EL25-49-002 · 2026-01-20 · Constellation Energy Generation, LLC
Constellation Energy Generation, LLC submits Request for Clarification or, in the Alternative, Rehearing of the 12/18/2025 Order
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket No. EL25-49-000
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
REQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING
OF CONSTELLATION ENERGY GENERATION, LLC
Constellation Energy Generation, LLC (“Constellation”) requests clarification, or in the alternative, rehearing, of the order issued by the Commission on December 18, 2025, in the above- captioned dockets.1 The Commission should clarify two discrete issues. First, consistent with existing rules for non-firm exports, a capacity resource should not be required to delist when it is serving Co-Located Load2 taking non-firm contract demand transmission service, so long as the capacity resource has no obligation to serve the Co-Located Load during a capacity emergency. In that scenario, the capacity resource remains available to serve the grid when needed for resource adequacy; forcing the capacity resource nevertheless to delist would needlessly remove available capacity from serving the grid. Moreover, the Commission should seek to encourage this type of arrangement—in which the generation resource remains available to the grid in capacity emergencies, and the Co-Located Load either curtails or self-supplies using backup generation—
1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”).2 Unless otherwise defined, all capitalized terms have the same meaning as in the December 18th Order.
PDF page 2
2
because such an arrangement allows for the interconnection of new data center load, vital to our national interest, without any impact on the capacity price or reliability. Second, the Commission should clarify that it did not intend to change the scope of its jurisdiction over a generator’s wholesale sales and transmission and, specifically, that (i) the sales and transmission between a generator and any wholesale entity are not a “question of state law,”3 and (ii) states may not use their jurisdiction over the allocation of the costs of interstate wholesale sales to indirectly regulate the interconnection of generators serving Co-Located Load. To the extent that these clarifications are denied, we respectfully seek rehearing.
LIST OF ERRORS/STATEMENT OF ISSUES
We seek clarification or rehearing on two issues:
1. The Commission should clarify, that consistent with PJM’s existing tariff, capacity resources are not required to delist their capacity before making interruptible commitments to serve Co-Located Load taking non-firm contract demand transmission service, provided PJM can verify that the generator will be available to support the grid during capacity emergencies because the load is interruptible or has its own backup generation arrangements. See 5 U.S.C. § 706(2)(A); Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (State Farm); Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265 (D.C. Cir. 2022); Elec. Consumers Res. Council v. FERC, 747 F.2d 1511, 1513-14 (D.C. Cir. 1984).
2. The Commission should clarify that the December 18th Order did not change the scope of its jurisdiction over a generator’s wholesale sales and transmission. Specifically, the Commission should clarify that (i) sales and transmission between a generator and any wholesale entity are not a “question of state law”4 and (ii) that states may not use their jurisdiction over the allocation of the costs of interstate wholesale sales among retail customers to indirectly regulate the interconnection of generators serving Co-Located Load. See 5 U.S.C. § 706(2)(A); State Farm, 463 U.S. at 43; Elec. Consumers Res. Council
v. FERC, 747 F.2d at 1513-14.
To the extent that the requested clarifications are denied, we respectfully request rehearing.
3 December 18th Order, 193 FERC ¶ 61,217 at P 169.
4 Id.
PDF page 3
3
ARGUMENT
I. The Commission Should Clarify that Capacity Resources are Not Required to Delist Before Making Interruptible Commitments.
Read by its terms, the December 18th Order could appear to require the delist of capacity resources even when the capacity resources remain fully capable of serving the grid during capacity emergencies. The Order states, “[i]n accordance with the existing rules for removing Capacity Resource status, … an existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its [capacity interconnection rights] for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving [Network Integration Transmission Service (NITS)].”5
But generators and Co-Located Load may seek contractual arrangements in which, during a capacity emergency, the generator will serve the grid rather than the Co-Located Load. The Co- Located Load, in turn, could either curtail or rely on its own backup generation. Constellation seeks clarification that the Commission did not intend to discourage or frustrate those arrangements or insist the generation that is capable of supplying the grid during a capacity performance event delist.
Indeed, the Commission should encourage arrangements in which Co-Located Load can receive non-NITS service (such as non-firm contract service) and also curtail its reliance on the Co-Located generator during capacity emergencies. Such an arrangement allows the interconnection of new data center load, important to our economic competitiveness and national security; the co-location of that load, minimizing the need for grid upgrades; and the continued
5 December 18th Order, 193 FERC ¶ 61,217 at P 230 (citing PJM, Intra-PJM Tariffs, OATT, attach. DD.6, § 6.6 Offer Requirement for Capacity Resources (3.0.0); PJM March 24 Response at 58) (emphasis added).
PDF page 4
4
availability of the co-located generator to serve the grid when it is needed to ensure resource adequacy. In other words, such an arrangement facilitates the prompt interconnection of new data center load without any impact on capacity prices or reliability. Requiring the delist of capacity in such an arrangement would needlessly reduce the capacity available for existing customers. It would also be inconsistent with PJM’s existing rules, which only require capacity
resources entering external sales to delist capacity interconnection rights if a resource “has a financially and physically firm commitment to an external sale of its capacity.”6 But again, not all agreements by Co-located Generators to serve Co-Located Load will be “physically firm
commitments.” Some may be interruptible. As the Commission recognizes, “the record
demonstrates … Co-Located Loads are willing and able to limit their energy withdrawals from the transmission system under certain conditions.”7 Co-Located Load may likewise agree to limit their reliance on a co-located generator under certain conditions, such as a capacity emergency, and agree either to curtail itself or be served by backup generation or batteries.8
Accordingly, it is vitally important for the Commission to clarify that it did not intend to require capacity resources to delist to serve co-located loads that are taking non-firm contract demand transmission service, so long as PJM can verify that co-located customer has no
6 PJM Tariffs, OATT, Attachment DD.6, § 6.6 (emphasis added); see also PJM Interconnection, L.L.C. September 17, 2007 Filing, Docket No. ER07-1050-001, at 4-5 (“[A]s set forth in the must-offer rule of section 6.6, a PJM resource that can qualify as a capacity resource must offer its capacity into the RPM auctions unless it can show that it is committed to a firm export, will be physically unavailable in the relevant delivery year, or was interconnected to the system as an ‘energy-only’ resource.”).7 December 18th Order, 193 FERC ¶ 61,217 at P 199; id. P 204 (“We note that, in general, special protection schemes allow Eligible Customers on behalf of Co-Located Load to effectively limit their withdrawals from the transmission system.”) (citing Constellation April 23 Reply Comments Herling Aff. ¶ 23).8 Constellation April 23, 2025 Reply Comments at 98 (“‘[d]ata centers almost always have their own backup power supply ….’”) (quoting Michael Kormos, The Co-Located Load Solution at 10; Kormos Aff., Appendix).
PDF page 5
5
contractual right to energy from the generator during a capacity emergency9 and has the ability to
(i) interrupt and/or (ii) turn on back-up diesels or other back-up power or draw on batteries when transmission under the non-firm contract demand service is interrupted and the co-located
generator is serving the grid.
To the extent there are concerns that PJM would be “in competition with non-capacity
backed co-located loads for output of a Capacity Resource,”10 the Commission could require the Co-Located Load to disclose information regarding protective relay scheme and its interruptible commitment, and impose penalties on that Co-Located Load for failure to comply with its
commitment.11 Those assurances could be provided by the Co-located Load confirming its
willingness and the ability to interrupt or demonstrating that it has back-up diesels or batteries that will take over its supply. If such assurances are provided, it is not reasonable for the Commission to require a Co-Located Generator to delist.
Interruptible commitments are not firm. To treat them otherwise would needlessly deprive
PJM of capacity that would be committed to serve its load, compounding resource adequacy
9 As Constellation stated in its April 23, 2025 Reply Comments, “Constellation’s view is that any Existing Generation Capacity Resources that would prioritize serving co-located load over following PJM dispatch should instead seek removal of Capacity Resource status or otherwise seek appropriate replacement capacity to cover its capacity supply obligation.” Constellation April 23, 2025 Reply Comments at 92-93. 10 PJM March 24, 2025 Answer at 59; id. (“PJM cannot be simultaneously responsible for ensuring the energy needs of the PJM Region and unsure whether a Capacity Resource will decide to serve PJM loads or co-located loads.”) (emphasis in original).11 See December 18th Order, 193 FERC ¶ 61,217 at P 219 (requesting that parties answer “What are the appropriate rates, terms, and conditions” for new Firm Contract Demand and Non-Firm Contract Demand transmission service and “What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system” for an Eligible Customer taking Firm Contract Demand or Non-Firm Contract Demand). On rehearing, Indicated PJM Transmission Owners repeat their prior arguments that protective relays might fail. See Indicated PJM Transmission Owners, January 16, 2026 Request for Rehearing, at 39-41, 49. The Commission should continue to reject these arguments. As supported by Michael Kormos, the former Chief Operations Officer of PJM, “[p]rotective mechanisms are commonplace and frequently used by PJM and others in situations beyond co-located load to ensure safe and reliable grid operations, including for example, primary and secondary relays and redundant protection systems.” Constellation April 23, 2025 Reply Comments at 48-49 (citing Kormos Aff. at ¶ 6).
PDF page 6
6
challenges. In the event the Commission disagrees, we seek rehearing. Requiring capacity
resources to delist when arrangements other than a co-located generator are in place to curtail or serve the large load when transmission service is interrupted would be a failure of reasoned decision making.12 It would also be unduly discriminatory, and therefore arbitrary and capricious, to require capacity resources serving large load to delist for entering into interruptible commitments to serve Co-Located Load, but not requiring capacity resources to delist before making other non-firm commitments.13
II. The Commission Should Clarify the Scope of its Jurisdiction Over a Generator’s
Wholesale Sales and Transmission.
Constellation agrees with the Commission’s conclusions regarding the scope of its
jurisdiction but there are two statements in the December 18th Order that could be misinterpreted in a manner inconsistent with settled jurisdictional principles. Accordingly, Constellation respectfully requests that the Commission clarify the following two points.
First, in the December 18th Order, the Commission concludes that “states have authority
over their generation resource mix, including through their siting authority” and that, therefore, “which generating facilities are sited and allowed to serve Co-Located Load is also a question of state law.”14 Often, however, a generator will not serve Co-Located Load directly. Rather, the
12 See Elec. Consumers Res. Council v. FERC, 747 F.2d 1511, 1513-14 (D.C. Cir. 1984) (“We defer to the agency’s expertise ... so long as its decision is supported by ‘substantial evidence’ in the record and reached by ‘reasoned decisionmaking,’ including an examination of the relevant data and a reasoned explanation supported by a stated connection between the facts found and the choice made.”) (citing Burlington Truck Lines v. United States, 371 U.S. 156, 168 (1962); Memphis Light, Gas & Water Div. v. FPC, 504 F.2d 225, 230 (D.C. Cir. 1974); 16 U.S.C. § 825l (1982)).13 5 U.S.C. § 706(2)(A) (a court must set aside any Commission order that is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law”); see also Consol. Edison Co. of N.Y., Inc. v. FERC, 45 F.4th 265 (D.C. Cir. 2022) (finding the Commission violated the Administrative Procedure Act for failure to provide a satisfactory explanation for treating projects differently).14 December 18th Order, 193 FERC ¶ 61,217 at P 169 (emphasis added).
PDF page 7
7
generator will first sell electricity at wholesale to an entity, such as a retail supplier, that will then engage in the ultimate retail sale to the Co-Located Load. Such sales for resale are exclusively within the Commission’s jurisdiction, not the states’.15 State jurisdiction is limited to the “ultimate [retail] sale of the energy.”16 The Commission should therefore clarify that state authority does not extend to the wholesale sale of energy by a generator to a retail supplier, even if the retail supplier then resells that energy to a load co-located with the generator. Such jurisdiction lies exclusively with the Commission.
Second, in the December 18th Order, the Commission asserts that “states have exclusive jurisdiction over how to allocate the costs of all Commission-jurisdictional rates (including for energy, capacity, and transmission) among retail customers, including allocating costs among different classes of retail customers.”17 While states generally do have authority over the allocation of the costs of interstate wholesale sales among the wholesaler’s retail customers, that authority is not unlimited. As the Supreme Court has repeatedly stated, “even when States exercise their traditional authority over retail rates,” the “States may not seek to achieve ends, however legitimate, through regulatory means that intrude on FERC’s authority over interstate wholesale rates.”18
15 See 16 U.S.C. § 824(b)(1); see also Orangeburg, S.C. v. FERC, 862 F.3d 1071, 1086-87 (D.C. Cir. 2017) (“FERC— not state commissions—has ‘exclusive authority to regulate the transmission and sale at wholesale of electric energy in interstate commerce.’”) (quoting New England Power Co. v. New Hampshire, 455 U.S. 331, 340 (1982)).
16 New York v. FERC, 535 U.S. 1, 23 (2002) (emphasis removed).17 December 18th Order, 193 FERC ¶ 61,217 at P 167 (emphasis added).18 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164-65 (2016); see also Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 966 (1986) (“Once FERC sets such a rate, a State may not conclude in setting retail rates that the FERC-approved wholesale rates are unreasonable.”).
PDF page 8
8
We therefore respectfully request that the Commission clarify that, consistent with
longstanding Supreme Court precedent,19 states do not have unlimited authority “over how to allocate the costs of all Commission-jurisdictional rates” and that they cannot use their authority over retail allocation to indirectly regulate the interconnection of generators serving Co-Located Load. For instance, a state cannot impose a requirement via the exercise of their jurisdiction over retail sales that attempts to contradict or prohibit a transaction or sale that the Commission has said is permitted. This is not a hypothetical concern. Some utilities have in fact asked their state commission for authority to condition retail service in the state on the load’s acceptance of a Transmission Security Agreement that calculates its security requirement based on a gross NITS rate despite the fact that this Commission has said that other rates must be made available.20 The Commission should make clear that a state may not frustrate the Commission’s policy in this manner, and, moreover, that any such Transmission Security Agreement would be unjust and unreasonable as a matter of federal law.
CONCLUSION
For the foregoing reasons, the Commission should clarify the December 18th Order or, in the alternative, grant rehearing.
19 See, e.g., Hughes, 578 U.S. at 164-65; Thornburg, 476 U.S. at 966.20 See Commonwealth Edison Co., Constellation Energy Generation, LLC Motion to Reopen the Evidentiary Record for Supplemental Discovery, Testimony, and Briefing, Illinois Commerce Comm’n Docket No. 25-0677, at 1-2 (filed Dec. 23, 2025), https://www.icc.illinois.gov/docket/P2025-0677/documents/374492/files/656364.pdf (“ComEd’s proposed changes to its General Terms and Conditions referencing a requirement to enter into a Transmission Security Agreement (‘TSA’), and the TSA general terms and conditions shared by ComEd in this proceeding, assume that all customers will take Network Integration Transmission Service (‘NITS’) billed based on gross billing determinants, and that service will begin when network upgrades are constructed…. ComEd’s assumptions regarding transmission service applicable to LDPACs are no longer valid under the recent FERC order.”).
PDF page 9
9
Respectfully submitted,
/s/ Paul F. Wight
January 20, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Jacob I. Chefitz
DLA Piper LLP (US)
1251 Avenue of the Americas
New York, NY 10020
212-335-4500
jacob.chefitz@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 10
CERTIFICATE OF SERVICE
I hereby certify that I have on this 20th day of January, 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025).
/s/ Sophia Browning
Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
Suite 1100
San Diego, California 92121
858-677-1455
sophia.browning@us.dlapiper.com