Att. C - Wharton Affidavit
Text extracted from the eLibrary original (SHA-256 5267d0fe8580b1b0…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Attachment C
printed heading · Topic match: Connecting load and generation
I am submitting this affidavit in support of PJM’s proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order1 to establish three new transmission services for…Read this passage Filed comments: Connecting load and generation
I. QUALIFICATIONS
printed heading
I joined PJM in January of 2013 and was continuously employed by PJM until April 2021.Read this passage
II. PJM’S ROLE IN SYSTEM OPERATIONS
printed heading
PJM must comply with reliability standards set by NERC, with oversight from FERC. 10.Read this passage
III. THE OPERATIONAL COMPLEXITIES ASSOCIATED WITH REMEDIAL
printed heading
All RAS must meet the NERC RAS definition and comply with the NERC Reliability Standard PRC-012-2, as well as other NERC Reliability Standards applicable to RAS (e.g., PRC-005-613). 18.Read this passage