Co-Located Load Tariff Revisions to Comply with Order in EL25-49, et al
Text extracted from the eLibrary original (SHA-256 d00276ca9e032489…). Download the original from the official source.
Contents · 18 sections
- I. INTRODUCTION AND BACKGROUND
- A. Commission Order
- B. Stakeholder Engagement
- III. DESCRIPTION OF PROPOSED TARIFF REVISIONS
- A. Revisions to Behind The Meter Generation (“BTMG”) Rules
- B. Transmission Services for Co-Located Load
- Attachment F-4. PJM is filing a “shell” of Attachment F-4, to show that the service
- Attachment F-4 is discussed in its Initial Brief.66
- C. Necessary Studies and Necessary Studies Agreement
- D. Other Tariff Revisions (Generation Interconnection Procedures, pro
- VIII. This use of terminology promotes alignment with PJM’s generator interconnection
- IV. REQUESTED EFFECTIVE DATE FOR TARIFF REVISIONS
- V. DOCUMENTS ENCLOSED
- Attachment A:
- Attachment B:
- VI. CORRESPONDENCE AND COMMUNICATIONS
- VII. SERVICE
- VIII. CONCLUSION
Read topic-matched comments in ER26-1479
Topics in the text: Connecting load and generation · Reliability and curtailment · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
In response to the Order to Show 1 16 U.S.C. § 824e. 2 Terms not otherwise defined herein shall have the same meaning as set forth in the Tariff.Read this passage Filed comments: Connecting load and generation
I. INTRODUCTION AND BACKGROUND
printed heading
INTRODUCTION AND BACKGROUND PJM understands the importance of, and remains committed to, advancing our nation’s leadership in connecting large loads, including supporting the development of Artificial Intelligence (“AI”) infrastructure.Read this passage
A. Commission Order
printed heading · Topic match: Connecting load and generation
Commission Order On December 18, 2025, the Commission issued the Order to Show Cause finding the Tariff unjust and unreasonable due to the lack of specificity for the rates, terms, and conditions that apply to Co-Located Load and directing PJM to make several compliance and informational filings.6…Read this passage Filed comments: Connecting load and generation
B. Stakeholder Engagement
printed heading · Topic match: Connecting load and generation
PJM appreciates the extensive stakeholder 7 PJM, Co-Located Load Order Workshop Meetings Materials (2026), https://www.pjm.com/committees- and-groups/workshops/cllsco (postings of Co-Located Load Order Workshop upcoming meetings schedule and past meeting materials on PJM’s website). 8 PJM,…Read this passage Filed comments: Connecting load and generation
III. DESCRIPTION OF PROPOSED TARIFF REVISIONS
printed heading
III.Read this passage
A. Revisions to Behind The Meter Generation (“BTMG”) Rules
printed heading · Topic match: Reliability and curtailment
Any facility that qualifies 28 Order to Show Cause at P 179. 29 Id. at P 222. as Retail Behind The Meter Generation shall be excluded from Co-Located Load configurations. a.Read this passage Filed comments: Reliability and curtailment
B. Transmission Services for Co-Located Load
printed heading · Topic match: Connecting load and generation
Transmission Services for Co-Located Load In compliance with the Order to Show Cause,52 PJM is proposing to add to its Tariff three new transmission services that an Eligible Customer taking transmission service on behalf of a Co-Located Load may select, in addition to existing Network Integration…Read this passage Filed comments: Connecting load and generation
Attachment F-4. PJM is filing a “shell” of Attachment F-4, to show that the service
printed heading
PJM is filing a “shell” of Attachment F-4, to show that the service agreement will be a new Attachment F-4,65 but notes that the proposed language ofRead this passage
Attachment F-4 is discussed in its Initial Brief.66
printed heading · Topic match: Connecting load and generation
Id. at P 193. requirements such as designation of an Eligible Customer and the individual Co-Located Load.75 PJM also clarifies that the Network Integration Transmission Service that is applicable to Eligible Customers taking transmission service on behalf of Co-Located Load shall be Regional…Read this passage Filed comments: Connecting load and generation
C. Necessary Studies and Necessary Studies Agreement
printed heading · Topic match: Connecting load and generation
Reform of Generator Interconnection Procedures and Agreements, Order No. 845-A, 166 FERC ¶ 61,137, at P 116 (2019) (“if the interconnection customer requests interconnection service below generating capacity, it commits to operate consistent with such a request under section 3.1 of the pro forma…Read this passage Filed comments: Connecting load and generation
D. Other Tariff Revisions (Generation Interconnection Procedures, pro
printed heading · Topic match: Connecting load and generation
FERC Requirement How PJM Complies Revise Tariff, Part VIII to add to the list of requirements for a New Service Request that an Interconnection Customer who will use its generating facility to serve Co-Located Load must specify an Eligible Customer who will take transmission service on behalf of…Read this passage Filed comments: Connecting load and generation
VIII. This use of terminology promotes alignment with PJM’s generator interconnection
printed heading · Topic match: Connecting load and generation
This use of terminology promotes alignment with PJM’s generator interconnection reform efforts, and promotes greater clarity for interconnection parties about the facilities to which Co-Located Load can attach.Read this passage Filed comments: Connecting load and generation
IV. REQUESTED EFFECTIVE DATE FOR TARIFF REVISIONS
printed heading · Topic match: Connecting load and generation
Once the Commission issues an order or opinion on this filing, and the non-rate terms and conditions subject to the paper hearing, 98 Order to Show Cause at P 227 (“We disagree with parties such as PIOs who claim that the necessary study process is inappropriate for generation interconnection…Read this passage Filed comments: Connecting load and generation
V. DOCUMENTS ENCLOSED
printed heading
DOCUMENTS ENCLOSED In addition to this transmittal letter, PJM encloses the following: 1.Read this passage
Attachment A:
printed heading
Attachment A: Tariff Revisions (Clean); and 2.Read this passage
Attachment B:
printed heading
Attachment B: Tariff Revisions (Redline). 99 See also PJM’s Initial Brief at Part V.Read this passage
VI. CORRESPONDENCE AND COMMUNICATIONS
printed heading
CORRESPONDENCE AND COMMUNICATIONS Correspondence and communications with respect to this filing should be sent to, and PJM requests the Secretary to include on the official service list, the following:100 Craig Glazer Vice President – Federal Government Policy PJM Interconnection, L.L.C. 1200 G…Read this passage
VII. SERVICE
printed heading
SERVICE PJM has served a copy of this filing on all PJM Members and on the affected state utility regulatory commissions in the PJM Region by posting this filing electronically.Read this passage
VIII. CONCLUSION
printed heading
CONCLUSION PJM respectfully requests that the Commission accept the proposed revisions in accordance with the requirements of the Order to Show Cause.Read this passage