EL25-49-000 · 2026-02-23 · PJM Interconnection, L.L.C.

Att. D - Horger Affidavit

PDF page 1

Attachment D

Affidavit of Timothy Horger,
Senior Director, Forward Market Operations

PDF page 2

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company Delmarva Power & Light Company

Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company

Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.

The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.

AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

              Docket Nos. EL25-49-000
                                   EL25-49-001

PDF page 3

2
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

                                  AD24-11-000

                                   EL25-20-000
                                 (Consolidated)

AFFIDAVIT OF TIMOTHY HORGER,
ON BEHALF OF PJM INTERCONNECTION, L.L.C.

1. My name is Timothy Horger.  I am the Senior Director of Forward Market Operations for PJM Interconnection, L.L.C. (“PJM”).  My business address is 2750 Monroe Boulevard, Audubon, Pennsylvania 19403.  I am submitting this affidavit in support of PJM’s proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order1 to establish three new transmission services for Eligible Customers seeking to take transmission service on behalf of Co-Located Load.

2. Specifically, in this affidavit, I provide support for an effective date of June 1, 2029, for the Tariff revisions relating to the three new transmission services for Eligible Customers seeking to take transmission service on behalf of Co-Located Load.

I. QUALIFICATIONS
3. I joined PJM in 2002.  In my current role, I oversee PJM’s Financial Transmission Rights, Capacity, and Demand Side Markets, including the design, development, and execution of

1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18, 2025 Order”).

PDF page 4

3
those markets, the facilitation of PJM stakeholder initiatives related to those markets, and the professional development of PJM Staff who work in the departments administering those markets.  I am also responsible for overseeing all activities associated with the Market Efficiency Economic Planning process at PJM.  In addition, I am responsible for efforts associated with Strategic Market initiatives.

4. Prior to my current position, I served as Director of Market Operations and also held manager positions in the Interregional Market Operations and Market Simulation groups. Prior to my employment at PJM, I worked as a Power Systems and Control Engineer at Laser Technology, Inc.

5. I hold a Bachelor of Science degree in Electrical Engineering from Drexel University, and a Masters degree in Systems Engineering from Penn State Great Valley School of Graduate Professional Studies.

II. PJM’S PROPOSED EFFECTIVE DATE OF JUNE 1, 2029, IS APPROPRIATE
FOR IMPLEMENTATION OF THE THREE NEW TRANSMISSIONS SERVICES.
6. The forward nature of PJM’s capacity market, the Reliability Pricing Model (“RPM”), directly informs PJM’s proposed effective date of June 1, 2029, for the three new transmission services described in the December 18, 2025 Order.

7. PJM’s RPM auctions procure capacity for future Delivery Years based on expected demand for that given Delivery Year.  The expected demand is, in turn, based on the PJM Load Forecast for that Delivery Year.  It is important that the PJM Load Forecast includes all load expecting to be served for the relevant RPM Auction Delivery Year.  The three new transmission services for Eligible Customers seeking to take transmission service on behalf of a Co-Located Load will significantly impact the PJM Load Forecast and expected demand, which will, in turn, have significant implications for the RPM.

8. The amount of capacity PJM’s RPM procures has significant impacts on both physical and financial expectations.  For example, eligible capacity must demonstrate that it can be physically “deliverable” to the PJM system before the RPM Auction is conducted. Additionally, in times when supply is tight and demand is growing, an increase in the amount of demand can significantly impact the auction clearing price.

9. In PJM, one of the ways in which deliverability is demonstrated is through Capacity Interconnection Rights (“CIRs”) that are verified for each Capacity Resource.  This deliverability concept ensures that any capacity cleared in an RPM auction is reliable and accountable.  Under PJM’s Capacity Performance construct, each Capacity Resource that clears an RPM auction is (except in very limited circumstances) required to be available, and is subject to severe penalties if not available.

10. In light of the interaction between the RPM and the impact on expected demand that Eligible Customers taking the three new transmissions services on behalf of Co-Located Load will have, PJM has proposed an effective date of June 1, 2029.

PDF page 5

4

11. The RPM is premised primarily on a three-year forward Base Residual Auction (“BRA”), and while it is currently operating under a compressed auction schedule, PJM has been on track to return to a normal three-year forward auction for its capacity market by May 2027 (for the 2030/2031 Delivery Year).  The BRA for the 2027/2028 Delivery Year took place in December 2025.

12. The next BRA is currently scheduled for June 30, 2026, and will be conducted for the 2028/2029 Delivery Year beginning June 1, 2028.  Importantly, as of today, the PJM Load Forecast for the 2028/2029 Delivery Year BRA is already determined, and eligible capacity has already been determined for the 2028/2029 Delivery Year BRA.

13. Thus, it is no longer possible to update the PJM Load Forecast, update the RPM auction input parameters (planning parameters), and implement necessary changes before the 2028/2029 RPM BRA is conducted, even if the Commission were to theoretically approve the proposed changes today.  Accordingly, any new load or Capacity Resource coming online or, for example, existing generation delisting of CIRs to allow a Capacity Resource to leave the market and dedicate capacity to serving a Co-Located Load affected by the proposed changes associated with this filing would not be accounted for in the RPM Auction planning parameters or the PJM Load Forecast for the 2028/2029 Delivery Year BRA.

14. The next available BRA that can include the updated demand and potential new or removed capacity (including accounting for any change in CIRs) is the BRA for the 2029/2030 Delivery Year starting June 1, 2029.  The 2029/2030 Delivery Year BRA is scheduled to take place in December 2026, and the expected demand and eligible capacity for the 2029/2030 Delivery Year have not yet been determined.  Thus, because this would be the first BRA in which the effects of these new transmission services could be considered (including procuring necessary capacity for firm transmission services), PJM is proposing a June 1, 2029, implementation date for the three new transmission services.

15. It is unlikely that generation associated with these three new transmission service products would be included in the intervening, incremental RPM auctions.  Incremental Auctions are conducted to allow for replacement resource procurement, along with increases and decreases in resource commitments due to reliability requirement adjustments.  These adjustments are typically small.

16. Second, implementing the three new transmission services will necessitate modifications to the PJM core Markets and Operations systems, including modifying the Intermediate and Real-Time Security Constrained Economic Dispatch (“IT SCED” and “RT SCED”), Day-Ahead Market software, and PJM dispatch tools.  Two of the new transmission service products, specifically Interim NITS and Non-Firm Contract Demand Transmission Service, will be among the first to be curtailed under certain conditions.  Curtailment can affect prices and dispatch instructions, for which automation will be necessary to avoid non-optimal, untimely, and inefficient outcomes.  Development and implementation of changes to these core systems is dependent on design, vendor availability, costs, and

PDF page 6

5
managing competing priorities that include other Commission-directed initiatives.  Given the significant uncertainty surrounding these novel services, PJM cannot initiate the

necessary work (including software changes) until the Commission’s final order in the
paper hearing is issued in this docket, and the specific rates, terms, and conditions of these new transmission services are correspondingly finalized.

17. Finally, it is unlikely that Eligible Customers and associated generation will be online and taking service under any of the new transmission services before June 1, 2029, as the

process of getting through the interconnection queue, being constructed, and becoming
operational will likely be more than three years, particularly in light of current supply chain issues, Transmission Owner and PJM Interconnection queue requirements, and RPM

auction timelines.2  There is a known challenge to procure equipment, such as turbines,3 and it is not currently expected that a generator could be physically built in less than three years.4  The earliest expected Delivery Year a new generator can participate in an RPM

BRA or an existing capacity resource can delist, which includes required interconnection modified studies, is for the 2029/2030 Delivery Year.

18. This concludes my Affidavit.

2 Notably, however, as the Commission recently reiterated, for purposes of the RPM, “Capacity prices are intended to send longer-term investment signals to which developers respond over time[]” and “delays in the interconnection queue, compressed auction schedules, and supply chain issues” do not render RPM auction results unjust and unreasonable.  PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, at P 50 (2025) (citing PJM Interconnection, L.L.C., 126 FERC ¶ 61,275, at P 150 (2009) (“RPM was designed to provide long-term forward price signals . . . .”)).
3 Jared Anderson, US gas-fired turbine wait times as much as seven years; costs up sharply, S&P Global (May 20, 2025), https://www.spglobal.com/energy/en/news-research/latest-news/electric-power/052025-us-gas-fired-turbine- wait-times-as-much-as-seven-years-costs-up-sharply.
4 See, e.g., The Brattle Group, et al., Brattle 2025 CONE Report for PJM, PJM Interconnection, L.L.C. (Apr. 9, 2025), https://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2025/20250411-special/item-1-02- revised-cone-report-final.pdf.

PDF page 7

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company Delmarva Power & Light Company

Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company

Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.

The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.

AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

              Docket Nos. EL25-49-000
                                   EL25-49-001

PDF page 8

Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

                                  AD24-11-000

                                   EL25-20-000
                                 (Consolidated)

VERIFICATION OF TIMOTHY HORGER

I, Timothy Horger, pursuant to 28 U.S.C. § 1746, state, under penalty of perjury, that I am the Timothy Horger referred to in the foregoing “Affidavit of Timothy Horger on Behalf of PJM Interconnection, L.L.C.,” that I have read the same and am familiar with the contents thereof, and that the facts set forth therein are true and correct to the best of my knowledge, information, and belief.

/s/ Timothy Horger

Timothy Horger
Senior Director
Forward Market Operatins
PJM Interconnection, L.L.C.

Executed on: February 23, 2026