EL25-49-000 · 2026-02-23 · PJM Interconnection, L.L.C.

Att. D - Horger Affidavit

Text extracted from the eLibrary original (SHA-256 ad4bf4d0ce7c26fb…). Download the original from the official source.

Contents · 3 sections
  1. Attachment D p. 1
  2. I. QUALIFICATIONS p. 3
  3. II. PJM’S PROPOSED EFFECTIVE DATE OF JUNE 1, 2029, IS APPROPRIATE p. 4

Read the parent filing

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Attachment D

printed heading · Topic match: Connecting load and generation

I am submitting this affidavit in support of PJM’s proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order1 to establish three new transmission services for…
Read this passage Filed comments: Connecting load and generation

I. QUALIFICATIONS

printed heading

In my current role, I oversee PJM’s Financial Transmission Rights, Capacity, and Demand Side Markets, including the design, development, and execution of 1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18, 2025 Order”). 3 those markets, the facilitation of PJM stakeholder…
Read this passage

II. PJM’S PROPOSED EFFECTIVE DATE OF JUNE 1, 2029, IS APPROPRIATE

printed heading · Topic match: Connecting load and generation

For example, eligible capacity must demonstrate that it can be physically “deliverable” to the PJM system before the RPM Auction is conducted.
Read this passage Filed comments: Connecting load and generation