EL25-49-000 · 2026-02-23 · PJM Interconnection, L.L.C.

Att. C - Wharton Affidavit

PDF page 1

Attachment C

Affidavit of Matthew Wharton,
Manager, Reliability Engineering

PDF page 2

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company Delmarva Power & Light Company

Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company

Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.

The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.

AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

              Docket Nos. EL25-49-000
                                   EL25-49-001

PDF page 3

2
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

                                  AD24-11-000

                                   EL25-20-000
                                 (Consolidated)

AFFIDAVIT OF MATTHEW WHARTON
ON BEHALF OF PJM INTERCONNECTION, L.L.C.

1. My name is Matthew Wharton, PE, and my business address is 2750 Monroe Blvd., Audubon, Pennsylvania 19403.  My current title is Manager, Reliability Engineering at PJM Interconnection, L.L.C. (“PJM”).  I am submitting this affidavit in support of PJM’s proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order1 to establish three new transmission services for Eligible Customers seeking to take service on behalf of Co-Located Load.

2. Specifically, in this affidavit, I explain:

• How PJM operationally carries out its key responsibilities as the “air traffic controller” of the PJM Region’s high-voltage electric transmission system to ensure reliability, manage power flow, and handle emergency operations as the region’s North American Electric Reliability Corporation (“NERC”)-registered Reliability Coordinator, Balancing Authority, and Transmission Operator; and

1 PJM Interconnection, L.L.C, 193 FERC ¶ 61,217, at PP 2, 161, 231-36 (2025).

PDF page 4

3
• The operational complexities associated with Remedial Action Schemes
(“RAS”) and PJM’s application of the applicable requirements of NERC
mandatory reliability standard PRC-012-2.2
I. QUALIFICATIONS
3. I joined PJM in January of 2013 and was continuously employed by PJM until April 2021. I returned in January 2022 and have been continuously employed by PJM ever since.  As Manager, Reliability Engineering, I am responsible for coordinating next-day and real-time operating plans between PJM, its member Transmission Owners and Generation Owners, and our neighboring entities.  This function includes ensuring the real-time reliable operation of the power grid and generation connected to it, in accordance with all PJM and NERC reliability standards pertaining to the functions of Reliability Coordinator, Balancing Authority, and Transmission Operator.  Prior to my role in the Reliability Engineers, I served as Manager, Transmission Planning – MAAC & South, in which I performed planning coordinator functions in a managerial role.

4. Prior to these positions in PJM’s Reliability Engineering Department, I was an Associate Engineer (Electrical) in the Design Engineering department at PSEG Nuclear LLC in the Hope Creek Nuclear Power Plant, as an Engineer in the PJM – Transmission Services department, as a Sr. Engineer in the PJM – Transmission Operations department, as an Associate Director in the Guidehouse – Energy, Sustainability, and Infrastructure department, as a Reliability Engineer in the PJM – Reliability Engineering Department, as Principal Reliability Engineer – Reliability Engineering, and then as Manager, Transmission Planning – MAAC & South at PJM.

5. I hold a Bachelor of Science degree in Electrical Engineering, from The College of New Jersey, a Master of Science degree in Electrical Engineering from Drexel University, and a Master of Science degree in Engineering Management from Drexel University.

6. In addition to my formal education, I am currently a NERC Certified System Operator at the Reliability Coordinator level (Certification Number: RC201607020), PJM Certified Transmission Owner Operator (Certificate Number: PT2016080), PJM Certified Generation Dispatcher (Certificate Number: PG2016642), and a licensed Professional Engineer in the state of New Jersey (License Number: 24GE05437900).

II. PJM’S ROLE IN SYSTEM OPERATIONS

7. PJM is a Commission-approved Regional Transmission Organization that independently directs operations on the PJM Transmission System.  Importantly, PJM does not physically and directly control transmission equipment, but rather acts as the “air traffic controller,” coordinating and directing system operations with its Member Transmission Owners.  Put

2 PRC-012-2 – Remedial Action Schemes, North American Electric Reliability Corporation (Apr. 28, 2025), https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012-2.pdf (“NERC Reliability Standard PRC-012-2”).

PDF page 5

4
another way, just as air traffic controllers do not own or fly the airplanes, PJM does not own or operate the generation or transmission facilities of the PJM Region.

8. Like an air traffic controller, PJM directs energy “traffic,” ensuring that electricity from generators moves safely to load.  PJM has decision-making authority to act and/or to direct actions to be taken by Transmission Operators, Transmission Owners, Generator Operators, Load-Serving Entities, and Purchasing-Selling Entities within its Reliability Coordinator Area to preserve the integrity and reliability of the Bulk Electric System.3

9. PJM is the Reliability Coordinator, Balancing Authority, and Transmission Operator for the PJM Region.  First, as the federally-designated Reliability Coordinator for the PJM Region, PJM coordinates the operation of transmission and generation on a second-by- second, hour-by-hour, and day-to-day basis throughout the year.  PJM must comply with reliability standards set by NERC, with oversight from FERC.

10. Second, as the region’s Balancing Authority, PJM ensures electricity supply continuously matches load in real-time to reliability serve the over 67 million customers within our region.  PJM’s system operators maintain frequency control by directing Generator Operators to increase or lower generation output to maintain the delicate balance of supply and demand on the high-voltage electric transmission system at the standard frequency of 60 cycles per second (i.e., 60 Hertz in the United States).  PJM is a centrally dispatch Balancing Authority, which uses Security Constrained Economic Dispatch that utilizes least-cost solutions while controlling active transmission constraints to ensure load is served.  A reliable centrally dispatched Balancing Authority relies on Network Integration Transmission Service (“NITS”) to ensure that generation is not “bottled”4 and is deliverable to load, as Dr. Sami Abdulsalam explains in his affidavit.5

11. Third, as the PJM Region’s Transmission Operator, PJM manages the physical transmission grid, directing power flow over 88,333 miles of transmission lines to minimize  congestion and prevent equipment overload to the extent possible.

12. PJM manages the reliability of the transmission grid by maintaining an uninterrupted flow of high-voltage electricity, monitoring congestion, and by preventing and, if necessary, addressing outages and emergencies within the PJM footprint.  As electricity usage changes throughout the day, PJM must balance supply and demand by telling generation how much energy to supply while simultaneously working with PJM Transmission Owners to ensure that transmission lines and facilities are functioning properly.

13. Operating the electric system is a balancing act that requires continuous monitoring of the system.  From PJM’s dual, fully redundant control rooms, PJM’s system operators work

3 See Systems Operation Division, PJM Manual 37: Reliability Coordination, PJM Interconnection, L.L.C. (Rev. 22, May 11, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m37.pdf.
4 “Bottled” in this context means a generation that cannot output the electricity it creates to the grid or is undeliverable to the grid.
5 Affidavit of Dr. Sami Abdulsalam on Behalf of PJM Interconnection L.L.C. (Attachment B) ¶¶ 7-8.

PDF page 6

5
24 hours a day, seven days a week to anticipate and respond, on a second-by-second basis, to shifts in demand for power and changes in the flow of electricity, equipment problems, weather conditions and other factors to maintain safe and reliable service while meeting customer needs for electricity when and where it’s needed.  System operators are responsible for directing generators to increase or lower generation to maintain the delicate balance between the supply and demand for electricity.  They monitor the equipment on the transmission system (such as transmission lines, transformers) to ensure they are loaded and operated within their limits.  Additionally, they monitor the transmission equipment for the “what could go wrong,” also known as “contingency analysis,” to ensure the system will remain secure and safe, even if something does go wrong.

14. From an Industry perspective, there are multiple efforts reviewing the Operational, Planning, and Security impacts of the large load.  One of the most notable whitepapers was developed by NERC, Characteristics and Risks of Emerging Large Loads,6 in which I am listed for supporting the development of the paper.  From a high level, the operational risks include forecasting, balancing and reserves, lack of real-time coordination, stability, and power quality.  Two of the NERC Whitepaper’s recommendations include (i) tasking two NERC Working Groups to develop load models that can show the characteristics and risks for simulations, and (ii) to assess possible protection system impacts to the Bulk Power System.  Industry has recognized and is responding to the potential and substantial impacts from large loads.7

III. THE OPERATIONAL COMPLEXITIES ASSOCIATED WITH REMEDIAL
ACTION SCHEMES AND PJM’S APPLICATION OF NERC RELIABILITY
STANDARD PRC-012-2

15. A Special Protection System (“SPS”) or Remedial Action Scheme (“RAS”) is designed to detect abnormal system conditions (e.g., abnormal system configuration) and to automatically take appropriate corrective action to maintain system stability, acceptable system voltages, and acceptable facility loading.  The term SPS has more historical context as NERC set the industry term for these protection schemes as Remedial Action Schemes, as defined in the NERC Glossary of Terms8 and described in PJM Manual 7.9  Whereas “normal” protective relaying systems are typically designed to isolate faulted elements, a RAS may take actions seemingly unrelated to the cause such as the tripping of local or remote

6 Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, North American Electric Reliability Corporation (July 2025), https://www.nerc.com/globalassets/who-we-are/standing- committees/rstc/whitepaper-characteristics-and-risks-of-emerging-large-loads.pdf (“NERC Whitepaper”).
7 NERC Whitepaper at vii.
8 Glossary of Terms Used in NERC Reliability Standards, North American Electric Reliability Corporation (Feb. 17, 2026), https://www.nerc.com/globalassets/standards/reliability-standards/glossary_of_terms.pdf (“NERC Glossary of Terms”). 9 System Planning Division Transmission Planning Department, PJM Manual 07: PJM Protection Standards, PJM Interconnection, L.L.C. (Rev. 5, Sep. 25, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m07.pdf (“PJM Manual 7”).

PDF page 7

6
system elements (including generators), generator runback, and load shedding for the purpose of maintain system or equipment reliability.

16. A RAS should not be installed as a substitute for good system design or operating practices. PJM Manuals reflect this caution of relying on such schemes on a permanent basis.  The implementation of a RAS is generally limited to temporary conditions involving the outage of critical equipment.  The decision to employ a RAS should consider the complexity of the scheme and the consequences of misoperation, as well as its benefits.  The use of a RAS, like any protection scheme, entails the risk that it will misoperate.  However, the consequences of a RAS misoperation are often more severe than those of fault protection schemes.10  While a RAS may be a temporary solution until the transmission system is reinforced, PJM Manuals indicate that PJM’s systems and operating procedures were designed to be served by NITS, eliminating the need for RAS while ensuring generation can be dispatched to serve load.11

17. PJM has a well-defined process in PJM Manual 3, section 1.7 (PJM Procedure to Review Remedial Action Schemes (RAS)),12 for new, retiring, or functional modifications to a RAS.  All RAS must meet the NERC RAS definition and comply with the NERC Reliability Standard PRC-012-2, as well as other NERC Reliability Standards applicable to RAS (e.g., PRC-005-613).

18. For any RAS, PJM, in its role as the Reliability Coordinator, reviews the scheme and provides feedback to the RAS-entity within four full calendar months or a schedule that is mutually agreed upon in keeping with R2 of NERC Reliability Standard PRC-012-2.  The scheme will be reviewed for the need and reliability purposes.  Then the owner will be provided with feedback for recommendations.  If the RAS is a viable scheme, it will be documented in PJM Manual 03B: Transmission Operation Procedures (CEII).  Consistent with PJM Manual 3, to achieve Reliability Coordinator (i.e., PJM) endorsement, the RAS will need to be endorsed by the following PJM Stakeholder Committees:

a. PJM System Operator Committee
b. PJM Relay Subcommittee (Conditional if impacting facilities 200 kV or above) c. PJM Operating Committee

d. PJM Market Implementation Committee
e. PJM Planning Committee
f. PJM Markets and Reliability Committee

10 See PJM Manual 7.
11 See System Operations Division, PJM Manual 13: Emergency Operations, PJM Interconnection, L.L.C., section 2.3 (Rev. 97, Nov. 20, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m13.pdf. (a Manual Load Dump Action is the last controlling action available to operators to resolve capacity or transmission issues).
12 Transmission Operations, PJM Manual 03: Transmission Operations, PJM Interconnections, L.L.C., section 1.7 (Rev. 69, Nov. 20, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m03.pdf (“PJM Manual 3”). 13 Standard PRC-00562 – Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance, North American Electric Reliability Corporation (Apr. 28, 2025), https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-005-6.pdf.

PDF page 8

7
19. To implement a RAS, PJM and Transmission Owner system operators will need to be trained prior to use within real-time operation.  The training ensures operators know the conditions for which the RAS will be utilized and the actions the RAS scheme will perform. PJM operators have the responsibility for directing the arming and disarming of the RAS scheme during real-time operations.  Ultimately, the PJM and Transmission Owner will need to properly screen for the contingency plus the RAS action in their respective Energy management Systems.14

20. The PJM transmission system is robust and constitutes a tightly coupled network. Practically, this means the load centers are electrically close to each other and the transmission system has multiple elements connecting to each other.

21. There is the possibility of interactions between RAS schemes in a tightly coupled network. As detailed from the NERC Incident Review, Considering Simultaneous Voltage-Sensitive Load Reductions,15 a failed lightning arrestor on the 230 kV transmission system led to the loss of approximately 1,500 megawatts within the PJM region at multiple substations.16 The diagram below illustrates the event.  Although this event was not triggered by a misoperation of a RAS, the risk of having multiple RASs within a single area increases the likelihood of a misoperation.

14 See PJM Manual 3.
15 Incident Review: Considering Simultaneous Voltage-Sensitive Load Reductions, North American Electric Reliability Corporation (Jan. 8, 2025), https://www.nerc.com/globalassets/our-work/reports/event- reports/incident_review_large_load_loss.pdf.
16 Matthew Gooding, Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once, Data Center Dynamics (Mar. 20, 2025), https://www.datacenterdynamics.com/en/news/virginia-narrowly-avoided-power- cuts-when-60-data-centers-dropped-off-the-grid-at-once/.

PDF page 9

8
22. A RAS is designed for specific conditions to occur prior to activating.  Since the PJM network is tightly coupled with multiple transmission lines, the RAS or multiple RASs will need to monitor and activate for a multitude of conditions.  Typically, a RAS monitors one specific condition and is armed to respond to one condition.  Thus, each condition would require its own RAS that can be independently armed or disarmed.  This is not ideal to operate or control the system with each scheme carrying additional risk.  Moreover, the transmission system is a dynamic system that is constantly changing with generation online or transmission outages.  The conditions for a RAS may change based on the dynamic system conditions.  As such, a pre-defined RAS may not be sufficient for all scenarios.

Similarly, with a network diagram as described above, all the interim or non-firm loads within an electrically close area may have similar violations. This could create a scenario where the loss of a facility requires reducing or dropping all the interim or non-firm load within that area.  This quick and large change in PJM system load could cause Area Control Error (“ACE”) deviations—the metric that evaluates generation to load balancing, and generator stability issues.17  Each Balancing Authority is required to calculate a Reporting ACE.  This is an important calculation that is required to be available at a minimum of 99.5% of each calendar year and a minimum accuracy of 0.001 Hz.  The Reporting ACE is used to ensure the frequency of the Eastern Interconnection (“EI”) is maintained.  There is a potential with a “local failure or misoperation” of a RAS in PJM could impact the entire EI, depending on the amount of load that is quickly removed from the system.  This is a risk identified as part of the Frequency Stability portion of the NERC Whitepaper stating: “All these issues have the potential to cause further operation of protection systems.  With each protection system operation, more [Bulk Power System] equipment is taken out of service, and the possibility for cascading outages grows.”18

23. The term “stability limits” refers to the ability of an electric system to maintain or regain an equilibrium state during normal operations or a contingency event or system disturbance.  A “contingency event” refers to an unplanned outage of a system element (lines, transformers), loss of generation, sudden large load changes, or loss of other power system elements (circuit breakers, switches, reactive devices).

24. A generator is constantly matching equal but opposite forces by the system load.  A sudden large loss of load within a short time frame, from the perspective of a generator, is like riding a bike uphill and having the chain snap.  The pedals will speed up because the bike rider (generator) cannot instantaneously respond to the chain snapping (loss of load).  If the rider was working hard, they could catapult over the handlebars and get injured (damage).  There is a similar response from nearby generators where there is a sudden loss of large load.  The generator will speed up and if severe enough, it could cause mechanical stress to generator components or damage to the machine.

17 ACE is the “instantaneous difference between a Balancing Authority’s net actual and scheduled interchange, taking into account the effects of Frequency Bias and correction for meter error.”  See NERC Glossary of Terms at 54 of PDF (definition of Area Control Error).
18 NERC Whitepaper at 25.

PDF page 10

9
25. There is one scenario where a RAS would be overwhelmingly beneficial and would have a minimal impact on the overall grid.  A RAS will be required for the loss of the Co- Located Generating Facility.  In this instance, PJM would expect the RAS to actuate on the loss of the Co-Located Generating Facility and the load served by Non-Firm Contract Demand Transmission Service or Interim NITS will automatically be removed from the system by the RAS scheme.  In other words,  after the co-located generator is offline, only the NITS or Firm Contract Demand Transmission Service will remain connected and served by PJM.  At that point, PJM could evaluate if additional non-firm load could be supported after the loss of generation occurs.

26. There are some impacts that are outside of the operations that should be noted as well.  The first is for the RAS-entity, as defined in the NERC Reliability Standard PRC-012-2.  The RAS-entity, which will typically but not always (e.g. in the case that the Eligible Customer contracts out the RAS) be the Eligible Customer, will be responsible for meeting NERC compliance.  This includes participating in analyzing the RAS operational performance after a RAS operation or failure, develop/implement Corrective Action Plans, and periodically perform functional testing.  Finally, the Planning Coordinator, in collaboration with the RAS-entity, will need to perform an evaluation of each RAS within its area.

27. This concludes my Affidavit.

PDF page 11

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company Delmarva Power & Light Company

Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company

Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.

The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.

AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

              Docket Nos. EL25-49-000
                                   EL25-49-001

PDF page 12

Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

                                  AD24-11-000

                                   EL25-20-000
                                 (Consolidated)

VERIFICATION OF MATTHEW WHARTON, PE

I, Matthew Wharton, PE, pursuant to 28 U.S.C. § 1746, state, under penalty of perjury, that I am the Matthew Wharton referred to in the foregoing “Affidavit of Matthew Wharton, PE on Behalf of PJM Interconnection, L.L.C.,” that I have read the same and am familiar with the contents thereof, and that the facts set forth therein are true and correct to the best of my knowledge, information, and belief.

/s/ Matthew Wharton
Matthew Wharton
Manager
Reliability Engineering
PJM Interconnection, L.L.C.

Executed on: February 23, 2026