ER26-1479-000 · 2026-02-23 · PJM Interconnection, L.L.C.

Co-Located Load Tariff Revisions to Comply with Order in EL25-49, et al

PDF page 1

PJM Interconnection, L.L.C.
2750 Monroe Boulevard
Audubon, PA 19403

Mark J. Stanisz
Associate General Counsel
Ph: (610) 666-4707
Mark.Stanisz@pjm.com

February 23, 2026

Honorable Debbie-Anne A. Reese
Secretary
Federal Energy Regulatory Commission
888 First Street, NE, Room 1A
Washington, DC 20426

Re:
PJM Interconnection, L.L.C., Docket No. ER26-____-000
60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access
Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, et
al.
Dear Secretary Reese:
Pursuant to section 206 of the Federal Power Act,1 PJM Interconnection, L.L.C.
(“PJM”) hereby submits proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”)2 of PJM Interconnection to comply with the Federal Energy Regulatory

Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order3 to
(1) revise its behind-the-meter generation Tariff provisions, (2) establish three new transmission services for Eligible Customers4 seeking to take service on behalf of Co- Located Load, and (3) revise its necessary studies processes,5 among other changes (collectively, the “February 23 Compliance Filing”).  In response to the Order to Show

1 16 U.S.C. § 824e.
2 Terms not otherwise defined herein shall have the same meaning as set forth in the Tariff.  PJM anticipates needing to make subsequent conforming clean-up filings to the Tariff, Amended and Restated Operating Agreement (“Operating Agreement”), and the Reliability Assurance Agreement Among Load-Serving Entities in the PJM Region (“RAA”) in regards to the compliance filings being submitted in response to the Order to Show Cause.  Based on continued stakeholder engagement and in the Commission’s active dockets, PJM may also seek leave to submit additional compliance filings to, among other things, streamline Commission resolution of issues and enhance Tariff clarity.
3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 2, 161, 231-36 (2025) (“Order to Show Cause”).
4 Capitalized terms not otherwise defined herein shall have the meanings given to them in the Tariff.
5 Order to Show Cause at P 160.

PDF page 2

Cause, PJM already filed a first compliance filing (in Docket No. ER26-1088-000) and an informational report.

In response to twin Commission directives in the Order to Show Cause, PJM is concurrently filing two packages:  (1) this Transmittal Letter, including filed Tariff revisions, which respond to Commission’s specific compliance directives, and (2) an Initial Brief, including “illustrative” Tariff language that is not filed in eTariff, specifically describing the non-rate terms and conditions for new transmission services.  PJM understands that the PJM Transmission Owners will be making a submission regarding the rates for these new services.

I. INTRODUCTION AND BACKGROUND
PJM understands the importance of, and remains committed to, advancing our nation’s leadership in connecting large loads, including supporting the development of Artificial Intelligence (“AI”) infrastructure.  PJM continues to work with its members to support efforts to accelerate the speed and increase the scale with which the United States can build the next generation of AI infrastructure, especially the necessary capacity to support this load while also ensuring reliability and fair treatment for all users of the grid.

A. Commission Order
On December 18, 2025, the Commission issued the Order to Show Cause finding the Tariff unjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply to Co-Located Load and directing PJM to make several compliance and informational filings.6  In the Order to Show Cause, the Commission directed PJM to file several 60-day compliance directives which are discussed here.  As noted above, the

6 Id. at PP 1-2.

PDF page 3

Commission also required PJM to submit a brief to build a record on the appropriate rates, terms, and conditions of these new services.  PJM is submitting that brief concurrently with this February 23 Compliance Filing.

B. Stakeholder Engagement
PJM consulted with stakeholders in its development of the proposed revisions.  PJM held a workshop on January 9, 2026 to give stakeholders an opportunity to provide feedback for PJM to consider as it developed the proposed revisions filed on January 20.7 Additional stakeholder workshops followed on January 23,8 January 26,9 February 5,10 February 10,11 and February 20.12

On February 19, 2026, PJM posted a preliminary draft of the proposed revisions for stakeholder awareness and discussion prior to submission.13  PJM also solicited and received written stakeholder input on posted proposed tariff language and concepts related to meeting the compliance directives.  PJM appreciates the extensive stakeholder

7 PJM, Co-Located Load Order Workshop Meetings Materials (2026), https://www.pjm.com/committees- and-groups/workshops/cllsco (postings of Co-Located Load Order Workshop upcoming meetings schedule and past meeting materials on PJM’s website).

8
PJM,
Co-Located
Load
Order
Workshop
Meeting
Materials
(Jan.
23,
2026),
https://www.pjm.com/committees-and-groups/workshops/cllsco.
9
PJM,
Co-Located
Load
Order
Workshop
Meeting
Materials
(Jan.
26,
2026),
https://www.pjm.com/committees-and-groups/workshops/cllsco.
10
PJM,
Co-Located
Load
Order
Workshop
Meeting
Materials
(Feb.
5,
2026),
https://www.pjm.com/committees-and-groups/workshops/cllsco.
11
PJM,
Co-Located
Load
Order
Workshop
Meeting
Materials
(Feb.
10,
2026),
https://www.pjm.com/committees-and-groups/workshops/cllsco.
12
PJM,
Co-Located
Load
Order
Workshop
Meeting
Materials
(Feb.
20,
2026),
https://www.pjm.com/committees-and-groups/workshops/cllsco.
13
PJM,
Preliminary
Drafts
of
Proposed
Revisions
for
Stakeholders
(Feb.
20,
2026),
https://www.pjm.com/committees-and-groups/workshops/cllsco (follow “Meeting Materials” subheading; then choose “2026” from dropdown; then choose “2.20.2026 Item 01 – 1” and “2.20.2026 Item 01 – 2” PDFs).

PDF page 4

engagement and considered that feedback in refining and developing the proposed revisions.

III. DESCRIPTION OF PROPOSED TARIFF REVISIONS
A. Revisions to Behind The Meter Generation (“BTMG”) Rules
The Commission found that PJM’s existing Retail Behind The Meter Generation (“Retail BTMG”) rules in the Tariff are no longer just and reasonable, in part, because “PJM’s existing [Retail] BTMG rules may lead to both reliability and resource adequacy risks.”14  Accordingly, in the Order, the Commission required PJM to revise the rules for “retail BTMG” to (1) establish a “materiality threshold,” (2) set a three-year transition period for implementation of the threshold, and (3) establish a legacy arrangement to allow entities with existing contracts effectuating retail BTMG arrangements above the newly established threshold to continue utilizing the existing retail BTMG rules through the remainder of the current contract terms.15

1. Existing BTMG Rules

PJM’s BTMG rules originated in 2004, when the Commission accepted PJM’s
proposal to allow market participants to net BTMG against load “at the same electrical location for the purposes of calculating applicable PJM charges.”16  The Commission found that the BTMG rules would “encourage demand response programs” and “provide a benefit to qualifying behind the meter generation that contributes to network load reductions by allocating a fairer share of transmission system and other operating costs.”17  The use of

14 Order to Show Cause at P 186.
15 Id. at PP 179, 221-24.
16 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 1 (2004).
17 Id. at PP 27, 29.

PDF page 5

netting between BTMG and load that are located “at a single electrical location such that no transmission or distribution facilities are used to deliver energy from the generating unit to the load”18 is commonly referred to as “Retail BTMG.”  As originally conceived, there is no limit on the size of a BTMG that could be netted with load in a retail BTMG configuration.19

In 2005, the Commission initiated an investigation into whether PJM should expand BTMG netting to “include generation connected to electric distribution systems.”20  Later that year, the Commission accepted a settlement between PJM and several municipal systems, which “expands applicability of PJM’s BTM generation netting provisions to BTM generation used by municipal electric systems, electric cooperatives and municipal electric distribution companies . . . to serve load so long as permission is obtained from the facility owner, lessee or operator.”21  BTMG used to net against load through a distribution system is defined as Non-Retail Behind The Meter Generation.22

As a result of these proceedings, the current Tariff specifies netting rules and includes definitions for Behind The Meter Generation and Non-Retail Behind the Meter Generation.  Specifically, Behind The Meter Generation is defined as:

a generation unit that delivers energy to load without using the
Transmission System or any distribution facilities (unless the entity
that owns or leases the distribution facilities has consented to such
use of the distribution facilities and such consent has been
demonstrated
to
the
satisfaction
of
the
Office
of
the

18 Id. at P 4.
19 See Order to Show Cause at P 186.
20 PJM Interconnection, L.L.C., 112 FERC ¶ 61,034, at P 1 (2005).
21 PJM Interconnection, L.L.C., 113 FERC ¶ 63,024, at P 8 (2005) (Order certifying uncontested settlement); PJM Interconnection, L.L.C., 113 FERC ¶ 61,279 (2005) (Order accepting settlement and dismissing rehearing request).
22 Tariff, Part I, Definitions A-B (“Behind The Meter Generation”); Tariff, Part I, Definitions L-M-N (“Non- Retail Behind The Meter Generation”).

PDF page 6

Interconnection); provided, however, that Behind  The Meter
Generation does not include (i) at any time, any portion of such
generating unit’s capacity that is designated as a Generation
Capacity Resource; or (ii) in an hour, any portion of the output of
such generating unit that is sold to another entity for consumption at another electrical location or into the PJM Interchange Energy

Market.23
The term Non-Retail Behind The Meter Generation refers to the Behind the Meter Generation definition and is further defined as: “Behind the Meter Generation that is used by municipal electric systems, electric cooperatives, or electric distribution companies to serve load.”24  Currently, there is no definition of “Retail BTMG.”

As discussed above, the Tariff permits netting of load with BTMG to reduce applicable PJM charges.25  Accordingly, Section 34.2 of the Tariff states, “[t]he daily load of a Network Customer does not include load served by operating Behind The Meter Generation.  The daily load of a Network Customer shall not be reduced by energy injections into the transmission system by the Network Customer.”26  Section 34.3 sets forth a cap on the netting of Non-Retail BTMG not to exceed 3000 MW across the PJM Region.27  Thus, under the current rules, retail BTMG is not capped, but Non-Retail BTMG is limited to 3000 MW across the PJM Region.

2. Satisfaction of the Commission’s Compliance Directive
Pursuant to the Commission’s order, PJM is updating the definition of Behind the Meter Generation and adding a new definition for Retail Behind the Meter Generation to:

23 Tariff, Part I, Definitions A-B (“Behind The Meter Generation”).
24 Tariff, Part I, Definitions L-M-N (“Non-Retail Behind The Meter Generation”).
25 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 1.
26 Tariff, Part III, section 34.2.
27 Tariff, Part III, section 34.3.  The cap for the PJM Region was initially set at 1500 MW in 2006, and “proportionately increased based on load growth in the PJM Region [thereafter] but shall not be greater than 3000 megawatts.”  Id.

PDF page 7

(1) establish a “materiality threshold” for Retail BTMG, (2) implement a “three-year transition period,” and (3) provide the ability to “grandfather certain entities with existing contracts.”28  In accordance with the Commission’s clarification, this compliance filing is limited to retail BTMG and did not direct any changes to Non-Retail BTMG rules.29 Specifically, PJM’s proposed definition for Retail Behind the Meter Generation (to be added to Parts I and VIII of the Tariff, and not Part VII which relates to a transition process no longer accepting new applications) is: “Retail Behind The Meter Generation” shall refer to Behind The Meter Generation that is used to serve a retail load served by a Network Customer located at the same electrical location, where such generation has a cumulative nameplate rating of no greater than 50 MW (not including back-up generation at the same electrical location as the retail load that can only be used to serve such retail load during conditions that may threaten the integrity or reliability of the PJM

Region
or
the
regional
power
system).
Notwithstanding the foregoing and for a transition period through December 18, 2028, Retail Behind The Meter Generation includes any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load prior to December 18, 2025. Provided further, Retail Behind The Meter Generation includes any generation used to serve a retail load served by a Network Customer to net load if it is the subject of a contractual arrangement (including but not limited to a bilateral agreement or interconnection agreement) that was in effect as of December 18, 2025 through the end of the term of such agreement, which may be renewed or extended per the terms of such agreement. Further, Retail Behind The Meter Generation also includes any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load that, as of December 18, 2025, was a Qualifying Facility consistent with the requirements of the Public Utility Regulatory Policies Act of 1978, as amended, and its implementing regulations.  Any facility that qualifies

28 Order to Show Cause at P 179.
29 Id. at P 222.

PDF page 8

as Retail Behind The Meter Generation shall be excluded
from Co-Located Load configurations.

a. Legacy Treatment of Contracts that Effectuate Retail BTMG
Arrangements
The Commission recognized that certain parties “may . . . have contracted for the specific purpose of effectuating a BTMG arrangement.”30  Accordingly, the Commission directed that, “[t]o the extent that an entity is a party to an existing contract for such a purpose, we find that it is appropriate to grandfather such entity so that it may continue using BTMG for the current term remaining under the existing contract.”31  In other words, any existing retail BTMG with a contract that was entered into for the purpose of effectuating a BTMG arrangement as of the date of the Commission’s order (i.e., December 18, 2025) through the term of such agreement would be permitted to remain eligible to net against Network Loads as Retail BTMG irrespective of the threshold proposed below. Businesses and institutions operating on-site generation have relied on the Retail BTMG rules for over two decades, some investing substantial sums in building and maintaining units that are deeply embedded into their own operations.  Considering the complexity and maturity of these configurations, a wide variety of contracts may be employed and relied on for the operation of these units, including utility contracts, fuel contracts, maintenance contracts, and more.  PJM understands the Commission’s contract- exception to the three-year transition mandate to be designed to generally enable these established generation investments to operate under existing assumptions while those contracts remain effective.

30 Id. at P 224.
31 Id.

PDF page 9

Specifically, PJM interprets the Commission’s compliance directive to allow existing BTMG arrangements to qualify for legacy treatment so long as there is an existing contractual agreement for the purpose of effectuating a BTMG arrangement (e.g., bilateral agreement, interconnection agreement, etc.)32 that was in effect prior to December 18, 2025.  And to recognize contracting parties’ expectation of renewal or extension rights under such existing agreements and to avoid interference with such reliance expectations upon which investment decisions likely have been made (the specific terms and conditions of which PJM does not have knowledge of), PJM further interprets the Commission’s use of the phrase “the current term remaining under the existing contract” to encompass existing renewal or extension rights recognized under such existing contracts. In addition, the Commission’s compliance directive was issued against the backdrop of the Public Utility Regulatory Policies Act of 1978, as amended, and its implementing regulations.  While the Order to Show Cause does not reference this regulatory regime and its impacts, PJM interprets the Commission’s compliance directive as allowing the extension of legacy treatment to any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load that, as of December 18, 2025, was a Qualifying Facility (“QFs”).  In light of stakeholder engagement and pleadings submitted in this proceeding, PJM understands that there exists today Retail BTMG that were QFs as of December 18, 2025, with many being cogeneration QFs that are often used in manufacturing and other processes to produce both electricity and useful thermal energy that often lead to economic

32 If accepted by the Commission, PJM will explore with stakeholders whether Manual language should be developed to help elaborate on what types of agreements may qualify.  Further, PJM notes that some of the prerequisites for participation are compliance obligations Retail BTMG must be able to establish and verify for purposes of their own compliance even if PJM may not have a role in reviewing such information.

PDF page 10

and energy efficiency benefits.33  Under Commission regulations, QFs have built-in size limits or, for cogeneration, meet strict efficiency requirements.34  Specifically, for a cogeneration QF, the generating facility and its load are closely integrated.  For example, some retail customers’ loads may be configured such that the load reduces if on-site generation is unavailable because manufacturing processes reliant on thermal heat will discontinue.

Given that existing retail BTMG arrangements with such contractual agreements
and that otherwise have QF status have been in place and netted against Network Loads within PJM without known operational issues to date, PJM proposes to allow such

arrangements, which in some cases have been in place for decades, to qualify for legacy treatment and continue to be eligible to net under the existing BTMG rules.

Going forward, however, consistent with the Commission’s directive, any new
large Retail BTMG that is greater than the proposed threshold would not be eligible to qualify as Retail BTMG given that significant increases of new large loads generally on the system that the Commission determined could increase operational risks and costs shifting concerns.35  Specifically, the Commission directed PJM to “maintain the current BTMG rules for customers that fall below a new MW materiality threshold.”36  Given the

33 PJM Interconnection, L.L.C., et al., PJM Industrial Customer Coalition’s Request for Clarification or Rehearing, Docket No. EL25-49-000, et al., at 10 (Jan. 20, 2026).  Indeed, the PJM Industrial Customer Coalition asserts that, “PURPA has been a boon to manufacturers and the electric grid for well over four decades, providing market access where such access did not previously exist, taking strain off the grid, and supporting American industry by allowing for economic means of reducing energy costs.  Many QFs are highly efficient facilities, including cogeneration facilities, which produce both electricity and heat from the same fuel source, then making use of the ‘waste heat’ in industrial operations.  QFs are entitled to have access to supplementary power, back-up power, maintenance power, and interruptible power, pursuant to enacting regulations.”  Id.
34 16 U.S. Code § 824a-3; 18 C.F.R. § 292.204.
35 Order to Show Cause at PP 179, 186.
36 Id. at P 179.

PDF page 11

Commission’s identified cost causation, transition, and resource adequacy concerns with the existing Retail BTMG rules, the proposal is based on an interpretation of the compliance directive that demands an “all or nothing” approach to Retail BTMG qualification – meaning that a Retail BTMG cannot both net up to a certain threshold but still potentially have generation and load above that threshold which cannot be netted.  PJM understands that such a hybrid approach would impose significant costs on all Retail BTMG that would have to install previously unnecessary metering equipment (that, for some facilities, may be cost prohibitive) and it amplifies compliance risks for units because it might require many facilities to monitor and report different generator output and load thresholds in relation to the threshold.

b. Three-Year Transition Period
To “minimize the impact” of changing the BTMG rules on existing customers, the Commission ordered PJM “to allow Network Customers already using the BTMG rules to continue to do so for a transition period of three years . . . from the date of issuance of this order.”37  Thus, in the event there are any existing Retail BTMG larger than the proposed threshold discussed below and not the subject of an existing contractual agreement in effect or qualifying QF status as of December 18, 2025, such resources would continue to be eligible to participate as retail BTMG for up to three additional years (i.e., through December 18, 2028).

c. Materiality Threshold
In accordance with the Commission’s compliance directive, PJM proposes to establish a materiality threshold of up to 50 MW for a generator at the same electrical

37 Id. at P 223.

PDF page 12

location as the Network Load for generation units to qualify as Retail BTMG.  This 50 MW threshold aligns with the PJM Board’s definition of large loads additions, which comprise of individual loads at or above 50 MW at a single point of interconnection.38  Based on stakeholder feedback and engagement on this point, PJM understands the proposed 50 MW threshold to avoid unneeded regulatory uncertainty for retail customers whose grid impacts on reliability are more limited and have been in existence without noted impact for decades.39

Further, the proposed threshold and proposed exclusion for backup generation from the threshold (along with the proposed legacy treatment) will avoid the unintended consequence of causing Retail BTMG resources to prematurely cease operations and discontinue investment in grid-enhancing backup generation, outcomes which would frustrate system reliability in an unintended fashion.  In developing the materiality threshold, PJM discussed with stakeholders that a lower threshold of 10 or 20 MW would likely exclude from Retail BTMG a much larger volume of retail customers whose grid impacts are small or de minimis when compared with the Co-Located Load coming online today.  Further, concerns were raised that a lower threshold could force many existing Retail BTMG resources offline during the transition period because such resources do not intend to enter into PJM’s interconnection queue to become a market resource.  PJM understands that many of the existing Retail BTMG are decades old and may need significant upgrades prior to directly interconnecting into the PJM system.  However, given

38 PJM, Board Decisional Letter on Critical Issue Fast Path – Large Load Additions, at 2 (Jan. 16, 2026), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm- board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.
39 Order to Show Cause at P 221 (“Such a threshold should reduce the reliability and resource adequacy risks discussed that large loads may pose to PJM, while also allowing for Network Customers to reduce their transmission charges in a transparent, not unduly discriminatory fashion.”).

PDF page 13

the costs associated with such significant upgrades, the owners of such resources may decide to forgo the option of interconnecting into the PJM system altogether.  The effect of such an outcome would result in higher Network Loads requiring grid service, as loads that are currently netted by the retail BTMG would not be matched with additional supply of Capacity Resources.  Because the Order to Show Cause’s BTMG reforms are directed at stemming reliability concerns, not exacerbating them, the 50 MW threshold is a justified threshold for Retail BTMG eligibility.

Additionally, excluding true on-site back-up power from determining whether the threshold has been reached critically avoids disincentivizing and discouraging retail customers from installing back-up power installations that would have positive reliability implications for the region.  The Department of Energy recently observed that “[d]eployment of backup generation resources . . . can prevent avoidable blackouts, thereby saving lives and reducing costs to the American people.”40  The proposed Retail BTMG threshold should not frustrate investment by such resources in such reliability enhancing backup generation.  In the PJM Region specifically, it is notable that during the recent Winter Storm Fern, the Department of Energy issued an Order applicable in the PJM Region pursuant to Section 202(c) of the Federal Power Act that directed “PJM, in collaboration with its Transmission Owners, . . . to direct backup generation resources . . . to operate as a last resort before declaring an Energy Emergency Alert (EEA) 3 (i.e., before firm load interruption) or during an EEA 3.”41  The language in the proposal excepting

40 US Department of Energy, Order No. 202-26-06 (Jan. 26, 2026), https://www.energy.gov/documents/doe- order-no-202-26-06-pjm. 41 Id.

PDF page 14

certain on-site back-up power from the materiality threshold will preserve the availability of this potential reliability tool.

PJM proposes to establish a threshold based on the size of the generator that may qualify as retail BTMG, which is consistent with the Commission’s points of reference to potential threshold sizes based on various generator sizes.42  Establishing a threshold based on the size of the generator to qualify as retail BTMG is similarly consistent with the recognition that BTMG is defined as a generation unit, rather than a load.  Further, a threshold based on the size of the generator provides a clear and bright line for what can continue qualifying as retail BTMG.  That is, load sizes can fluctuate, unlike the nameplate rating of a generator, which is static.  In short, proposing a threshold based on the size of the generator to qualify as retail BTMG is superior to or consistent with the Commission’s compliance directive and underlying goal of limiting the risk of the resource adequacy concerns43 arising from allowing large BTMG to net against Network Loads.

While a 50 MW materiality threshold for new retail BTMG is appropriate going forward, in the event the Commission does not accept PJM’s proposed legacy treatment for the purpose of effectuating BTMG discussed above, PJM requests that the Commission allow an interim initial materiality threshold to be in place for the start of the transition period to avoid setting an initial threshold that is too low and that could, for the reasons stated above, cause Retail BTMG resources to cease operations and in turn exacerbate in an unintended fashion the resource adequacy issues in the PJM Region.  In this circumstance, as a potential short-term stopgap, if PJM’s proposed Retail BTMG revisions

42 Order to Show Cause at P 221.
43 Id. at P 186.

PDF page 15

are not accepted, PJM observes that the PJM Industrial Customer Coalition (“PJM ICC”)44 indicated that “a threshold of 200 MW would, as a practical matter, permit most existing industrial and institutional loads to continue to benefit from the major energy investments they have made over decades, consistent with the ‘actual use’ principle.  As super-sized loads are a largely new phenomenon, the number of entities requiring grandfathering of existing contracts and facilities would be far more limited at a 200 MW threshold.”45 Should the Commission adopt a higher interim materiality threshold of this sort at the start of the transition period, PJM commits to reviewing additional data from Transmission Owners on the extent and size of existing Retail BTMG.46  This data could inform whether the interim materiality threshold should be further refined in the future through a separate filing on compliance in this docket or, if necessary, pursuant to section 205 of the Federal Power Act.

d. Proposed Tariff Updates
To effectuate the foregoing updates to the rules for retail BTMG, PJM proposes to establish a new definition for “Retail Behind The Meter Generation” and clarify that the definition of “Behind The Meter Generation” broadly reflects the two species of BTMG: Retail BTMG and Non-Retail BTMG.  Consistent with the Commission’s clarification that it does “not direct PJM to change its rules for non-retail BTMG,”47 it is appropriate to establish a new dedicated definition for Retail Behind The Meter Generation that clearly

44 PJM Interconnection, L.L.C., et al., PJM ICC’s Request for Clarification or Rehearing, Docket No. EL25- 49-000, et al., at 44 (Jan. 20, 2026).
45 Id.
46 PJM has existing authority to require Members to provide records and documentation of retail BTMG data given that it is necessary for the “coordination of operations” and “coordination of planning, including those data required for capacity accounting under the Reliability Assurance Agreement” pursuant to Operating Agreement, section 11.3.1(a). 47 Order to Show Cause at P 222.

PDF page 16

distinguishes this type of resource.  PJM is also seeking to avoid any inadvertent changes to the substantive rules pertaining to Non-Retail Behind The Meter Generation.  For this reason, PJM also proposes to add clarifying language in Tariff, Part III, section 34.3 providing that “The daily load of a Network Customer does not include load served by operating Non-Retail Behind The Meter Generation.”48  This insertion preserves the status quo on this issue for Non-Retail Behind The Meter Generation.

For the new definition of Retail Behind The Meter Generation, PJM is defining that as “Behind The Meter Generation that is used to serve a retail load served by a Network Customer located at the same electrical location, where such generation has a cumulative nameplate rating of no greater than 50 MW (not including back-up generation at the same electrical location as the retail load that can only be used to serve such retail load during conditions that may threaten the integrity or reliability of the PJM Region or the regional power system).”49

To effectuate the legacy treatment discussed above, PJM proposes to include language in the newly defined Retail Behind The Meter Generation that states: “Retail Behind The Meter Generation includes any generation used to serve a retail load served by a Network Customer to net load if it is the subject of a contractual arrangement (including but not limited to a bilateral agreement or interconnection agreement) that was in effect as of December 18, 2025 through the end of the term of such agreement, which may be

48 PJM understands Tariff, Section 34.2 was originally drafted to generally state that all BTMG, including Non-Retail BTMG, can be netted against a Network Customer’s daily load.  Tariff, Section 34.3 goes on to place a limitation on the amount of Non-Retail BTMG that can be used for those netting purposes.  While it is implicit in Tariff, Section 34.3 that Non-Retail BTMG can net against load, the proposed revision to Tariff, Section 34.2 suggests clarification to Tariff, Section 34.3 is necessary since the Tariff otherwise no longer has an explicit statement that says that the daily load of a Network Customer does not include load served by Non-Retail BTMG.
49 Proposed Tariff Revisions, Part I, Definition of Retail Behind The Meter Generation.

PDF page 17

renewed or extended per the terms of such agreement.  Further, Retail Behind The Meter Generation also includes any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load that, as of December 18, 2025, was a Qualifying Facility consistent with the requirements of the Public Utility Regulatory Policies Act of 1978, as amended, and its implementing regulations.”50

Next, consistent with the Commission’s order, PJM is also including language regarding the three-year transition that would be applicable to any existing retail BTMG that does not have an agreement in effect as of December 18, 2025, in the definition of Retail Behind The Meter Generation.  Specifically, PJM proposes to specify that “for a transition period through December 18, 2028, Retail Behind The Meter Generation includes any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load prior to December 18, 2025” may continue to be included as Retail Behind The Meter Generation.

In accordance with the Commission’s compliance directive, PJM’s compliance filing “maintain[s] the current BTMG rules for customers that fall below [the] new materiality threshold for the amount of load at a particular electrical location that Network Customers may net using BTMG.”51  That is, PJM is proposing to only establish a generator size threshold, along with the legacy and transition rules, for what can qualify as Retail Behind The Meter Generation while retaining all substantive existing netting provisions related to Retail BTMG, and BTMG in general, as part of this compliance filing.

50 Id.
51 Order to Show Cause at P 179.

PDF page 18

Lastly, PJM proposes language for the definition of Retail BTMG that provides that “Any facility that qualifies as a Retail Behind The Meter Generation shall be excluded from Co-Located Load configurations.”  This language is intended to provide clarity and direction to project developers about what pathways are available to serve load that is co- located, and to avoid unexpected and unintended hybrid scenarios mixing BTMG and the new transmission service products the Commission has directed in the Order to Show Cause.

B. Transmission Services for Co-Located Load
In compliance with the Order to Show Cause,52 PJM is proposing to add to its Tariff three new transmission services that an Eligible Customer taking transmission service on behalf of a Co-Located Load may select, in addition to existing Network Integration Transmission Service.  Furthermore, PJM is proposing three new transmission service agreements to reflect the rates, terms, and conditions for these new transmission service options that are available to Eligible Customers.  Below, the Tariff revisions proposed here effectuate several discrete directives in the Order to Show Cause relating to the new transmission services (while the rates, terms, and conditions of such services remain uncertain and the subject of an ongoing paper hearing).

1. Tariff Revisions in Transmittal Letter v. Illustrative Tariff Revisions in PJM’s Initial Brief.

To be clear, the Tariff changes proposed in this Transmittal letter comprise only a minority of the Tariff revisions that will be needed to effectuate these transmission services.

52 Id. at PP 160, 178.

PDF page 19

Concurrently with this Transmittal Letter, PJM is filing an Initial Brief to address the paper hearing questions that the Commission required in its Order to Show Cause.53 In that Initial Brief, PJM will provide illustrative Tariff language for the majority of the non-rate terms and conditions of service for these new transmission services.54 Because such language will change upon a Commission action in the paper hearing, PJM is not filing the new transmission services Tariff language as part of this Transmittal Letter, but is rather labeling the language in Attachment A to the Initial Brief as “illustrative” to signal that it is subject to the outcome of the paper hearing.

Putting aside the non-rate terms and conditions that are the subject of PJM’s Initial Brief, the Order to Show Cause required PJM to file several specific Tariff revisions to effectuate these new transmission services.  PJM describes these Tariff revisions below.

1. New Part XI, Attachments F-3A and F-4
First, the Commission required PJM to establish several new transmission services for Eligible Customer serving Co-Located Load.55

Interim Network Integration Transmission Service:  PJM is proposing to revise its Tariff to allow an Eligible Customer serving Co-Located Load that is seeking to take NITS under Tariff, Part III the option to seek Interim NITS subject to provisions in a new Tariff, Part XI.  With this Transmittal letter, PJM is filing a “shell” of Tariff, Part XI, to show that this service will be housed in a new Part XI of PJM’s Tariff,56 and provides the proposed

53 Id. at P 219; Ordering Paragraph E.
54 PJM Interconnection, L.L.C., et al., PJM’s Initial Brief, Attachment A, Docket No. EL25-49-000, et al. (Feb. 23, 2026) (“PJM Initial Brief”).
55 Order to Show Cause at PP 160, 178.
56 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).

PDF page 20

non-rate terms and conditions in PJM’s Initial Brief.57  As discussed further in PJM’s Initial Brief, this new transmission service, as required by the Order to Show Cause,58 would allow an Eligible Customer taking service on behalf of Co-Located Load that has requested NITS to receive transmission service on behalf of a Co-Located Load on a non-firm, interruptible basis for the period until transmission upgrades required to provide NITS are complete and placed in service.

With this Transmittal, PJM is proposing a new Attachment F-3A, which will serve as the service agreement for Eligible Customers taking on behalf of a Co-Located Load Network Integration Transmission Service and/or Interim Network Integration Transmission Service.59  The Commission requires PJM to establish “a transmission service agreement that reflects the rates terms, and conditions of these new transmission service options is available to Eligible Customers.”60  PJM is filing a “shell” of Attachment F-3A, to show that the service agreement will be a new Attachment F-3A,61 but notes that the proposed language of Attachment F-3A is discussed in the Initial Brief.62  As explained in PJM’s Initial Brief, the new Attachment F-3A is based upon existing Attachment F-3 for Network Integration Transmission Service, but is tailored to arrangements that involve Co-Located Load.

Firm Contract Demand Transmission Service and Non-Firm Contract Demand
Transmission Service:  In compliance with the Order to Show Cause, PJM is also proposing

57 PJM Initial Brief, Attachment A (new Part XI illustrative language, with sections 700-707 setting forth proposed non-rate terms and conditions for Interim Network Integration Transmission Service).
58 Order to Show Cause at PP 201, 203.
59 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).
60 Order to Show Cause at P 193. 61 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).
62 See PJM Initial Brief, Attachment A (Attachment F-3A).

PDF page 21

two new Contract Demand Transmission Services.  First, PJM is proposing a new Firm Contract Demand Transmission Service which would allow an Eligible Customer taking transmission service on behalf of a Co-Located Load to take service up to a pre-specified MW quantity.  Second, PJM is proposing a new Non-Firm Contract Demand Transmission Service for those Eligible Customers taking service on behalf of Co-Located Loads that do not necessarily plan to withdraw energy from PJM’s transmission system on a regular basis.  These customers will only take energy on an as-needed and as-available basis. With this Transmittal, PJM is filing a “shell” of Tariff, Part XI, to show that these two services will be housed in a new Part XI of PJM’s Tariff,63 with the proposed Part XI language contained in PJM’s Initial Brief.64  Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service will be subject to a new Service Agreement specific to Contract Demand Transmission Service to be contained in Tariff, Attachment F-4.  PJM is filing a “shell” of Attachment F-4, to show that the service agreement will be a new Attachment F-4,65 but notes that the proposed language of Attachment F-4 is discussed in its Initial Brief.66

PJM will file the full text of Part XI, Attachment F-3A, and Attachment F-4 upon the Commission’s decision following the conclusion of the paper hearing procedures.

63 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).
64 See PJM Initial Brief, Attachment A (new Part XI illustrative language). 65 See Attachment A (Clean Tariff Revisions); Attachment B (Redline Tariff Revisions).
66 See PJM Initial Brief, Attachment A (new Part XI illustrative language, with sections 708-716 setting forth proposed non-rate terms and conditions for Contract Demand Transmission Services).

PDF page 22

2. Part III Revisions
PJM is also proposing Tariff revisions to Part III (Network Integration Transmission Service), to comply with several discrete requirements in the Commission’s Order to Show Cause.

Eligible Customers remain eligible to take Network Integration Transmission Service under Tariff, Part III on the same terms and conditions as before.  First, the Commission required PJM to file a new provision explaining that an Eligible Customer taking transmission service on behalf of the Co-Located Load takes one of three transmission services.67  PJM includes the following redline in Part III to comply with this requirement.68

Eligible Customers taking transmission service on behalf of
Co-Located Load must take one of the following services:
(1) Network Integration Transmission Service under Tariff,
Part III, with the option to seek Interim Network Integration
Transmission Service subject to the provisions in Part XI;
(2) Firm Contract Demand Transmission Service under
Tariff, Part XI; or (3) Non-Firm Contract Demand
Transmission Service under Tariff, Part XI.  Co-Located
Load, which is not served through one of these services must
take all necessary steps to disconnect from the Transmission
System.

Additionally, the Commission provided that while Eligible Customers serving Co- Located Load may take a “combination” of the Firm and Non-Firm Contract Demand services,69 if the Eligible Customer elects to take NITS or Interim NITS, it may not

67 Order to Show Cause at P 193.
68 See Attachment A (Clean Tariff Revisions; Part III General); Attachment B (Redline Tariff Revisions, Part III General).
69 Order to Show Cause at PP 194, 197.

PDF page 23

combine NITS with the Contract Demand services.70  Therefore, PJM also included the following proposed revision in Tariff, Part III:71

An Eligible Customer taking transmission service on behalf
of a Co-Located Load may not take Network Integration
Transmission Service or Interim Network Integration
Transmission Service for that Co-Located Load at the same
time it is taking Firm Contract Demand Transmission
Service or Non-Firm Contract Demand Transmission
Service on behalf of that Co-Located Load.

Additionally, the title of the initial section of Part III has been changed from “Preamble” to “General,” to reflect the broader nature of the provisions contained in the Part.72

Other changes have been made to Tariff, Part III.  In section 28.1, PJM has added a sentence that Eligible Customers taking service on behalf of Co-Located Load may also receive Network Integration Transmission Service.  This is compliant with the Commission’s order that Network Integration Transmission Service must be one of the several transmission service choices that Eligible Customers taking transmission service on behalf of Co-Located Load may select.73

Additionally, in Part III, section 29.1, PJM has clarified that such Network Integration Transmission Service taken on behalf of Co-Located Load will be (1) subject to a new Form of Service Agreement (Attachment F-3A)74 and (2) must satisfy certain

70 Id. at n.408, P 197.
71 See Attachment A (Clean Tariff Revisions; Part III General); Attachment B (Redline Tariff Revisions, Part III General).
72 See Id.
73 Order to Show Cause at P 193.
74 This complies with the Commission’s requirement that PJM establish a new transmission service agreement for the transmission services available to Eligible Customers serving Co-Located Load.  Id. at P 193.

PDF page 24

requirements such as designation of an Eligible Customer and the individual Co-Located Load.75  PJM also clarifies that the Network Integration Transmission Service that is applicable to Eligible Customers taking transmission service on behalf of Co-Located Load shall be Regional Network Integration Transmission Service, not Cross-Border Network Integration Transmission Service.76

Other changes have been made throughout Part III to clarify that Eligible Customers taking Network Integration Transmission Service on behalf of Co-Located Load are subject to the same requirements as other Network Integration Transmission Service Customers.77

Finally, PJM includes revisions to Part III, section 31.6, regarding submission of annual load and resource information, to clarify the additional information that PJM will require Eligible Customers taking Network Integration Transmission Service on behalf of Co-Located Load to provide, including the demand characteristics of the Co-Located Load, and the supply characteristics of the designated Co-Located Generating Facility.

C. Necessary Studies and Necessary Studies Agreement

PJM is further proposing Tariff revisions to Parts III and VIII of the Tariff to comply with the Commission’s directives regarding the Necessary Study Process for Existing Interconnection Customers.78  These proposed revisions are intended to apply uniformly to all existing customers regardless of whether they have presently effective

75 This complies with the Commission’s requirement that an Eligible Customer must be designated.  Id. at P 188.  See also proposed revision to Tariff, Part IX, Subpart B (pro forma GIA), Schedule O (requiring designation of “Eligible Customer taking transmission service on behalf of the Co-Located Load” among other information).
76 Proposed Tariff revisions, Part III, section 29.2.
77 See, e.g., Tariff, Part III, Section 29.2.
78 Order to Show Cause at PP 225-230.

PDF page 25

interconnection agreements issued pursuant to Parts IV, VI, VII, or VIII of the Tariff.79 Notably, in some instances, a customer may not yet have a three-party interconnection agreement involving PJM in which case additional processes are required to convert to a three-party agreement before the necessary study process can be followed.

The thrust of PJM’s proposed revisions require any Existing Interconnection Customer that seeks to serve Co-Located Load to follow a clarified necessary study process detailed in Part VIII of the Tariff and the related Form of Necessary Study Agreement set forth in Tariff, Part IX, Subpart G.  If there is an Existing Interconnection Customer that desires to serve Co-Located Load with a Service Agreement issued pursuant to Tariff, Parts IV and VI, proposed revisions to Part III of the Tariff will require such customers to begin the process of amending such service agreements by following the tariffed necessary study process in Part VIII.80  The same process will be followed for any customers with effective interconnection agreements issued pursuant to Parts VII or VIII.  In all situations, customers will be required to enter into a Necessary Study Agreement with PJM in the form already in the Tariff (subject to proposed modifications set forth in the filing).81 Consistent with the requirements in Paragraph 227 of the Order to Show Cause, PJM proposes to require customers to provide PJM with all information needed to perform the Necessary Studies, as further detailed in the PJM Manuals, including but not limited to82:

79 The next section of this transmittal letter notes revisions to PJM’s interconnection application for new generator interconnection requests that intend to serve Co-Located Load.  Order to Show Cause at P 188.
80 Proposed Tariff Revisions, Part III (General).
81 Order to Show Cause at P 226. 82 See generally proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.i - iii.

PDF page 26

• the proposed configuration for the Co-Located Load and Co-Located Generating
Facility, including a single-line diagram.
• all Eligible Customer information required in the application including the type of
Transmission Service the Eligible Customer will take on behalf of the Co-Located
Load.
• the amount of Capacity Interconnection Rights (“CIRs”) reduction resulting from
the Co-Located Load configuration.83
• Details of any necessary control technologies and protection systems needed to
prevent withdrawals of energy from the Transmission System in excess of the
energy withdrawals permitted under the Eligible Customer’s Service Agreement.84
Further, consistent with the Commission’s directive in the Order to Show Cause,
Paragraph 230, PJM’s necessary study procedures are also being amended to leave no
doubt that “[a] Project Developer shall not implement any planned modifications to its

83 The Order to Show Cause provides that an “existing generating facility may not begin serving Co-Located Load that is not Network Load until it has delisted its CIRs for the portion of the generating facility to be designated to serve any Co-Located Load that is not receiving NITS.  In order for an existing generator to de-list its CIRs to serve Co-Located Load, the Interconnection Customer must revise its ISA or GIA and bear the cost of all required system upgrades[.]”  Id. at P 230.  To promote clarity about this issue to readers of the Tariff, PJM’s filing also proposes to memorialize this directive in the Tariff language itself.  See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.a - b.
84 Consistent with Commission directives in Order Nos. 845 and 845-A and language already embedded in PJM’s pro forma LGIP, PJM’s proposal here uses the term “necessary control technologies and protection systems,” which may include Remedial Action Schemes.  Reform of Generator Interconnection Procedures and Agreements, Order No. 845-A, 166 FERC ¶ 61,137, at P 116 (2019) (“if the interconnection customer requests interconnection service below generating capacity, it commits to operate consistent with such a request under section 3.1 of  the pro forma LGIP, which states that ‘[t]he necessary control technologies and protection systems … for exceeding the level of Interconnection Service established in the executed, or requested to be filed unexecuted, LGIA shall be established in Appendix C of that executed, or requested to be filed unexecuted, LGIA.’”); Order No. 845, 163 FERC P 61,043, at P 396 (2018) (requiring “any interconnection customer that seeks interconnection service below its generating facility capacity install appropriate monitoring and control technologies at its generating facility”); see also Tariff, Part IV, Subpart A, section 36.1.1A (“The necessary control technologies and protection systems shall be established in Tariff, Attachment O, Schedule K (Requirements for Interconnection Service Below Full Electrical Generating Capability) of the executed, or requested to be filed unexecuted Interconnection Service Agreement.”).

PDF page 27

facilities until the Necessary Studies have been completed and the amended Generation Interconnection Agreement reflecting the results of such studies is fully executed and effective.”85  This necessarily includes reflecting any CIR reduction necessary and resulting from a pursued Co-Located Load configuration.

PJM’s proposed Tariff revisions also provide that the Necessary Studies to be performed include thermal, short circuit, and stability studies under various seasonal and load conditions, as specified in more detail in PJM’s Manuals.86  In addition, the proposed revisions provide that PJM shall assess the impact of87 the reduction in CIRs associated with the Co-Located Load and Co-Located Load Generating Facility, any necessary control technologies and protection systems required as part of the Co-Located Load configuration, and any other changed conditions identified by Project Developer or Transmission Owner associated with the Co-Located Load configuration.88

In addition, PJM is proposing other conforming changes to the pro forma Necessary Study Agreement to operationalize the proposed Tariff revisions and facilitate PJM’s collection of the information necessary to perform requested Necessary Studies.89 Lastly, consistent with the directives in Paragraph 228 of the Order to Show Cause, PJM is also proposing revisions that clarify that the “Project Developer shall be responsible

85 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.a.
86 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.ii.
87 The definition of “Necessary Study” in Tariff, Part VIII, Subpart A, section 400 explains that the necessary study is an “assessment[] undertaken by the Transmission Provider to determine whether a planned modification . . . will have a permanent material impact on the Transmission System”, among other things. PJM does not interpret the Commission’s compliance directives to narrow the scope of the Necessary Study inquiry and PJM has not elected to do so in this filing.  In fact, the Commission is directing consideration and evaluation of necessary control technologies and protection systems.
88 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.iii.
89 See proposed revision to Tariff, Part IX, Subpart A (pro forma application and necessary study agreement).

PDF page 28

for the costs of any modifications or Network Upgrades identified by Transmission Provider, as applicable, as a result of the change to the Interconnection Service Agreement or Generation Interconnection Agreement to serve Co-Located Load, including to reflect any reduction in Capacity Interconnection Rights.  Subject to Project Developer having a fully executed and effective Generation Interconnection Agreement governing a Co- Located Load configuration, Project Developer may not begin serving Co-Located Load from the existing Generating Facility until all required Network Upgrades, necessary control technologies and protection systems and metering identified as necessary are complete and in service.”90

D. Other Tariff Revisions (Generation Interconnection Procedures, pro forma GIA, pro forma Application and Studies Agreement, Other

Definitions, etc.)
The Order to Show Cause further directs a number of prescriptive clarifications and revisions.  The chart below reflects the various directives (including a citation to the relevant paragraph of the Order to Show Cause), and explains how PJM’s February 23 Compliance Filing addresses the directive with a reference to the proposed governing document revision.

FERC Requirement
How PJM Complies
Revise Tariff, Part VIII to add to
the list of requirements for a New
Service
Request
that
an
Interconnection Customer who will
use its generating facility to serve
Co-Located Load must specify an
Eligible Customer who will take
transmission service on behalf of
the Co-Located Load.  (Order to
Show Cause at P 188)
PJM complies by making the revision in Part VIII,
Subpart B, section 403(1), new subsection “r.”  See
also proposed revision to Tariff, Part IX, Subpart
B (pro forma GIA), Schedule O; proposed revision
to Tariff, Part III, General.

90 See proposed revisions to Tariff, Part VII, Subpart A, section 401.H.3.b.iii.

PDF page 29

Revise Tariff, Part VIII to explain
that if Interconnection Customer
wants to serve Co-Located Load
but
not
identify
an
Eligible
Customer, then it may take steps to
terminate its generating facility’s
interconnection and serve the Co-
Located Load fully islanded from
PJM’s transmission system.  (Order
to Show Cause at P 189)
PJM complies by making the revision in two
places:  (1) Part III (General), and (2) Part VIII,
Subpart B, section 403(1), new subsection “r.”

Revise Tariff, Part VIII to explain
that these above requirements
apply to “all” Interconnection
Customers
requesting
to
interconnect generating facilities to
serve Co-Located Load.  (Order to
Show Cause at P 189)
PJM complies by making revisions in two places:
(1) Part III (General), and (2) Part VIII, Subpart B,
section 403(1), new subsection “r.”
Revise Tariff, Part VIII to specify
any operational procedures or data
exchange requirements that PJM
deems necessary for Co-Location
Arrangements.  (Order to Show
Cause at P 188)
PJM complies by adding a new schedule in the pro
forma GIA (Schedule O), in the form of a
placeholder for such information as the case may
require.

The remainder of Schedule O is discussed in the
Initial Brief because it relates to specific non-rate
terms and conditions of service for Co-Located
Load arrangements.
Revise pro forma GIA to reflect
above requirement to specify an
Eligible Customer that will take
transmission service on behalf of
the Co-Located Load.  (Order to
Show Cause at P 190)
PJM complies by proposing revisions to the pro
forma GIA, Schedule O.
Revise
Tariff
to
establish
a
transition mechanism for existing
customers who wish to add Co-
Located Load.  (Order to Show
Cause at P 191)91
PJM complies by including the transition
mechanism in three places (1) Part I (definition of
“Co-Located Generating Facility”); (2) Part III
(General), (3) Part VIII, Subpart A, Section 400,
Definition
C’s
definition
of
“Co-Located

91 Order to Show Cause at P 191 (“Third, we direct PJM to submit, within 60 days of the date of issuance of this order, a compliance filing to add a new provision to Part I, Common Service Provisions, of the Tariff that requires Interconnection Customers with ISAs or GIAs executed, or requested to be filed unexecuted, prior to the effective date of the revised generation interconnection procedures and pro forma GIA directed in this order that wish to add Co-Located Load or are currently serving Co-Located Load to publicly notify PJM of that addition and identify the Eligible Customer that will take transmission service on behalf of that Co-Located Load.  As discussed further below, that Eligible Customer must abide by the terms of the Tariff, including terms regarding transmission service.”).

PDF page 30

Generating
Facility”.92

Because
PJM
is
augmenting the Co-Located Generating Facility
definition previously submitted in the January 20
Compliance Filing, for sake of clarity, PJM is
submitting its proposed definition in full as part of
the February 23 Compliance Filing.

Although the Order to Show Cause suggested that
these changes would be in Part I (Common Service
Provisions) and Attachment O,93 Appendix 2, PJM
respectfully offers that placement in Part III and
Part VIII (in addition to Part I Definitions) is
superior to or consistent with the Commission’s
directive because it promotes tariff readability and
usability.  In particular, Attachment O is for
Interconnection Service Agreements under Part VI
of the Tariff, and since PJM’s Transition Date,
PJM has not issued new Interconnection Services
Agreements.

92 In all such places, the new transition mechanism language reads: “Any Generation Project Developer with an effective Service Agreement that plans to use a Generating Facility to serve Co-Located Load must provide PJM and the Transmission Owner with advance written notice to begin the Necessary Studies process provided in Tariff, Part VIII, Subpart A, section 401(H)(3)(b).  If such a Generation Project Developer has an effective Interconnection Service Agreement pursuant to Tariff, Part VI or a Generation Interconnection Agreement pursuant to Tariff, Part VII, such agreement must be superseded by a Generation Interconnection Agreement pursuant to Tariff, Part VIII and the pro forma GIA in Part IX, Subpart B.”

93 Order to Show Cause at P 191.

PDF page 31

Additionally, although PJM filed Tariff revisions on January 20, 2026 to include a definition of Co-Located Load in Parts VII and VIII of the Tariff, with this filing PJM is also adding that same definition to Part I of the Tariff.94  Adding this proposed definition to Part I will allow more streamlined use of this term for Tariff, Part III and new Tariff, Part XI.

“Co-Located Load” shall mean a configuration that refers to
end-use customer load that is physically connected to the
facilities of an existing or planned Generating Facility on the
Project Developer’s side of the Point of Change in
Ownership to the Transmission Provider’s Transmission
System.

PJM is also including a definition of Co-Located Generating Facility (as augmented by the transition language referenced in the chart above) to allow more streamlined use of this term in Tariff Parts III, VIII, and new Part XI:

“Co-Located Generating Facility” shall mean an existing or
planned Generating Facility that is physically connected to a
Co-Located Load.
The modest change in the Co-Located Load definition from what is reflected in the Order to Show Cause by using “Point of Change in Ownership” is consistent with or superior to the Order’s use of the term “Point of Interconnection” for a number of reasons: clarity for the interconnection parties, ease of administration, and the realization of efficiencies for parties at the Regional Transmission Organization (“RTO”) level and before the Commission in the form of reduced litigation potential and costs (both in the form of alternative dispute resolution procedures and formal complaint and petition for

94 See Attachment A and B.

PDF page 32

declaratory order litigation).  The Commission should accept PJM’s modest clarifying revision to the definition.95

“Point of change in ownership” establishes the legal and financial boundary where, as a general matter, ownership responsibility, maintenance, and liability change between the utility and developer.  That point is clearly and plainly memorialized today (and long has been) in both existing Interconnection Service Agreements and the newer Generator Interconnection Agreements.  Interconnection facilities owned by the developer are identified and distinguished from interconnection facilities owned by the utility in the parties’ existing interconnection agreements.  Which interconnection party owns what facilities is an essential component of an interconnection agreement and promotes clarity about roles, responsibilities, and ownership.  Indeed, PJM’s proposed reforms to the Necessary Study Agreement and Generator Interconnection Agreement being filed in compliance with the Order to Show Cause leverage this term because to know where a proposed Co-Located Load is “physically connected to the facilities of an existing or planned Generating Facility,” the developer must identify the specific “Project Developer Interconnection Facilities” to which such load will be connected.

To be sure, “point of interconnection” is also a long-used and important term. While Point of Change in Ownership describes where a developer’s portion of the Interconnection Facilities connect to the Transmission Owner’s portion of the Interconnection Facilities, Point of Interconnection is a technical and physical term about “where” those Interconnection Facilities connect to the PJM Transmission System.  As

95 Proposed Tariff Revisions, Part I, Definition of Co-Located Load.

PDF page 33

such, using the term “Point of Change in Ownership” provides greater clarity regarding the location of Co-Located Load, compared to “Point of Interconnection.”

The helpful discussion of this issue in Docket No. ER26-1088 is corroborative of these points about the consistency with or superiority of PJM’s modest revisions to the definition of Co-Located Load by using the more precise “Point of Change in Ownership.” These concerns have benefited from discussion and further consideration, and PJM continues to support and files again here the modestly modified Co-Located Load definition also filed on January 20, 2026 for at least the following reasons. First, PJM has been focused on developing in consultation with stakeholders a compliance filing that can be efficiently implemented across the RTO and that is reflective of considerations of import to the Commission and to all affected stakeholders.  Because of the inherent clarity in the term, use of Point of Change in Ownership appears poised to reduce the need for unique, one-off Co-Located Load filings of the sort that the Commission has previously rejected96 in favor of rules of generic applicability within PJM’s Tariff.

Second, the Commission has broad authority to fashion a remedy under Section 206 of the Federal Power Act in a proceeding such as this and can accept PJM’s proposed modification on compliance.  Indeed, one stakeholder’s conditional protest in Docket No. ER26-1088 offers another alternative for the Commission to consider in reliance on this Commission authority.

Third, using the term Point of Change in Ownership is consistent with the parties’ existing PJM Service Agreements and affords greater certainty to all interconnection

96 See Docket No. ER24-2172.

PDF page 34

parties and reduces issues about what a “Point of Interconnection” is or is not that are likely to be litigated in RTO Alternative Dispute Resolution processes or before the Commission in formal regulatory litigation.  Parties today know what interconnection facilities they own and can plan the connection of Co-Located Load to such facilities accordingly.  The Docket No. ER26-1088 conditional protest does not appear inconsistent with recognizing the principle that Co-Located Loads should only interconnect to a Project Developer’s portion of the Interconnection Facilities.

As previously detailed in PJM’s January 20 compliance filing,97 which was about certain clarifications applicable only to Project Developers/Interconnection Customers seeking to serve Co-Located Load with new Generating Facilities (as opposed to existing Generating Facilities), PJM proposed a definition that uses the term “Point of Change in Ownership” rather than “Point of Interconnection” to comport with the use of this term in PJM’s new Generation Interconnection Process (“GIP”) set forth in Tariff, Parts VII and

VIII.  This use of terminology promotes alignment with PJM’s generator interconnection reform efforts, and promotes greater clarity for interconnection parties about the facilities to which Co-Located Load can attach.

Under PJM’s GIP, the Point of Change in Ownership represents the point where the change in ownership over the Interconnection Facilities occurs.  The Project Developer Interconnection Facilities are the segment of the Interconnection Facilities between a Generating Facility and the Point of Change in Ownership, and include “the facilities and equipment owned and/or controlled, operated and maintained by the Project Developer on Project Developer’s side of the Point of Changes in Ownership, including any

97 PJM Interconnection, L.L.C., et al., PJM’s Compliance Filing to the Order to Show Cause, Docket No. EL25-49-000, et al. (Jan. 20, 2026).

PDF page 35

modifications, additions, or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility.”     As set forth in this filing, an Existing Interconnection Customer seeking to develop a Co-Located Load configuration would be required to enter a superseding Generation Interconnection Agreement to reflect the results of the necessary studies, including the planned

modifications, additions, or upgrades to the Project Developer Interconnection Facilities, and identification of the Point of Change in Ownership.  The proposed changes comply with the Commission’s directive that PJM use the necessary studies process to evaluate the Project Developer’s planned modifications to its facilities, including changes to its Interconnection Facilities, in order to incorporate a Co-Located Load configuration.98

IV. REQUESTED EFFECTIVE DATE FOR TARIFF REVISIONS
Because the timing of PJM’s implementation date will depend in part on the
Commission’s issuance of an order or opinion on these Tariff revisions, as well as on the non-rate terms and conditions proposed in PJM’s Initial Brief, PJM’s effective date for the revisions proposed herein is uncertain.

Given this uncertainty, PJM has entered a placeholder effective date of 12/31/9998
for the tariff records associated with this proposal.  Once the Commission issues an order or opinion on this filing, and the non-rate terms and conditions subject to the paper hearing,

98 Order to Show Cause at P 227 (“We disagree with parties such as PIOs who claim that the necessary study process is inappropriate for generation interconnection modification to serve Co-Located Load.”); id. (“To the extent that PJM seeks to enhance the necessary study process, including as it gains experience evaluating requests from Interconnection Customers to modify their interconnection to serve Co-Located Load, PJM may submit such enhancements in an FPA section 205 filing.”); id. at P 225 ( “Based on our finding above that the PJM Tariff is unjust and unreasonable because it lacks sufficient clarity and consistency with respect to the rules for Co-Location Arrangements, we direct PJM to revise its Tariff to provide sufficient clarity regarding the responsibilities of existing Interconnection Customers seeking to serve Co-Located Load using their generating facilities.”) (emphasis added).

PDF page 36

and PJM’s ability to implement the proposal becomes clearer, PJM will submit a clean-up filing to enter the actual effective date.

As noted earlier, PJM anticipates needing to make subsequent conforming clean- up filings to the Tariff, Operating Agreement, and the RAA in regards to the compliance filings being submitted in response to the Order to Show Cause.  Based on continued stakeholder engagement and in the Commission’s active dockets, PJM may also seek leave to submit additional compliance filings to, among other things, streamline Commission resolution of issues and enhance Tariff clarity.99

V. DOCUMENTS ENCLOSED

In addition to this transmittal letter, PJM encloses the following:
1. Attachment A:
Tariff Revisions (Clean); and
2. Attachment B:
Tariff Revisions (Redline).

99 See also PJM’s Initial Brief at Part V.

PDF page 37

VI. CORRESPONDENCE AND COMMUNICATIONS

Correspondence and communications with respect to this filing should be sent to,
and PJM requests the Secretary to include on the official service list, the following:100

Craig Glazer
Vice President – Federal Government Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W., Suite 600
Washington, D.C. 20005
(202) 423-4743
Craig.Glazer@pjm.com

Mark J. Stanisz
Associate General Counsel
Thomas DeVita
Associate General Counsel
Chenchao Lu
Associate General Counsel
2750 Monroe Blvd,
Audubon, PA 19403
(610) 666-8800
Mark.Stanisz@pjm.com
Thomas.Devita@pjm.com
Chenchao.Lu@pjm.com

100 To the extent necessary, PJM requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3), to permit all of the persons listed to be placed on the official service list for this proceeding.

PDF page 38

VII. SERVICE

PJM has served a copy of this filing on all PJM Members and on the affected state utility regulatory commissions in the PJM Region by posting this filing electronically.  In accordance with the Commission’s regulations,101

PJM will post a copy of this filing to
the FERC filings section on its internet site, https://pjm.com/library/filing-order, and will send an email on the same date as this filing to all PJM Members and all state utility regulatory commissions in the PJM Region,102 alerting them that this filing has been made by PJM and is available by following such link.  If the document is not immediately available by using the referenced link, the document will be available through the referenced link within 24 hours of the filing.

101 See 18 C.F.R. §§ 35.2(e) & 385.2010(f)(3).
102 PJM already maintains, updates, and regularly uses email lists for all PJM Members and affected state commissions.

PDF page 39

VIII. CONCLUSION
PJM respectfully requests that the Commission accept the proposed revisions in accordance with the requirements of the Order to Show Cause.

Respectfully submitted,
/s/   Mark J. Stanisz

Craig Glazer
Vice President – Federal
Government Policy
PJM Interconnection, L.L.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 423-4743
craig.glazer@pjm.com

Mark J. Stanisz
Associate General Counsel
Thomas DeVita
Associate General Counsel
Chenchao Lu
Associate General Counsel
2750 Monroe Blvd,
Audubon, PA 19403
(610) 666-8800
mark.stanisz@pjm.com
thomas.devita@pjm.com
chenchao.lu@pjm.com

Counsel for PJM Interconnection, L.L.C.
February 23, 2026