40 Order P 198.
41 PJM Open Access Transmission Tariff (OATT) Network Integration Transmission Service (NITS) & Zonal Rates Schedule 9: Network Integration Transmission Service Schedule 12: Charges for Required Transmission Enhancements.
42 PIO Comments at 13.

PDF page 8

8

data center represents 7% of the zone’s peak determinants, it contributes only $203M, leaving a $4.877B gap for unrelated regional and zonal customers. The Commission has already recognized the need for a departure from the status quo allocation in other contexts. In its October 10, 2025 approval of SPP’s Provisional Load Process (Docket No. ER25-2430), the Commission accepted a cost causation approach that initially assigns upgrade costs to transmission customers to protect existing users from “the uncertain nature of load and generation additions.”43

Accordingly, we request that the Commission clarify how “roughly
commensurate” is evaluated when a discrete driver’s pro-rata contribution is dwarfed by the multi-billion-dollar infrastructure it necessitates. Furthermore, the Commission should direct PJM and its Transmission Owners to provide transparent reporting for major projects that explicitly compares incremental cost causation against pro-rata billing determinant recovery, ensuring the resulting allocation is not unjust and unreasonable, or unduly discriminatory or preferential.

III. Conclusion
For the foregoing reasons, Earthjustice, Environmental Defense Fund, and Sierra Club respectfully request that the Commission clarify its December 18, 2025 Order.

Dated: January 20, 2026

Respectfully submitted,
/s/ Christine Powell
Christine Powell
Earthjustice
180 Steuart St. #194330
San Francisco, CA 94105
Telephone: (415) 217-2091
Email: cpowell@earthjustice.org

/s/ Aaron Stemplewicz
Aaron Stemplewicz
Earthjustice
1617 John F. Kennedy Blvd., Suite 2020
Philadelphia, PA 19103
Telephone: (917) 628-7411
Email: astemplewicz@earthjustice.org

/s/ Ted Kelly

43  Southwest Power Pool, Inc., 193 FERC ¶ 61,018, at P 57 (2025).

PDF page 9

9

Ted Kelly
Environmental Defense Fund
555 12th St. NW Suite 400
Washington, DC 20004
Telephone: (202)572-3317
tekelly@edf.org

/s/ Justin Vickers
Justin Vickers
Senior Attorney
Sierra Club
Chicago, IL
Telephone: (224) 420-0614
justin.vickers@sierraclub.org

PDF page 10

10

CERTIFICATE OF SERVICE

The undersigned certifies that a copy of this filing has been served this day upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated: January 20, 2026.
/s/ Aaron Stemplewicz
Aaron Stemplewicz
Earthjustice
1617 John F. Kennedy Blvd., Suite 2020
Philadelphia, PA 19103
Telephone: (917) 628-7411
Email: astemplewicz@earthjustice.org