EL25-49-002 · 2026-01-20 · Eolian, L.P.Antora Energy LLC
Eolian, L.P. et al. submit Request for Rehearing of the 12/18/2025 Order
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems,
Incorporated
Atlantic City Electric Company
Baltimore Gas and Electric Company Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC Hudson Transmission Partners, LLC Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc.
AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
) Docket Nos.
EL25-49-000
)
EL25-49-001
PDF page 2
2
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission
Company
Large Loads Co-Located at Generating
Facilities
AD24-11-000
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
EL25-20
(Consolidated)
Request for Clarification of Eolian LP, Antora Energy LLC, and Verrus LLC Pursuant to Rule 212 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”),1 Eolian L.P. (Eolian), Antora Energy LLC, and Verrus LLC request clarification of the Commission’s December 18 Order in the above- captioned proceeding (Order). Specifically, the undersigned parties ask the Commission to clarify that where the Order provides that a Co-Located load may “request only the minimum level of interconnection service it deems necessary to effectuate its Co-Location Arrangement,”2 that it means the Co-Located Load may nominate a net withdrawal limit in the same manner that
1 18 C.F.R. § 385.212. 2 Order at P 232.
PDF page 3
3
it may nominate a net injection limit. Making this clarification will ensure that Co-Located loads paired with energy storage can use their full technical capabilities to avoid unnecessary network upgrades, thereby advancing the Commission’s twin goals of protecting ratepayers and advancing speed-to-power within PJM.
The Commission’s order is a big step forward in delivering a commonsense solution to growing demand. As Commissioner Rosner explains, it does so by “enabl[ing] large loads to reduce how much they lean on the grid, while ensuring that they pay their fair share.”3 In the Order, the Commission found PJM’s tariff unjust and unreasonable because it does not include transmission service reflecting that some Co-Located Loads “are willing and able to limit their energy withdrawals from the transmission system.”4 The Commission found that extending new transmission service options is necessary to ensure that Co-Located Loads pay only for the services they use, and also to ensure that Co-Located Loads use their ability to limit withdrawals to avoid “costly and inefficient transmission system buildout.”5 The Commission’s logic should compel complementary reforms to the generator interconnection process, because that process also may evaluate withdrawals from the Co-Located Load and therefore may also result – absent clarification – in “costly and inefficient transmission system buildout.”
The Commission should make clear that PJM must enable interconnection customers to nominate withdrawal limits in the interconnection process, just as it requires PJM to allow generators to limit their proposed output. Accurate modeling of withdrawals is particularly critical to the ability of Co-Located Loads incorporating energy storage to connect without triggering transmission upgrade needs. Due to their unique technical capabilities and ability to
3 Id. at P 4.4 Id. at P 177.5 Id.
PDF page 4
4
deploy quickly, energy storage is an essential piece of the solution to enabling timely connection of large electricity customers. While energy storage currently comprises a small portion of the overall resource mix in PJM, there are many projects in development and storage is an integral piece of multi-technology solutions for large customers. The Commission’s Order is an important step in enabling such solutions but without clarification, ambiguity in how such solutions are to be studied in the interconnection process could continue to stymie their development.
I. BACKGROUND
A. Energy storage resources are critical for meeting data center loads quickly
and reliably
Energy storage resources are positioned to play a critical role in meeting demand from new large loads, especially co-located data center loads. A key reason is that batteries are uniquely well suited to respond to the minute-to-minute volatility of data center loads. Natural gas turbines and reciprocating engines can play an important role in providing energy to a Co- Located Load, but are not capable of following the highly volatile load profiles of AI data centers, and risk damage when they do.6 For these reasons, battery storage is being deployed across a range of data center applications, including many that also incorporate thermal generation.
Energy storage resources are also faster to deploy and can meet the aggressive schedules of data center loads. For example, 7,722 MW of the 26,618 MW selected in PJM’s RRI were
6 Authors from Siemens Energy note” “In large data centers, demand swings can reach 100 MW or more, occurring multiple times per minute on sub-second timescales. . . The unpredictable demand profile created by these transients can be challenging for gas turbines or reciprocating engines, which are designed for relatively stable baseload operation. . . .Even the most advanced droop control governing in gas turbines cannot handle the rapid changes in frequency. If left unmitigated over time, severe damage can occur, shortening the lifespan of gas turbine units.” Danny Clayton and Nico Jansen van Rensburg, Pipeline & Gas Journal (Dec. 1, 2025).
PDF page 5
5
from batteries.7 And, of the “new” projects selected in the RRI (as opposed to uprates), all but one of the projects scheduled to deploy this decade are batteries.8 Market rules that do not utilize storage to its full capabilities will necessarily slow progress.
The Order is premised in no small part on the concept that Co-Located loads can manage their total withdrawals from the grid, and that their capability to do so should be enabled to reduce overall system costs. Energy storage resources are better positioned than any other resource to manage the total withdrawals from a Co-Located load quickly and reliably. As Constellation explained in this docket, using battery energy storage systems to provide backup service at data centers “can supply a consistent level of energy for several hours,” allowing a developer to “minimize costs related to system design.”9
B. Request for Clarification
Clarification is necessary to realize the Commission’s intent of ensuring that Co-Located Loads do not pay for services that they do not use and do not trigger network upgrades that they do not need. The Commission’s order requires PJM to establish rules for Interconnection Customers serving co-located load,10 both for new service requests,11 and for modifications to existing facilities through the necessary study process.12 For both processes, we seek clarification that interconnection customers serving co-located load must be permitted to nominate net
7 PJM, Reliability Resource Initiative Results Summary (May 6, 2025), available at https://www.pjm.com/- /media/DotCom/committees-groups/committees/pc/2025/20250506/20250506-item-06---reliability-resource- initiative---summary-results.pdf.8 The lone exception is the Three Mile Island restart, which was in planning well before selected in the RRI. See, PJM, Reliability Resource Initiative Additional Summaries (May 6, 2025) at 6 – 8, available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/pc/2025/20250506/20250506-rri-addendum- --post-meeting.pdf.9 Answer of Constellation Energy Generation, LLC, at 98-99 (April 23, 2025).10 Order at P 187.11 Id. at PP 231-236.12 Id. at PP 225-230.
PDF page 6
6
withdrawal limitations for purposes of these interconnection study processes.13 The Commission’s order requires PJM to develop transmission service frameworks that allow customers to take curtailable service based on the use of special protection schemes that enable reliable, curtailable service based on technical and engineering requirements set by PJM,14 and requires PJM to enable an interconnection customer to request the “minimum level of interconnection service it deems necessary.”15 We seek clarification that, as applied to an interconnection request by a Co-Located Load that includes energy storage components, this means that to the extent PJM performs study steps involving withdrawal assumptions from both the storage facility components and the co-located load components, these study steps must allow the interconnection customer to provide for limits to the injection and withdrawal rights for the generation and co-located load facilities reflecting the proposed integration of those facilities.
1. The order’s requirements and necessary clarification
The Commission’s Order finds that “the PJM Tariff is unjust and unreasonable because it lacks sufficient clarity and consistency with respect to the rules for Co-Location Arrangements” and on this basis directs changes to the new service request process, as well as the necessary study process for modifications to existing facilities. With regard to “Interconnection Customers seeking to use new generating facilities to serve Co-Located Load,” the Commission requires PJM to clarify that it “shall consider requests for interconnection service below the full generating capability of the generating facility, so that an Interconnection Customer may request interconnection service at a level below its maximum facility output to serve Co-Located
13 See Comments of Bloom Energy Corporation at 11 (requesting an interconnection study process that limits net load impacts to “the nominated net grid withdrawal” of the co-located facilities).14 Order at P 212.15 Id. at P 232.
PDF page 7
7
Load.”16 The Order specifies that “[t]his revision will clarify that an Interconnection Customer seeking to use a new generating facility to serve a Co-Located Load may request only the minimum level of interconnection service it deems necessary to effectuate its Co-Location Arrangement.”17 With regard to the necessary study process, the Commission requires PJM “to add to the Tariff a description of the scope of the analysis that it will perform as part of the necessary study process when an Interconnection Customer seeks to use its existing generating facility to serve Co-Located Load,” which must include a description of “the information that the Interconnection Customer must provide about the Co-Located Load for purposes of the necessary study.”18
While these directives from the Commission make clear that an interconnection customer must be able to request service below a generator’s full output capability, they do not explicitly address how PJM must modify its tariff with regard to the study assumptions used for interconnection requests involving energy storage resources co-located with loads. With energy storage resources, the assumptions that PJM uses for purposes of the resource’s withdrawals from the grid are an important part of the study process. PJM’s study process sets forth rules for how withdrawals from energy storage facilities will be modeled, and PJM recently submitted a compliance filing in Docket No. ER24-2045 to effectuate the Commission’s requirement in Order No. 2023 to use operating assumptions in interconnection studies that reflect the proposed charging behavior of electric storage resources.19 Missing from that framework, however, is a description of whether and how such studies may factor in co-located load when a co-located generation facility is proposed. To fill that gap, the Commission should require that, to the extent
16 Order at P 232.17 Id.18 Id. at P 227.19 See PJM Transmittal Letter, Docket No. ER24-2045, at 39-42 (Oct. 22, 2025).
PDF page 8
8
that PJM includes the co-located load in such studies,20 it must allow the interconnection customer to provide withdrawal limits for both the energy storage resource components and the co-located load. This clarification should apply to both new interconnection service request study processes, as well as the necessary study process. Further, just as the Commission requires “PJM to describe the information that the Interconnection Customer must provide about the Co- Located Load for purposes of the necessary study,”21 the Commission should also require PJM to specify what information about the Co-Located Load is required for purposes of the new service request study process. As Antora previously explained, without such information, any process that includes the impact of the proposed load may not capture the proposed “load shape and flexibility,” or account for special protection schemes proposed to be integrated into the co- located facilities.22 In other words, the Commission should clarify that PJM must not include overlapping load and energy storage withdrawal impacts in its generator interconnection study process unless it does so accurately, based on information about both the load and storage components of the facility, and the proposed net withdrawal limits of the facility. Without such direction, there is a risk that imprecise or inaccurate modeling assumptions will identify network upgrades that are not needed to integrate the proposed facilities with the grid.
20 We recommend that the Commission avoid necessarily requiring the co-located load to be modeled as part of such studies, as the decision whether to include load may depend on the timing of the load interconnection request study processes vis-à-vis the generation interconnection request; and the question of whether and how the load is modeled may implicate complex questions concerning the interaction between the load and generation interconnection processes. However, the Commission should require that, to the extent that load is included within the generation interconnection study assumptions, it must be incorporated in a manner that allows for the interconnection customer to provide for joint withdrawal limits between the storage and load components, based on the facility’s capabilities and plan for operation, as supported by information about the generation resource and load submitted by the interconnection customer. 21 Order at P 227.22 Motion to Intervene Out of Time and Comments of Antora Energy LLC In Response to the Commission’s Co- location Order, at 9-10 (April 23, 2025).
PDF page 9
9
2. Clarification is required in order to ensure just and reasonable rates
The Order finds the existing PJM tariff unjust and unreasonable because it lacks clear provisions to govern the “rates, terms, and conditions of service that apply to Interconnection Customers serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.”23 The requested clarification aims to address precisely this defect: the absence of clear rules that govern how co-located load paired with storage will be studied in the generator interconnection process. The PJM tariff, as currently drafted, does not specify how storage withdrawals will be modeled when a storage facility is seeking to co-locate with a large load.
This absence of clear tariff provisions means that without clarification, there is a risk that the interconnection study process could include assumptions that the load and the charging load of the storage resource create bluntly overlapping grid impacts (e.g. coincident withdrawals at peak), when in fact the storage resources and co-located load could be managed to limit the overall withdrawal of the co-located resource and to avoid withdrawal when doing so would create grid impacts necessitating network upgrades. The record demonstrates that interconnection customers can build facilities that integrate a variety of “onsite self-supply resources—such as fuel cells, gas turbines, or battery storage” and use “controls and protection mechanisms” such that the integrated facility “can limit maximum flows into and out of” co-located facilities.24 Yet as Bloom Energy Corporation explains, PJM’s tariff has “no existing protocols” for studying new generation (including energy storage) together with load.2523 Order at P 175.24 Comments of Bloom Energy Corporation, Attachment, Brattle Report at 9, 27 (April 23, 2025).25 Comments of Bloom Energy Corporation at 10.
PDF page 10
10
The Order recognizes that co-located resources can be integrated so as to “limit [the] energy withdrawals” of co-located loads so as to prevent “inefficient and costly transmission buildout.”26 But it does so in the context of requiring PJM to offer non-firm transmission service, without expressly applying this reasoning to the interconnection study context. In requiring PJM to offer co-located loads a menu of transmission service options, the Order ensures that such loads have the opportunity to receive service that “reflect[s] their actual impact on the transmission system.”27 But the value presented by the option to obtain non-firm transmission service would be substantially diminished if the generator interconnection process separately forces the co-located load to bear the cost and delay of unnecessary network upgrades that do not “reflect[s] their actual impact on the transmission system.”28 The Commission should clarify that its findings in requiring non-firm service also apply with regard to PJM’s interconnection study processes, as this is the process that directly identifies necessary transmission upgrades. The Commission must require PJM to allow for non-firm withdrawal and integrated operation of co- located facilities including net withdrawal limits to be integrated into interconnection study assumptions because failing to do so “could necessitate inefficient and costly transmission buildout.”29
While the Order’s clear intent is to protect customers from unnecessary upgrade costs,30 the path to realizing billions in transmission infrastructure savings enabled by facilities that incorporate “controls and protection mechanisms used to limit physical withdrawals” is to reflect the controllable nature of those withdrawals in interconnection studies that identify the need for
26 Order at P 199.27 Id. at P 162.28 Id.29 Id. at P 199.30 See id. at P 162.
PDF page 11
11
transmission upgrades.31 By expressly requiring PJM to allow interconnection customers seeking to use new generating facilities to serve Co-Located Load to nominate net withdrawal limits, the Commission will enable the avoidance of unnecessary upgrades and allow for the faster integration of new customers and a more affordable grid.
The Order permits a co-located generator to nominate an injection limit that is less than its total capacity.32 The requested clarification is the logical extension of that principle to withdrawals and would result in the same benefits of avoided costs and faster interconnection times. Conversely, study assumptions that ignore the joint capabilities of energy storage resources paired with co-located loads paired would frustrate the objectives of the Order and render its replacement rate ineffectual for those resources. Allowing co-located loads paired with storage to nominate withdrawal limits will encourage innovation that will bring down these costs. It will allow developers to optimize the configuration of load, generation and storage in a way that internalizes impacts to the transmission system, bringing down overall system costs and accelerating speed to power.
.
31 Comments of Bloom Energy Corporation at 2, 5, 11-12.32 See Order at P 232.
PDF page 12
12
Respectfully submitted,
Ariel Horowitz
Head of Market Strategy
Eolian, L.P.
Noah Long
Director, State and Regulatory Affairs
Antora Energy LLC
Jeff Bladen
Head of Energy
Verrus LLC
PDF page 13
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary of the Commission in this proceeding.
Dated: January 20, 2026
Ariel Horowitz
Head of Market Strategy
Eolian, L.P.