Initial Brief of PJM Interconnection, L.L.C
Text extracted from the eLibrary original (SHA-256 2c8e7693c6426b51…). Download the original from the official source.
Contents · 55 sections
- A. Overview of Contract Demand Transmission Services in Illustrative
- B. Firm Contract Demand Transmission Service in Illustrative Tariff,
- F. Conditions Precedent and Technical Requirements for Contract
- G. Termination of Service Agreement for Contract Demand Transmission
- H. Designation of Co-Located Load and Co-Located Generating
- D. Study Procedures for Non-Firm Contract Demand Transmission
- F. Necessary Control Technologies and Protection Systems to Protect the
- G. Rates and Charges for Non-Firm Contract Demand Transmission
- B. Financial Penalty for Unreserved Use of the PJM Transmission
- A. New Curtailment Procedures Applicable to Eligible Customers Taking
- B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm
- H. Pro Forma Service Agreement Specific to Eligible Customers Serving
- I. INTRODUCTION AND BACKGROUND
- II. RESPONSES TO THE PAPER HEARING QUESTIONS
- A. Overview of Contract Demand Transmission Services in Illustrative
- B. Firm Contract Demand Transmission Service in Illustrative Tariff,
- C. Provision of Contract Demand Transmission Services
- D. Nature of Contract Demand Transmission Services
- E. Application for Contract Demand Transmission Services
- F. Conditions Precedent and Technical Requirements for Contract Demand
- G. Termination of Service Agreement for Contract Demand Transmission
- H. Designation of Co-Located Load and Co-Located Generating Facility
- I. Restrictions on Use of Service and Anti-Toggling Provision
- A. Provision of Non-Firm Contract Demand Transmission Service
- B. Nature of Non-Firm Contract Demand Transmission Service
- C. Initiating Non-Firm Contract Demand Transmission Service
- D. Study Procedures for Non-Firm Contract Demand Transmission Service
- E. Curtailment of Non-Firm Contract Demand Transmission Service
- F. Necessary Control Technologies and Protection Systems to Protect the
- G. Rates and Charges for Non-Firm Contract Demand Transmission Service
- H. Pro Forma Contract Demand Transmission Service Agreement
- A. Disqualification or Pause in Service
- B. Financial Penalty for Unreserved Use of the PJM Transmission System
- A. New Curtailment Procedures Applicable to Eligible Customers Taking
- B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm
- III. INTERIM NETWORK INTEGRATION TRANSMISSION SERVICE
- A. Provision of Interim NITS and Nature and Scope of Service
- B. Initiating Service
- C. Designation of Co-Located Load
- D. Study Procedures for Interim NITS
- E. Load Shedding and Curtailments
- F. Rates and Charges for Interim NITS
- G. Operating Agreement
- H. Pro Forma Service Agreement Specific to Eligible Customers Serving
- Attachment F-3A.209 In addition to the NITS terms carried over from the pro forma NITS
- Attachment F-3.
- IV. OTHER ILLUSTRATIVE TARIFF REVISIONS
- V. RESERVATION OF RIGHTS TO SUPPLEMENT FILING
- VI. IMPLEMENTATION AND EFFECTIVE DATE
- VII. DOCUMENTS ENCLOSED
- Attachment A: Illustrative Language for New Tariff, Part XI; Attachments
- Attachment B: Affidavit of
- Attachment C: Affidavit of Matthew Wharton, Manager, Reliability
- Attachment D: Affidavit of Timothy Horger, Senior Director, Forward
- VIII. CONCLUSION
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage
TABLE OF CONTENTS
printed heading
TABLE OF CONTENTS I.Read this passage
A. Overview of Contract Demand Transmission Services in Illustrative
printed heading
A.Read this passage
B. Firm Contract Demand Transmission Service in Illustrative Tariff,
printed heading
B.Read this passage
F. Conditions Precedent and Technical Requirements for Contract
printed heading
F.Read this passage
G. Termination of Service Agreement for Contract Demand Transmission
printed heading
G.Read this passage
H. Designation of Co-Located Load and Co-Located Generating
printed heading · Topic match: Connecting load and generation
Initial Study Procedures for Contract Demand Transmission Service 24 K.Read this passage Filed comments: Connecting load and generation
D. Study Procedures for Non-Firm Contract Demand Transmission
printed heading · Topic match: Reliability and curtailment
D.Read this passage Filed comments: Reliability and curtailment
F. Necessary Control Technologies and Protection Systems to Protect the
printed heading
F.Read this passage
G. Rates and Charges for Non-Firm Contract Demand Transmission
printed heading
G.Read this passage
B. Financial Penalty for Unreserved Use of the PJM Transmission
printed heading
B.Read this passage
A. New Curtailment Procedures Applicable to Eligible Customers Taking
printed heading · Topic match: Connecting load and generation
A.Read this passage Filed comments: Connecting load and generation
B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm
printed heading · Topic match: Connecting load and generation
B.Read this passage Filed comments: Connecting load and generation
H. Pro Forma Service Agreement Specific to Eligible Customers Serving
printed heading · Topic match: Connecting load and generation
The Commission found that additional record evidence was needed to set the appropriate replacement rates, terms, and conditions for several new transmission services for Eligible Customers2 serving Co-Located Load: Interim Network Integration Transmission Service (“Interim NITS”), Firm Contract…Read this passage Filed comments: Connecting load and generation
I. INTRODUCTION AND BACKGROUND
printed heading · Topic match: Filing procedure
Consistent with the allocation of rights between PJM and PJM Transmission Owners under the Consolidated 1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”); see also PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos.Read this passage Filed comments: Filing procedure
II. RESPONSES TO THE PAPER HEARING QUESTIONS
printed heading · Topic match: Cost allocation
Thus, PJM will first provide an overview of the two transmission services and how, together, they will provide an alternative to NITS for those Co-Located Loads willing and able to limit energy withdrawals from the Transmission System.Read this passage Filed comments: Cost allocation
A. Overview of Contract Demand Transmission Services in Illustrative
printed heading · Topic match: Connecting load and generation
Reform of Generator Interconnection Procedures and Agreements, Order No. 845, 163 FERC ¶ 61,043, at P 396 (2018) (requiring “any interconnection customer that seeks interconnection service below its generating facility capacity install appropriate monitoring and control technologies at its…Read this passage Filed comments: Connecting load and generation
B. Firm Contract Demand Transmission Service in Illustrative Tariff,
printed heading · Topic match: Connecting load and generation
Firm Contract Demand Transmission Service in Illustrative Tariff, Part XI Attachment A describes Firm Contract Demand Transmission Service as the transfer of capacity and energy for an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, predetermined MW level of…Read this passage Filed comments: Connecting load and generation
C. Provision of Contract Demand Transmission Services
printed heading · Topic match: Connecting load and generation
Provision of Contract Demand Transmission Services In Attachment A, section 708, PJM provides illustrative language detailing the scope of Contract Demand Transmission Service on both a Firm and Non-Firm basis. 29 Of course, to the extent an Eligible Customer takes only one of the two new contract…Read this passage Filed comments: Connecting load and generation
D. Nature of Contract Demand Transmission Services
printed heading · Topic match: Connecting load and generation
An Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm Contract Demand Transmission Service equivalent to the MW level of the Co-Located Generating Facility dedicated to serving the Co-Located Load, and an Eligible Customer with an effective Service Agreement will…Read this passage Filed comments: Connecting load and generation
E. Application for Contract Demand Transmission Services
printed heading · Topic match: Connecting load and generation
Application for Contract Demand Transmission Services Illustrative section 710 in Attachment A details how an Eligible Customer seeking transmission service on behalf of a Co-Located Load will initiate service requests for Firm and Non-Firm Contract Demand Transmission Service.Read this passage Filed comments: Connecting load and generation
F. Conditions Precedent and Technical Requirements for Contract Demand
printed heading · Topic match: Connecting load and generation
Conditions Precedent and Technical Requirements for Contract Demand Transmission Services Prior to obtaining service, the Eligible Customer must meet several enumerated conditions precedent, many of which are ministerial in nature but have significant importance in ensuring that the Eligible…Read this passage Filed comments: Connecting load and generation
G. Termination of Service Agreement for Contract Demand Transmission
printed heading · Topic match: Connecting load and generation
One, where the Eligible Customer “is in breach of its obligations under the Service Agreement or the Tariff, Part XI,” which could include, for example, “any material changes to the gross demand of the Co-Located Load or the design, configuration, or output of the Co-Located Generating Facility…Read this passage Filed comments: Connecting load and generation
H. Designation of Co-Located Load and Co-Located Generating Facility
printed heading · Topic match: Connecting load and generation
Designation of Co-Located Load and Co-Located Generating Facility The Show Cause Order requires the Co-Located Generating Facility to “designat[e] an Eligible Customer . . . take transmission service on behalf of a Co-Located Load.”61 Consistent with this requirement, Attachment A, section 711…Read this passage Filed comments: Connecting load and generation
I. Restrictions on Use of Service and Anti-Toggling Provision
printed heading · Topic match: Connecting load and generation
Load Shedding and Curtailment for Contract Demand Transmission Services The Commission directed that, “[f]or the Eligible Customer taking transmission service on behalf of a co-Located Load to be eligible for these new transmission services, the co-Located Load must be able and willing to prevent…Read this passage Filed comments: Connecting load and generation
A. Provision of Non-Firm Contract Demand Transmission Service
printed heading · Topic match: Connecting load and generation
Provision of Non-Firm Contract Demand Transmission Service The Show Cause Order recognizes that “not all Co-Located Loads will necessarily plan to withdraw energy from the transmission system on a regular basis” and “Eligible Customers taking service on behalf of such loads may . . . seek to…Read this passage Filed comments: Connecting load and generation
B. Nature of Non-Firm Contract Demand Transmission Service
printed heading · Topic match: Connecting load and generation
Nature of Non-Firm Contract Demand Transmission Service Non-Firm Contract Demand Transmission Service allows an Eligible Customer taking service on behalf of a Co-Located Load to access the Transmission System on a non-firm, interruptible basis during normal operations, and receive that…Read this passage Filed comments: Connecting load and generation
C. Initiating Non-Firm Contract Demand Transmission Service
printed heading · Topic match: Connecting load and generation
Initiating Non-Firm Contract Demand Transmission Service As with requests for Firm Contract Demand Transmission Service, upon receiving a request for Non-Firm Contract Demand Transmission Service, PJM will coordinate with the affected Transmission Owner(s) to complete necessary studies to determine…Read this passage Filed comments: Connecting load and generation
D. Study Procedures for Non-Firm Contract Demand Transmission Service
printed heading
Study Procedures for Non-Firm Contract Demand Transmission Service As discussed, PJM will not study transmission service requests alone, but rather will coordinate and consult with any affected Transmission Owners to determine whether and how the requested transmission service may be provided.Read this passage
E. Curtailment of Non-Firm Contract Demand Transmission Service
printed heading · Topic match: Reliability and curtailment
Curtailment of Non-Firm Contract Demand Transmission Service Non-Firm Contract Demand Transmission Service will be Curtailed before Firm Contract Demand Transmission Service and NITS as required by the Commission in the Show Cause Order.110 As discussed in greater detail in response to Question 11,…Read this passage Filed comments: Reliability and curtailment
F. Necessary Control Technologies and Protection Systems to Protect the
printed heading · Topic match: Reliability and curtailment
Necessary Control Technologies and Protection Systems to Protect the Transmission System by Limiting Energy Withdrawals As part of implementing the key principles that (1) the services are designed to serve loads that are “willing and able to control their withdrawals from the transmission…Read this passage Filed comments: Reliability and curtailment
G. Rates and Charges for Non-Firm Contract Demand Transmission Service
printed heading · Topic match: Connecting load and generation
In addition, Non-Firm Contract Demand Transmission Service customers will be responsible for Regulation and Black Start Service charges based on the gross demand of the Co-Located Load, to the extent the customer is not paying such charges associated with its Firm Contract Demand Transmission…Read this passage Filed comments: Connecting load and generation
H. Pro Forma Contract Demand Transmission Service Agreement
printed heading · Topic match: Connecting load and generation
To the extent the Eligible Customer does not have an effective Service Agreement for Firm Contract Demand Transmission Service, Eligible Customer shall pay Regulation charges based on a gross demand of the Co-Located Load.”). 124 Illustrative Tariff, Attachment F-4. 38 Question 3: As noted above, a…Read this passage Filed comments: Connecting load and generation
A. Disqualification or Pause in Service
printed heading · Topic match: Connecting load and generation
Disqualification after first failure of Eligible Customer to shed load or curtail in accordance with established procedures Under PJM’s approach, Eligible Customers taking Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS on behalf of a…Read this passage Filed comments: Connecting load and generation
B. Financial Penalty for Unreserved Use of the PJM Transmission System
printed heading · Topic match: Connecting load and generation
However, the foregoing limitations will “not apply in the event of (i) a physical change to the Co-Located Generating Facility that would materially and permanently alter the [MW] level dedicated to the Co-Located Load; or (ii) a physical change to the Co-Located Load that would materially and…Read this passage Filed comments: Connecting load and generation
A. New Curtailment Procedures Applicable to Eligible Customers Taking
printed heading · Topic match: Reliability and curtailment
This effectively means that Interim NITS and Non-Firm Contract Demand Transmission Service will be 64 curtailed before Demand Response resources are called upon to reduce load.163 For purposes of Curtailment, Firm Contract Demand Transmission Service will be treated as the equivalent of NITS.164 To…Read this passage Filed comments: Reliability and curtailment
B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm
printed heading · Topic match: Connecting load and generation
Curtailment of an Eligible Customer Taking Both Firm and Non-Firm Contract Demand Transmission Service on Behalf of a Co-Located Load During Emergency Operations Question 11 asks, “in particular, whether PJM can shed all or a portion of a Co- Located Load on whose behalf an Eligible Customer takes…Read this passage Filed comments: Connecting load and generation
III. INTERIM NETWORK INTEGRATION TRANSMISSION SERVICE
printed heading · Topic match: Connecting load and generation
INTERIM NETWORK INTEGRATION TRANSMISSION SERVICE The Commission in the Show Cause Order recognized that Co-Located Loads desire a way to more rapidly interconnect to the PJM Transmission System and begin operation.170 The Commission ordered PJM to develop a new service transitional to obtaining…Read this passage Filed comments: Connecting load and generation
A. Provision of Interim NITS and Nature and Scope of Service
printed heading · Topic match: Connecting load and generation
Provision of Interim NITS and Nature and Scope of Service Generally speaking, the non-rate terms and conditions for Interim NITS are the same as for NITS,172 with modifications necessary to implement the interim and non-firm nature of the service.Read this passage Filed comments: Connecting load and generation
B. Initiating Service
printed heading · Topic match: Connecting load and generation
Initiating Service Illustrative section 702 in Attachment A details how an Eligible Customer seeking Interim NITS on behalf of a Co-Located Load will initiate service requests.Read this passage Filed comments: Connecting load and generation
C. Designation of Co-Located Load
printed heading · Topic match: Connecting load and generation
Thus, section 703.2 provides that “[p]rior to the Service Commencement Date of Network Integration Transmission Service, if an Eligible Customer designates a new Co-Located Load, or increases the size of the designated Co- Located Load, the new Co-Located Load shall be studied pursuant to a new…Read this passage Filed comments: Connecting load and generation
D. Study Procedures for Interim NITS
printed heading
Study Procedures for Interim NITS To assess whether the Transmission System can accommodate a request for Interim NITS, PJM will determine whether additional studies beyond what is required to evaluate 184 Illustrative Tariff, Part XI, Subpart A, section 703.3. 185 Illustrative, Part XI, Subpart A,…Read this passage
E. Load Shedding and Curtailments
printed heading · Topic match: Reliability and curtailment
Likewise, as explained, above, in response to Question 5, an Eligible Customer that fails to respond to established Load Shedding and Curtailment procedures on one occasion will be disqualified from taking Interim NITS.197 To the extent an Eligible Customer is disqualified from taking Interim NITS,…Read this passage Filed comments: Reliability and curtailment
F. Rates and Charges for Interim NITS
printed heading · Topic match: Connecting load and generation
Rates and Charges for Interim NITS Consistent with the allocation of rights between PJM and PJM Transmission Owners,199 PJM expects the PJM Transmission Owners to brief a transmission rate appropriate for Interim NITS.Read this passage Filed comments: Connecting load and generation
G. Operating Agreement
printed heading
The Commission’s pro forma Open Access Transmission Tariff uses the term “Network Operating Agreement.” In PJM, the “Operating Agreement of the PJM Interconnection, L.L.C., as amended from time to time, shall constitute the Network Operating Agreement.” Tariff, Attachment G. 75 conditions under…Read this passage
H. Pro Forma Service Agreement Specific to Eligible Customers Serving
printed heading · Topic match: Connecting load and generation
Pro Forma Service Agreement Specific to Eligible Customers Serving Co-Located Load Via NITS or Interim NITS To facilitate the automatic transition from Interim NITS to NITS and to best administer the terms and conditions specific to serving Co-Located Loads, PJM has developed a single Service…Read this passage Filed comments: Connecting load and generation
Attachment F-3A.209 In addition to the NITS terms carried over from the pro forma NITS
printed heading · Topic match: Connecting load and generation
Attachment F-3A.209 In addition to the NITS terms carried over from the pro forma NITS Service Agreement (Attachment F-3), PJM has added terms specific to Co-Located Load arrangements, including, for example, a description of Co-Located Generating Facility and its Maximum Facility Output, and a…Read this passage Filed comments: Connecting load and generation
Attachment F-3.
printed heading
Attachment F-3. 210 Illustrative Tariff, Attachment F-3A. 211 Illustrative Tariff, Attachment F-3A, section 2.0. 76Read this passage
IV. OTHER ILLUSTRATIVE TARIFF REVISIONS
printed heading · Topic match: Connecting load and generation
First, PJM provides illustrative Tariff language to the definition of “Curtailment” in Part I, which refers to the specific Curtailment procedures provided in the new Tariff, Part XI applicable to Interim NITS or Non-Firm Contract Demand Transmission Service.212 This definitional change…Read this passage Filed comments: Connecting load and generation
V. RESERVATION OF RIGHTS TO SUPPLEMENT FILING
printed heading · Topic match: Connecting load and generation
RESERVATION OF RIGHTS TO SUPPLEMENT FILING As discussed throughout this brief and shown in the illustrative Tariff provisions, the addition of three new transmission services, and revisions to the NITS to accommodate Eligible Customers serving Co-Located Load, requires complex revisions to PJM’s…Read this passage Filed comments: Connecting load and generation
VI. IMPLEMENTATION AND EFFECTIVE DATE
printed heading · Topic match: Connecting load and generation
Regardless, it is unlikely that generation intended to serve Co-Located Load will be constructed and operational before June 1, 2029.Read this passage Filed comments: Connecting load and generation
VII. DOCUMENTS ENCLOSED
printed heading
DOCUMENTS ENCLOSED In addition to this initial brief, PJM encloses the following: 1.Read this passage
Attachment A: Illustrative Language for New Tariff, Part XI; Attachments
printed heading
Attachment A: Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions; 2.Read this passage
Attachment B: Affidavit of
printed heading · Topic match: Connecting load and generation
Sami Abdulsalam, Director of Transmission Planning; 229 Notably, however, as the Commission recently reiterated, for purposes of the RPM, “Capacity prices are intended to send longer-term investment signals to which developers respond over time[]” and “delays in the interconnection queue,…Read this passage Filed comments: Connecting load and generation
Attachment C: Affidavit of Matthew Wharton, Manager, Reliability
printed heading
Attachment C: Affidavit of Matthew Wharton, Manager, Reliability Engineering; and 4.Read this passage
Attachment D: Affidavit of Timothy Horger, Senior Director, Forward
printed heading
Attachment D: Affidavit of Timothy Horger, Senior Director, Forward Market Operations.Read this passage
VIII. CONCLUSION
printed heading
CONCLUSION PJM respectfully requests that the Commission find that the illustrative Tariff revisions included in Attachment A are part of a just and reasonable replacement rate in accordance with the requirements of the Show Cause Order.Read this passage