EL25-49-000 · 2026-02-12 · Exelon Corporation, The FirstEnergy Transmission Companies
Answer of Exelon Corporation et al. in Opposition to Constellation Energy Generation LLC's 02/02/2026 Motion and Answer to the 01/16/2026 Rehearing Request
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket Nos. EL25-49-000
EL25-49-002
Large Loads Co-Located at Generating
Facilities
)
AD24-11-000
AD24-11-001
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
)
)
)
EL25-20-000
EL25-20-001
(consolidated)
THE INDICATED PJM TRANSMISSION OWNERS’ ANSWER IN OPPOSITION TO
CONSTELLATION’S MOTION
The Indicated PJM Interconnection, L.L.C. (“PJM”) Transmission Owners (“Indicated TOs”)1 file this answer under 18 C.F.R. § 385.2132 in response to Constellation Energy Generation, LLC’s (“Constellation”) February 2, 2026 motion for leave to answer and answer (“Constellation’s Answer” or “Answer”). Constellation filed its motion and answer in response to the Indicated TOs’ January 16, 2026 rehearing request. The Federal Energy Regulatory Commission’s (“FERC”) regulations are clear: “The Commission will not permit answers to
1 This filing was prepared on behalf of the following PJM Transmission Owners: Exelon Corporation (“Exelon”), on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; and FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”). 2 18 C.F.R. § 385.213(a)(3) (permitting an answer to any other pleading if not otherwise prohibited under the regulations).
PDF page 2
2
requests for rehearing.”3 Thus, Constellation’s Answer is barred under the Commission’s own regulations, its motion should be denied, and its Answer should be rejected.4
Significantly, Constellation has not demonstrated good cause to accept its impermissible Answer. If Constellation thought that the Commission’s 206 Order5 needed “elaborat[ion],”6 it could have, and should have, raised that point in its request for clarification or rehearing.7 It did not.
For example, Constellation’s Answer provides no new information and points to no record evidence that contradicts the Indicated TOs’ request for rehearing. Nothing in the 206 Order or in the uncorroborated/uncross-examined “record” assertions demonstrate that just and reasonable service to co-located load is not available under Network Integration Transmission Service (“Network Service”). The co-location arrangement of Talen Energy and its subsidiary
3
Id. § 385.713(d)(1); see id. § 385.213(a)(2) (“An answer may not be made to . . . a request for rehearing[] unless otherwise ordered by the decisional authority.”).
4
See, e.g., PJM Interconnection, L.L.C., 193 FERC ¶ 61,229, at P 13 (2025) (rejecting an answer filed to a rehearing request because “[t]he Commission’s Rules of Practice and Procedure prohibit answers to a request for rehearing”) (citation omitted); Consumers Energy Co. v. Midcontinent Indep. Sys. Operator, Inc., 193 FERC ¶ 61,228, at P 20 (2025) (stating that “Rule 713(d)(1) of the Commission’s Rules of Practice and Procedure prohibits an answer to a request for rehearing” and therefore rejecting the answer filed to the rehearing request) (citation omitted); Sw. Power Pool, Inc., 193 FERC ¶ 61,198, at P 43 (2025) (same); Appalachian Power Co., 193 FERC ¶ 61,091, at P 8 (2025) (same); AEP Oklahoma Transmission Co., Inc., 193 FERC ¶ 61,092, at P 8 (2025) (same); Colonial Pipeline Co., 192 FERC ¶ 61,239, at P 12 (2025) (same); PJM Interconnection, L.L.C., 192 FERC ¶ 61,233, at P 9 (2025) (same); H.A. Wagner LLC, 192 FERC ¶ 61,189, at P 23 (2025) (same); see also, e.g., Midship Pipeline Co., LLC, 192 FERC ¶ 61,172, at P 12 (2025); QT Fuels Inc. v. Colonial Pipeline Co., 192 FERC ¶ 61,139, at P 18 (2025); E. Tennessee Nat. Gas, LLC, 192 FERC ¶ 61,153, at P 13 (2025); PJM Interconnection, L.L.C., 192 FERC ¶ 61,135, at P 16 (2025); Transcon. Gas Pipe Line Co., LLC, 192 FERC ¶ 61,134, at P 24 (2025); BlackRock, Inc., 192 FERC ¶ 61,125, at P 19 (2025); PJM Interconnection, L.L.C., 191 FERC ¶ 61,221, at P 8 (2025).
5
PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“206 Order”).
6
Constellation’s Answer at 2. Constellation’s Answer states that “there is good cause for the Commission to accept this answer as it elaborates on points in the [206 Order] and is intended to aid the Commission in its decision-making to affirm the [206 Order] . . . .” Id.
7
Constellation filed a request for clarification, or in the alternative, a request for rehearing on January 20, 2026.
PDF page 3
3
Susquehanna Nuclear, LLC has moved forward under Network Service.8 Likewise, suggestions that Exelon delayed work on Constellation’s requests to interconnect have been demonstrated to be false.9 The problem causing delays was Constellation’s attempts to circumvent Network Service to obtain subsidized rates.10 To the extent that Constellation makes blanket claims of large loads having project delays,11 that is not due to the type of transmission services offered. Nor is it due to any actions on the part of the Indicated TOs.
In its Answer, Constellation also attempts to stretch the testimony of Exelon’s witness, David Weaver, to suggest his testimony provides record evidence that PJM’s open access transmission tariff (“PJM Tariff”) has been interpreted inconsistently.12 It does not. Mr. Weaver stated the following during FERC’s technical conference: “[W]hat we could really use is . . . some clarity around the rules of the road, so that . . . we don’t have non-conforming agreements, and we don’t have language that doesn’t exist in the tariffs.”13 Mr. Weaver’s desire for “clarity” was not a statement that the PJM Tariff or Network Service were inadequate; it was a concern that customers were trying to avoid following the PJM Tariff, and avoid paying for Network Service, and that those attempts at evasion and bypass led to vague requests that violated tariff procedures and were thus causing problems. In fact, the Commission rejected the non-conforming Susquehanna Nuclear, LLC interconnection service agreement on the same day Mr. Weaver
8 See Indicated TOs’ Rehearing Request at 17-18.9 See id. at 15-17.10 See id.11 See Constellation’s Answer at 6-7 & n.28.12 See id. at 4.13 Transcript, Large Loads Co-Located at General Facilities Technical Conference, Docket No. AD24-11-000, at 100 (Nov. 1, 2024).
PDF page 4
4
provided his testimony.14 Constellation has cited no example, i.e., not a single instance, where transmission service was unable to be obtained.
Constellation’s Answer is merely a continuation of its debate with the Indicated TOs; it is not worthy of acceptance by the Commission. It begins with two pages dedicated to parsing the number of parties in the Indicated TOs’ coalition. Constellation claims the Indicated TOs are incorrect in arguing that reliability concerns were ignored,15 but points to no record evidence undermining the Indicated TOs’ position. Indeed, where Constellation says these arguments are “premature,”16 it underscores the Indicated TOs’ argument that the Commission has not yet engaged in the analysis. Constellation claims that the Commission precedent regarding “split load,” which the Indicated TOs rely upon, is inapplicable.17 It is not. The cases cited by the Indicated TOs were exactly on point,18 and Constellation’s continued need to debate the issue in its Answer does not serve the Commission’s decision-making process.
Ultimately, there is no good cause for the Commission to disregard its own regulations by granting Constellation’s request. Nothing submitted in Constellation’s Answer undercuts any of the arguments presented in the Indicated TOs’ rehearing request and Constellation had several opportunities throughout the course of this proceeding to raise its arguments in the record. Constellation’s motion should be denied, and its Answer should be rejected.
14 See PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024).15 See Constellation’s Answer at 14-16. 16 Id. at 15.17 Id. at 8-9.18 See Indicated TOs’ Rehearing Request at 22-26.
PDF page 5
5
Respectfully submitted,
/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com /s/ Bradley R. Perkins
Bradley R. Perkins
Vice President and Deputy General Counsel Exelon Corporation
Chase Building
10 S. Dearborn, 52nd Floor
Chicago, IL 60603
Telephone: 312-394-2632
Email: bradley.perkins@exeloncorp.com
On behalf of Exelon Corporation
/s/ Amanda P. Parker
Amanda P. Parker
Corporate Counsel
FirstEnergy Service Company
341 White Pond Drive
Akron, OH 44320
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com
On behalf of The FirstEnergy
Transmission Companies
PDF page 6
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated at Chicago, IL this 12th day of February, 2026.
/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation