EL25-49-000 · 2026-02-02 · Constellation Energy Generation, LLC
Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to the rehearing request filed by the Indicated PJM Transmission…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-002
AD24-11-000
AD24-11-001
EL25-20-000
EL25-20-001
(Consolidated)
MOTION FOR LEAVE AND ANSWER OF
CONSTELLATION ENERGY GENERATION, LLC
Constellation moves for leave and submits this answer1 in response to the rehearing request filed by the Indicated PJM Transmission Owners2 in the above-captioned dockets. Remarkably, in a proceeding with over 135 parties3 and a record spanning multiple dockets and thousands of pages, there were only two requests for rehearing of the Commission’s December 18, 2025 Order.4 Of these, only the Indicated TOs—now reduced from sixteen parties to two, Exelon and
1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213.2 Request for Rehearing of the Indicated PJM Transmission Owners (Jan. 16, 2026) (“Rehearing Request”). The Indicated PJM Transmission Owners (“Indicated TOs”) include Exelon and FirstEnergy and their subsidiaries.3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at App. A (2025) (“December 18th Order”).4 See Request for Clarification or, in the Alternative, Rehearing of the Industrial Customer Coalitions (Jan. 20, 2026).
PDF page 2
2
FirstEnergy5—argued that the Commission’s findings regarding Co-Located Load6 under section 206 of the Federal Power Act (“FPA”) were arbitrary and capricious. Exelon and FirstEnergy’s position remains the same—Co-Located Loads should only be able to take Network Integration Transmission Service (“Network Service” or “NITS”) and pay gross rates. But PJM and nearly every other party, including nearly all other PJM transmission owners, support or do not contest that the Commission met its two-step showing under section 206 of the FPA to change the PJM Tariff.
Constellation respectfully submits there is good cause for the Commission to accept this answer as it elaborates on points in the December 18th Order and is intended to aid the Commission in its decision-making to affirm the December 18th Order and deny Exelon and FirstEnergy’s rehearing request.7
I. The Commission Satisfied the First Step of Section 206 of the FPA by Demonstrating that PJM’s Tariff is Unjust and Unreasonable
A. Record Evidence Shows Transmission Owners Interpret PJM’s Tariff
Differently
Exelon and FirstEnergy seek rehearing of the Commission’s finding that PJM’s Tariff “is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service,”8 arguing that the Commission’s finding
5 Of the sixteen transmission owners joining Indicated PJM Transmission Owners’ March 24 Answer, two remain in support of the Rehearing Request. Compare Indicated PJM Transmission Owners March 24 Answer at 1 n.2 with supra n.2.
6 Unless otherwise defined, all capitalized terms have the same meaning as in the December 18th Order.7 See Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that “clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas Storage Co., 164 FERC ¶ 61,212, at P 2, n.6 (2018) (accepting answers that “assist the Commission in understanding the issues raised[] and will ensure a complete record”). 8 December 18th Order, 193 FERC ¶ 61,217 at PP 2, 159.
PDF page 3
3
“has no citation to evidence.”9 They claim “[t]here is none.”10 They further claim Sections 31 and 32 of PJM’s Tariff “already … explain[] how Network Service works and how loads of Network
Customers will be served.”11
Exelon and FirstEnergy are incorrect. Citing to the record, the December 18th Order states, “[m]any parties to this proceeding filed comments supporting the Commission’s preliminary
finding that PJM’s Tariff lacks sufficient clarity or consistency as to the rules for Co-Location Arrangements.”12 In that proceeding, the Commission stated, “the record of proceedings before the Commission appear to suggest that Transmission Owners are taking different approaches to performing the steps necessary to accommodate a co-location arrangement and in the transmission service that they are requiring entities to take.”13 The Commission acknowledged, “there are
9 Rehearing Request at 14.10 Id.11 Id. at 15.12 December 18th Order, 193 FERC ¶ 61,217 at P 175 n.376 (citing Constellation May 8 Answer at 9 (“In sum, the record in this proceeding unequivocally supports the Commission’s preliminary finding that the PJM Tariff lacks clear co-location rules and is unjust and unreasonable.”); Advanced Energy United April 23 Reply Comments at 19 (“Loads and generators pursuing [C]o-[L]ocation [A]rrangements need clarity as to how these arrangements will be studied, and how those studies will be evaluated. There must be a level of uniformity and detail outlining study requirements to ensure regulatory certainty for large loads and new generation and storage resources seeking to serve large loads. This level of uniformity is currently lacking in PJM’s interconnection procedures and cost allocation methodology ....”); EPSA/P3 April 23 Reply Comments at 2 (“EPSA and P3 agree with the Commission that PJM needs to establish tariff provisions and rules to accommodate the array of [C]o-[L]ocated [L]oad arrangements that will facilitate the timely and effective integration of large loads locating in the region.”); Data Center Coalition April 23 Reply Comments at 7 (“... [T]he Commission should direct PJM to develop clear, enforceable tariff language that affirms the permissibility of multiple co-location configurations, including those where load is served directly from a generation resource located on or near the same site. Tariff clarity is essential to reduce unnecessary disputes, avoid case-by-case confusion, and enable transmission providers to process interconnection and load addition requests efficiently and predictably.”)); see also Invenergy Renewables LLC, et al. April 23 Comments at 4 (“[T]here is little, if any, transparency on how M-3 studies are conducted, or the timeline for completing such studies. Large load interconnection customers are already facing interconnection delays as a result of this uncertainty, and the lack of transparency is creating opportunities for undue discrimination that will decrease competition and raise systemwide costs.”); Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., FERC Docket No. EL25- 20-000 (filed Nov. 22, 2024) at 6 (“Even before the Susquehanna ISA Order, local utilities were taking advantage of the lack of clarity in the Tariff to block or delay competition to serve data centers.”).13 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (2025) (“Order Instituting Show Cause”).
PDF page 4
4
allegations in the record that Exelon has delayed work on Constellation’s requests to co-locate load with its generators … due to Exelon’s concerns that such requests are not allowed under the Tariff” and “[o]n the other hand, as a factual matter, … PPL allowed a generator in its service territory to enter into a co-location arrangement without requiring the co-located load to take Network Integration Transmission Service.”14
The record affirms that PJM’s Tariff is being inconsistently interpreted. Exelon’s own
witness agreed, “what we could really use is … some clarity around the rules of the road, so that … we don’t have non-conforming agreements, and we don’t have language that doesn’t exist in the tariffs. And we’re in a place where … we’re all handling and interconnecting these important loads in the same manner.”15 The testimony of Zach Ming demonstrated that the lack of clarity in PJM’s Tariff has “result[ed] in different interpretations and applications of the tariff by different transmission owners within PJM.”16 Like the Commission, Mr. Ming found that “[s]everal
transmission owners have interpreted the tariff as requiring all loads (co-located or not) to be served under NITS” and “[o]ther transmission owners have interpreted the tariff as allowing co- located configurations.”17 Mr. Ming’s testimony also discussed how even PJM’s interpretation of its Tariff changed over time.1814 Id.15 Transcript of November 1, 2024 Large Loads Co-Located at General Facilities Technical Conference, Docket No. AD24-11-000, at 100-101 (Comments of Dave Weaver, Vice President of Transmission Strategy, Exelon Utilities).16 Constellation April 23 Answer, Exh. 2 at 19:5-6 (Testimony of Zach Ming) (“Ming Testimony”).17 Id. at 19:6-20.18 Id. at 20:3-6 (“Even PJM until recently supported the notion that ‘[c]o-located must either be PJM Network Load (with applicable firm transmission service[)] or not PJM Network Load (load without applicable transmission service[)].’”); see also Constellation April 23 Reply Comments at 13 n.30 (“PJM recently rescinded the Guidance Document despite previously relying on that Guidance Document in developing changes to the ISA for Susquehanna. Similarly, PPL Electric Utilities Corporation (‘PPL’) agreed to the co-located load arrangement for Susquehanna without requiring NITS, but now, as an Indicated Transmission Owner, takes the view that co-located load must be a Network Customer, taking NITS. Even earlier, PJM had issued guidance in the form of a ‘Frequently
PDF page 5
5
“The fact that different transmission owners are interpreting the tariff differently is an obvious indicator of the ambiguity of the existing tariff.”19 As the Order Instituting Show Cause preliminarily found, “this lack of applicable Tariff provisions raises the potential for undue discrimination or preferential treatment.”20 There is ample record evidence of transmission owner monopolistic behavior for the Commission to conclude with finality that undue discrimination has occurred.21 The Commission did not tolerate such monopolistic behavior when it justified imposing open access requirements, and it should not do so here.22
B. Record Evidence Supports that PJM’s Tariff is Unjust and Unreasonable
Because it Does Not Include Flexible Load Transmission Services
Exelon and FirstEnergy argue there is no evidentiary support for the “building-block
assumptions”23 upon which the Commission found “PJM’s Tariff is unjust and unreasonable
because it does not include transmission services that reflect an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit its energy withdrawals from the
Asked Questions’ document on co-location, which also contemplated co-location configurations other than the NITS-only approach now prevailing at some transmission owners’ instigation.”) (citations removed).
19 Ming Testimony at 20:10-12.20 Order Instituting Show Cause, 190 FERC ¶ 61,115 at P 75; see also id. (“We find that these dynamics raise the potential for undue discrimination—albeit, in this example, by the Transmission Owners, not PJM—due to the lack of Tariff provisions governing colocation arrangements.”).21 See, e.g., Constellation April 23 Reply Comments at 14 (“Some of the Indicated Transmission Owners have refused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, and forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) (citing Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Docket No. EL25-20- 000, at 7 (filed Nov. 22, 2024) (citing Protest of Constellation Energy Generation, LLC, Docket No. EL24-149-000, Exh. 2 (correspondence with Exelon) (filed Oct. 30, 2024); Motion to Lodge of Constellation Energy Generation, LLC, Docket No. EL24-149-000, Exh. 1 (November 12, 2024 Exelon Letter) (filed Nov. 18, 2024))).22 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, 31,682 (1996) (cross-referenced at 75 FERC ¶ 61,080 (1996)).23 Rehearing Request at 22.
PDF page 6
6
transmission system under certain conditions.”24 First, Exelon and FirstEnergy state that
arguments stating large loads are “unable to interconnect or are experiencing delays” are “false and any delay is of their own making.”25 The record is replete with evidence “suggesting
otherwise.”26 As stated in the Affidavit of Michael Kormos, the former Chief Operating Officer of PJM, “traditional utility models for connecting large load directly to the grid are proving ineffective at keeping pace with demands of new large loads and are taking five years or longer to connect such load.… [W]ait times for new large load connections in PJM are taking even longer
– as long as seven to ten years.”27 Other record evidence shows the same.28
24 December 18th Order, 193 FERC ¶ 61,217 at PP 2, 159. In support of the Commission’s finding, the Commission stated, “[r]equiring [NITS] could necessitate inefficient and costly transmission buildout and costs paid by transmission customers that may not be necessary if Eligible Customers taking transmission service on behalf of Co-Located Loads are willing to limit their energy withdrawals and take a transmission service that requires fewer Network Upgrades to provide.” Id. P 199. The Commission also stated, “requiring … Eligible Customers to take NITS on behalf of … Co-Located Loads may in some circumstances result in costly and inefficient transmission system buildout that may not be necessary if such Eligible Customers are willing and able to take a transmission service that requires fewer Network Upgrades to provide, and therefore may result in lower Network Upgrade costs, than would NITS.” Id. P 177.
25 Rehearing Request at 6.26 Id. at 18.27 Constellation April 23 Reply Comments, Exh. 5, at ¶ 3 (Affidavit of Michael Kormos).28 See, e.g., Michael Kormos, The Co-Located Load Solution, Docket No. AD24-11-000, at 2 (Nov. 4, 2024) (“The standard utility models are struggling to accommodate large data center projects on a workable timeline, and can take five years or longer.”); Intersect Power, LLC Dec. 9 Comments, Docket No. AD24-11-000, at 2 (“Large loads face backlogs and multi-year delays, similar to those faced by generating resources in standard interconnection processes. Large loads cannot wait years for power supply arrangements, or they risk losing business to their competition, including overseas competition.”) (citing Todd Shatzki, Joseph Cavicchi, Megan Accordino, Co- Located Load: Market, Economic, and Ratemaking Implications, Analysis Group, at 14 (Oct. 28, 2024) (“Co- Located Load”), https://www.analysisgroup.com/globalassets/insights/publishing/2024_co_located_load_market_economic_and_ra temaking_implications.pdf); Co-Located Load at 12 (“Several utilities have reported that the expected wait time for connecting new large loads is as long as 7 to 10 years. AEP Ohio has responded to the influx of requests by suspending acceptance of new load service agreements from data center customers, to give the utility time to study the potential impacts of the proposed additions on its transmission and distribution systems.”); id. at 12 n.43 (“Grant PUD estimates a wait time of 7-10 years. Dominion Energy expects the time it takes to connect large data centers to the electric grid to increase by one to three years amid a surge in requests, bringing the total wait time to as long as seven years…. AEP Ohio has stated that, because Central Ohio lacks RTO-controlled generation, serving new data center load will require investment in extra high voltage transmission to import power from other parts of the grid. That investment, AEP says, could take 7-10 years to plan, design, site, and construct.”); see also Joint Electricity Customer Alliance Oct. 30 Comments, Docket No. AD24-11-000, at 1 (“When properly executed, co-location aims
PDF page 7
7
Second, Exelon and FirstEnergy argue there is “no evidence” for finding “Co-Located
Loads may be able to receive transmission service faster with use of a new, limited transmission service product than they would if they selected NITS, to the extent that providing NITS would require Network Upgrades that the limited transmission service would not.”29 Again, record evidence contradicts Exelon and FirstEnergy’s claim. In his testimony, Mr. Ming states, “[m]aking interruptible service available on an interim basis provides the important benefit of facilitating faster interconnection for loads …. This is because transmission reinforcements and network upgrades required for a generator-contingent or firm configuration can take many years to plan and build.”30 Other evidence states similarly.31
to reduce overall costs, not shift them. It is a rational response given the slow pace of transmission and generation development across the grid, driven by interconnection delays, for both load and generation, and poor regional transmission planning.”); Mainspring Energy, Inc. April 23 Comments, at Attachment at 2 (“New load interconnection also faces significant delays. Some data center customers report that they’re being given 3-5 year estimates for grid delivery of data center power. For a 100 MW data center, assuming US$150,000/MW of revenue per month (~US$150/month/kW), three years of delay translates to over US$500M in lost revenue.”); Dr. Paul Stockton, et al. April 22 Letter from National Security Experts, at 1 (“In some states, including those in the Eastern US served by PJM Interconnection, L.L.C., data centers seeking to connect and take service from the grid may face delays of seven to ten years before they can receive power. Those delays are unconscionable, given the DOD’s rapidly growing requirements for AI services and the imperative to counter China’s drive for AI primacy.”); Constellation April 23 Reply Comments, Exh. 1 at 9 n.38 (Declaration of Dr. Paul Stockton) (“AI, data center electricity demand could drive advanced nuclear investment: NERC head Jim Robb,” Utility Dive (June 6, 2024) (“it takes me about four years to build a substation,” according to David Schleicher, Northern Virginia Electric Cooperative
CEO),
https://www.utilitydive.com/news/ai-datacenter-electricity-demand-advanced-nuclear-
investment-Robb/718181/; “Elk Grove Mayor Meets With ComEd on Substations for Data Centers,” Journal & Topics (Mar. 14, 2024) (Mayor of Elk Grove, Illinois, “expressed frustration with ComEd, saying the electricity utility was ‘dragging their feet’ in building substations to support the growing data center industry”), https://www.journal-topics.com/articles/elk-grove-mayor-meets-with-comed-on-substations-for-data-centers/); Statement of Cole Muller, Executive Vice President of Strategic Ventures Talen Energy Corporation, Docket No. AD24-11, at 2 (Oct. 16, 2024) (“Co-locating data center load with generation allows the load to be served efficiently and economically. The alternative in many cases is years-long delays to connect in front of the meter, i.e., directly to the grid.”).
29 Rehearing Request at 20 (quoting December 18th Order, 193 FERC ¶ 61,217 at P 205).30 Ming Testimony at 49:6-10; id. at 22:14-16 (“[U]nnecessary and inefficient costs may slow down–or even discourage–the interconnection of new beneficial load, which would hinder the interests of the United States.”).31 See Enchanted Rock April 23 Reply Comments at 5 (“Enabling a temporary flexibility option that large loads can opt into would therefore mitigate some of these risks and allow for faster load interconnection.”); id. at 9 (“The LCDG option provides more than a traditional demand response or peak shaving program during the operating period. The flexibility provided by the LCDG option would be considered in the planning and study process for
PDF page 8
8
Third, Exelon and FirstEnergy argue “there is no evidence that the cost of paying for
Network Service deters service or has any impact whatsoever on development of data centers.”32 The Commission did not find that the cost for Network Service deters data centers. The
Commission found that “[i]t would be inconsistent with cost causation principles” to charge Co- Located Loads the same as Network Load, and that “Co-Located Loads should be allowed to
choose the transmission service that aligns with their use of the transmission system and therefore aligns the charges for service with the benefits received.”33 This too is supported by record evidence. “Charging customers that impose different costs on the system in an equivalent manner is misaligned with the principle of fair apportionment of costs and is inequitable.”34
C. The Commission’s Precedent Prohibiting “Split Load” for Network Service Is
Inapplicable
Exelon and FirstEnergy argue that the Commission’s Contract Demand services depart
from its precedent on “split load” without explanation.35 This argument misses the mark. The
large load interconnection, local and regional planning, and resource adequacy. The LCDG option therefore permits large loads to utilize flexibility to achieve faster interconnection through the deployment of dispatchable, co-located generation. Under the LCDG option, the firm commitment to dispatch co-located generation would serve as a bridge to permanent grid upgrades for projects that would otherwise be delayed while new infrastructure is planned, permitted, and constructed.”); id. at 14 (“it may defer the need for certain upgrades for reliable interconnection until such time that infrastructure expansion can occur. Consideration for colocated arrangements in the retail load integration process would also allow for faster load interconnections and mitigates commercial risks for both load and generation developers”); Advanced Energy United April 23 Reply Comments at 16-17 (discussing a co-location arrangement that “co-locates load with dispatchable generation to allow for load flexibility and use of as-available transmission service until necessary transmission upgrades make it possible for the load to fully integrate into the system” and “would allow for faster interconnection for load that brings its own generation and has the ability to be flexible.”) (citation omitted).
32 Rehearing Request at 18.33 December 18th Order, 193 FERC ¶ 61,217 at P 199.34 Ming Testimony at 21:19 to 22:1-2.35 Rehearing Request at 22-30 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 (2020); Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, 78 FERC ¶ 61,220 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888- C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225
PDF page 9
9
Commission has explained, “splitting a discrete load is antithetical to the concept of network service” because “a load at a discrete point of delivery cannot be partially integrated—it is either fully integrated or not integrated.”36 Contract Demand services are not Network Service. Nor do Contract Demand services raise the same cost causation concerns as the split load contemplated in Order No. 888-A.37 “Firm Contract Demand transmission service customers will be charged based on their contract demand irrespective of usage and therefore will not be able to reduce their load- ratio cost responsibility.”38 In addition, “PJM will only plan the transmission system and procure generation capacity for [Firm Contract Demand]—not for load growth, like it does for NITS customers—and PJM will have no obligation to serve … beyond the contract demand.”39 Similarly, PJM has no obligation to plan the transmission system or procure generation for Non- Firm Contract Demand service.40
II. The Commission Satisfied the Second Prong of Section 206 of the FPA by Fixing a Just and Reasonable Replacement Rate
A. The Commission Has the Authority to Establish New Transmission Services
Contrary to Exelon and FirstEnergy’s argument, the Commission’s order did not exceed its jurisdiction. As the Commission correctly observed, the FPA provides the Commission with
F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002); Fla. Power & Light, 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, 264 F. App’x 4 (D.C. Cir. 2008); Idaho Power Co., 106 FERC ¶ 61,329 (2004); Ameren Servs. Co. v. Prairieland Energy Inc., 131 FERC ¶ 61,125 (2010); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015)).
36 December 18th Order, 193 FERC ¶ 61,217 at P 196 (quoting Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 at 30,262) (emphasis added). 37 Id. P 211.38 Id.39 Id.40 Id. P 218.
PDF page 10
10
jurisdiction over “the transmission of electric energy in interstate commerce.”41 The FPA does not limit the Commission’s “transmission jurisdiction to the wholesale market”42; to the contrary, “the FPA authorizes FERC’s jurisdiction over interstate transmissions, without regard to whether the transmissions are sold to a reseller or directly to a consumer.”43 The Commission therefore correctly concluded that it “has exclusive jurisdiction over the provision of transmission service used by an Eligible Customer to serve Co-Located Load” when the transmission is in interstate commerce.44 And because the Commission has jurisdiction over the provision of such transmission service, it has the authority to regulate the type of transmission service taken by “an Eligible Customer taking transmission service on behalf of a Co-Located Load,” whether that service is Network Service (to which Exelon and FirstEnergy do not object) or Contract Demand services. In nonetheless asserting that the Commission has exceeded its jurisdiction, Exelon and FirstEnergy make two arguments, neither of which has merit. First, they argue that the Commission’s replacement rate violates the major questions doctrine.45 But the major questions doctrine has no role to play here. It is reserved for “extraordinary cases” where an agency leverages a statute’s “modest words,” “vague terms,” or “subtle devices” to give itself “sweeping and consequential authority.”46 That is not the case here. The FPA clearly and “unambiguously”47 gives the Commission broad authority over “the transmission of electric energy in interstate
41 16 U.S.C. § 824(b)(1); see also December 18th Order, 193 FERC ¶ 61,217 at P 166. 42 New York v. FERC, 535 U.S. 1, 17 (2002).43 Id. at 20.44 December 18th Order, 193 FERC ¶ 61,217 at P 173; see also New York, 535 U.S. 1, 16 (“[W]e agree with FERC that transmissions on the interconnected national grids constitute transmissions in interstate commerce.”).45 Rehearing Request at 12, 52-53.46 West Virginia v. EPA, 597 U.S. 697, 721, 723 (2022) (quotations omitted and alteration removed).47 New York, 535 U.S. 1, 19.
PDF page 11
11
commerce,”48 and the Commission is entitled to regulate such transmission consistent with its statutory authority, just as it did in promulgating Order No. 88849 and just as it did here. Second, Exelon and FirstEnergy argue that the Firm and Non-Firm Contract Demand
services provided in the Commission’s replacement rate “interfere with States’ regulation of the terms of sale at retail,” thereby indirectly intruding on the States’ authority. But whether the Commission’s replacement rate has “natural consequences at the retail level”50 does not change the fact that the Commission is acting here pursuant to its express jurisdiction over the transmission of electricity in interstate commerce. As the Supreme Court has explained, “[w]hen FERC regulates what takes place on the wholesale market, as part of carrying out its charge to improve how that market runs, then no matter the effect on retail rates, §824(b)[’s limitation on FERC’s retail sale jurisdiction] imposes no bar.”51 That is no less true of the Commission’s transmission jurisdiction, and ensuring that transmission rates remain just and reasonable—as the Commission did here by allowing for Contract Demand services—“falls within the sweet spot of FERC’s statutory charge.”52
Indeed, Exelon and FirstEnergy have it exactly backward. To conclude that the States’ authority over retail sales prohibits the Commission from regulating interstate transmission rates— as Exelon and FirstEnergy urge—would upend the FPA’s balance of federal and State jurisdiction.
48 16 U.S.C. § 824(b)(1).
49 See New York, 535 U.S. 1, 23 (2002).
50 FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 281 (2016); see also id. (“When FERC sets a wholesale rate, when it changes wholesale market rules, when it allocates electricity as between wholesale purchasers—in short, when it takes virtually any action respecting wholesale transactions—it has some effect, in either the short or the long term, on retail rates. That is of no legal consequence.”)51 Id. at 281-82 (emphasis added); see also id. at 281 (“[A] FERC regulation does not run afoul of §824(b)’s proscription just because it affects – even substantially – the quantity or terms of retail sales.”).52 Id. at 287.
PDF page 12
12
In fact, “even when States exercise their traditional authority over retail rates,” the “States may not seek to achieve ends, however legitimate, through regulatory means that intrude on FERC’s authority over interstate wholesale rates.”53 The Commission should reject any argument that the States’ jurisdiction over retail sales limits the Commission’s jurisdiction to allow for non-Network Service in Co-Located Load arrangements and thereby regulate the interstate transmission of electricity.
B. The Replacement Rate is Not Unduly Discriminatory or Preferential
Exelon and FirstEnergy argue that Interim Service and Contract Demand services “would
grant an undue preferential rate for co-located loads.”54 This argument is unavailing. Courts have long held that, “undue discrimination occurs only if the entities are ‘similarly situated,’ such that ‘there is no reason for the difference.’”55 The courts have also given the Commission “‘wide discretion … to determine what constitute[s]’ undue discrimination.”56
Co-located loads that are subject to express limitations on their right to service are not similarly situated to traditional network load that relies on NITS. The December 18th Order
53 Hughes v. Talen Energy Mktg., LLC, 578 U.S. 150, 164-65 (2016); see also Nantahala Power & Light Co. v. Thornburg, 476 U.S. 953, 966 (1986) (“Once FERC sets such a rate, a State may not conclude in setting retail rates that the FERC-approved wholesale rates are unreasonable.”).54 Rehearing Request at 34; see also id. at 3 (“The Commission’s replacement rate that imposes new CD Service and Interim Service options could … grant an undue preference to certain categories of customers.”); id. at 36 (“The Commission, by requiring the new forms of service discussed above, would establish rates that grant an undue preference or advantage to co-located loads.”); id. at 38 (“the new service grants an undue preference for co-located loads.”); id. at 52 (“[T]he replacement rate directed by FERC—because it favors a narrow category of customers (i.e., co-located load) without reasoned explanation—violates the requirement in the FPA that no rate by a public utility grants an undue preference or advantage or unreasonable difference in rates.”). 55 Mo. River Energy Servs. v. FERC, 918 F.3d 954, 958 (D.C. Cir. 2019) (quoting State Corp. Comm’n v. FERC, 876 F.3d 332, 335 (D.C. Cir. 2017); Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667, 721 (D.C. Cir. 2000)).56 Mo. River Energy Servs., 918 F.3d at 958 (quoting Transmission Access Policy Study Grp. v. FERC, 225 F.3d at 721).
PDF page 13
13
explains co-location arrangements will have a “reduced impact on the transmission system … as compared to traditional Network Load.”57 In addition, the December 18th Order states co-located load arrangements will “not require PJM to plan the transmission system to serve these Co-Located Loads to the same extent as PJM must plan the transmission system to serve Network Load,
possibly reducing the need for new Network Upgrades.”58 These findings are neither “fiction” nor “false presumption[s].”59 Indeed, as Mr. Ming stated, “[n]one of the configurations of co-located load … impose the same costs on the transmission system as a NITS customer that is directly connected to the transmission system.”60
C. The Replacement Rate Promotes Competition
Exelon and FirstEnergy argue the new transmission services are “an illegal effort to stifle competition” that “flout” the Commission’s open-access policies.61 This argument should be rejected. The new transmission services “promote competition”62 by allowing Co-Located Loads
57 December 18th Order, 193 FERC ¶ 61,217 at P 205 (citing PJM March 24 Response at 13-15, 18-19; Glatz and Silverman April 23 Reply Comments at 12-13; Constellation April 23 Reply Comments at 65; Vistra April 23 Reply Comments at 28) (emphasis added). See also SEIA April 23 Reply Comments at 8 (citing Duke University’s Nicholas Institute for Energy, Environment & Sustainability, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems (“Duke Study”) https://nicholasinstitute.duke.edu/sites/default/files/publications/rethinking-load-growth.pdf (2025) (“Co-located loads with the ability to curtail or shift demand in coordination with generator output or grid constraints should be treated differently than firm grid-dependent load, as these loads would be capable of reducing their demand on the grid.”)).58 December 18th Order, 193 FERC ¶ 61,217 at P 205 (citing Enchanted Rock April 23 Reply Comments at 17) (emphasis added); see also id. P 211 (“PJM will only plan the transmission system and procure generation capacity for the contract demand—not for load growth, like it does for NITS customers”); Kormos, The Co-Located Load Solution, at 8 (“By placing a data center where it can be directly served by a generator versus locating the load somewhere remote from the ultimate generation needed to serve it, the grid requires fewer upgrades to serve that new demand.”). 59 Rehearing Request at 4.60 Ming Testimony at 21:17-20.61 Rehearing Request at 40.62 FERC, Fact Sheet: FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers (Dec. 18, 2025), https://www.ferc.gov/news-events/news/fact-sheet-ferc-directs-nations-largest-
PDF page 14
14
to take transmission services other than Network Service.63 With more options available, Co- Located Load is no longer “beholden to taking Network or Point-to-Point firm transmission service on the TO’s terms (and at their pace), or fully isolated and completely disconnected Behind-the- Meter subject to state jurisdiction.”64 Likewise, load seeking to co-locate with a generator is also no longer forced by transmission owners to procure additional services not required by the Tariff.65
D. The Replacement Rate Addresses Reliability
The Commission should reject Exelon and FirstEnergy’s argument that the replacement
rate is not just and reasonable because the Commission “disregard[ed]” reliability considerations.66 A review of the December 18th Order shows otherwise.67 The Commission explained the new
Interim Service “will facilitate the timely provision of transmission service to Eligible Customers taking transmission service on behalf of Co-Located Loads, while preserving reliability for other
grid-operator-create-new-rules-embrace?new= (“As technology leaps forward, clear and fair regulations must keep pace to support advancement, help prevent price volatility, and promote competition, ultimately benefitting consumers by keeping electricity costs manageable.”).
63 December 18th Order, 193 FERC ¶ 61,217 at P 195 (“While we find that NITS charged on a gross demand basis is one just and reasonable transmission service option for Eligible Customers taking transmission service on behalf of Co-Located Loads, it is not the only option. This order establishes new transmission service options that Eligible Customers taking transmission service on behalf of Co-Located Loads may use if they do not wish to take NITS on a gross demand basis.”); see also Transcript of December 18, 2025 Open Meeting at 25, https://www.ferc.gov/media/transcript-december-18-2025-open-meeting (Commissioner See stating, “Today’s order chooses an options-based approach over a one-size-fits-all solution.”).64 EPSA/P3 April 23 Reply Comments at 12.65 See supra note 21.66 Rehearing Request at 49.67 See, e.g., December 18th Order, 193 FERC ¶ 61,217 at P 227 (“PJM’s necessary study process, as reflected in the record, assesses any special protection scheme that is a part of a Co-Location Arrangement.”); id. P 212 (“PJM will determine the technical and engineering requirements of special protection schemes to help address reliability risks associated with unreserved use of the transmission system.”); id. P 227 (discussing measures that will “provide additional clarity and transparency regarding the steps that PJM and Interconnection Customers are taking to maintain transmission system reliability before an existing generating facility can serve Co-Located Load.”).
PDF page 15
15
transmission customers.”68 PJM similarly described this option as “providing an opportunity for large load to integrate as a non-capacity backed load … if willing to curtail to support reliability in advance of emergency conditions” and as a preferred option as PJM “maintains resource adequacy.”69
The Commission should also reject Exelon and FirstEnergy’s arguments that the
December 18th Order does not address “risks associated with protective system failures or removal” raised in the record and does not provide “guideposts” on Interim Service.70 These arguments are at best premature. The Commission appropriately requested briefing on interconnection requirements and operational practices necessary for special protection schemes and procedures for PJM to curtail Interim Service.71 In addition, as cited by the December 18th Order, the testimony of Steven Herling, PJM’s former Vice President of Planning, addresses the risks associated with protective system failures or removal.72 Based on his over 30-year experience at PJM, Mr. Herling explained, “protection schemes are regularly employed on the PJM transmission system, and the successful operation of such protective systems is a common observance within PJM.”73 “The protection system … is fully redundant and, while it cannot be guaranteed to never fail, it is unreasonable to treat the failure of both primary and secondary relay
68 Id. P 205, n.436 (“Proper special protection scheme design is also subject to NERC standards to ensure they do not introduce unintentional or unacceptable reliability risks to the system.”) (citing Remedial Action Schemes Reliability Standard, Order No. 837, 160 FERC ¶ 61,071 (2017) (approving Reliability Standard PRC-012-2)) (emphasis added).69 PJM March 24 Answer at 18 (capitalization removed).70 Rehearing Request at 49-50.71 December 18th Order, 193 FERC ¶ 61,217 at P 219.72 Id. P 205, n.436. See also Vistra Corp. May 8 Answer, at Att. A ¶ 21 (Herling testifying that “It is also important to note that the voltage-sensitivity issue underlying the 1,500 MW load loss event cited by NERC is not a co-location issue. Nothing in the NERC Comments or the attached materials suggests that any of the data centers involved in the event were co-located with generating resources.”).73 Constellation April 23 Reply Comments, Exh. 3 at ¶ 23 (Affidavit of Steven Herling).
PDF page 16
16
system facilities following the loss of a generator as anything other than a third contingency.”74 “PJM does not plan for or require upgrades for such third contingencies, nor would it be reasonable to do so, short of events that would result in a cascading outage of grid facilities.”75 CONCLUSION
Constellation submits that good cause exists to accept this answer because it should assist the Commission as it determines whether to deny Exelon and FirstEnergy’s request for rehearing. The Commission should deny the Rehearing Request and affirm its December 18th Order.
74 Id.75 Id.
PDF page 17
17
Respectfully submitted,
/s/ Paul F. Wight
February 2, 2026
Carrie Hill Allen
Sr. Vice President & Deputy General Counsel Seth Lucia
Assistant General Counsel
Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
carrie.allen@constellation.com
seth.lucia@constellation.com
Christopher A. Wilson
Managing Director, Federal Regulatory Affairs Constellation Energy Generation, LLC 250 Massachusetts Ave. NW, Suite 760 Washington, D.C. 20001
202-347-7500
FERCe-filings1@constellation.com
Paul F. Wight
Carolyn E. Clarkin
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
703-773-4058
paul.wight@us.dlapiper.com
carolyn.clarkin@us.dlapiper.com
Sophia Browning
DLA Piper LLP (US)
4365 Executive Drive
San Diego, CA 92121
858-677-1455
sophia.browning@us.dlapiper.com
Jacob I. Chefitz
DLA Piper LLP (US)
1251 Avenue of the Americas
New York, NY 10020
212-335-4500
jacob.chefitz@us.dlapiper.com
Counsel for Constellation Energy
Generation, LLC
PDF page 18
18
CERTIFICATE OF SERVICE
I hereby certify that I have on this 2nd day of February 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010.
/s/ Semhal Gebrekirstos
Semhal Gebrekirstos
DLA Piper LLP (US)
500 Eighth Street NW
Washington, D.C. 20004
202-799-4471
semhal.gebrekirstos@us.dlapiper.com