Attachment A - New Transmission Services Tariff Sheets
PDF page 1
Attachment A
Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and
Other Illustrative Tariff Revisions
PDF page 2
1
Tariff, Part XI
Transmission Services Available for Eligible Customers Taking Service
on Behalf of Co-Located Loads
Subpart A – Interim Network Integration Transmission Service
700 Provision of Interim Network Integration Transmission Service
The Transmission Provider may provide Interim Network Integration Transmission Service to an Eligible Customer requesting Network Integration Transmission Service on behalf of a Co- Located Load pursuant to the applicable terms and conditions contained in the Tariff and the Service Agreement for Interim Network Integration Transmission Service, which is provided in Attachment F-3A. PJMSettlement shall be the Counterparty to the Interim Network Integration Transmission Service transactions under this Tariff.
Requests for Interim Network Integration Transmission Service must be made through the Transmission Provider. These requests shall require the filing of an Application as set forth in Tariff, Part XI, Subpart A, section 702 and be submitted in accordance with the applicable terms and conditions in the Tariff.
701 Nature of Interim Network Integration Transmission Service
701.1 Scope of Service
Interim Network Integration Transmission Service is a transmission service that allows an Eligible Customer taking service on behalf of a Co-Located Load that has requested Network Integration Transmission Service pursuant to Tariff, Part III, to receive transmission service on behalf of a Co-Located Load on a non-firm, interruptible basis for the period until the transmission upgrades required to provide the requested level of Network Integration Transmission Service are completed and placed in service. Such upgrades required to provide the requested level of Network Integration Transmission Service, along with the expected in-service dates, shall be set forth in the Service Agreement for Interim Network Integration Transmission Service.
Once the required transmission upgrades are completed and placed in service, according to the terms of the Service Agreement for Interim Network Integration Transmission Service in Attachment F-3A, the transmission service provided to the Eligible Customer will automatically convert from Interim Network Integration Transmission Service to Network Integration Transmission Service. As a result, the Co-Located Load will be designated as Network Load under Tariff, Part III, section 31.1.
An Eligible Customer taking transmission service on behalf of a Co-Located Load may not take Network Integration Transmission Service or Interim Network Integration Transmission Service for that Co-Located Load at the same time it is taking Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service on behalf of that Co-Located Load. The Eligible Customer taking Interim Network Integration Transmission Service must obtain or provide Ancillary Services pursuant to Tariff, Part I, section 3.
PDF page 3
2
701.2 Interim Network Integration Transmission Service
The Transmission Provider may provide non-firm, interruptible transmission service over the Transmission System to the Eligible Customer for the delivery of capacity and energy to serve the Co-Located Load.
701.3 Restrictions on Use of Service
The Eligible Customer shall not use Interim Network Integration Transmission Service for (i) sales of capacity and energy to loads other than the Co-Located Load designated in its Service Agreement for Interim Network Integration Transmission Service, or (ii) direct or indirect provision of transmission service by the Eligible Customer to third parties. 701.4 Termination of Interim Network Integration Transmission Service
The provision of Interim Network Integration Transmission Service shall terminate upon completion of all upgrades identified in the Service Agreement for Interim Network Integration Transmission Service necessary to provide Eligible Customer with Network Integration Transmission Service under Tariff, Part III, according to the terms of the Service Agreement.
702 Initiating Service
702.1 Conditions Precedent for Receiving Service
Subject to the terms and conditions of Tariff, Part XI, the Transmission Provider may provide Interim Network Integration Transmission Service to any Eligible Customer taking transmission service on behalf of Co-Located Load, provided that:
(i) The Eligible Customer has been designated to take transmission service on behalf of a Co-Located Load in the relevant Application, Service Agreement, or the Generation Interconnection Agreement for the Co-Located Generating Facility;
(ii) The Eligible Customer has provided the information specified in, and otherwise complied with, the “PJM Credit Policy” set forth in Tariff, Attachment Q hereto;
(iii) The Eligible Customer executes a Service Agreement for Interim Network Integration Transmission Service with the Transmission Provider pursuant to Tariff, Attachment F-3A, or requests in writing that the Transmission Provider file a proposed unexecuted Service Agreement for Interim Network Integration
Transmission Service;
(iv) The Eligible Customer has certified, in accordance with the PJM Manuals, that it is willing and able to limit energy withdrawals from the Transmission System when requested by the Transmission Provider; and
(v) An Eligible Customer requesting Interim Network Integration Transmission Service and taking Interim Network Integration Transmission Service shall otherwise execute, if necessary, and comply with the PJM Governing Agreements. The Eligible Customer shall submit an Application under this section 702.
PDF page 4
3
702.2 Application Procedures
An Eligible Customer seeking Network Integration Transmission Service may apply for Network Integration Transmission Service and Interim Network Integration Transmission Service at the same time. However, an Eligible Customer shall not apply for Interim Network Integration Service without applying for Network Integration Transmission Service.
To apply for Interim Network Integration Transmission Service, an Eligible Customer must pay a study fee under Tariff, Part XI, Subpart A, section 704.2, which is in addition to the study fee required under an Application for Network Integration Transmission Service under Tariff, Part III, section 32.2.
702.3 Determination of Whether Interim Network Integration Transmission Service Can Be Reliably Provided
The Transmission Provider, in consultation with the affected Transmission Owner(s), will determine the amount of Interim Network Integration Transmission Service that can be provided to an Eligible Customer, including through the use of temporary solutions, while maintaining the reliability of the Transmission System. This determination will consider the results of the study procedures set forth in Tariff, Part XI, Subpart A, section 704.
702.4 Technical Requirements Prior to Commencement of Service
Interim Network Integration Transmission Service shall not commence until the Transmission Provider, the affected Transmission Owner(s), and the Eligible Customer, or a third party, have completed installation of all equipment specified under the Service Agreement for Interim Network Integration Transmission Service, consistent with Good Utility Practice and any additional requirements reasonably and consistently imposed to ensure the reliable operation of the Transmission System. The Transmission Provider and the affected Transmission Owner(s) shall exercise reasonable efforts, in coordination with the Eligible Customer, to complete such arrangements as soon as practicable taking into consideration the Service Commencement Date. These technical requirements include, but are not limited to: (i) installation of necessary hardware and software to limit energy withdrawals, including metering equipment; (ii) provision of an operational contact and backup contact for the Eligible Customer, available twenty-four (24) hours a day and seven (7) days a week; (iii) certification from the Eligible Customer that it is staffed with PJM Certified Operators pursuant to PJM Manual 40; (iv) demonstration from the Eligible Customer of its ability to receive voice and electronic signals from the Transmission Provider; (v) demonstration that the Eligible Customer has operational control to respond to operating instructions from the Transmission Provider to reduce or disconnect the Co-Located Load within five (5) minutes or as specified in PJM Manuals; and (vi) demonstration that the Eligible Customer has operational control of the necessary control technologies and protection systems set forth in Tariff, Part XI, Subpart A, section 705, as applicable.
702.5 Eligible Customer Facilities
The provision of Interim Network Integration Transmission Service shall be conditioned upon the Eligible Customer constructing, maintaining, and operating the facilities on its side of the Delivery Point necessary to reliably deliver capacity and energy from the Transmission Provider’s Transmission System to the Eligible Customer or, with respect to service provided pursuant to a
PDF page 5
4
state required retail access program, for otherwise arranging for the delivery of its energy from the Delivery Point or interconnection. The Eligible Customer shall be solely responsible for constructing or installing all facilities on the Eligible Customer’s side of such Delivery Point or, with respect to service provided pursuant to a state required retail access program, for otherwise arranging for the delivery of its energy from the Delivery Point or interconnection. 702.6 Filing of Service Agreement
The Transmission Provider will file the Service Agreement for Interim Network Integration Transmission Service, provided in Attachment F-3A, with the Commission in compliance with applicable Commission regulations.
703 Designation of Co-Located Load
703.1 Co-Located Load
The Eligible Customer must designate the individual Co-Located Load on whose behalf the Transmission Provider will provide Interim Network Integration Transmission Service. The Co-Located Load shall be specified in the Service Agreement for Interim Network Integration Transmission Service except with respect to loads served pursuant to state required retail access programs for which the Transmission Customer shall provide information regarding Network Loads using the Transmission Provider’s specified electronic information system for such programs in accordance with the Service Agreement.
703.2 New Co-Located Loads Connected with the Transmission Provider
Prior to the Service Commencement Date of Network Integration Transmission Service, if an Eligible Customer designates a new Co-Located Load, or increases the size of the designated Co- Located Load, the new Co-Located Load shall be studied pursuant to a new Application. 703.3 Information Updates
The Eligible Customer shall provide the Transmission Provider with annual updates of (i) the demand characteristics of the Co-Located Load, and (ii) the supply characteristics of the Co- Located Generating Facility, both consistent with those included in its Application for Network Integration Transmission Service under Tariff, Part III, Section 31.6.
In addition, the Eligible Customer also shall have an ongoing obligation to provide the Transmission Provider with timely written or electronic notice of material changes in the foregoing sentence as well as any other information listed in Tariff, Part XI, Subpart A, section 702 or provided in its Application for Network Integration Transmission Service pursuant to Tariff, Part III, section 31.6 relating to the Eligible Customer’s Co-Located Load or other aspects of its facilities or operations affecting the Transmission Provider’s ability to provide reliable service. Failure to timely inform the Transmission Provider of a material change in (i) the demand characteristics of the Co-Located Load, or (ii) the supply characteristics of the Co-Located Generating Facility may constitute a breach of the Eligible Customer’s Service Agreement.
PDF page 6
5
704 Study Procedures for Interim Network Integration Transmission Service Requests 704.1 Notice of Need for Study
After receiving a request for Interim Network Integration Transmission Service, the Transmission Provider shall determine on a non-discriminatory basis whether additional studies are needed beyond what was required to evaluate the Eligible Customer’s request for Network Integration Transmission Service.
If the Transmission Provider determines that additional studies are necessary to evaluate the requested service, it shall inform the Eligible Customer of those studies as soon as practicable. In such cases, the Transmission Provider shall, within thirty (30) days of receipt of a Completed Application, tender an Application and Studies Agreement pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider for the required studies. For a service request to remain a Completed Application, the Eligible Customer shall execute the Application and Studies Agreement and return it to the Transmission Provider within fifteen (15) days and provide a study fee pursuant to Tariff, Part XI, Subpart A, section 704.2. If the Eligible Customer elects not to execute the Application and Studies Agreement, its Application for Interim Network Integration Transmission Service shall be deemed withdrawn and its study fee shall be returned with interest.
704.2 Study Fee for Interim Network Integration Transmission Service
Eligible Customer shall pay a study fee, as determined by the Transmission Provider, to apply for Interim Network Integration Transmission Service.
705 Load Shedding and Curtailments
705.1 General
Prior to the Service Commencement Date, the Eligible Customer shall demonstrate its ability to fully comply with the Load Shedding and Curtailment procedures pursuant to this section 705, and the Service Agreement for Interim Network Integration Transmission Service. The Eligible Customer shall implement any Load Shedding and/or Curtailment directive given by Transmission Provider. To the extent practicable, the Transmission Provider will notify the Eligible Customer of any Curtailment in a timely manner. The Eligible Customer must respond to any real time instructions to curtail or otherwise reduce load within five (5) minutes. Curtailments will be made on a non-discriminatory basis. Any requests by the Transmission Provider to Curtail will be consistent with Good Utility Practice.
705.2 Curtailment of Interim Network Integration Transmission Service
Interim Network Integration Transmission Service shall be Curtailed before Firm Contract Demand Transmission Service and Network Integration Transmission Service. The Transmission Provider may curtail Interim Network Integration Transmission Service prior to dispatching the Pre-Emergency Load Response Program as further set forth in the PJM Manuals, or in response to a transfer capability shortage as a result of system reliability conditions.
PDF page 7
6
705.3 Load Shedding
To the extent that a system contingency exists on the Transmission Provider’s Transmission System and the Transmission Provider determines that it is necessary for the Transmission Owners and the Eligible Customer taking Interim Network Integration Transmission Service to shed load, the Eligible Customer and the Transmission Owners shall shed load in accordance with previously established procedures under the Service Agreement for Interim Network Integration Transmission Service and the PJM Manuals.
705.4 System Reliability
Notwithstanding any other provisions of this Tariff, the Transmission Provider reserves the right, consistent with Good Utility Practice and on a not unduly discriminatory basis, to Curtail Interim Network Integration Transmission Service without liability on the Transmission Provider’s part for the purpose of making necessary adjustments to, changes in, or repairs on its lines, substations and facilities, and in cases where the continuance of Interim Network Integration Transmission Service would endanger persons or property. In the event of any adverse condition(s) or disturbance(s) on the Transmission Provider’s Transmission System or on any other system(s) directly or indirectly interconnected with the Transmission Provider’s Transmission System, the Transmission Provider, consistent with Good Utility Practice, also may Curtail Interim Network Integration Transmission Service in order to (i) limit the extent or damage of the adverse condition(s) or disturbance(s); (ii) prevent damage to generating or transmission facilities; or (iii) expedite restoration of service. The Transmission Provider will give the Eligible Customer as much advance notice as is practicable in the event of such Curtailment.
705.5 Necessary Control Technologies and Protection Systems
To ensure protection of the Transmission System, and to ensure that the Eligible Customer taking Interim Network Integration Transmission Service on behalf of a Co-Located Load limits its energy withdrawals from the Transmission System to its approved level of Interim Network Integration Transmission Service, including during a period in which the Transmission Provider has directed Curtailment or Load Shedding, prior to the Service Commencement Date, the Transmission Provider, affected Transmission Owner(s), and the Eligible Customer shall establish necessary control technologies and protection systems in accordance with the PJM Manuals, which may include a Remedial Action Scheme, for each Service Agreement for Interim Network Integration Transmission Service. The necessary control technologies and protection systems must be developed in accordance with the PJM Manuals and be approved by the Transmission Provider. The necessary control technologies and protection systems may be functionally modified from time to time in accordance with the PJM Manuals. Any functional modification to the necessary control technologies and protection systems must be developed with the affected Transmission Owner(s) and, before taking effect, such functional modification must be approved by the Transmission Provider.
705.6 Consequences of Failure to Follow Instructions or Misoperation of Necessary Control Technologies and Protection Systems
(a) In the first instance that an Eligible Customer fails to respond to established Load Shedding and Curtailment procedures, as set forth in this section 705, the Eligible Customer shall be disqualified from taking Interim Network Integration Transmission Service.
PDF page 8
7
(b) In the first instance that a necessary control technology or protection system for a given Service Agreement misoperates, the Eligible Customer shall be prohibited from taking transmission service under its Service Agreement or otherwise withdrawing energy from the Transmission System for a period of up to one hundred and twenty (120) days from such event, which may be shortened or extended per mutual agreement, to allow for an analysis of the such event, which may be shortened or extended per mutual agreement, to allow for an analysis of the operational performance of the necessary control technologies and protection systems. In the second instance that an Eligible Customer’s necessary control technology or protection system associated with a Service Agreement misoperates, the Eligible Customer shall be disqualified from taking Interim Network Integration Transmission Service.
(c) Following disqualification in accordance with subsections (a) or (b) above, to receive transmission service on behalf of the subject Co-Located Load, the Eligible Customer may only take Network Integration Transmission Service and such service may only commence after all upgrades necessary for the Transmission Provider to provide Network Integration Transmission Service are placed into service.
705.7 Penalty for Unreserved Use of Interim Network Integration Transmission Service [Reserved]
706 Rates and Charges
706.1 Monthly Demand Charge
[Reserved]
706.2 Redispatch Charge
The Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in Tariff, Attachment K.
706.3 Stranded Cost Recovery
Any Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant to this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. 888. However, the Transmission Owner must separately file any proposal to recover stranded costs under section 205 of the Federal Power Act.
706.4 Other Charges
Eligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, Schedule 9; and Tariff, Schedule 10, consistent with the charges assessed to loads taking Network Integration Transmission Service.
Eligible Customer shall pay Ancillary Services charges in accordance with Tariff, Part I, section 3. Eligible Customer shall pay Black Start Service charges in accordance with Tariff, Schedule 6A.
PDF page 9
8
707 Operating Agreement
707.1 Operation under The Operating Agreement
The Eligible Customer shall plan, construct, operate, and maintain its facilities in accordance with Good Utility Practice and in conformance with the Operating Agreement.
The terms and conditions under which the Eligible Customer shall operate its facilities and the technical and operational matters associated with the implementation of Tariff, Part XI shall be specified in the Operating Agreement.
The Operating Agreement shall provide for the Eligible Customer and Transmission Provider to
(i) operate and maintain equipment necessary for integrating the Eligible Customer within the Transmission Provider’s Transmission System (including, but not limited to, remote terminal units, metering, communications equipment and relaying equipment); (ii) transfer data between the Transmission Provider and the Eligible Customer (including, but not limited to, heat rates and operational characteristics of Network Resources, generation schedules for units outside the Transmission Provider’s Transmission System, interchange schedules, required unit outputs for redispatch, voltage schedules, loss factors and other real time data); (iii) use software programs required for data links and constraint dispatching; (iv) exchange data on forecasted loads and resources necessary for long-term planning; and (v) address any other technical and operational considerations required for implementation of Tariff, Part XI, including scheduling protocols.
PDF page 10
9
Subpart B – Contract Demand Transmission Services
708 Provision of Contract Demand Transmission Services
(a) The Transmission Provider will provide Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, to an Eligible Customer taking service on behalf of a Co-Located Load pursuant to the applicable terms and conditions contained in Tariff, Part XI and the Service Agreement for Contract Demand Transmission Services, provided in Attachment F-4. Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service are for an Eligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit withdrawals of energy from the Transmission System when required by the Transmission Provider.
(b) Firm Contract Demand Transmission Service is for the transfer of capacity and energy to an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, predetermined megawatt level of transmission service as requested by the Eligible Customer and confirmed by the Transmission Provider, using capacity and energy procured by the Transmission Provider. Non-Firm Contract Demand Transmission Service is for the transmission of energy to an Eligible Customer on behalf of a designated Co-Located Load, on an as-available basis, up to a defined, predetermined megawatt level of transmission service as requested by the Eligible Customer and confirmed by the Transmission Provider, using energy procured by the Transmission Provider. PJMSettlement shall be the Counterparty to the Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service transactions under this Tariff.
(c) Prior to the Commencement of Service, for an Eligible Customer to take Non-Firm Contract Demand Transmission Service on behalf of a Co-Located Load, the Eligible Customer must demonstrate the implementation of the necessary control technologies and protection systems, approved by the Transmission Provider to allow the Eligible Customer to effectively limit withdrawals from the Transmission System to serve such Co-Located Load.
(d) Requests for Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, must be made through the Transmission Provider. These requests shall (i) require the filing of an Application as set forth in Tariff, Part XI, Subpart B, section 710.1 and Tariff, Part XI, Subpart B, section 710.2, and (ii) be submitted in accordance with the applicable terms and conditions in the Tariff.
709 Nature of Firm and Non-Firm Contract Demand Transmission Service
709.1 Priority of Service
Firm Contract Demand Transmission Service will always have priority over Non-Firm Contract Demand Transmission Service under the Tariff. All Firm Contract Demand Transmission Service will have equal priority with Network Integration Transmission Service.
PDF page 11
10
709.2 Scope of Service
(a) Firm Contract Demand Transmission Service is a transmission service that allows an Eligible Customer taking service on behalf of a Co-Located Load to receive firm transmission service on behalf of that Co-Located Load up to a defined, predetermined megawatt level of service pursuant to the applicable terms and conditions contained in the Tariff and the Service Agreement for Contract Demand Transmission Service provided in Tariff, Attachment F-4. An Eligible Customer taking service on behalf of a Co-Located Load must apply for Firm Contract Demand Transmission Service for no less than the megawatt level of the gross demand of the Co-Located Load that will not be served by the dedicated level of energy from the Co-Located Generating Facility.
(b) Non-Firm Contract Demand Transmission Service is a transmission service that allows an Eligible Customer taking service on behalf of Co-Located Loads to obtain non-firm, interruptible transmission service on behalf of a Co-Located Load in the event the Co-Located Generating Facility is on outage and unable to provide any of the dedicated level of energy, and receive that service up to defined, predetermined megawatt level of service pursuant to the applicable terms and conditions contained in the Tariff and Service Agreement for Contract Demand Transmission Service, provided in Tariff Attachment F-4. An Eligible Customer taking service on behalf of a Co-Located Load must apply for Non-Firm Contract Demand Transmission Service equivalent to the megawatt level of the Co-Located Generating Facility dedicated to serving the Co-Located Load; provided however, that the level of service required under the foregoing may be reduced to the extent the amount of Firm Contract Demand Transmission Service contracted exceeds megawatt level of the gross demand of the Co-Located Load that will not be served by the dedicated level of energy from the Co-Located Generating Facility. An Eligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage.
(c) The cumulative amount of Firm Contract Demand Transmission Service and Non- Firm Contract Demand Transmission Service requested by the Eligible Customer on behalf of the Co-Located Load must equal the entire gross demand of the Co-Located Load.
(d) For any given Co-Located Load, once an Eligible Customer has taken, or is applying for, Network Integration Transmission Service or Interim Network Integration Transmission Service on behalf of such Co-Located Load, an Eligible Customer shall not be eligible to apply for or take Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service for that same Co-Located Load.
(e) After an Eligible Customer has submitted an Application for Contract Demand Transmission Service for a given Co-Located Load, any material change in the megawatt level of the gross-demand of the Co-Located Load or in the megawatt level of the Co-Located Generating Facility dedicated to the Co-Located Load would require a new Application.
709.3 Restrictions on Use of Service
The Eligible Customer shall not use Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service for (i) sales of capacity and energy to loads other than the
PDF page 12
11
Co-Located Load designated in its Service Agreement for Contract Demand Transmission Service, or (ii) direct or indirect provision of transmission service by the Eligible Customer to third parties. 709.4 Anti-Toggling Provision
To the extent permitted in accordance with section 709.2, for the portion of the Co-Located Load served by Firm Contract Demand Transmission Service, the Eligible Customer, or its successor, shall not seek Non-Firm Contract Demand Transmission Service for five (5) years following the effective date of the Service Agreement for Contract Demand Transmission Service. However, the foregoing limitation in this subsection shall not apply in the event of (i) a physical change to the Co-Located Generating Facility that would materially and permanently alter the megawatt level dedicated to the Co-Located Load, or (ii) a physical change to the Co-Located Load that would materially and permanently alter the megawatt level of its gross demand.
710 Initiating Service
710.1 Conditions Precedent for Receiving Service
Subject to the terms and conditions of Tariff, Part XI, the Transmission Provider will provide Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, to any Eligible Customer taking transmission service on behalf of Co-Located Load, provided that:
(i) The Eligible Customer has been designated to take transmission service on behalf of a Co-Located Load in the relevant Application, Service Agreement, or the Generation Interconnection Agreement for the Co-Located Generating Facility;
(ii) The subject Co-Located Load has not been served by any Eligible Customer on behalf of such Co-Located Load taking, or applying to take, Network Integration Transmission Service or Interim Network Integration Transmission Service;
(iii) The Eligible Customer has provided the information specified in, and otherwise complied with, the “PJM Credit Policy” set forth in Tariff, Attachment Q hereto;
(iv) The Eligible Customer has executed a Service Agreement for Contract Demand Transmission Service with the Transmission Provider pursuant to Tariff,
Attachment F-4, or requests in writing that the Transmission Provider file a proposed unexecuted Service Agreement for Contract Demand Transmission
Service; such Service Agreement shall include (a) for Non-Firm Contract Demand Transmission Service, the operational procedures necessary to implement
necessary control technologies and protection systems approved by the
Transmission Provider that will limit energy withdrawals consistent with the terms of the Service Agreement; and (b) its agreement to be curtailed under certain conditions set forth in the Service Agreement and in the PJM Tariff;
(v) The Eligible Customer has certified, in accordance with the PJM Manuals, that it is willing and able to limit energy withdrawals from the Transmission System when requested by the Transmission Provider;
(vi) The Eligible Customer must, in accordance with the PJM Manuals, submit to the Transmission Provider an authorization or certification from its Relevant Electric
PDF page 13
12
Retail Regulatory Authority which affirms that the Eligible Customer is authorized to provide energy to the Co-Located Load; and
(vii) Eligible Customer has completed other certification requirements provided in the PJM Manuals, including to be an Electric Distributor, as applicable; and
(viii) The Eligible Customer taking Contract Demand Transmission Service on behalf of a Co-Located Load shall otherwise execute, if necessary, and comply with the PJM Governing Agreements.
710.2 Application Procedures
An Eligible Customer may apply for Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, to take service on behalf of a Co-Located Load. The entire gross demand of the Co-Located Load must be served by a combination of Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service. To the extent the dedicated portion of the Co-Located Generating Facility does not meet the entire gross demand of the Co-Located Load, an Eligible Customer seeking Contract Demand Transmission Service must apply for: (i) Firm Contract Demand Transmission Service for at least the portion of the gross demand of the Co-Located Load not served by dedicated output from the Co-Located Generating Facility; and (ii) Non-Firm Contract Demand Transmission Service for the portion of the gross demand of the Co-Located Load served by dedicated output from the Co- Located Generating Facility; provided however, that the level of Non-Firm Contract Demand Transmission Service required may be reduced to the extent the amount of Firm Contract Demand Transmission Service contracted exceeds megawatt level of the gross demand of the Co-Located Load that will not be served by the dedicated level of energy from the Co-Located Generating Facility.
If requested by the Transmission Provider, an Application for Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service shall provide all of the information included in 18 C.F.R. § 2.20, including but not limited to the following:
(i) The identity, address, email address, and telephone number of the entity requesting service;
(ii) A statement that the entity requesting service is, or will be upon Commencement of Service, an Eligible Customer under the Tariff;
(iii) A demonstration that the Co-Located Load on behalf of which the Eligible Customer is seeking to obtain service and the Co-Located Generating Facility are located on the same side of the Delivery Point to the Transmission Provider’s Transmission System as the Co-Located Load;
(iv) A description of the supply characteristics of the Co-Located Generating Facility identified in subsection (iii) above, including the generation profile, its Maximum Facility Output, the megawatt level dedicated to serving the Co-Located Load, and other technical specifications as may be requested by the Transmission Provider;
(v) A description of the demand characteristics of the Co-Located Load identified in subsection (iii) above, including the demand profile and other technical
specifications as may be requested by the Transmission Provider;
PDF page 14
13
(vi) The requested Service Commencement Date;
(vii) The transmission capacity requested for the Delivery Point on the Transmission Provider’s Transmission System behind which the Co-Located Load and Co-Located Generating Facility are located; and
(viii) Any additional information required by the Transmission Provider.
The Transmission Provider shall treat this information consistent with the standards of conduct contained in Part 37 of the Commission’s regulations.
If an Application fails to meet the requirements of the Tariff, the Transmission Provider shall notify the Eligible Customer requesting service within fifteen (15) days of receipt of the reasons for such failure. The Transmission Provider will attempt to remedy minor deficiencies in the Application through informal communications with the Eligible Customer. If such efforts are unsuccessful, the Transmission Provider shall return the Application, along with any deposit, with interest. Upon receipt of a new or revised Application that fully complies with the requirements of this section 710, the Eligible Customer shall be assigned a new queued time and/or Project Identifier, as applicable, consistent with the date of the new or revised Application. 710.3 Determination of Whether Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service Can Be Reliably Provided
Pursuant to Tariff, Part XI, Subpart B, section 712, Transmission Provider will coordinate with the affected Transmission Owner(s) to complete studies, including load integration studies, which will provide data relevant to the determination of whether (and to what level as applicable) (i) Firm Contract Demand Transmission Service can be reliably provided and identify any necessary enhancements to the Transmission System to accommodate the requested level of service, and/or
(ii) Non-Firm Contract Demand Transmission Services can be reliably provided. During this study period, Transmission Provider may also perform other studies.
Following completion of all studies, Transmission Provider will make the determination, in consultation with the affected PJM Transmission Owner(s), about whether (and to what level as applicable) Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Services can be reliably provided for an Application, and if so, what level of service may be provided.
If the Transmission Provider determines that only a portion of the Non-Firm Contract Demand Transmission Service requested by Eligible Customer can be provided reliably, the Transmission Provider will provide a written explanation of its reasons for partial denial of service. In such an event, the Eligible Customer must apply for either (i) Firm Contract Demand Transmission Service for the balance of the gross demand of its Co-Located Load, consistent with Tariff, Part XI, Subpart B, section 709.2, or (ii) Network Integration Transmission Service under Tariff, Part III. If the Transmission Provider determines that no level of Non-Firm Contract Demand Transmission Service requested by Eligible Customer can be provided reliably, the Transmission Provider will provide a written explanation of its reasons for denial of service. In such an event, to receive Contract Demand Transmission Service, the Eligible Customer must apply for either (i) Firm Contract Demand Transmission Service for the entire gross demand of its Co-Located Load,
PDF page 15
14
consistent with Tariff, Part XI, Subpart B, section 709.2, or (ii) Network Integration Transmission Service under Tariff, Part III.
Descriptions of the Transmission Provider’s and/or the applicable Transmission Owner(s)’ specific methodology for assessing whether Firm Contract Demand Transmission Service or Non- Firm Contract Demand Transmission Service, or both, can be reliably provided, will be set forth in Tariff, Part XI, Subpart B, section 712, in the PJM Manuals, and in Transmission Owner standards, as applicable.
710.4 Technical Requirements Prior to Commencement of Service
Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service shall not commence until the Transmission Provider, the affected Transmission Owner(s), and the Eligible Customer, or a third party, have completed installation of all equipment specified under the Service Agreement for Contract Demand Transmission Service, as provided in Attachment F-4, consistent with Good Utility Practice and any additional requirements reasonably and consistently imposed to ensure the reliable operation of the Transmission System. The Transmission Provider and the affected Transmission Owner(s) are to complete such arrangements as soon as practicable taking into consideration the Service Commencement Date. As applicable, these technical requirements may include, but are not limited to: (i) installation of necessary hardware and software to limit energy withdrawals, including metering equipment and any facilities necessary to implement the necessary control technologies and protection systems associated with the provisions of Non-Firm Contract Demand Transmission Service set forth in the Service Agreement for Contract Demand Transmission Service; (ii) provision of an operational contact and backup contact for the Eligible Customer, available twenty-four (24) hours a day and seven (7) days a week; (iii) certification from the Eligible Customer that it is staffed with PJM Certified Operators (PJM Manual 40); (iv) demonstration from the Eligible Customer of its ability to receive voice and electronic signals from the Transmission Provider; (v) demonstration that the Eligible Customer has operational control to respond to operating instructions from the Transmission Provider to reduce energy withdrawals or disconnect the Co-Located Load; and (vi) as applicable, demonstration that the Eligible Customer has operational control of the necessary control technologies and protection systems required pursuant to Tariff, Part XI, Subpart B, section 713 and set forth in the Service Agreement for Contract Demand Transmission Service. 710.5 Eligible Customer Facilities and Network Facilities
The provision of Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, shall be conditioned upon the Eligible Customer constructing, maintaining, and operating the facilities (i) on its side of the Delivery Point necessary to reliably deliver and receive energy and capacity; and (ii) only in the case of Non-Firm Contract Demand Transmission Service, to implement the necessary control technologies and protection systems required pursuant to Tariff, Part XI, Subpart B, section 713 and specified in the Service Agreement for Contract Demand Transmission Service, as Transmission Provider may require. As set forth in the Service Agreement for Contract Demand Transmission Service, the Eligible Customer may also be responsible for the cost of network upgrades from the Transmission Provider’s Transmission System to the Delivery Point. In the case of Firm Contract Demand
PDF page 16
15
Transmission Service, the Transmission Provider shall be responsible for ensuring the Transmission System can deliver and receive energy and capacity to the Delivery Point. The Eligible Customer shall be solely responsible for constructing or installing all facilities on the Eligible Customer’s side of each such Delivery Point or, with respect to service provided pursuant to a state required retail access program, for otherwise arranging for the delivery of its energy from the Delivery Point.
710.6 Execution and Filing of Service Agreement
The Transmission Provider will file the Service Agreement for Contract Demand Transmission Service, as set forth in Attachment F-4, with the Commission in compliance with applicable Commission regulations, and subject to the provisions below.
(a) Transmission Provider shall provide the final Service Agreement for Contract Demand Transmission Service, along with any applicable schedules, to the parties in electronic form. Not later than fifteen (15) Business Days after receipt of the Service Agreement for Contract Demand Transmission Service, Eligible Customer shall:
(i) execute the final Service Agreement for Contract Demand Transmission
Service in electronic form and return it to Transmission Provider
electronically;
(ii) request in writing dispute resolution as allowed under Tariff, Part I,
section 12; or
(iii) request in writing that Transmission Provider file with the Commission the final Service Agreement for Contract Demand Transmission Service in
unexecuted form. The unexecuted Service Agreement for Contract Demand
Transmission Service shall contain terms and conditions deemed
appropriate by Transmission Provider for the Application.
As needed for Firm Contract Demand Transmission Service, the Eligible Customer shall also provide any required adjustments to Security for facility upgrades.
(b) If the Eligible Customer determines that final agreement negotiations are at an impasse, the Eligible Customer shall notify Transmission Provider of the impasse, and Eligible Customer may request Transmission Provider to file the unexecuted agreement with FERC or request in writing dispute resolution as allowed under Tariff, Part I, section 12. If Transmission Provider, in its sole discretion, determines that the negotiations are at an impasse, Transmission Provider shall notify the Eligible Customer of the impasse, and may file the unexecuted agreement with the FERC.
(c) Eligible Customer and Transmission Provider may not proceed under such Service Agreement for Contract Demand Transmission Service until:
(i) thirty (30) days after such agreement, if executed and nonconforming, has been filed with FERC;
(ii) such agreement, if unexecuted, has been filed with and accepted by FERC; or
PDF page 17
16
(iii) the earlier of thirty (30) days after such agreement, if conforming, has been executed or has been reported in Transmission Provider’s Electronic
Quarterly Reports.
710.7 Termination
Although the Service Agreement for Contract Demand Transmission Service is presumed to continue without expiration, it may be terminated where:
(a) An incumbent Eligible Customer will be replaced by a successor Eligible Customer, in which case the incumbent’s service shall only terminate if the successor agrees to commence the taking of the service, the appropriate service agreement is executed, and all other applicable terms and conditions of the Tariff and PJM Governing Agreements are satisfied;
(b) An incumbent Eligible Customer seeks to terminate its service and no successor Eligible Customer exists, in which case the incumbent must provide PJM with forty-two (42) months’ notice prior to the commencement of a Delivery Year in which Eligible Customer seeks the termination, subject to receiving all necessary regulatory approvals for such termination, if any;
(c) An Eligible Customer is disqualified from receiving Contract Demand
Transmission Service under Tariff, Part XI, Subpart B, section 713.7;
(d) The Eligible Customer is in breach of its obligations under the Service Agreement or the Tariff, Part XI. For example, to the extent any material changes to the gross demand of the Co-Located Load or the design, configuration, or output of the Co-Located Generating Facility occur without being studied by the Transmission Provider to determine whether such changes would affect the Transmission Provider’s ability to reliably provide the level of service specified in the Eligible Customer’s Contract Demand Transmission Service Agreement, the Eligible Customer may be considered in breach of its obligations and the agreement may be subject to termination in accordance with the provisions of this Tariff and/or the Service Agreement for Contract Demand Transmission Service; or
(e) On such other date as mutually agreed upon by the parties.
711 Designation of Co-Located Load and Co-Located Generating Facility
711.1 Required Designations
(a) The Eligible Customer must designate the individual Co-Located Load on behalf of which it is taking Firm Contract Demand Transmission Service, or Non-Firm Contract Demand Transmission Service, or both. The Co-Located Load shall be specified in the Service Agreement for Contract Demand Transmission Service, provided in Attachment F-4.
(b) The Eligible Customer must designate the individual Co-Located Generating Facility that will serve the individual Co-Located Load in subsection (a) and provide the megawatt level of energy from the Co-Located Generating Facility dedicated to serving the Co-Located Load.
PDF page 18
17
711.2 No Change in Delivery Point
No change in the Delivery Point for any Firm Contract Demand Transmission Service or Non- Firm Contract Demand Transmission Service shall be permitted.
711.3 Information Updates
The Eligible Customer shall provide the Transmission Provider with annual updates of (i) the demand characteristics of the Co-Located Load, and (ii) the supply characteristics of the designated Co-Located Generating Facility, both consistent with the information included in its Application for Contract Demand Transmission Service under Tariff, Part XI.
In addition, the Eligible Customer also shall have an ongoing obligation to provide the Transmission Provider with timely written or electronic notice of material changes in the foregoing sentence as well as any other information listed in Tariff, Part XI, Subpart B, section 710 or provided in its Application for Contract Demand Transmission Service or other aspects of its facilities or operations affecting the Transmission Provider’s ability to provide reliable service. Failure to timely inform the Transmission Provider of a material change in (i) the demand characteristics of the Co-Located Load, or (ii) the supply characteristics of the Co-Located Generating Facility may constitute a breach of the Eligible Customer’s Service Agreement and subject to termination under Tariff, Part XI, Subpart B, section 710.7.
712 Study Procedures for Contract Demand Transmission Service
712.1 Study Procedures for Firm Contract Demand Transmission Service
After the Eligible Customer submits a Completed Application for Firm Contract Demand Transmission Service, the Transmission Provider shall notify the affected Transmission Owner(s) of the Completed Application. As necessary, Transmission Provider and the affected Transmission Owner(s) shall coordinate to study the effects of providing the requested Firm Contract Demand Transmission Service on the affected Transmission Owner(s)’s system pursuant to the applicable affected Transmission Owner requirements.
After receiving the Application for Firm Contract Demand Transmission Service, the Transmission Provider shall determine, in accordance with the PJM Manuals, any necessary studies for reliably providing the requested Firm Contract Demand Transmission Service. If the Transmission Provider determines that such studies are necessary to evaluate the requested service, it shall inform the Eligible Customer of those studies as soon as practicable. The Transmission Provider will also consider the results of any studies conducted by the affected Transmission Owner(s).
712.2 Study Procedures for Non-Firm Contract Demand Transmission Service
After receiving a request for Non-Firm Contract Demand Transmission Service, the Transmission Provider shall determine on a non-discriminatory basis, and in accordance with the PJM Manuals, whether studies are needed to assess whether the Transmission System has sufficient available capacity to provide Non-Firm Contract Demand Transmission Service, and if so, which studies are appropriate. Transmission Provider may notify the affected Transmission Owner of such
PDF page 19
18
request for Non-Firm Contract Demand Transmission Service, and the Transmission Provider will also consider the results of any studies conducted by the affected Transmission Owner(s). 712.3 Application and Studies Agreement
In the event the Transmission Provider determines studies are necessary to evaluate the requested Contract Demand Transmission Service, the Transmission Provider shall tender an Application and Studies Agreement pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider for the required studies. For a service request to remain a Completed Application, the Eligible Customer shall execute the Application and Studies Agreement and return it to the Transmission Provider within fifteen (15) Business Days and provide the study fee pursuant to Tariff, Part XI, Subpart B, section 712.4. If the Eligible Customer elects not to execute the Application and Studies Agreement, its Application shall be deemed withdrawn and its fee shall be returned with interest.
712.4 Study Fee
Eligible Customer shall pay a study fee, as determined by the Transmission Provider, to apply for Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service.
713 Load Shedding and Curtailments for Contract Demand Transmission Service
713.1 General
Prior to the Service Commencement Date, the Eligible Customer shall demonstrate its ability to fully comply with the Load Shedding and Curtailment procedures pursuant to this section 713, the PJM Manuals, and the Service Agreement for Contract Demand Transmission Service, as provided in Attachment F-4. The Eligible Customer shall implement any Load Shedding and/or Curtailment directive given by Transmission Provider. To the extent practicable, the Transmission Provider will notify the Eligible Customer of any Curtailment in a timely manner. Eligible Customers must respond to any real time instruction to curtail or otherwise reduce load within five (5) minutes. Curtailments will be made on a non-discriminatory basis.
713.2 Load Shedding
To the extent that a system contingency exists on the Transmission Provider’s Transmission System and the Transmission Provider determines that it is necessary for the Eligible Customer to shed load at the designated Co-Located Load, the Eligible Customer shall shed load in accordance with previously established procedures under the Service Agreement for Contract Demand Transmission Service.
713.3 Curtailment of Firm Contract Demand Transmission Service
For purposes of Curtailment, Firm Contract Demand Transmission Service shall be treated as the equivalent of Network Integration Transmission Service.
713.4 Curtailment of Non-Firm Contract Demand Transmission Service
Non-Firm Contract Demand Transmission Service shall be Curtailed before Firm Contract Demand Transmission Service and Network Integration Transmission Service. The Transmission
PDF page 20
19
Provider may Curtail Non-Firm Contract Demand Transmission Service prior to dispatching the Pre-Emergency Load Response Program as further set forth in the PJM Manuals, or in response to a transfer capability shortage as a result of system reliability conditions. 713.5 System Reliability
Notwithstanding any other provisions of this Tariff, the Transmission Provider reserves the right, consistent with Good Utility Practice and on a not unduly discriminatory basis, to Curtail Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, without liability on the Transmission Provider’s part, for the purpose of making necessary adjustments to, changes in, or repairs on its lines, substations, and facilities, and in cases where the continuance of Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both, would endanger persons or property. In the event of any adverse condition(s) or disturbance(s) on the Transmission Provider’s Transmission System or on any other system(s) directly or indirectly interconnected with the Transmission Provider’s Transmission System, the Transmission Provider, consistent with Good Utility Practice, also may Curtail Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service in order to (i) limit the extent or damage of the adverse condition(s) or disturbance(s), (ii) prevent damage to generating or transmission facilities, or (iii) expedite restoration of service. The Transmission Provider will give the Eligible Customer as much advance notice as is practicable in the event of such Curtailment.
713.6 Necessary Control Technologies and Protection Systems for Non-Firm Contract Demand Transmission Service
To ensure protection of the Transmission System and that the Eligible Customer limits its energy withdrawals from the Transmission System to the level of Contract Demand Transmission Service provided in its Service Agreement for Contract Demand Transmission Service, including during a period in which the Transmission Provider has directed Curtailment or Load Shedding, prior to the Service Commencement Date, the Transmission Provider, affected Transmission Owner(s), and the Eligible Customer shall establish necessary control technologies and protection systems in accordance with the PJM Manuals, which may include a Remedial Action Scheme, for each Service Agreement for Non-Firm Contract Demand Transmission Service. The necessary control technologies and protection systems must be developed in accordance with the PJM Manuals and be approved by the Transmission Provider. The necessary control technologies and protection systems may be functionally modified from time to time. Any functional modification to the necessary control technologies and protection systems must be developed with the affected Transmission Owner(s) and approved by the Transmission Provider.
713.7 Consequences of Failure to Follow Instructions or Misoperation of Necessary Control Technologies and Protection Systems in a Contract Demand Transmission Service Agreement
(a) In the first instance that an Eligible Customer taking Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service fails to respond to established Load Shedding and Curtailment procedures, as set forth in this section 713, the Eligible Customer shall be disqualified from taking Firm Contract Demand Transmission Service and Non- Firm Contract Demand Transmission Service.
PDF page 21
20
(b) In the first instance that a necessary control technology or protection system for a given Service Agreement for Non-Firm Contract Demand Transmission Service misoperate, the Eligible Customer shall be prohibited from taking transmission service under its Service Agreement (both Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service) or otherwise withdrawing energy from the Transmission System for a period of up to one hundred and twenty (120) days from such event, which may be shortened or extended per mutual agreement, to allow for an analysis of the operational performance of the necessary control technologies and protection systems.
In the second instance that an Eligible Customer’s necessary control technology or protection system associated with a Service Agreement for Non-Firm Contract Demand Transmission Service misoperate, the Eligible Customer shall be disqualified from taking Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.
(c) Following disqualification under subsections (a) or (b) above, to receive any transmission service over the Transmission System, the Eligible Customer must apply for Network Integration Transmission Service under Tariff, Part III, with the option to qualify for Interim Network Integration Transmission Service under Tariff, Part XI subject to the provisions of the Tariff.
713.8 Penalty for Unreserved Use of Contract Demand Transmission Service
[Reserved]
714 Rates and Charges for Firm Contract Demand Transmission Service
714.1 Monthly Demand Charge
[Reserved]
714.2 Network Upgrade Charge
[Reserved]
714.3 Redispatch Charge
The Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in Tariff, Attachment K.
714.4 Stranded Cost Recovery
Any Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant to this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. 888. However, the Transmission Owner must separately file any proposal to recover stranded costs under section 205 of the Federal Power Act.
714.5 Other Charges
Eligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, Schedule 9; and Tariff, Schedule 10 based on the total quantity of MWHs of energy delivered using Firm Contract Demand Transmission Service, except in the case of any capacity-related
PDF page 22
21
charges under these schedules, which shall be based on the Eligible Customer’s Unforced Capacity Obligation.
Eligible Customer shall pay Ancillary Services charges, except for Regulation, based on the total quantity in MWhs of energy delivered to the Co-Located Load using Firm Contract Demand Transmission Service in accordance with Tariff, Part I, section 3.
Eligible Customer shall pay Black Start Service charges based on the gross demand of the Co- Located Load in accordance with Tariff, Schedule 6A.
Eligible Customer shall pay Regulation charges based on the gross demand of the Co-Located Load.
715 Rates and Charges for Non-Firm Contract Demand Transmission Service
715.1 Monthly Demand Charge
[Reserved]
715.2 Redispatch Charge
The Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in Tariff, Attachment K.
715.3 Stranded Cost Recovery
Any Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant to this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. 888. However, the Transmission Owner must separately file any proposal to recover stranded costs under section 205 of the Federal Power Act.
715.4 Other Charges
Eligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, Schedule 9; and Tariff, Schedule 10 based on the total quantity of MWhs of energy delivered using Non-Firm Contract Demand Transmission Service, except any capacity-related charges under these schedules will not apply.
Eligible Customer shall pay Ancillary Services charges, except for Regulation, based on the total quantity in MWhs of energy delivered to the Co-Located Load using Non-Firm Contract Demand Transmission Service in accordance with Tariff, Part I, section 3.
To the extent the Eligible Customer does not have an effective Service Agreement for Firm Contract Demand Transmission Service, Eligible Customer shall pay Black Start Service charges based on the gross demand of the Co-Located Load in accordance with Tariff, Schedule 6A. To the extent the Eligible Customer does not have an effective Service Agreement for Firm Contract Demand Transmission Service, Eligible Customer shall pay Regulation charges based on a gross demand of the Co-Located Load.
PDF page 23
22
716 Operating Agreement
716.1 Operating Agreement
The Eligible Customer shall plan, construct, operate and maintain its facilities in accordance with Good Utility Practice and in conformance with the Operating Agreement.
The terms and conditions under which the Eligible Customer shall operate its facilities and the technical and operational matters associated with the implementation of Tariff, Part XI shall be specified in the Operating Agreement.
The Operating Agreement shall provide for the Eligible Customer and Transmission Provider to
(i) operate and maintain equipment necessary for integrating the Eligible Customer within the Transmission Provider’s Transmission System (including, but not limited to, remote terminal units, metering, communications equipment and relaying equipment); (ii) transfer data between the Transmission Provider and the Eligible Customer (including, but not limited to, heat rates and operational characteristics of Network Resources, generation schedules for units outside the Transmission Provider’s Transmission System, interchange schedules, unit outputs for required redispatch, voltage schedules, loss factors and other real time data); (iii) use software programs required for data links and constraint dispatching; (iv) exchange data on forecasted loads and resources necessary for long-term planning; and (v) address any other technical and operational considerations required for implementation of Tariff, Part XI, including scheduling protocols.
PDF page 24
23
Service Agreement No. [Insert]
ATTACHMENT F-3A
Service Agreement For
Regional Network Integration Transmission Service
And/or
Interim Network Integration Transmission Service
(For Co-Located Load)
1.0
This Service Agreement, dated as of the date the last party executes this agreement, is entered into, by and between the Office of the Interconnection of PJM Interconnection, L.L.C. (the Transmission Provider) as the administrator of the Tariff, PJMSettlement Inc. (“Counterparty”) as the counterparty, and ____________ (“Network Customer”). [If applicable: This Service Agreement supersedes the Service Agreement among Transmission Provider, Counterparty, and [insert prior Network Customer’s entity name], [insert Service Agreement Number], effective date [insert], which was filed with the Commission in Docket No. [insert].]
2.0
[Instructions: Choose one of the following]
[The Network Customer has been determined by the Transmission Provider to have a valid request for Network Transmission Service under the Tariff and to have satisfied the conditions for service imposed by the Tariff.]
[or]
[The Network Customer, which is an Eligible Customer taking transmission service on behalf of Co-Located Load, has been determined by the Transmission Provider to have a valid request for Network Transmission Service under the Tariff and to have satisfied the conditions for service imposed by the Tariff, except for the condition that the following facilities must be completed and placed into service:
[If applicable, list facilities to be completed and placed into service.]
Until the facilities listed above are completed, the Transmission Owner provides a Notice of Completion to PJM, and the facilities listed above are in service, the Eligible Customer may not only receive Interim Regional Network Integration Transmission Service subject to the conditions of Part XI of the Tariff.
3.0
Regional Network Integration Transmission Service under this agreement shall commence on the later of: (l) the requested service commencement date of ___________________, or
(2) the date on which construction of any Direct Assignment Facilities and/or Network Upgrades are completed, or (3) such other date as it is permitted to become effective by
PDF page 25
24
the Commission. Network Customer taking Regional Network Integration Transmission Service shall take such service on terms that do not expire.
Regional Network Integration Transmission Service shall terminate consistent with Tariff, Part I, section 2.5. Specifically, Regional Network Integration Transmission Service may be terminated where: (1) an incumbent Network Customer will be replaced by a successor Network Customer, in which case the incumbent’s service shall only terminate if the successor agrees to commence the taking of the service, the appropriate service agreement is executed, and all other applicable terms and conditions of the PJM Governing Agreements are satisfied; (2) an incumbent Network Customer seeks to terminate its service and no successor Network Customer exists, in which case the incumbent must provide PJM with forty-two (42) months’ notice prior to the commencement of a Delivery Year, subject to receiving all necessary regulatory approvals for such termination, if any; or (3) on such other date mutually agreed upon by the Parties.
[If applicable] [Interim Network Integration Transmission Service under this agreement shall commence on the later of: (l) the requested service commencement date of ___________________, or (2) such other date as it is permitted to become effective by the Commission. On the date on which construction of any Direct Assignment Facilities and/or Network Upgrades are completed, Interim Network Integration Transmission Service shall terminate consistent with Tariff, Part XI, and Regional Network Integration Transmission Service shall begin.]
4.0
The Transmission Provider agrees to provide and the Network Customer agrees to take and pay for Regional Network Integration Transmission Service, when applicable, and Interim Regional Network Integration Transmission Service, when applicable, in accordance with the provisions of the Tariff, including the Operating Agreement (which is incorporated herein by reference), and this Service Agreement as they may be amended from time to time. Failure to timely inform the Transmission Provider of a material change in (i) the demand characteristics of the Co-Located Load or (ii) the supply characteristics of the Co- Located Generating Facility may constitute a breach of the Eligible Customer’s Service Agreement and this Service Agreement may be terminated pursuant to Tariff, Part XI, Subpart B, section 710.7.
[If applicable] [The Eligible Customer will comply with the necessary control technologies and protection systems provisions in Tariff, Part XI, prior to the Service Commencement Date.]
5.0
The Eligible Customer certifies it is willing and able to limit its usage of the Transmission System when requested by the Transmission Provider.
6.0
Any notice or request made to or by either Party regarding this Service Agreement shall be made to the representative of the other Party as indicated below.
PDF page 26
25
Transmission Provider (on behalf of Transmission Provider and Counterparty):
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA 19403
Network Customer:
_____________________________________
_____________________________________
_____________________________________
7.0
The Tariff for Network Integration Transmission Service, Tariff, Part III, and Interim Network Integration Transmission Service, Tariff, Part XI, is incorporated herein and made a part hereof.
PDF page 27
26
IN WITNESS WHEREOF, the Parties have caused this Service Agreement to be executed by their respective authorized officials.
Office of the Interconnection:
By:
______________________ _______________
______________
Name
Title
Date
Counterparty:
By:
______________________ _______________
______________
Name
Title
Date
Network Customer:
By:
______________________ _______________
______________
Name
Title
Date
PDF page 28
27
CERTIFICATION
I, ___________________________, certify that I am a duly authorized officer of ___________________________________ (Network Customer) and that
___________________________________ (Network Customer) will not request service under this Service Agreement to assist an Eligible Customer to avoid the reciprocity provision of this Open-Access Transmission Tariff.
_____________________________
(Name)
_____________________________
(Title)
Subscribed and sworn before me this _____ day of _____________, _______.
_____________________________
(Notary Public)
My Commission expires:_____________________
PDF page 29
28
SPECIFICATIONS FOR
REGIONAL NETWORK INTEGRATION TRANSMISSION SERVICE
1.0
Regional Network Integration Transmission Service Amount (MW): ______MW
2.0
Description of Co-Located Generating Facility:________________________________
________________________________________
________________________________________
Maximum Facility Output of Co-Located Generating Facility:
_______MW
3.0
Description of Co-Located Load:
________________________________________
________________________________________
________________________________________
Gross Demand of Co-Located Load:
______MW
4.0
Service under this Agreement may be subject to some combination of the charges detailed below. (The appropriate charges for individual transactions will be determined in accordance with the terms and conditions of the Tariff.)
4.1
Embedded Cost Transmission Charge:_______________________
______________________________________________________
4.2
Facilities Study Charge:__________________________________
______________________________________________________
4.3
Direct Assignment Facilities Charge:________________________
______________________________________________________
4.4
Ancillary Services Charge:________________________________
______________________________________________________
4.5
Other Supporting Facilities Charge:_________________________
______________________________________________________
PDF page 30
29
{If applicable} SPECIFICATIONS FOR
INTERIM REGIONAL NETWORK INTEGRATION TRANSMISSION SERVICE
1.0
Interim Regional Network Integration Transmission Service Amount (MW): ______MW
2.0
Description of Co-Located Generating Facility:________________________________
________________________________________
________________________________________
Maximum Facility Output of Co-Located Generating Facility:
_______MW
3.0
Description of Co-Located Load:
________________________________________
________________________________________
________________________________________
Gross Demand of Co-Located Load:
______MW
4.0
Service under this Agreement may be subject to some combination of the charges detailed below. (The appropriate charges for individual transactions will be determined in accordance with the terms and conditions of the Tariff.)
4.1
Embedded Cost Transmission Charge:_______________________
______________________________________________________
4.2
Facilities Study Charge:__________________________________
______________________________________________________
4.3
Direct Assignment Facilities Charge:________________________
______________________________________________________
4.4
Ancillary Services Charge:________________________________
______________________________________________________
4.5
Other Supporting Facilities Charge:_________________________
______________________________________________________
PDF page 31
30
Service Agreement No. [Insert]
ATTACHMENT F-4
Service Agreement For
Contract Demand Transmission Service
(For Co-Located Load)
1.0
This Service Agreement, dated as of the date the last party executes this agreement, is entered into, by and between the Office of the Interconnection of PJM Interconnection, L.L.C. (the Transmission Provider) as the administrator of the Tariff, PJMSettlement Inc. (“Counterparty”) as the counterparty, and ____________ (“Eligible Customer”). [If applicable: This Service Agreement supersedes the Service Agreement among Transmission Provider, Counterparty, and [insert prior Eligible Customer’s entity name], [insert Service Agreement Number], effective date [insert], which was filed with the Commission in Docket No. [insert].]
2.0
[Instructions: Choose one of the following depending on whether facilities upgrades are needed.]
[If facilities upgrades are not needed or if Eligible Customer is seeking solely Non-Firm Contract Demand Transmission Service] The Eligible Customer, who is taking transmission service on behalf of Co-Located Load, has been determined by the Transmission Provider to have a valid request for [Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service] under the Tariff and to have satisfied the conditions for service imposed by the Tariff.
[or]
[If facilities upgrades are needed, assuming Eligible Customer is seeking at least a portion of Firm Contract Demand Transmission Service] [The Eligible Customer, who is taking transmission service on behalf of Co-Located Load, has been determined by the Transmission Provider to have a valid request for Firm Contract Demand Transmission Service under the Tariff and to have satisfied the conditions for service imposed by the Tariff, except for the condition that the following facilities must be completed and placed into service:]
[If applicable, list facilities to be completed and placed into service.]
Until the facilities listed above are completed, the Transmission Owner provides a Notice of Completion to PJM, and the facilities listed above are in service, the Eligible Customer may not receive Firm Contract Demand Transmission Service under Tariff, Part XI.
3.0
Contract Demand Transmission Service under this agreement shall commence on the later of: (l) the requested service commencement date of ___________________, or (2) the date
PDF page 32
31
on which construction of any Direct Assignment Facilities and/or Network Upgrades are completed, or (3) such other date as it is permitted to become effective by the Commission.
Contract Demand Transmission Service shall terminate consistent with Tariff, Part XI, section 710.7.
4.0
The Transmission Provider agrees to provide and the Eligible Customer agrees to take and pay for Contract Demand Transmission Service in accordance with the provisions of the Tariff, including the Operating Agreement (which is incorporated herein by reference), and this Service Agreement, as they may be amended from time to time. Failure to timely inform the Transmission Provider of a material change in (i) the demand characteristics of the Co-Located Load or (ii) the supply characteristics of the Co-Located Generating Facility may constitute a breach of the Eligible Customer’s Service Agreement and this Service Agreement may be terminated pursuant to Tariff, Part XI, Subpart B, section 710.7.
5.0
The Eligible Customer will comply with the necessary control technologies and protection systems provisions in Tariff, Part XI, prior to the Service Commencement Date.
6.0
The Eligible Customer certifies it is willing and able to limit its usage of the Transmission System when requested by the Transmission Provider.
7.0
Any notice or request made to or by either Party regarding this Service Agreement shall be made to the representative of the other Party as indicated below.
Transmission Provider (on behalf of Transmission Provider and Counterparty):
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA 19403
Eligible Customer:
_____________________________________
_____________________________________
_____________________________________
8.0
Tariff, Part XI, for Contract Demand Transmission Services, as it may be revised from time to time, is incorporated herein and made a part hereof.
PDF page 33
32
IN WITNESS WHEREOF, the Parties have caused this Service Agreement to be executed by their respective authorized officials.
Office of the Interconnection:
By:
______________________ _______________
______________
Name
Title
Date
Counterparty:
By:
______________________ _______________
______________
Name
Title
Date
Eligible Customer:
By:
______________________ _______________
______________
Name
Title
Date
PDF page 34
33
CERTIFICATION
I, ___________________________, certify that I am a duly authorized officer of ___________________________________ (Eligible Customer) and that
___________________________________ (Eligible Customer) will not request service under this Service Agreement to assist an Eligible Customer to avoid the reciprocity provision of this Open-Access Transmission Tariff.
_____________________________
(Name)
_____________________________
(Title)
Subscribed and sworn before me this _____ day of _____________, _______.
_____________________________
(Notary Public)
My Commission expires:_____________________
PDF page 35
34
SPECIFICATIONS FOR
CONTRACT DEMAND TRANSMISSION SERVICE
1.0
Firm Contract Demand Transmission Service Amount (MW):
______MW
Non- Firm Contract Demand Transmission Service Amount (MW):
______MW
2.0
Description of Co-Located Generating Facility:________________________________
________________________________________
________________________________________
Maximum Facility Output of Co-Located Generating Facility:
_______MW
MW of Co-Located Generating Facility dedicated to Co-Located Load: _______MW
3.0
Description of Co-Located Load:
________________________________________
________________________________________
________________________________________
Gross Demand of Co-Located Load:
______MW
4.0
Service under this Agreement may be subject to charges specified in the Tariff, which may change from time to time, plus some combination of the charges detailed below. (The appropriate charges for individual transactions will be determined in accordance with the terms and conditions of the Tariff.)
4.1
Embedded Cost Transmission Charge:_______________________
______________________________________________________
4.2
Facilities Study Charge:__________________________________
______________________________________________________
4.3
Direct Assignment Facilities Charge:________________________
______________________________________________________
4.4
Ancillary Services Charge:________________________________
______________________________________________________
PDF page 36
35
4.5
Other Supporting Facilities Charge:_________________________
______________________________________________________
PDF page 37
36
Schedule A
Single Line Diagram
PDF page 38
37
PART I DEFINITIONS
Definitions – C – D . . .
“Curtailment” shall mean a reduction in firm or non-firm transmission service in response to a transfer capability shortage as a result of system reliability conditions, or in the case of Interim Network Integration Transmission Service or Non-Firm Contract Demand Transmission Service, in accordance with the terms of Tariff, Part XI.
. . .
Definitions – R . . .
“Remedial Action Scheme” shall have the meaning set forth in the North American Electric Reliability Corporation Glossary of Terms.
. . .
PDF page 39
38
Part III Network Integration Transmission Service
29
Initiating Service . . .
29.2
Application Procedures: . . .
(x) For Eligible Customers taking service on behalf of Co-Located Load: (1) a demonstration that the Co-Located Load on behalf of which the Eligible Customer is seeking to obtain service and the Co-Located Generating Facility are located on the same side of the Delivery Point to the Transmission Provider’s Transmission System as the Co-Located Load; (2) description of the supply characteristics of the Co-Located Generating Facility, including the generation profile and other technical specifications as may be requested by the Transmission Provider; and (3) a description of the demand characteristics of the Co-Located Load above, including the demand profile and other technical specifications as may be requested by the Transmission Provider.
. . .
PDF page 40
39
Tariff, Part IX, Subpart B
FORM OF
GENERATION INTERCONNECTION AGREEMENT COMBINED WITH CONSTRUCTION SERVICE AGREEMENT
. . .
PDF page 41
40
SCHEDULE O
Co-Located Generating Facility Associated with Co-Located Load {Include the appropriate language from the alternatives below.}
{Include the following language if the Generating Facility is not associated with Co-Located Load:}
Not Required
{If applicable: the following applies when a Project Developer intends to use its Generating Facility to serve Co-Located Load through Tariff, Part XI}
Information required for a Project Developer who intends to use its Generating Facility to serve Co-Located Load through Tariff, Part XI:
a. Eligible Customer taking transmission service on behalf of the Co-Located Load: ______________________________________________________________
______________________________________________________________
______________________________________________________________
b. Gross Demand (MW) of Co-Located Load
_____ MW
c. Contact Information for Co-Located Load:
_____ MW
______________________________________________________________
______________________________________________________________
______________________________________________________________
______________________________________________________________
d. Contact Information for Eligible Customer:
______________________________________________________________
______________________________________________________________
______________________________________________________________
PDF page 42
41
e. Identify the Project Developer Interconnection Facilities to which the Co-Located Load will interconnect.
Additional Requirements for a Project Developer who intends to use its Generating Facility to serve Co-Located Load through Tariff, Part XI:
1. {Include reference to, and incorporation of, operational or administrative requirements necessary for Co-Located Generating Facility based on fuel type, including, for example, any relevant Nuclear Plant Interface Agreement and Procedures.}
2. {If applicable} Project Developer will transfer power to the transmission facilities of the Co-Located Load behind Project Developer’s revenue meter. Project Developer has designed and installed, and will operate and maintain in good working condition and in accordance with Good Utility Practice, necessary control technologies and protection systems, to ensure that the Co-Located Load separates in the event of loss of generation output from the Generating Facility to ensure no power flows from Transmission Owner Interconnection Facilities and/or Transmission Owner Upgrades to the Co-Located Load.
3. {If applicable} Project Developer agrees to notify Transmission Owner and Transmission Provider as soon as possible and no later than next calendar day in the event of any failure of the Operating Procedure or any equipment malfunction or misoperation related to these protections.