EL25-49-000 · 2026-02-02 · Constellation Energy Generation, LLC

Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to the rehearing request filed by the Indicated PJM Transmission…

Text extracted from the eLibrary original (SHA-256 512705ae2b37f07c…). Download the original from the official source.

Contents · 10 sections
  1. I. The Commission Satisfied the First Step of Section 206 of the FPA by Demonstrating p. 2
  2. A. Record Evidence Shows Transmission Owners Interpret PJM’s Tariff p. 2
  3. B. Record Evidence Supports that PJM’s Tariff is Unjust and Unreasonable p. 5
  4. C. The Commission’s Precedent Prohibiting “Split Load” for Network Service Is p. 8
  5. II. The Commission Satisfied the Second Prong of Section 206 of the FPA by Fixing a Just p. 9
  6. A. The Commission Has the Authority to Establish New Transmission Services p. 9
  7. B. The Replacement Rate is Not Unduly Discriminatory or Preferential p. 12
  8. C. The Replacement Rate Promotes Competition p. 13
  9. D. The Replacement Rate Addresses Reliability p. 14
  10. CONCLUSION p. 16

Read topic-matched comments in EL25-49

Topics in the text: Filing procedure · Connecting load and generation · Cost allocation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

Remarkably, in a proceeding with over 135 parties3 and a record spanning multiple dockets and thousands of pages, there were only two requests for rehearing of the Commission’s December 18, 2025 Order.4 Of these, only the Indicated TOs—now reduced from sixteen parties to two, Exelon and 1…
Read this passage Filed comments: Filing procedure

I. The Commission Satisfied the First Step of Section 206 of the FPA by Demonstrating

printed heading

The Commission Satisfied the First Step of Section 206 of the FPA by Demonstrating that PJM’s Tariff is Unjust and Unreasonable
Read this passage

A. Record Evidence Shows Transmission Owners Interpret PJM’s Tariff

printed heading · Topic match: Filing procedure

Similarly, PPL Electric Utilities Corporation (‘PPL’) agreed to the co-located load arrangement for Susquehanna without requiring NITS, but now, as an Indicated Transmission Owner, takes the view that co-located load must be a Network Customer, taking NITS.
Read this passage Filed comments: Filing procedure

B. Record Evidence Supports that PJM’s Tariff is Unjust and Unreasonable

printed heading · Topic match: Connecting load and generation

Record Evidence Supports that PJM’s Tariff is Unjust and Unreasonable Because it Does Not Include Flexible Load Transmission Services Exelon and FirstEnergy argue there is no evidentiary support for the “building-block assumptions”23 upon which the Commission found “PJM’s Tariff is unjust and…
Read this passage Filed comments: Connecting load and generation

C. The Commission’s Precedent Prohibiting “Split Load” for Network Service Is

printed heading · Topic match: Filing procedure

The large load interconnection, local and regional planning, and resource adequacy.
Read this passage Filed comments: Filing procedure

II. The Commission Satisfied the Second Prong of Section 206 of the FPA by Fixing a Just

printed heading

The Commission Satisfied the Second Prong of Section 206 of the FPA by Fixing a Just and Reasonable Replacement Rate
Read this passage

A. The Commission Has the Authority to Establish New Transmission Services

printed heading · Topic match: Connecting load and generation

Power & Light, 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, 264 F.
Read this passage Filed comments: Connecting load and generation

B. The Replacement Rate is Not Unduly Discriminatory or Preferential

printed heading · Topic match: Connecting load and generation

FERC, 225 F.3d at 721). 13 explains co-location arrangements will have a “reduced impact on the transmission system … as compared to traditional Network Load.”57 In addition, the December 18th Order states co-located load arrangements will “not require PJM to plan the transmission system to serve…
Read this passage Filed comments: Connecting load and generation

C. The Replacement Rate Promotes Competition

printed heading · Topic match: Filing procedure

The Replacement Rate Promotes Competition Exelon and FirstEnergy argue the new transmission services are “an illegal effort to stifle competition” that “flout” the Commission’s open-access policies.61 This argument should be rejected.
Read this passage Filed comments: Filing procedure

D. The Replacement Rate Addresses Reliability

printed heading · Topic match: Filing procedure

P 205, n.436 (“Proper special protection scheme design is also subject to NERC standards to ensure they do not introduce unintentional or unacceptable reliability risks to the system.”) (citing Remedial Action Schemes Reliability Standard, Order No. 837, 160 FERC ¶ 61,071 (2017) (approving…
Read this passage Filed comments: Filing procedure

CONCLUSION

printed heading · Topic match: Filing procedure

CONCLUSION Constellation submits that good cause exists to accept this answer because it should assist the Commission as it determines whether to deny Exelon and FirstEnergy’s request for rehearing.
Read this passage Filed comments: Filing procedure

CERTIFICATE OF SERVICE

printed heading

CERTIFICATE OF SERVICE I hereby certify that I have on this 2nd day of February 2026, caused to be served a copy of the foregoing upon all parties on the service lists in these proceedings in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18…