Attachment B
Affidavit of Dr. Sami Abdulsalam,
Director of Transmission Planning
PDF page 2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-001
PDF page 3
2
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
AFFIDAVIT OF DR. SAMI ABDULSALAM,
ON BEHALF OF PJM INTERCONNECTION, L.L.C.
1. My name is Sami Abdulsalam, Ph.D., P.Eng. I am the Director of Transmission Planning for PJM Interconnection, L.L.C. (“PJM”). My business address is 2750 Monroe Boulevard, Audubon, Pennsylvania 19403. I am submitting this affidavit in support of PJM’s proposed revisions to the PJM Open Access Transmission Tariff (“Tariff”) to comply with the Federal Energy Regulatory Commission’s (“Commission” or “FERC”) directives in its December 18, 2025 order1 to establish three new transmission services for Eligible Customers (“EC”) seeking to take service on behalf of Co-Located Load.
2. Specifically, in this affidavit, I explain:
• Why Network Integration Transmission Service (“NITS”) is used for internal (non-border) transmission service in the PJM Region, and the planning and operational benefits that NITS provides to the PJM Region;
• The complexity associated with Non-Firm Contract Demand Transmission Service from an operations and planning perspective; and
1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18, 2025 Order”).
PDF page 4
3
• The corresponding reasons why PJM is recommending that Non-Firm Contract Demand Transmission Service be limited to a maximum of 100% of the
generation Maximum Facility Output.
I. QUALIFICATIONS
3. I joined PJM in January of 2022. I have been in my current position as the Director of PJM Transmission Planning since March 2024, and I previously served as the Senior Manager of PJM Transmission Planning. My principal responsibility is to lead the development of PJM’s Regional Transmission Expansion Plan. This function centers on the planning of the regional transmission system for the provision of reliable electric service in accordance with North American Electric Reliability Corporation Reliability Standards, as well as PJM and Transmission Owner reliability and operational criteria. I will also lead the team that will implement PJM’s Long-Term Regional Transmission Planning Protocol, as accepted by FERC.
4. Prior to this position, I served as Senior Manager, Consulting at Siemens PTI where I was responsible for power system analysis, transmission planning, and protection studies; as Principal Engineer at Sustainable Grid Power, Inc.; and, for more than ten years, held various transmission planning positions of increasing responsibility, including Director, Transmission Planning and Director, Transmission System Projects, at the Alberta Electric System Operator in Canada.
5. Earlier in my career, I held various positions in the oil and gas industry, and was an Operational Engineer in thermal power plants in Egypt. My academic research focused on power system performance under voltage stability/high power transfer conditions as well as dynamic and transient behavior of power systems.
6. I hold a Bachelor of Science degree and Master of Science degree in Electrical Engineering received from the University of El-Mansoura in Egypt in 1997 and 2001, respectively. I received a Ph.D. in Electrical Engineering from the University of Alberta in Edmonton, Alberta, Canada in 2007. I also completed a post-doctoral fellowship in the Electrical and Computer Engineering Department at the University of Alberta, Edmonton, Alberta, Canada from 2007 to 2008. In addition, I am a registered Professional Engineer (P.Eng.) in Alberta, Canada.
II. WHY NITS IS USED FOR INTERNAL TRANSMISSION SERVICE IN THE PJM
REGION
7. In PJM, NITS is used for internal (non-border) transmission service in the PJM Region. The NITS type of transmission service enables a high level of reliability across the region under system normal and abnormal operating conditions. This type of service ensures the transmission network and the needed capacity to serve such load and allows PJM to plan for and secure the requisite level of service needed to accommodate changes in system conditions and the resource mix, as it shifts with time. NITS also ensures the system overall
PDF page 5
4
is “proactively” planned to a forecasted level of service and the needed resource capacity to maintain the reliability of service is secured ahead of time. Given the level of reliability offered by the NITS to its transmission service loads, such loads rarely face situations of curtailments or load shedding, as they are usually limited to extreme transmission outage conditions or resource emergency conditions.
8. In addition, PJM serves a system load that is high in density compared to its geographic footprint. The high load density in the PJM Region means that a higher load level is served from a single point of service/delivery. As a result, a higher number of customers could be exposed to interruption risk under malfunction, misoperation, or unplanned interaction between more than one necessary control technologies or protection systems, which may include Remedial Action Schemes (“RAS”). Hence, the reliability of service is critical to avoid impacting large lumps of loads under normal and contingency (outage) conditions in accordance with PJM planning criteria. Loads with non-firm transmission service would not benefit from either (i) the availability of service under normal and abnormal system operating conditions and (ii) the proactive transmission planning and capacity procurements. There is no guarantee to the availability of transmission capacity nor resource adequacy to support such type of load when it requests the service, nor do they affect any adjustments to transmission development or capacity procurements on a forward-looking basis.
III. THE COMPLEXITY ASSOCIATED WITH NON-FIRM CONTRACT DEMAND
TRANSMISSION SERVICE FROM AN OPERATIONS AND PLANNING
PERSPECTIVE
9. In order to ensure reliable and secure performance of the interconnected system, PJM must ensure the system operates strictly within the planned-for conditions. Hence, for any Co- Located Load arrangement, needed special protection schemes will be installed and set to ensure such load does not withdraw energy in excess of the megawatt level permitted under its effective service agreement. A non-firm type of transmission service will need to be evaluated on a per-request basis and will be tied to necessary control technologies or protection systems, which may include RAS (together, “protection systems”) to ensure that the contracted-for withdrawal level is not exceeded and that the pre-scheduled, non-firm withdrawal level can only be reliably enabled under conditions that PJM has agreed to.
10. Hence, PJM will allow for expedited interconnection of a Co-Located Load requesting NITS—through Interim NITS—even while the required network upgrades are pending or under construction through the design and implementation of temporary and practical protection systems. Such protection systems will allow for reliable operation of the transmission system pending energization of the identified upgrades and during the “interim” arrangement, on the further condition that such load will be curtailed prior to loads taking NITS. The temporary nature of such a protection system for this type of firm service is necessary to ensure the integrity and reliable operation of the transmission system as a whole since protection systems are designed based on system conditions anticipated at that time and will continue to change as system conditions evolve. With increased adoption of protection systems, these schemes may also interact under abnormal operating
PDF page 6
5
conditions leading to unintended consequences or even cascading actions that are not foreseen or planned for.
11. It is to be noted that the transmission facilities serving large loads will likely have multiple feeders supplying the end-user load that will vary in configuration and loading level based on end-user operating conditions. Moreover, these facilities will have redundancies that can allow for the same load to be supplied from multiple feeders for reliability purposes. Designing a protection system scheme that can selectively drop a pre-defined amount of load by discrete actions does not guarantee providing the need offered by a single protection system action and will also rely on multiple measurements and logics that all combined lead to a much-reduced reliability and security level of such a protection system. In addition, the level of load that could be served based on anticipated system conditions can vary, and having the protection systems flexible enough to be “dialed” to a specific load-level will add significant complexity as the protection system action to relief the reliability constraints could be different depending on the scheduled non-firm load level.
12. For Non-Firm Contract Demand Transmission Service, the non-firm withdrawals will be offered on a pre-scheduled/requested basis and are not guaranteed. As I mentioned earlier, this load is neither planned for (i.e., PJM’s transmission planning does not consider this load and so the system is not designed to accommodate it) nor is this load considered in PJM’s resource adequacy planning—therefore, PJM does not secure Capacity Resources to meet the load’s needs. Only the portion of the gross load for which the Eligible Customer has contracted for Firm Contract Demand Transmission Service will be enabled through any needed transmission development and Capacity Resources. The non-firm service will be offered on a scheduled, per-request basis under system conditions that are not planned- for beforehand. Since the conditions of the system coincident with such service could vary widely, it will be difficult to design a single protection system that covers and adapts all potential conditions under which the non-firm service could be offered while maintaining reliable system operation. For Non-Firm Contract Demand Transmission Service, PJM will be offering and managing these pre-scheduled services “operationally” and ensure that permanent monitoring and aggressive, fast-acting protections are in place if conditions arise that may compromise reliable system operations. This approach allows for more reliable system operation, reduces the number of permanent protection systems on the system, thereby reducing the likelihood of unintended protection system misoperation that could lead to cascading events.
IV. WHY IS PJM RECOMMENDING THAT NON-FIRM CONTRACT DEMAND
TRANSMISSION SERVICE BE LIMITED TO A MAXIMUM OF 100% OF THE
GENERATION MAXIMUM FACILITY OUTPUT?
13. The intent of the December 18, 2025 Order on Co-Located Load appears to be to provide Eligible Customers co-locating with generation behind a single Point of Interconnection flexibility in selecting transmission service that is commensurate with and reflective of their use of the transmission system and their relative willingness and ability to limit energy withdrawals from the transmission system. But the flexibility to select non-firm transmission service is not intended as a path to avoid reasonable costs of services such loads receive (either on basis of use or causation) compared to firm-load services.
PDF page 7
6
14. The order also specifically notes that the flexibility of Non-Firm Contract Demand Transmission Service is targeted at Eligible Customers using the transmission system on behalf of a Co-Located Load in a more limited manner2—e.g., Eligible Customers that rely on a “co-location” arrangement with either a proposed or existing generator that allows the Eligible Customer to supply their loads directly from the co-located generator without using the transmission system. An Eligible Customer would only need to take non-firm transmission service under limited circumstances—e.g., if the co-located generator is unavailable or operating at a reduced capacity.3
15. The order also requires Non-Firm Contract Demand Transmission Service to be requested ahead of time and on a relatively short duration basis (one hour to one month).4 This forward request for service implies foreseeable conditions where the Co-Located Load is expected to withdraw power from the PJM network. Such conditions only materialize if the generator is planned to go out of service or face operating conditions requiring its output to be derated for a relatively short timeframe. Such flexibility and conditions in operation can only exist if the non-firm load size can be served fully through the co-located generator (i.e., the generator is at least 100% of the non-firm load size).
16. By contrast, allowing for a non-firm transmission service exceeding 100% of the generator Maximum Facility Output (“MFO”), implies that the load is oversized relative to the size of the co-located generator, and is intending to lean on and use the transmission system 100% of the time for all load above the generator MFO. Load that is oversized relative to the size of the co-located generator should be required to take NITS or Firm Contract Demand Transmission Service to avoid excessive use of the resources and transmission system that have been only planned for to serve the NITS and other firm load services.
17. PJM proposes to limit non-firm transmission service to a maximum of 100% of generator MFO to ensure that loads that are “willing and able” to reduce their withdrawal from the system and can benefit from having a co-located generator on-site be offered their requested level of service without (i) compromising the level of reliability to firm loads, or
(ii) over utilizing their non-firm contract arrangements at the cost of firm service ratepayers. At the same time PJM and Transmission Owner operator intervention and assistance is reserved to be available on an as-needed basis, rather than becoming a daily, if not hourly, burden that can consequently inhibit the work of PJM operations staff.
18. This concludes my Affidavit.
2 December 18, 2025 Order at P 214 (“The new Non-Firm Contract Demand service will provide an option for Eligible Customers seeking to use the transmission system on behalf of a Co-Located Load in this more limited manner, while still charging customers for regulation and black start services, for the reasons discussed above.”).
3 December 18, 2025 Order at P 214; id., concur op. (Commissioner Rosner) at P 6.b (“[A] data center may instead elect to purchase Non-Firm Contract Demand Transmission Service if, for example, it only plans to pull energy from the grid temporarily while its co-located generator is undergoing scheduled maintenance.”).4 December 18, 2025 Order at P 215.
PDF page 8
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company
Trans-Allegheny Interstate Line Company Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.
The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000
EL25-49-001
PDF page 9
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
AD24-11-000
EL25-20-000
(Consolidated)
VERIFICATION OF DR. SAMI ABDULSALAM
I, Dr. Sami Abdulsalam, pursuant to 28 U.S.C. § 1746, state, under penalty of perjury, that I am the Sami Abdulsalam referred to in the foregoing “Affidavit of Dr. Sami Abdulsalam on Behalf of PJM Interconnection, L.L.C.,” that I have read the same and am familiar with the contents thereof, and that the facts set forth therein are true and correct to the best of my knowledge, information, and belief.
/s/ Dr. Sami Abdulsalam
Dr. Sami Abdulsalam
Director, Transmission Planning
PJM Interconnection, L.L.C.
Executed on: February 23, 2026