EL25-49-000 · 2026-02-23 · PJM Interconnection, L.L.C.

Attachment A - New Transmission Services Tariff Sheets

Text extracted from the eLibrary original (SHA-256 83dbbaa1031964e9…). Download the original from the official source.

Contents · 8 sections
  1. Attachment A p. 1
  2. Attachment F-3A. PJMSettlement shall be the Counterparty to the Interim Network Integration p. 2
  3. Attachment F-3A, the transmission service provided to the Eligible Customer will automatically p. 2
  4. Attachment F-3A, or requests in writing that the Transmission Provider file a p. 3
  5. Attachment F-4, or requests in writing that the Transmission Provider file a p. 12
  6. Attachment F-4, consistent with Good Utility Practice and any additional requirements reasonably p. 15
  7. ATTACHMENT F-3A p. 24
  8. ATTACHMENT F-4 p. 31

Read the parent filing

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Attachment A

printed heading

Attachment A Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions 1 Tariff, Part XI Transmission Services Available for Eligible Customers Taking Service on Behalf of Co-Located Loads Subpart A – Interim Network Integration Transmission…
Read this passage

Attachment F-3A. PJMSettlement shall be the Counterparty to the Interim Network Integration

printed heading · Topic match: Connecting load and generation

PJMSettlement shall be the Counterparty to the Interim Network Integration Transmission Service transactions under this Tariff.
Read this passage Filed comments: Connecting load and generation

Attachment F-3A, the transmission service provided to the Eligible Customer will automatically

printed heading · Topic match: Connecting load and generation

The Eligible Customer taking Interim Network Integration Transmission Service must obtain or provide Ancillary Services pursuant to Tariff, Part I, section 3. 2 701.2 Interim Network Integration Transmission Service The Transmission Provider may provide non-firm, interruptible transmission service…
Read this passage Filed comments: Connecting load and generation

Attachment F-3A, or requests in writing that the Transmission Provider file a

printed heading · Topic match: Connecting load and generation

An Eligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage. (c) The cumulative…
Read this passage Filed comments: Connecting load and generation

Attachment F-4, or requests in writing that the Transmission Provider file a

printed heading · Topic match: Connecting load and generation

If requested by the Transmission Provider, an Application for Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service shall provide all of the information included in 18 C.F.R. § 2.20, including but not limited to the following: (i) The identity, address,…
Read this passage Filed comments: Connecting load and generation

Attachment F-4, consistent with Good Utility Practice and any additional requirements reasonably

printed heading · Topic match: Connecting load and generation

The Co-Located Load shall be specified in the Service Agreement for Contract Demand Transmission Service, provided in Attachment F-4. (b) The Eligible Customer must designate the individual Co-Located Generating Facility that will serve the individual Co-Located Load in subsection (a) and provide…
Read this passage Filed comments: Connecting load and generation

ATTACHMENT F-3A

printed heading · Topic match: Connecting load and generation

ATTACHMENT F-3A Service Agreement For Regional Network Integration Transmission Service And/or Interim Network Integration Transmission Service (For Co-Located Load) 1.0 This Service Agreement, dated as of the date the last party executes this agreement, is entered into, by and between the Office…
Read this passage Filed comments: Connecting load and generation

ATTACHMENT F-4

printed heading · Topic match: Connecting load and generation

“Remedial Action Scheme” shall have the meaning set forth in the North American Electric Reliability Corporation Glossary of Terms. . . . 38 Part III Network Integration Transmission Service 29 Initiating Service . . . 29.2 Application Procedures: . . . (x) For Eligible Customers taking service on…
Read this passage Filed comments: Connecting load and generation