EL25-49-002 · 2026-01-20 · Constellation Energy Generation, LLC

Constellation Energy Generation, LLC submits Request for Clarification or, in the Alternative, Rehearing of the 12/18/2025 Order

Text extracted from the eLibrary original (SHA-256 b140828cda1ad3e0…). Download the original from the official source.

Contents · 3 sections
  1. I. The Commission Should Clarify that Capacity Resources are Not Required to Delist p. 3
  2. II. The Commission Should Clarify the Scope of its Jurisdiction Over a Generator’s p. 6
  3. CONCLUSION p. 8

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Filing procedure · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

EL25-20-000 (Consolidated) REQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING OF CONSTELLATION ENERGY GENERATION, LLC Constellation Energy Generation, LLC (“Constellation”) requests clarification, or in the alternative, rehearing, of the order issued by the Commission on December 18, 2025,…
Read this passage Filed comments: Filing procedure

I. The Commission Should Clarify that Capacity Resources are Not Required to Delist

printed heading · Topic match: Connecting load and generation

The Order states, “[i]n accordance with the existing rules for removing Capacity Resource status, … an existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its [capacity interconnection rights] for the portion of the generating facility…
Read this passage Filed comments: Connecting load and generation

II. The Commission Should Clarify the Scope of its Jurisdiction Over a Generator’s

printed heading · Topic match: Connecting load and generation

Some utilities have in fact asked their state commission for authority to condition retail service in the state on the load’s acceptance of a Transmission Security Agreement that calculates its security requirement based on a gross NITS rate despite the fact that this Commission has said that other…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Filing procedure

Vice President & Deputy General Counsel Seth Lucia Assistant General Counsel Constellation Energy Generation, LLC 250 Massachusetts Ave.