Att. B - Abdulsalam Affidavit
Text extracted from the eLibrary original (SHA-256 950bf2de1b88fde5…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Attachment B
printed heading · Topic match: Connecting load and generation
I am submitting this affidavit in support of PJM’s proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order1 to establish three new transmission services for…Read this passage Filed comments: Connecting load and generation
I. QUALIFICATIONS
printed heading
I have been in my current position as the Director of PJM Transmission Planning since March 2024, and I previously served as the Senior Manager of PJM Transmission Planning.Read this passage
II. WHY NITS IS USED FOR INTERNAL TRANSMISSION SERVICE IN THE PJM
printed heading · Topic match: Reliability and curtailment
There is no guarantee to the availability of transmission capacity nor resource adequacy to support such type of load when it requests the service, nor do they affect any adjustments to transmission development or capacity procurements on a forward-looking basis.Read this passage Filed comments: Reliability and curtailment
III. THE COMPLEXITY ASSOCIATED WITH NON-FIRM CONTRACT DEMAND
printed heading · Topic match: Connecting load and generation
In order to ensure reliable and secure performance of the interconnected system, PJM must ensure the system operates strictly within the planned-for conditions.Read this passage Filed comments: Connecting load and generation
IV. WHY IS PJM RECOMMENDING THAT NON-FIRM CONTRACT DEMAND
printed heading · Topic match: Connecting load and generation
PJM proposes to limit non-firm transmission service to a maximum of 100% of generator MFO to ensure that loads that are “willing and able” to reduce their withdrawal from the system and can benefit from having a co-located generator on-site be offered their requested level of service without (i)…Read this passage Filed comments: Connecting load and generation