EL25-49-000 · 2026-02-23 · PJM Interconnection, L.L.C.

Initial Brief of PJM Interconnection, L.L.C

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems, Incorporated Atlantic City Electric Company

Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC

Hudson Transmission Partners, LLC
Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative

PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc.

The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc. AEP Ohio Transmission Company, Inc.

AEP West Virginia Transmission Company, Inc. Appalachian Power Company

Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

              Docket Nos. EL25-49-000
                                   EL25-49-001

PDF page 2

Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power City of Hamilton, OH

Southern Maryland Electric Cooperative, Inc. Ohio Valley Electric Corporation

AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.

Wabash Valley Power Association, Inc. Keystone Appalachian Transmission Company Large Loads Co-Located at Generating Facilities Constellation Energy Generation, LLC

v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

                                  AD24-11-000

                                   EL25-20-000
                                 (Consolidated)

INITIAL BRIEF OF PJM INTERCONNECTION, L.L.C. Craig Glazer

Vice President – Federal
Government Policy
PJM Interconnection, L.L.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 423-4743
craig.glazer@pjm.com

Mark J. Stanisz
Associate General Counsel
Thomas DeVita
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd,
Audubon, PA  19403
(610) 666-8800
mark.stanisz@pjm.com
thomas.devita@pjm.com
Wendy Warren
Ryan Collins
Vivian W. Chum
Qingliu (Mary) Yang
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 393-1200
warren@wrightlaw.com
collins@wrightlaw.com
chum@wrightlaw.com
yang@wrightlaw.com

Counsel for PJM Interconnection, L.L.C.

PDF page 3

TABLE OF CONTENTS
I. INTRODUCTION AND BACKGROUND … 1
II. RESPONSES TO THE PAPER HEARING QUESTIONS … 5
Question 1 … 5
A. Overview of Contract Demand Transmission Services in Illustrative
Tariff, Part XI … 5
B. Firm Contract Demand Transmission Service in Illustrative Tariff,
Part XI … 13
C. Provision of Contract Demand Transmission Services … 13
D. Nature of Contract Demand Transmission Services … 15
E. Application for Contract Demand Transmission Services … 17
F. Conditions Precedent and Technical Requirements for Contract
Demand Transmission Services … 18
G. Termination of Service Agreement for Contract Demand Transmission
Services … 20
H. Designation of Co-Located Load and Co-Located Generating
Facility … 22
I. Restrictions on Use of Service and Anti-Toggling Provision … 23
J.
Initial Study Procedures for Contract Demand Transmission Service 24
K.
Load Shedding and Curtailment for Contract Demand Transmission
Services … 25 L.

Rates and Charges for Firm Contract Demand Transmission Service 26
M.
Applicability of Operating Agreement … 28 N.

Pro Forma Contract Demand Transmission Service Agreement … 28
Question 2 … 30
A. Provision of Non-Firm Contract Demand Transmission Service … 30
B. Nature of Non-Firm Contract Demand Transmission Service … 31
C. Initiating Non-Firm Contract Demand Transmission Service … 32

PDF page 4

ii
D. Study Procedures for Non-Firm Contract Demand Transmission
Service … 33
E. Curtailment of Non-Firm Contract Demand Transmission Service ... 34
F. Necessary Control Technologies and Protection Systems to Protect the
Transmission System by Limiting Energy Withdrawals … 34
G. Rates and Charges for Non-Firm Contract Demand Transmission
Service … 36
H. Pro Forma Contract Demand Transmission Service Agreement … 37
Question 3 … 38 Question 4 … 39 Question 5 … 40

A. Disqualification or Pause in Service … 41
1. Disqualification after first failure of Eligible Customer to shed
load or curtail in accordance with established procedures … 41
2. Misoperation of necessary control technology and protection
system schemes … 43
a. Pause in service after first misoperation of a necessary
control technology or protection system scheme … 44
b. Disqualification after second necessary control
technology or protection system scheme
misoperation … 45
c. Option to take NITS following disqualification … 47
B. Financial Penalty for Unreserved Use of the PJM Transmission
System … 50 Question 6 … 52 Question 7 … 53 Question 8 … 56 Question 9 … 59 Question 10 … 62

PDF page 5

iii
Question 11 … 63
A. New Curtailment Procedures Applicable to Eligible Customers Taking
Service on Behalf of a Co-Located Load During Emergency
Operations … 63
B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm
Contract Demand Transmission Service on Behalf of a Co-Located
Load During Emergency Operations … 65
III. INTERIM NETWORK INTEGRATION TRANSMISSION SERVICE … 66
A. Provision of Interim NITS and Nature and Scope of Service … 67
B. Initiating Service … 68
C. Designation of Co-Located Load … 69
D. Study Procedures for Interim NITS … 70
E. Load Shedding and Curtailments … 71
F. Rates and Charges for Interim NITS … 73
G. Operating Agreement … 74
H. Pro Forma Service Agreement Specific to Eligible Customers Serving
Co-Located Load Via NITS or Interim NITS … 75
IV. OTHER ILLUSTRATIVE TARIFF REVISIONS … 76
V. RESERVATION OF RIGHTS TO SUPPLEMENT FILING … 78
VI. IMPLEMENTATION AND EFFECTIVE DATE … 79
VII. DOCUMENTS ENCLOSED … 82
VIII. CONCLUSION … 83

PDF page 6

INITIAL BRIEF OF PJM INTERCONNECTION, L.L.C.

Pursuant to paragraph 219 and ordering paragraphs (D) and (E) of the Order on Show Cause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and Granting in Part and Denying in Part Complaint issued by the Federal Energy Regulatory Commission (“FERC” or “Commission”) on December 18, 2025, in the above-captioned proceeding,1 PJM submits this initial brief.  The Commission found that additional record evidence was needed to set the appropriate replacement rates, terms, and conditions for several new transmission services for Eligible Customers2 serving Co-Located Load: Interim Network Integration Transmission Service (“Interim NITS”), Firm Contract Demand Transmission Service, and Non-Firm Contract Demand Transmission Service. Accordingly, the Show Cause Order established paper hearing procedures to develop a record regarding these issues.3  This initial brief responds to the Commission’s Briefing Questions and sets forth non-rate terms and conditions for these new transmission services.

I. INTRODUCTION AND BACKGROUND
PJM’s responses to the Briefing Questions and discussion of Interim NITS in Section III below focus on the non-rate terms and conditions of the new transmission services for which the Show Cause Order seeks information.  Consistent with the allocation of rights between PJM and PJM Transmission Owners under the Consolidated

1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”); see also PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et al., at 3 (Jan. 23, 2026) (granting a 7-day extension of the deadline in ordering paragraph (D) of the Show Cause Order for PJM to submit its initial brief).
2 Capitalized terms not otherwise defined herein have the meanings set forth in PJM’s Open Access Transmission Tariff (“Tariff”).
3 Show Cause Order at P 219.

PDF page 7

2
Transmission Owners Agreement (“CTOA”),4 PJM expects the PJM Transmission Owners
to file briefing in the paper hearing record generally addressing the rates for each of these new transmission services.5

PJM has also attached the following materials in addition to PJM’s responses to the Briefing Questions and discussion of Interim NITS, which PJM will refer to and rely while responding to the Briefing Questions and discussing Interim NITS.

First, Attachment A to this initial brief provides illustrative Tariff language for a new Tariff, Part XI (among other illustrative language),6 which sets forth the non-rate terms and conditions for the new transmission services available to Eligible Customers taking service on behalf of Co-Located Loads.  The language is “illustrative” in the sense that PJM is including the language in Attachment A as part of the paper hearing record and is not formally filing it until the Commission rules on the record.  As reflected in PJM’s illustrative Tariff language, PJM places priority on the reliability of the transmission grid, which requires “maintaining an uninterrupted flow of high-voltage electricity, monitoring

4 CTOA Rate Schedule FERC No. 42; see also Atl. City Elec. Co., 190 FERC ¶ 61,109, at P 3 (2025) (providing history and authority for the CTOA under Pa.-N.J.-Md. Interconnection, 105 FERC ¶ 61,294 (2003) (“Atlantic City Settlement Order”), order on compliance, 108 FERC ¶ 61,033 (2004) by explaining that “[i]n the Atlantic City Settlement Order, the Commission explained that the settlement agreement essentially divides filing rights between ‘rate-related filings and terms and conditions-related filings – with the PJM [Transmission Owners] filing the former and PJM the latter’”); Atl. City Elec., 190 FERC ¶ 61,109, at P 4 (“[I]ndividual transmission owners do not have a right to file under FPA section 205 to modify ‘terms and conditions of the PJM Tariff . . . .’” (footnote omitted)); Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002) (explaining that the initial Settlement Agreement between PJM and PJM Transmission Owners “established procedures for changes to rate design and other tariff terms for transmission services.  It permitted the transmission owners to file changes in transmission service rate design and non-rate terms and conditions to the tariff under section 205.”).
5 However, PJM has rights associated with certain rates and charges, e.g., PJM’s administrative service charges, which are discussed in response to several Briefing Questions below.
6 Illustrative Language for New Tariff, Part XI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions (Attachment A) (“illustrative Tariff”).

PDF page 8

3
congestion, and . . . preventing and, if necessary, addressing outages and emergencies within the PJM footprint.”7

On compliance with a Commission decision determining the appropriate non-rate terms and conditions, PJM will submit a new Tariff, Part XI (in the manner shown in Attachment A), and other Tariff revisions necessary to integrate the new transmission services into PJM’s markets and operations, as applicable.  That said, as detailed in this initial brief, the illustrative language in Attachment A sets forth how PJM believes these new transmission services should be requested and studied, and what their terms and conditions of service should be.

The illustrative Tariff language setting forth the non-rate terms and conditions for each of these new transmission services (Interim NITS and the two Contract Demand Transmission Services) are based in large part on PJM’s existing (regional) Network Integration Transmission Service (“NITS”) language from Tariff, Part III.8  By building from the existing Tariff, Part III for developing these new transmission services, PJM is offering terms and conditions that are already familiar to customers and stakeholders, facilitating their implementation.

Second, Attachments B through D consist of affidavits in support of PJM’s filing and as referenced in PJM’s responses to the Commission’s paper hearing questions below. In Attachment B, PJM provides the Affidavit of Dr. Sami Abdulsalam on Behalf of PJM Interconnection, L.L.C. (“Abdulsalam Aff.”).  Dr. Abdulsalam is Director of Transmission

7 Wharton Aff. ¶ 12.
8 References to PJM’s existing NITS refers to Regional NITS, which is for service with deliveries within the PJM Region, unless otherwise indicated.  PJM’s Cross-Border NITS generally is not relevant to these new transmission services, as it is for delivery outside of PJM.

PDF page 9

4
Planning for PJM and testifies on the primacy of NITS for service within the PJM Region, the complexity associated with Non-Firm Contract Demand Transmission Service from an operations and planning perspective, and limitations on Non-Firm Contract Demand Transmission Service.

In Attachment C, PJM provides the Affidavit of Matthew Wharton, on Behalf of PJM Interconnection, L.L.C. (“Wharton Aff.”).  Mr. Wharton testifies as to how PJM operationally carries out its key responsibilities as the “air traffic controller” of the PJM Region’s high-voltage electric Transmission System to ensure reliability, manage power flow, and handle emergency operations as the region’s North American Electric Reliability Corporation (“NERC”)-registered Reliability Coordinator, Balancing Authority, and Transmission Operator, as well as the operational complexities associated with RASs. In Attachment D, PJM provides the Affidavit of Timothy Horger, on Behalf of PJM Interconnection, L.L.C. (“Horger Aff.”).  Mr. Horger provides support for an effective date of June 1, 2029, for Tariff revisions implementing the three new transmission services.

PDF page 10

5
II. RESPONSES TO THE PAPER HEARING QUESTIONS
Question 1:
What are the appropriate rates, terms, and conditions for the new Firm Contract Demand transmission service, including whether it would be just and reasonable to apply the current zonal firm PTPS charges to this new service and whether it would be just and reasonable and consistent with cost causation to include charges for any of PJM’s administrative services?9

Response to Question 1:
Below, PJM describes the specific non-rate terms and conditions for the new Firm Contract Demand Transmission Service, but it is important to first understand the relationship between the new Firm Contract Demand Transmission Service and the new Non-Firm Contract Demand Transmission Service.  Thus, PJM will first provide an overview of the two transmission services and how, together, they will provide an alternative to NITS for those Co-Located Loads willing and able to limit energy withdrawals from the Transmission System.  Then, PJM will detail, in response to Question 1, the non-rate terms and conditions for Firm Contract Demand Transmission Service, and then detail, in response to Question 2, the non-rate terms and conditions for Non-Firm Contract Demand Transmission Service.

A. Overview of Contract Demand Transmission Services in Illustrative Tariff, Part XI

The Show Cause Order requires PJM to develop and implement two new contract demand transmission services, Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.  These new services are to “serve as permanent alternatives to existing transmission services, unlike the new interim, non-firm transmission service, . . . . and the new transmission services would not require the

9 For simplicity, internal citations from the Show Cause Order have been omitted.

PDF page 11

6
Co-Located Load to become Network Load.”10  Contract Demand Transmission Services
are intended to provide options beyond full NITS to Eligible Customers taking service on behalf of Co-Located Loads that are “willing and able to control their withdrawals from the transmission system.”11

As directed by the Show Cause Order, PJM has conceptualized Contract Demand
Transmission Services based on two key principles:  (1) the services are designed to serve loads that are “willing and able to control their withdrawals from the transmission system;”12 and (2) the services are designed to allow PJM to maintain system reliability.13 The two Contract Demand Transmission Services are designed to work together to provide the opportunity for transmission service to serve the entire gross demand of the Co-Located Load.

In short, for reliability reasons, the portion of the Co-Located Load for which the Co-Located Generating Facility will dedicate its output (in whole or in part) may be covered by Non-Firm Contract Demand Transmission Service, but any portion of the gross demand of the Co-Located Load not served by the Co-Located Generating Facility must be covered by Firm Contract Demand Transmission Service.  This approach is necessary to maintain reliability, while allowing these loads to obtain transmission service based on their

10 Show Cause Order at P 206.
11 Id. at PP 204, 206. 12 Show Cause Order at P 204.
13 See, e.g., id. at PP 201 (“[T]his new interim, non-firm transmission service will facilitate the timely provision of transmission service to Eligible Customers taking transmission service on behalf of Co-Located Loads, while preserving reliability for other transmission customers.”), 212 (“We also note that, as discussed in the briefing questions below, PJM will determine the technical and engineering requirements of special protection schemes to help address reliability risks associated with unreserved use of the transmission system.”) & 227 (discussing requirement that would “provide additional clarity and transparency regarding the steps that PJM and Interconnection Customers are taking to maintain transmission system reliability before an existing generating facility can serve Co-Located Load”).

PDF page 12

7
willingness and ability to limit energy withdrawals.  To ensure reliability PJM’s studies of the transmission service requests for the Co-Located Load, and the Co-Located Load’s impact on the Transmission System, must capture the effects of any unscheduled energy withdrawals by the Co-Located Load, even if inadvertent or limited in duration (e.g., unit trip, failure of control technologies or protective schemes) and validate that such events would not jeopardize system reliability.14  In other words, there can be no “unstudied” and/or “unknown” portion of the Co-Located Load that is not covered by either Firm

Contract Demand Transmission Service or dedicated generation from the Co-Located
Generating Facility (as backed up by Non-Firm Contract Demand Transmission Service). Without such a requirement, PJM will not have visibility into situations that may jeopardize grid reliability, including load taking service beyond levels for which PJM has properly studied and planned.  This would expose the Transmission System to risk of equipment damage, unintended relay operations, and cascading outages.

To illustrate, assume a Co-Located Load with a gross demand of 900 megawatts
(“MWs”), and a Co-Located Generating Facility of 500 MWs.  The Co-Located Generating

14 Consistent with Commission directives in Order Nos. 845 and 845-A and language already embedded in PJM’s Tariff, PJM’s proposal here uses the term “necessary control technologies and protection systems,” which may include Remedial Action Schemes (“RASs”).  Reform of Generator Interconnection Procedures and Agreements, Order No. 845, 163 FERC ¶ 61,043, at P 396 (2018) (requiring “any interconnection customer that seeks interconnection service below its generating facility capacity install appropriate monitoring and control technologies at its generating facility”), order on reh’g & clarification, Order No. 845-A, 166 FERC ¶ 61,137, at P 114 (“[I]f the interconnection customer requests interconnection service below generating capacity, it commits to operate consistent with such a request under section 3.1 of the pro forma LGIP, which states that ‘[t]he necessary control technologies and protection systems . . . for exceeding the level of Interconnection Service established in the executed, or requested to be filed unexecuted, LGIA shall be established in Appendix C of that executed, or requested to be filed unexecuted, LGIA.’” (alteration in original) (footnote omitted)), order on reh’g & clarification, Order No. 845-B, 168 FERC ¶ 61,092 (2019); see also Tariff, Part IV, Subpart A, section 36.1.1A (“The necessary control technologies and protection systems shall be established in Tariff, Attachment O, Schedule K (Requirements for Interconnection Service Below Full Electrical Generating Capability) of the executed, or requested to be filed unexecuted Interconnection Service Agreement.”).

PDF page 13

8
Facility commits to dedicating 400 MWs of its output to the Co-Located Load.15  Here, the Eligible Customer designated by the Co-Located Generating Facility16 must contract for Firm Contract Demand Transmission Service of at least 500 MWs to cover the difference between the dedicated output of the Co-Located Generating Facility (400 MWs) and the gross demand of the Co-Located Load (900 MWs).17  Given the quality of Firm Contract Demand Transmission Service, this means that, generally speaking, the gross demand of the Co-Located Load (here, 900 MWs) should be met under most conditions by the portion of the Co-Located Generating Facility dedicated to the Co-Located Load (here, 400 MWs) plus the Firm Contract Demand Transmission Service the Eligible Customer takes from the Transmission System (here, 500 MWs).  This is illustrated by Figure 1 below.

15 The Co-Located Generating Facility would be free to offer the 100 MWs of Installed Capacity into PJM’s capacity market or be an energy-only resource.  However, the portion of Co-Located Generating Facility dedicated to the Co-Located Load would be ineligible to participate in PJM’s capacity market.  See PJM Transmittal Letter, section II.C (Necessary Studies and Necessary Studies Agreement).
16 Depending on the status of the Co-Located Generating Facility, the designation of the Eligible Customer will be in its Application or Service Agreements, such as its Generator Interconnection Agreement (“GIA”).
17 The Eligible Customer is free to contract for greater amounts of Firm Contract Demand Transmission Service than necessary to cover the portion of the Co-Located Load’s demand not met by the Co-Located Generating Facility.  For example, in the illustration above, the Eligible Customer may choose to contract for 500 MWs of Firm Contract Demand Transmission service and still dedicate 400 MWs of its Co-Located Generating Facility to its Co-Located Load.

PDF page 14

9
Figure 1:  Illustration of Relationship between Contract Demand Transmission Services and portion of Co-Located Generating Facility Dedicated to Co-Located Load

A Co-Located Generating Facility will not always be available (e.g., due to planned or unforced outage).  To the extent that the gross demand of a Co-Located Load is not covered by the Eligible Customer’s Firm Contract Demand Transmission Service, the Eligible Customer must cover the remaining gross demand by applying for Non-Firm Contract Demand Transmission Service.  In that case, the Non-Firm Contract Demand Transmission Service, if PJM determines it is available for the requested period, will act as a backup to allow the Co-Located Load to meet its full demand, while the portion of the Co-Located Generating Facility dedicated to the Co-Located Load is on outage and unable to provide energy.

Dr. Abdulsalam explains that Non-Firm Contract Demand Transmission Service offers non-firm withdrawals “on a pre-scheduled/requested basis and are not guaranteed.”18 This is consistent with the Show Cause Order’s finding that the Non-Firm Contract

18 Abdulsalam Aff. ¶ 12.

PDF page 15

10
Demand Transmission Service is intended for “Eligible Customers seeking to use the transmission system on behalf of a Co-Located Load in this more limited manner” by seeking a “transmission reservation for a Co-Located Load in advance for the duration of an expected outage of the associated generator.”19

More specifically, PJM will offer and manage pre-scheduled Non-Firm Contract Demand Transmission Service “‘operationally’ and ensure that permanent monitoring and aggressive, fast-acting protections are in place if conditions arise that may compromise reliable system operations.”20  This approach, as Dr. Abdulsalam explains, “allows for more reliable system operation, reduces the number of permanent protection systems on the system,” such as a RAS, on the PJM Transmission System, and thus “reduc[es] the likelihood of unintended protection system misoperation that could lead to cascading events.”21

In addition, as explained further below, and by Dr. Abdulsalam, from an operations and planning perspective, the complexities associated with the provision of Non-Firm Contract Demand Transmission Service call for relying on such service as a standby product only “under limited circumstances.”22  For example, an Eligible Customer that typically supplies load “directly from the co-located generator without using the transmission system” may rely on Non-Firm Contract Demand Transmission Service when the “co-located generator is unavailable or operating at a reduced capacity,”23 to enable the

19 Show Cause Order at P 214.
20 Abdulsalam Aff. ¶ 12.
21 Abdulsalam Aff. ¶ 12.
22 Abdulsalam Aff. ¶ 14. 23 Abdulsalam Aff. ¶ 14 (footnote omitted).

PDF page 16

11
Eligible Customer to substitute energy from the PJM Transmission System for the energy provided by the Co-Located Generating Facility.

Flexibility is built into PJM’s approach, which allows Eligible Customers to mix and match between Firm and Non-Firm Contract Demand Transmission Service when taking service on behalf of Co-Located Load, so long as the combination of the two services covers the entire gross demand of the Co-Located Load.  PJM’s approach also ensures that there is the opportunity to take transmission service even in the event a Co-Located Generating Facility is unable to provide energy consistent with its dedicated quantity. This approach is compliant with the Show Cause Order’s statement that “Eligible Customers taking transmission service on behalf of Co-Located Loads would . . . be able to take a combination of Firm Contract Demand transmission service and Non-Firm Contract Demand transmission service.”24  Additionally, the Commission explained that “the Eligible Customer may combine Firm Contract Demand transmission service with Non-Firm Contract Demand transmission service to withdraw, on an as-available basis, more energy than its firm entitlement.”25  Accordingly, PJM is allowing an Eligible Customer taking transmission service on behalf of a Co-Located Load to choose either Firm or Non-Firm Contract Demand Transmission Service, or some combination of the two so long as the Eligible Customer takes service that fully covers the Co-Located Load’s total energy needs.

24 Show Cause Order at P 206.
25 Show Cause Order at P 208 n.437; illustrative Tariff, Part XI, Subpart B, section 708.

PDF page 17

12
Also, as discussed in PJM’s Transmittal Letter,26 PJM is filing Tariff revisions which, as required by the Show Cause Order,27 provide that an Eligible Customer taking transmission service on behalf of a Co-Located Load that is taking Firm and/or Non-Firm Contract Demand Transmission Service may not also take NITS or Interim NITS on behalf of the same Co-Located Load.  Thus, while an Eligible Customer may choose some combination of Firm and Non-Firm Contract Demand Transmission Service, NITS and Interim NITS cannot be mixed with either one of the Contract Demand Transmission Services.28

Consistent with the directives and findings of the Show Cause Order, PJM developed non-rate terms and conditions for offering Contract Demand Transmission Service on firm and non-firm bases.  Attachment A to this initial brief includes an illustrative Tariff, Part XI, Subpart B, and sections 708 through 716 detail non-rate terms and conditions for the two new Contract Demand Transmission Services.  PJM also developed an Attachment F-4 to be the new pro forma Service Agreement for both Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.  That is, an Eligible Customer taking Firm and Non-Firm Contract Demand Transmission Service on behalf of a Co-Located Load will require only a single Service Agreement setting for the applicable terms for each service.  Such an approach is reasonable, as the two services are generally going to be taken simultaneously to ensure

26 PJM Transmittal Letter at 26-29 (discussing revisions to Part III).
27 Show Cause Order at PP 189, 193.
28 See Show Cause Order at P 206 (Eligible Customer “would also be able to take a combination of Firm Contract Demand transmission service and Non-Firm Contract Demand transmission service.”).

PDF page 18

13
the entire gross demand of the Co-Located Load can be covered by the Transmission System.29

Although the “shell” of Attachment F-4 is being filed concurrently as part of PJM’s compliance filing,30 the full illustrative text of Attachment F-4 is in Attachment A to PJM’s initial brief.

B. Firm Contract Demand Transmission Service in Illustrative Tariff,
Part XI
Attachment A describes Firm Contract Demand Transmission Service as the
transfer of capacity and energy for an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, predetermined MW level of transmission service as requested by the Eligible Customer and confirmed by PJM, using capacity and energy procured by PJM.31

PJM’s response to Question 1 below, covers (i) Tariff, Part XI provisions that apply to both Firm and Non-Firm Contract Demand Transmission Service; and (ii) Tariff, Part XI provisions that only apply to Firm Contract Demand Transmission Service.  Provisions that only apply to Non-Firm Contract Demand Transmission Service will be discussed further in response to Question 2 below.

C. Provision of Contract Demand Transmission Services
In Attachment A, section 708, PJM provides illustrative language detailing the scope of Contract Demand Transmission Service on both a Firm and Non-Firm basis.

29 Of course, to the extent an Eligible Customer takes only one of the two new contract demand transmission services, the portions of the agreement unrelated to the subscribed service will be inapplicable.
30 See PJM Transmittal Letter, Attachment A (Tariff Revisions (Clean)) and Attachment B (Tariff Revisions (Redline)).
31 Illustrative Tariff, Part XI, Subpart B, section 708.

PDF page 19

14
Firm Contract Demand Transmission Service will be provided to Eligible
Customers taking service on behalf of Co-Located Loads pursuant to the applicable terms and conditions in the Tariff and the Service Agreement for Contract Demand Transmission Service, provided in proposed Attachment F-4.32  The Commission instructed PJM to design its Firm Contract Demand Transmission Service to allow customers to take capacity and energy from the Transmission System up to a defined, predetermined MW level.33  The Commission stated, however, that while “Firm Contract Demand transmission service will have the same reservation and curtailment priority as existing firm transmission services, at the level of contract demand . . . unlike NITS customers, the Eligible Customer taking Firm Contract Demand transmission service on behalf of the Co-Located Load is not permitted to withdraw energy from the PJM transmission system beyond the contract demand level.”34  For both Contract Demand Transmission Services, Eligible Customers must be willing and able to limit withdrawals of energy from the Transmission System as required by PJM.35

A demonstrated and proven ability to limit withdrawals from the system is crucial to the reliability of the PJM system and to prevent Contract Demand Transmission Services from having an adverse impact on the electric system’s reliability and, per the Show Cause Order, a fundamental characteristic of Contract Demand Transmission Service.36

32 Illustrative Tariff, Part XI, Subpart B, section 708.
33 Show Cause Order at P 208; illustrative Tariff, Part XI, Subpart B, section 708.
34 Show Cause Order at P 208 (footnote omitted).
35 Illustrative Tariff, Part XI, Subpart B, section 708.
36 Show Cause Order at P 204 (The Commission stated that Eligible Customers seeking Contract Demand Transmission Services must be “willing and able to control their withdrawals from the transmission system.”).

PDF page 20

15
Relatedly, Co-Located Loads must be separately metered from the Co-Located Generating Facility.37  For Firm Contract Demand Transmission Service to properly function, it is essential that any associated Non-Firm Contract Demand Transmission Service taken on behalf of the same Co-Located Load has in place necessary control technologies and/or protective systems, which may include RASs, that are approved by PJM and that can effectively limit withdrawals from the Transmission System that serve Co-Located Loads.38  While the details surrounding such protective technologies and systems are detailed further below in response to Question 5, the need for such associated with the provision of Non-Firm Contract Demand Transmission Service is also discussed in response to Question 2.

Illustrative Tariff, Part XI, Subpart B, section 708 also provides that Eligible Customers must request both Firm and Non-Firm Contract Demand Transmission Service through their Transmission Provider by filing an Application, detailed further below.

D. Nature of Contract Demand Transmission Services
As required by the Show Cause Order, Firm Contract Demand Transmission
Service will also have priority over Non-Firm Contract Demand Transmission Service and will have equal priority, at the level of the contract demand, with other firm transmission services, including NITS.39

37 Show Cause Order at P 206; see illustrative Tariff, Part XI, Subpart B, section 710.4 (“[T]hese technical requirements include, but are not limited to: (i) installation of necessary hardware and software to limit energy withdrawals, including metering equipment . . . .”).
38 Illustrative Tariff, Part XI, Subpart B, section 708; see Show Cause Order at P 205 (“[I]n these instances where the Co-Location Arrangement includes special protection schemes that limit its energy withdrawals, we find that it is a just and reasonable replacement rate to allow an Eligible Customer taking transmission service on behalf of such load to take and be charged for new types of transmission service that are alternatives, and not equivalent, to NITS.”).
39 Illustrative Tariff, Part XI, Subpart B, section 709.1; Show Cause Order at P 208.

PDF page 21

16
Attachment A, section 709.2 details the scope of service for both Firm and Non-Firm Contract Demand Transmission Service.  An Eligible Customer requesting Firm Contract Demand Transmission Service will receive firm transmission service on behalf of a Co-Located Load up to its contract demand amount, as detailed in the applicable Service Agreement.  An Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm Contract Demand Transmission Service equivalent to the MW level of the Co-Located Generating Facility dedicated to serving the Co-Located Load, and an Eligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm Contract Demand Transmission Service on a given Operating Day only to the extent the portion of the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage.

Conversely, as discussed above in the overview section, an Eligible Customer taking service on behalf of a Co-Located Load must request Firm Contract Demand Transmission Service for no less than the MW level of the gross demand of the Co-Located Load that will not be served by the dedicated Co-Located Generating Facility.  As required by the Show Cause Order,40 for any given Co-Located Load, once an Eligible Customer has taken, or is applying for NITS or Interim NITS on behalf of such Co-Located Load, an Eligible Customer will not be eligible to apply for or take Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service for that same Co-Located Load.41  Finally, any material change in the MW level of the gross-demand of

40 Show Cause Order at P 200.
41 Illustrative Tariff, Part XI, Subpart B, section 709.3.

PDF page 22

17
the Co-Located Load, or in the output of the Co-Located Generating Facility would require a new Application.42

E. Application for Contract Demand Transmission Services
Illustrative section 710 in Attachment A details how an Eligible Customer seeking transmission service on behalf of a Co-Located Load will initiate service requests for Firm and Non-Firm Contract Demand Transmission Service.  Any request for Firm and/or Non-Firm Contract Demand Transmission Service must comply with the Commission’s requirements for new transmission service requests in 18 C.F.R. § 2.20, plus several data points specific to Contract Demand Transmission Service, including several items listed in section 710.2:

• “a description of the supply characteristics of the Co-Located Generating Facility . . . , including the generation profile, its Maximum Facility Output, the megawatt level dedicated to serving the Co-Located Load, and other

technical specifications;”
• “[a] description of the demand characteristics of the Co-Located Load . . . , including the demand profile and other technical specifications;” and

• “[t]he transmission capacity requested for the Delivery Point on the
Transmission Provider’s Transmission System behind which the Co-
Located Load and Co-Located Generating Facility are located.”
Upon receiving an Application, and the information required in section 710, PJM would evaluate whether the requested level of Firm Contract Demand Transmission Service and/or Non-Firm Contract Demand Transmission Service can be reliably provided. To do so, PJM would “coordinate with the affected Transmission Owner(s) to complete studies, including load integration studies, [to obtain] data relevant to the determination of

42 Illustrative Tariff, Part XI, Subpart B, section 709.2(e) (“After an Eligible Customer has submitted an Application for Contract Demand Transmission Service for a given Co-Located Load, any material change in the megawatt level of the gross-demand of the Co-Located Load or in the megawatt level of the Co-Located Generating Facility dedicated to the Co-Located Load would require a new Application.”).

PDF page 23

18
whether (and to what level)” Firm or Non-Firm Contract Demand Transmission Service “can be reliably provided” and “identify any necessary enhancements to the Transmission System to accommodate the requested level of service.”43  PJM’s Tariff language also recognizes that “[d]uring this study period, Transmission Provider may also perform other studies.”44

Based on the studies, PJM, in consultation with the affected PJM Transmission Owner(s), will determine the level of Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service that can be reliably provided and inform the Eligible Customer.45

F. Conditions Precedent and Technical Requirements for Contract Demand
Transmission Services
Prior to obtaining service, the Eligible Customer must meet several enumerated conditions precedent, many of which are ministerial in nature but have significant importance in ensuring that the Eligible Customer can receive its service while preserving the reliability of the Transmission System.

Specifically, among several enumerated conditions precedent, the language would require the Eligible Customer to comply with the provisions of the “PJM Credit Policy” set forth in Tariff, Attachment Q; “certify[y] that it is willing and able to limit energy withdrawals from the Transmission System when requested by [PJM];” “complete[] other

43 Illustrative Tariff, Part XI, Subpart B, section 710.3 (“Descriptions of the Transmission Provider’s and/or the applicable Transmission Owner(s)’ specific methodology for assessing whether Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or both can be reliably provided, will be set forth in Tariff, Part XI, Section 712, the PJM Manuals, and set forth in Transmission Owner standards, as applicable.”).
44 Illustrative Tariff, Part XI, Subpart B, section 710.3.
45 Illustrative Tariff, Part XI, Subpart B, section 710.3.

PDF page 24

19
certification requirements provided in the PJM Manuals,” including to be an Electric Distributor, as applicable; and “otherwise execute, if necessary, and comply with the PJM Governing Agreements.”46  In addition and crucially, the Eligible Customer must have been designated to take transmission service on behalf of a Co-Located Load in the relevant Application, Service Agreement, or GIA for the Co-Located Generating Facility, and provide PJM with “an authorization or certification from its Relevant Electric Retail Regulatory Authority which affirms that the Eligible Customer is authorized to provide energy to the Co-Located Load.”47

Illustrative Tariff, Part XI, Subpart B, sections 710.4 and 710.5 provide that certain facilities and necessary technical arrangements, such as an RAS, must be completed prior to commencement of requested service.48  Indeed, the Eligible Customer must “construct[], maintain[], and operat[e] the facilities (i) on its side of the Delivery Point necessary to reliably deliver and receive energy and capacity; and (ii) only in the case of Non-Firm Contract Demand Transmission Service, to implement the necessary control technologies and protection systems required pursuant to Tariff, Part XI, Subpart B, section 713 and specified in the Service Agreement for Contract Demand Transmission Service, as Transmission Provider may require.”49  Such facilities are necessary for the Eligible Customer to receive transmission service at its Delivery Point and to limit unauthorized

46 Illustrative Tariff, Part XI, Subpart B, section 710.1.
47 Illustrative Tariff, Part XI, Subpart B, section 710.1.
48 Illustrative Tariff, Part XI, Subpart B, section 710.4.
49 Illustrative Tariff, Part XI, Subpart B, section 710.5.

PDF page 25

20
withdrawals, consistent with the key principles underlying Contract Demand Transmission Service.50

Section 710.6 details the required steps for execution and filing of Service Agreements for the requested transmission service type.51  These procedures are modeled on those the Commission recently accepted for GIAs.52

G. Termination of Service Agreement for Contract Demand Transmission
Services
Consistent with the Show Cause Order’s holding that Contract Demand
Transmission Services are to be a “permanent alternative” to NITS, PJM’s approach in section 710.7 allows for a Service Agreement for Contract Demand Transmission Service to be “presumed to continue without expiration.”  PJM does set forth five circumstances under which it may be terminated.53  Three of the circumstances are mundane in nature:

(i) where an incumbent Eligible Customer is replaced by a successor Eligible Customer;54
(ii) on 42-months’ notice prior to the commencement of a Delivery Year; and (iii) by mutual agreement.55  The 42-month notice period is appropriate because the contracted-for service level under a Firm Contract Demand Transmission Service will be accounted for in

50 See Abdulsalam Aff. ¶¶ 9-12.
51 Illustrative Tariff, Part XI, Subpart B, section 710.6. 52 Tariff, Part VIII, Subpart D, section 411 (Final Negotiation Phase); PJM Interconnection, L.L.C., 192 FERC ¶ 61,077, at PP 66-70 (2024).
53 Illustrative Tariff, Part XI, Subpart B, section 710.7.
54 Illustrative Tariff, Part XI, Subpart B, section 710.7.
55 Illustrative Tariff, Part XI, Subpart B, section 710.7.

PDF page 26

21
PJM’s capacity market,56 as required by the Show Cause Order.57  Thus, given the 3-year forward nature of PJM’s capacity market—and the pre-auction development and posting

or relevant auction parameters, PJM must have sufficient notice to not include such contract demand in its Load Forecast for the relevant Delivery Year.58  The 42-months’ notice period is consistent with the termination provision in PJM’s pro forma pseudo-tie agreement and is designed to address the capacity market participation concerns.59

However, there are circumstances under which PJM could terminate the Service
Agreement for cause.  One, where the Eligible Customer “is in breach of its obligations under the Service Agreement or the Tariff, Part XI,” which could include, for example, “any material changes to the gross demand of the Co-Located Load or the design,

configuration, or output of the Co-Located Generating Facility occur without being studied by [PJM] to determine whether such changes would affect [PJM’s] ability to reliably

provide the level of service specified in the Eligible Customer’s Contract Demand
Transmission Service Agreement.”60  Two, the Eligible Customer is disqualified from
receiving Contract Demand Transmission Service upon an Eligible Customer’s failure to follow an operating instruction to curtail or shed load, or after the misoperation, on more

56 Illustrative Tariff, Part XI, Subpart B, section 708(b) (“Firm Contract Demand Transmission Service is for the transfer of capacity and energy to an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, predetermined megawatt level of transmission service as requested by the Eligible Customer and confirmed by the Transmission Provider, using capacity and energy procured by the Transmission Provider.”).
57 See Show Cause Order at P 210 (“PJM will procure generation capacity on behalf of the Co-Located Load served by Firm Contract Demand transmission service based on their contract demand[.]”).
58 See Horger Aff. ¶¶ 11-14.
59 See PJM Interconnection, L.L.C., 162 FERC ¶ 61,086, at P 89 (2018) (“Regarding PJM’s proposal for 42- months’ notice of a request to terminate where there is no system reliability concern, we agree that 42-months’ notice is an appropriate timeframe because it provides pseudo-tied resources with sufficient notice and allows PJM sufficient time to address changes in capacity market participation.”), reh’g denied, 167 FERC ¶ 61,069, at P 21 (2019).
60 Illustrative Tariff, Part XI, Subpart B, section 710.7(d).

PDF page 27

22
than one occasion, of any of the necessary control technologies or protection systems required under an Eligible Customer’s Non-Firm Contract Demand Transmission Service Agreement.  These latter circumstances are explained in response to Questions 5 and 6 below.

H. Designation of Co-Located Load and Co-Located Generating Facility
The Show Cause Order requires the Co-Located Generating Facility to “designat[e] an Eligible Customer . . . take transmission service on behalf of a Co-Located Load.”61 Consistent with this requirement, Attachment A, section 711 requires that an Eligible Customer designate the individual Co-Located Load on behalf of which the Eligible Customer is taking Contract Demand Transmission Service, whether it is Firm, Non-Firm, or both.62  The Eligible Customer must also designate the individual Co-Located Generating Facility that will serve the individual Co-Located Load that is designated by the Eligible Customer and provide the MW level of energy from the Co-Located Generating Facility dedicated to serving the Co-Located Load.63  Upon designation, no change in the Delivery Point for Contract Demand Transmission Service will be permitted.64

In order to maintain PJM’s operational visibility of the system and support efforts to manage reliability, Eligible Customers shall have an ongoing obligation to provide the Transmission Provider with timely written or electronic notice of material changes in the

61 Show Cause Order at P 226.
62 Illustrative Tariff, Part XI, Subpart B, section 711.1(a).
63 Illustrative Tariff, Part XI, Subpart B, section 711.1(b).
64 Illustrative Tariff, Part XI, Subpart B, section 711.2.

PDF page 28

23
demand characteristics of the Co-Located Load and the supply characteristics of the Co-Located Generating Facility.65

Necessary control technologies and protection systems for Non-Firm Contract Demand Transmission Service will be designed based on the specific circumstances and technical arrangements of each Co-Located Load arrangement, as outlined in each Service Agreement for Contract Demand Transmission Service.  Thus, any material changes to such control technologies and protection systems could have deleterious effects on the efficacy of the control technologies and protection systems and PJM’s ability to reliably operate the system.  Thus, failure to timely inform PJM of such material changes “may constitute a breach of the Eligible Customer’s Service Agreement and subject to termination under Tariff, Part XI, Subpart B, section 710.7.”66

I. Restrictions on Use of Service and Anti-Toggling Provision
To prevent retail sales, Eligible Customers will be prohibited from using Firm Contract Demand Transmission Service for the sale of either capacity or energy to loads other than those Co-Located Loads designated in its Service Agreement or the direct or indirect provision of transmission services by the Eligible Customer to third parties.67 The Commission recognized that an anti-toggling mechanism is necessary to avoid a situation in which an Eligible Customer taking transmission service on behalf of a Co-Located Load attempts to switch between Firm and Non-Firm Contract Demand Transmission Service for the same portion of total contracted demand based on expected

65 Illustrative Tariff, Part XI, Subpart B, section 711.3. 66 Illustrative Tariff, Part XI, Subpart B, section 711.3.
67 Illustrative Tariff, Part XI, Subpart B, section 709.3.

PDF page 29

24
capacity market conditions.68  PJM has included a proposed anti-toggling provision at Attachment A, section 709.4, which is described further below in response to Question 7.69 J.

Initial Study Procedures for Contract Demand Transmission Service
After receiving a completed Application for Firm Contract Demand Transmission Service by an Eligible Customer, PJM will notify the affected Transmission Owner(s) of the completed Application.70  The affected Transmission Owner(s) and PJM may need to coordinate to study potential impacts of providing Firm Contract Demand Transmission Service on the Transmission Owner’s system.71  PJM will then determine, in accordance with PJM Manuals, any necessary studies to provide the requested transmission service.72 If necessary studies are required, PJM will inform the Eligible Customer and will consider any results of the Transmission Owner studies.73  If PJM determines that necessary studies are needed to evaluate the requested transmission service request, PJM will provide an Application and Studies Agreement to the Eligible Customer in which the Eligible Customer will agree to reimburse PJM for the required study costs.  The Eligible Customer must execute an Application and Studies Agreement within 15 days of receiving notice from PJM and pay the study fee.  An Eligible Customer that does not execute an Application and Studies Agreement will be deemed withdrawn with the fee returned with

68 Show Cause Order at P 213 (“[T]he terms and conditions for taking the new Firm Contract Demand transmission service… must include an anti-toggling mechanism.”). 69 Illustrative Tariff, Part XI, Subpart B, section 709.4.
70 Illustrative Tariff, Part XI, Subpart B, section 712.1.
71 Illustrative Tariff, Part XI, Subpart B, section 712.1.
72 Illustrative Tariff, Part XI, Subpart B, section 712.1.
73 Illustrative Tariff, Part XI, Subpart B, section 712.1.

PDF page 30

25
interest.74  Finally, the Eligible Customer will be required to pay a study fee, as determined by PJM, to apply for Contract Demand Transmission Service.75

K.
Load Shedding and Curtailment for Contract Demand Transmission
Services
The Commission directed that, “[f]or the Eligible Customer taking transmission service on behalf of a co-Located Load to be eligible for these new transmission services, the co-Located Load must be able and willing to prevent or limit its energy withdrawals . . . .”76

PJM addresses the reasoning underlying its Curtailment and Load Shedding provisions in direct response to Question 11 below, but PJM takes the opportunity to describe those provisions here as requested by Question 1.  Consistent with the key principle that an Eligible Customer taking Contract Demand Transmission Service is willing and able to limit energy withdrawals from the Transmission System, section 713 details the Curtailment and Load Shedding rules for the two Contract Demand Transmission Services.

Specifically, an Eligible Customer must implement any Load Shedding or Curtailment directive ordered by PJM, and must respond 24 hours a day, 7 days a week, 365 days a year, to any real-time instruction to reduce or curtail load within five minutes of the directive.77  PJM will make Curtailments on a non-discriminatory basis.78  Load Shed instructions will be directed toward Eligible Customers in a manner that is consistent with

74 Illustrative Tariff, Part XI, Subpart B, section 712.3.
75 Illustrative Tariff, Part XI, Subpart B, section 712.4.
76 Show Cause Order at P 206.
77 Illustrative Tariff, Part XI, Subpart B, section 713.1.
78 Illustrative Tariff, Part XI, Subpart B, section 713.1.

PDF page 31

26
previously established procedures under the Service Agreement for Contract Demand Transmission Service.79

For purposes of Curtailment, Firm Contract Demand Transmission Service is to be treated as the equivalent of NITS.  Applying the same level of Curtailment priority as between Firm Contract Demand Transmission Service and NITS is reasonable, given that for both services, PJM will plan the Transmission System and procure capacity to meet their resource adequacy needs.  Further, this is compliant with the Show Cause Order’s holding that “Firm Contract Demand transmission service will have the same reservation and curtailment priority as existing firm transmission services, at the level of the contract demand.”80

PJM reserves the right to curtail Contract Demand Transmission Service to maintain system reliability.81  Processes and procedures applicable to control technologies and protection systems (e.g., RAS), along with disqualification from Contract Demand Transmission Service and penalties for unreserved use of the system, are detailed further below in response to Question 5.82

L.
Rates and Charges for Firm Contract Demand Transmission Service
Consistent with the allocation of rights between PJM and PJM Transmission Owners,83 PJM expects the PJM Transmission Owners to file briefing in the paper hearing record describing the proposed transmission rates for each of these new transmission

79 Illustrative Tariff, Part XI, Subpart B, section 713.2.
80 Show Cause Order at P 208.
81 Illustrative Tariff, Part XI, Subpart B, section 713.5. 82 See illustrative Tariff, Part XI, Subpart B, sections 713.6, 713.7 & 713.8.
83 See supra note 4.

PDF page 32

27
services for Co-Located Load.  However, Eligible Customers will be assessed other rates in addition to transmission service rates, and PJM has authority to institute such non- transmission-related rates.  Thus, section 714 provides that PJM would assess:

• administrative services charges under Tariff, Schedule 1A; Tariff, Schedule 9; and Tariff, Schedule 10 based on the total quantity of megawatt hours (“MWhs”) of energy delivered using Firm Contract Demand Transmission Service, except in the case of any capacity-related charges under these schedules, which shall be based on the Eligible Customer’s Unforced Capacity Obligation;84

• Ancillary Services charges, except for Regulation, based on the total quantity in MWhs of energy delivered to the Co-Located Load using Firm Contract Demand Transmission Service in accordance with Tariff, Part I, section 3;85

• Black Start Service charges based on the gross demand of the Co-Located Load in accordance with Tariff, Schedule 6A;86

• Regulation charges based on a gross demand of the Co-Located Load;87 and
• any redispatch costs as set forth in Tariff, Attachment K.88
These are standard charges associated with the use of the Transmission System over and above the transmission service rates.  Also, consistent with the directives in the Show Cause Order, PJM would assess Black Start and Regulation charges based on the gross demand of the Co-Located Load,89 while the other charges would be based on actual usage of the Transmission System, consistent with how other transmission services are charged.

84 Illustrative Tariff, Part XI, Subpart B, section 714.5. 85 Illustrative Tariff, Part XI, Subpart B, section 714.5. 86 Illustrative Tariff, Part XI, Subpart B, sections 714.5, 715.4.
87 Illustrative Tariff, Part XI, Subpart B, section 715.4. 88 Illustrative Tariff, Part XI, Subpart B, sections 714.3, 715.2.
89 Show Cause Order at P 209.

PDF page 33

28
Further, as with all transactions in PJM, PJMSettlement will be the Counterparty to the Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service transactions under this Tariff.

M.
Applicability of Operating Agreement
Consistent with PJM’s requirements for NITS and the Commission’s pro forma Open Access Transmission Tariff,90 PJM requires that the Eligible Customer taking Contract Demand Transmission Service to plan, construct, operate, and maintain its facilities in conformance with the Operating Agreement.91  Additionally, the terms and conditions under which the Eligible Customer will operate its facilities will be detailed in the Operating Agreement.92

N.
Pro Forma Contract Demand Transmission Service Agreement
PJM has provided in Attachment A an illustrative Tariff, Attachment F-4, a pro forma Service Agreement for Contract Demand Transmission Service, i.e., it will govern for both Firm and Non-Firm Contract Demand Transmission Services.93  The new Service Agreement requires the parties to identify the Eligible Customer and provide business contact information.  The parties will select whether facilities’ upgrades are necessary by the Eligible Customer  to take Firm Contract Demand Transmission Service on behalf of the Co-Located Load.94  The Service Agreement will also detail conditions for termination,

90 Pro Forma Open Access Transmission, Federal Energy Regulatory Commission, § 35.1 (April 2020), https://www.ferc.gov/sites/default/files/2020-04/pro-forma-open-access.pdf.
91 The Commission’s pro forma Open Access Transmission Tariff uses the term “Network Operating Agreement.”  In PJM, the “Operating Agreement of the PJM Interconnection, L.L.C., as amended from time to time, shall constitute the Network Operating Agreement.”  Tariff, Attachment G.
92 Illustrative Tariff, Part XI, Subpart B, section 716.1.
93 Illustrative Tariff, Attachment F-4.
94 Illustrative Tariff, Attachment F-4, section 2.0.

PDF page 34

29
such as misoperation of a necessary control technology or protection system under sections 710.7 and 713.7 or failure to timely inform PJM of material changes to the Co-Located Load or Co-Located Generating Facility.95  The Eligible Customer is also required to submit a single-line diagram as a part of Attachment F-4 to show the Delivery Point between the Co-Located Load and Co-Located Generating Facility.

As noted, the pro forma Service Agreement is designed to provide applicable terms and conditions for Non-Firm Contract Demand Transmission Service.  This will allow an Eligible Customer taking Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service on behalf of a Co-Located Load to consolidate its services into one agreement.  Further, using a single agreement to cover both services is consistent with the requirement that an Eligible Customer taking Contract Demand Transmission Service must use a combination of the two services to cover the entire gross demand of the Co-Located Load.96

95 Illustrative Tariff, Attachment F-4, sections 3.0, 4.0.
96 See, e.g., Illustrative Tariff, Subpart B, section 709.2.

PDF page 35

30
Question 2:
What are the appropriate rates, terms, and conditions for the new Non-Firm Contract Demand transmission service, including whether it would be just and reasonable to apply the current zonal non-firm PTPS charges to this new transmission service and whether it would be just and reasonable and consistent with cost causation to include charges for any of PJM’s administrative services? Response to Question 2:

As discussed above, many of the non-rate terms and conditions applicable to the new Non-Firm Contract Demand Transmission Service are the same as those for the new Firm Contract Demand Transmission Service, and are as described in response to Question 1.  Thus, PJM details those terms and conditions specific to Non-Firm Contract Demand Transmission Service that were not discussed above.

A. Provision of Non-Firm Contract Demand Transmission Service
The Show Cause Order recognizes that “not all Co-Located Loads will necessarily plan to withdraw energy from the transmission system on a regular basis” and “Eligible Customers taking service on behalf of such loads may . . . seek to withdraw energy from the transmission system from time to time when transmission capacity is available.”97  To implement this requirement, PJM has developed Non-Firm Contract Demand Transmission Service as a service offering the transmission of energy for an Eligible Customer on behalf of a designated Co-Located Load, on an as-available basis, up to a defined, predetermined MW level of transmission service as requested by the Eligible Customer and confirmed by the Transmission Provider, using energy procured by the Transmission Provider.98  Like Firm Contract Demand Transmission Service, the ability to request Non-Firm Contract

97 Show Cause Order at P 214.
98 See Show Cause Order at PP 193, 214.

PDF page 36

31
Demand Transmission Service on any given day, for any given period, is intended to be permanent—so long as the Service Agreement is effective.99

As discussed in Section E below, Eligible Customers taking Non-Firm Contract Demand Transmission Service on behalf of Co-Located Loads must have the necessary control technologies and protective systems (e.g., RAS) in place to appropriately limit their withdrawals of energy from the Transmission System, consistent with their contractual rights and PJM’s operational instructions.

B. Nature of Non-Firm Contract Demand Transmission Service
Non-Firm Contract Demand Transmission Service allows an Eligible Customer taking service on behalf of a Co-Located Load to access the Transmission System on a non-firm, interruptible basis during normal operations, and receive that transmission service up to a level defined in accordance with the terms of its Service Agreement.100  As discussed above in response to Question 1 and shown in Figure 1, such Eligible Customer must request Non-Firm Contract Demand Transmission Service equivalent to the MW level of the Co-Located Load’s gross demand not covered by Firm Contract Demand Transmission Service as part of the Service Agreement, such that the Eligible Customer is seeking to obtain sufficient Contract Demand Transmission Service to allow access to the Transmission System at a level capable of serving the Co-Located Load’s entire gross demand.

99 See Show Cause Order at P 215 (“Reservations for this service shall be available for terms ranging from one hour to one month, consistent with the terms available for Non-Firm PTPS in the PJM Tariff.” (footnote omitted)).
100 See Show Cause Order at P 215 (“Non-Firm Contract Demand transmission service must be available during normal operations and curtailed during emergency operations (i.e., it will be curtailed before existing firm transmission services and the new Firm Contract Demand Transmission Service.”)).

PDF page 37

32
PJM anticipates that in practice, requests for Non-Firm Contract Demand
Transmission Service will be at the MW level the Co-Located Generating Facility has dedicated to serving the Co-Located Load.101  The Eligible Customer may then, on any given day, reserve Non-Firm Contract Demand Transmission Service up to the amount specified in the Service Agreement (but only up to the MW level that the Co-Located Generating Facility is on outage).  However, such requests for Non-Firm service shall only be granted when PJM has determined there is available transmission capacity.102 Per the requirements of the Show Cause Order, Eligible Customers seeking Non-Firm Contract Demand Transmission Service “will be charged for transmission and ancillary services on an as-reserved contract demand [i.e., usage only] basis” and will be charged “regulation and black start services based on a gross demand basis.”103  Finally, consistent with the Show Cause Order, an Eligible Customer can seek a transmission reservation for Co-Located Load in advance for the duration of an expected outage of the associated Co-Located Generating Facility.104

C. Initiating Non-Firm Contract Demand Transmission Service
As with requests for Firm Contract Demand Transmission Service, upon receiving a request for Non-Firm Contract Demand Transmission Service, PJM will coordinate with the affected Transmission Owner(s) to complete necessary studies to determine whether— and at what level—Non-Firm Contract Demand Transmission Service can be reliably

101 Illustrative Tariff, Part XI, Subpart B, section 709.2.
102 See Show Cause Order at P 215; Tariff, Part II, section 14.1.  This is consistent with the Show Cause Order’s statement that an “Eligible Customer taking transmission service on behalf of Co-Located Loads that will not withdraw energy from the transmission system must take Non-Firm Contract Demand transmission service at 0 MW.”  Show Cause Order at P 206.
103 Show Cause Order at P 216.
104 See Show Cause Order at P 214.

PDF page 38

33
provided.105  If PJM determines that only a portion or none of the Non-Firm Contract Demand Transmission Service requested by an Eligible Customer can be provided reliably, PJM will provide a written explanation of its reasons for denial of service.106  In such case, the Eligible Customer may either apply for the amount of Firm Contract Demand Transmission Service necessary to cover the Co-Located Load’s entire gross demand, or alternatively, apply to serve the entire Co-Located Load through NITS.107

D. Study Procedures for Non-Firm Contract Demand Transmission Service
As discussed, PJM will not study transmission service requests alone, but rather will coordinate and consult with any affected Transmission Owners to determine whether and how the requested transmission service may be provided.  Thus, upon receipt of a request for Non-Firm Contract Demand Transmission Service, PJM will notify the affected Transmission Owner(s) of such request.108  PJM and the affected Transmission Owner(s) will determine whether additional studies are required “to assess whether the Transmission System has sufficient available capacity to provide Non-Firm Contract Demand Transmission Service, and if so, which studies are appropriate.”109  To be clear, these studies relate only to the maximum amount of Non-Firm Contract Demand Transmission Service that would be allowed under a specific Service Agreement.  PJM expects to perform different evaluations to actually use such service on the Transmission System on any given day.

105 Illustrative Tariff, Part XI, Subpart B, section 710.3.
106 Illustrative Tariff, Part XI, Subpart B, section 710.3.
107 Illustrative Tariff, Part XI, Subpart B, section 710.3.
108 Illustrative Tariff, Part XI, Subpart B, section 712.2.
109 Illustrative Tariff, Part XI, Subpart B, section 712.2.

PDF page 39

34
E. Curtailment of Non-Firm Contract Demand Transmission Service
Non-Firm Contract Demand Transmission Service will be Curtailed before Firm Contract Demand Transmission Service and NITS as required by the Commission in the Show Cause Order.110  As discussed in greater detail in response to Question 11, PJM may curtail Non-Firm Contract Demand Transmission Service prior to dispatching the Pre- Emergency Load Response Program as further set forth in the PJM Manuals,111 or in response to a transfer capability shortage.112

F. Necessary Control Technologies and Protection Systems to Protect the Transmission System by Limiting Energy Withdrawals

As part of implementing the key principles that (1) the services are designed to serve loads that are “willing and able to control their withdrawals from the transmission system;”113 and (2) the services are designed to allow PJM to maintain system reliability, PJM is requiring Eligible Customers taking Non-Firm Contract Demand Transmission Service to work with PJM and affected Transmission Owners to “establish necessary control technologies and protection systems, . . . which may include a [RAS], for each Service Agreement for Non-Firm Contract Demand Transmission Service.”114 The control technologies and protection systems necessary to provide Non-Firm Contract Demand Transmission Service (and Interim NITS) is emblematic of the

110 Show Cause Order at P 215; illustrative Tariff, Part XI, Subpart B, section 713.4.
111 The Tariff provides that the Pre-Emergency Load Response Program is “the program by which Curtailment Service Providers may be compensated by PJM for Demand Resources that will reduce load when dispatched by PJM during pre-emergency conditions, and is described in Operating Agreement, Schedule 1, section 8 and the parallel provisions of Tariff, Attachment K-Appendix, section 8.”  Tariff, Definitions – O – P - Q.
112 Illustrative Tariff, Part XI, Subpart B, section 713.4. 113 Show Cause Order at P 204 (footnote omitted).
114 Illustrative Tariff, Part XI, Subpart B, section 713.6.

PDF page 40

35
complexity associated with Non-Firm Contract Demand Transmission Service from an operations and planning perspective.115

Each and every Service Agreement for Non-Firm Contract Demand Transmission must include the necessary control technologies and protection systems to ensure the reliability and stability of PJM’s Transmission System.  As Dr. Abdulsalam explains, Non- Firm Contract Demand Transmission Service (or Interim NITS) “will need to be evaluated on a per-request basis and will be tied to necessary control technologies or protection systems, which may include RAS . . . to ensure that the contracted-for withdrawal level is not exceeded and that the pre-scheduled, non-firm withdrawal level can only be reliably enabled under conditions that PJM has agreed to.”116  In his affidavit, Mr. Wharton, a Manager of Reliability Engineering within PJM and a NERC Certified System Operator, further elaborates on the operational complexities that may be associated with RAS.117  As Mr. Wharton explains, an RAS “is designed to detect abnormal system conditions and “to automatically take appropriate corrective action to maintain system stability, acceptable system voltages, and acceptable facility loading.”118  Mr. Wharton testifies, however, that RAS “should not be installed as a substitute for good system design or operating practices.”119

Together, Dr. Abdulsalam and Mr. Wharton explain why control technologies and protection systems (e.g., RAS) are necessary to protect the Transmission System from

115 See Abdulsalam Aff. ¶¶ 9-12.
116 Abdulsalam Aff. ¶ 9.
117 Wharton Aff. ¶ 16.
118 Wharton Aff. ¶ 15.
119 Wharton Aff. ¶ 16.

PDF page 41

36
significant unexpected events that may occur with Non-Firm Contract Demand Transmission Service (and Interim NITS).  Without the necessary control technologies and protection systems tied to Non-Firm Contract Demand Transmission Service (and as discussed below, Interim NITS), an Eligible Customer may, for example, withdraw energy during peak periods above what it had previously contracted (or contrary to PJM dispatch instructions), for which PJM has not planned either adequate transmission or generation capacity, putting other customers at risk.120  PJM has developed penalties that address, inter alia, instances where a control technology or protection system tied to an Eligible Customer’s Non-Firm Contract Demand Transmission Service misoperates.  PJM describes these penalties in response to the Commission’s Briefing Questions 5 and 6 below.

G. Rates and Charges for Non-Firm Contract Demand Transmission Service
Consistent with the allocation of rights between PJM and PJM Transmission Owners,121 PJM expects the PJM Transmission Owners to file briefing in the paper hearing record describing the proposed transmission rates for each of these new transmission services, including Non-Firm Contract Demand Transmission Service.  However, with respect to the other rates that PJM has authority to institute, as for Firm Contract Demand Transmission Service, PJM will assess Eligible Customers taking Non-Firm Contract Demand Transmission Service based on their actual usage of the system:

• administrative services charges under Tariff, Schedule 1A; Tariff,
Schedule 9; and Tariff, Schedule 10 based on the total quantity of MWhs of

120 See Show Cause Order at P 211 (“PJM will only plan the transmission system and procure generation capacity for the contract demand—not for load growth, like it does for NITS customers—and PJM will have no obligation to serve the Eligible Customer beyond the contract demand.”).
121 See supra note 4.

PDF page 42

37
energy delivered using Non-Firm Contract Demand Transmission Service,
except any capacity-related charges under these schedules will not apply;122
• Ancillary Services charges, except for Regulation, based on the total
quantity in MWhs of energy delivered to the Co-Located Load using Non-
Firm Contract Demand Transmission Service in accordance with Part I,
section 3; and
• any redispatch costs as set forth in Tariff, Attachment K.
In addition, Non-Firm Contract Demand Transmission Service customers will be responsible for Regulation and Black Start Service charges based on the gross demand of the Co-Located Load, to the extent the customer is not paying such charges associated with its Firm Contract Demand Transmission Service.123  Notably, given that there is one Service Agreement for both Contract Demand Transmission Services, any Eligible Customer taking Contract Demand Transmission Service will not be double billed for the Regulation and Black Start Service for the Co-Located Load served under a given Service Agreement.

H. Pro Forma Contract Demand Transmission Service Agreement
As discussed, PJM has provided in Attachment A an illustrative Tariff, Attachment F-4, a pro forma Service Agreement for both Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.124  Thus, a single Service Agreement will detail an Eligible Customer’s subscription for both types of service, and allow one agreement to govern the Eligible Customer’s transmission service on behalf of the Co-Located Load.

122 Illustrative Tariff, Part XI, Subpart B, section 714.5.
123 See Illustrative Tariff, Part XI, Subpart B, section 715.4 (“To the extent the Eligible Customer does not have an effective Service Agreement for Firm Contract Demand Transmission Service, Eligible Customer shall pay Black Start Service charges based on the gross demand of the Co-Located Load in accordance with Tariff, Schedule 6A.  To the extent the Eligible Customer does not have an effective Service Agreement for Firm Contract Demand Transmission Service, Eligible Customer shall pay Regulation charges based on a gross demand of the Co-Located Load.”).
124 Illustrative Tariff, Attachment F-4.

PDF page 43

38
Question 3:
As noted above, a Co-Location Arrangement is synchronized to the transmission system.  Should the rate paid by an Eligible Customer on behalf of a Co-Located Load taking only the new Non-Firm Contract Demand transmission service that elects to not reserve any amount of that service for a period of time (e.g., one month) reflect not only charges for regulation and black start services, but also an additional charge given that regulation and black start services could not be provided without the transmission system?  If so, how should that additional charge be determined?

Response to Question 3:
Consistent with the allocation of rights between PJM and PJM Transmission Owners,125 PJM expects the PJM Transmission Owners to file briefing in the paper hearing record answering this question.  Upon review of that briefing, PJM may provide additional commentary or perspectives in its reply brief.

125 See supra note 4.

PDF page 44

39
Question 4:
As noted above, a Co-Location Arrangement is synchronized to the transmission system. Should the rate paid by an Eligible Customer on behalf of a Co-Located Load taking only a de minimis amount of the new Firm or Non-Firm Contract Demand transmission services reflect not only (i) charges for regulation and black start service and (ii) the transmission service charges for that de minimis amount of service, but also an additional charge reflecting that the Co-Location Arrangement is physically connected and synchronized to the PJM transmission system?  If so, how should that additional charge be determined?

Response to Question 4:
Consistent with the boundaries between PJM and PJM Transmission Owners,126 PJM expects the PJM Transmission Owners to file briefing in the paper hearing record answering this question.  Upon review of that briefing, PJM may provide additional commentary or perspectives in its reply brief.

126 See supra note 4.

PDF page 45

40
Question 5:
What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an Eligible Customer taking Firm Contract Demand transmission service on behalf of a Co- Located Load?

Response to Question 5:
PJM addresses, below, the appropriate penalty charges or other remedial actions (together “penalties”) applicable to Eligible Customers taking transmission service on behalf of a Co-Located Load using:  (i) Firm Contract Demand Transmission Service;

(ii) Non-Firm Contract Demand Transmission Service; and (iii) Interim NITS prior to automatically transitioning to NITS on behalf of a Co-Located Load.  PJM supports three different penalties applicable where such Eligible Customers:  (i) fail to follow established Load Shedding and Curtailment procedures; (ii) rely on necessary control technologies or protection systems in accordance with the PJM Manuals, which may include a RAS, that fail (i.e., misoperate) more than once; and (iii) makes unreserved use of the PJM Transmission System.

The illustrative Tariff provisions governing the three penalties applicable to Eligible Customers are as follows:

PDF page 46

41
Table 1.  Penalties Applicable to Eligible Customers Taking Contract Demand Transmission Service or Interim NITS

 Disqualification
(First Failure to
Shed Load or
Curtail)
Service
Paused
(First Control
Tech or
Protection
System
Misoperation)
Disqualification
(Second Control
Tech or Protection
System
Misoperation)
Financial Penalty
(Unreserved Use)
Firm Contract
Demand
Illustrative Tariff,
Part XI, Subpart B,
sections 713.7(a),
713.7(c)
N/A
N/A
To be determined
Non-Firm
Contract
Demand
Illustrative Tariff,
Part XI, Subpart B,
sections 713.7(a),
713.7(c)
Illustrative
Tariff, Part XI,
Subpart B,
sections
713.7(b),
713.7(c)
Illustrative Tariff,
Part XI, Subpart B,
sections 713.7(b),
713.7(c)
To be determined
Interim NITS
Illustrative Tariff,
Part XI, Subpart A,
sections 705.6(a),
705.6(c)
Illustrative
Tariff, Part XI,
Subpart A,
sections
705.6(b),
705.6(c)
Illustrative Tariff,
Part XI, Subpart A,
sections 705.6(b),
705.6(c)
To be determined

A. Disqualification or Pause in Service
1. Disqualification after first failure of Eligible Customer to shed load or curtail in accordance with established procedures

Under PJM’s approach, Eligible Customers taking Firm Contract Demand
Transmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS on behalf of a Co-Located Load may be subject to remedial action in the event that the Eligible Customer “fails to respond to established Load Shedding and Curtailment procedures.”127

The proposed remedial action is a strict liability rule that automatically applies after being triggered by one instance of an Eligible Customer failing to follow Curtailment or Load Shed procedures.  The rule is triggered after one failure and applied automatically on

127 Illustrative Tariff, Part XI, Subpart A, section 705.6(a); id., Part XI, Subpart B, section 713.7(a).

PDF page 47

42
a strict liability basis because of the significant reliability risk posed by Eligible Customers who disregard Load Shed or Curtailment procedures.

Such an approach is just and reasonable and consistent with the two key principles:
(1) these Eligible Customers are “willing and able to control their withdrawals from the transmission system;”128 and (2) the services are designed to allow PJM to maintain system reliability.  Allowing customers that are allowed on the system on the promise that they will control their energy withdrawals as necessary, and then not penalizing them for failing to honor that promise runs counter to the Show Cause Order and would implicitly bless such dangerous behavior.

Under illustrative Tariff, Part XI, Subpart B, section 713.7(a), an Eligible Customer taking Firm or Non-Firm Contract Demand Transmission Service on behalf of a Co- Located Load is disqualified from taking Firm or Non-Firm Contract Demand Transmission Service if the Eligible Customer fails to respond to Load Shedding and Curtailment under established procedures set forth in illustrative Tariff, Part XI, Subpart B, section 713.  Importantly, however, an Eligible Customer disqualified from taking Firm or Non-Firm Contract Demand Transmission Service may continue taking transmission service on behalf of Co-Located Load by either taking NITS or by qualifying for Interim NITS.

Under illustrative Tariff, Part XI, Subpart A, section 705.6(a), an Eligible Customer taking Interim NITS on behalf of a Co-Located Load is disqualified from taking Interim NITS, Firm Contract Demand Transmission Service, and Non-Firm Contract Demand Transmission Service if the Eligible Customer fails to respond to established Load

128 Show Cause Order at P 204 (footnote omitted).

PDF page 48

43
Shedding and Curtailment procedures set forth in illustrative Tariff, Part XI, Subpart A, section 705.  Importantly, however, such an Eligible Customer may take NITS, which would begin after all necessary upgrades are placed into service.

2. Misoperation of necessary control technology and protection system
schemes
Eligible Customers taking Interim NITS or Non-Firm Contract Demand
Transmission Service must, pursuant to illustrative Tariff, Part XI, Subpart A, section 705.5 and illustrative Tariff, Part XI, Subpart B, section 713.6, respectively, must implement all necessary control technology and protection system schemes, as outlined and agreed upon in their respective transmission Service Agreements.  As discussed above in response to Question 2, these control technology and protection schemes, which may include RAS, must be developed by PJM, the affected Transmission Owner(s), and the Eligible Customer and approved by PJM and operate in accordance with PJM Manuals and applicable NERC reliability requirements.129

When a control technology or protection scheme misoperates, there can be serious consequences.  Misoperation, as contemplated by PJM, relies on and incorporates the term as defined by NERC (e.g., PRC-004-6).130

According to PJM witness Mr. Wharton, “the consequences of an RAS
misoperation are often more severe than those of fault protection schemes.  While an RAS may be a temporary solution until the transmission system is reinforced, PJM Manuals indicate that PJM’s systems and operating procedures were designed to be served by NITS,

129 See illustrative Tariff, Part XI, Subpart A, section 705.6(b).
130 See, e.g., PRC-004-6 – Protection System Misoperation Identification and Correction, North American Electric Reliability Corporation (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability- standards/prc/prc-004-6.pdf.

PDF page 49

44
eliminating the need for RAS while ensuring generation can be dispatched to serve
load.”131  “For any RAS, PJM, in its role as the Reliability Coordinator, reviews the scheme and provides feedback to the RAS-entity within four full calendar months or a schedule that is mutually agreed upon in keeping with R2 of NERC Reliability Standard PRC-012- 02.”132  The illustrative Tariff provides PJM a similar authority as the ultimate decider for any necessary control technology or protective system for these services.133

a. Pause in service after first misoperation of a necessary
control technology or protection system scheme
PJM’s approach calls Eligible Customers taking Contract Demand Transmission
Service (both Firm and Non-Firm) or Interim NITS on behalf of a Co-Located Load be
subject to remedial action in the first instance where an Eligible Customer’s necessary control technology or protection system scheme misoperates.134  After one instance of misoperation, the Eligible Customer will be prohibited from taking transmission service or otherwise withdrawing energy from the Transmission System for a period up to 120 days from misoperation, which may be shortened or extended per mutual agreement, to allow for an analysis of the necessary control technology or protection system scheme’s

operational performance.135  The up to 120-day pause pending evaluation of the

131 Wharton Aff. ¶ 16. 132 Wharton Aff. ¶ 18; PRC-012-2 – Remedial Action Schemes, North American Electric Reliability Corporation (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012- 2.pdf.
133 See Illustrative Tariff, Part XI, Subpart A, section 705.5 (“The necessary control technologies and protection systems must: be developed in accordance with the PJM Manuals and be approved by the Transmission Provider.”); id., Part XI, Subpart B, section 713.6 (same).
134 Illustrative Tariff, Part XI, Subpart A, section 705.6(a)-(b); id., Part XI, Subpart B, section 713.7(a)-(b).
135 PJM is also evaluating whether modifications would be needed to the Co-Located Generating Facility’s GIA to preclude it from directly serving the Co-Located Load during this investigatory period following the failure of a necessary control technology or protection system.  Such preclusion of direct service is necessary because the underlying premise of permitting these Contract Demand Transmission Services is a functional

PDF page 50

45
misoperation of the necessary control technology or protection system scheme is consistent with NERC requirements for an investigation into the operation of a RAS (e.g., PRC-004-6 and PRC-012-02).136  Such a pause in service will allow PJM (and the affected Transmission Owner(s), as necessary) time to investigate, identify, and implement fixes to better protect the Transmission System, while respecting the Eligible Customer’s desire to retain this type of service based on its promised willingness to limit energy withdrawals. b. Disqualification after second necessary control technology

or protection system scheme misoperation
After a second instance of a necessary control technology or protection system scheme misoperating, the Eligible Customer will be disqualified from taking Contract Demand Transmission Service (both Firm and Non-Firm) or Interim NITS on behalf of a Co-Located Load.

The proposed remedial action is a strict liability rule that automatically applies after being triggered by two instances of an Eligible Customer’s necessary control technology or protection system scheme misoperation.  The rule is triggered after two instances in which a necessary control technology or protection system scheme(s) misoperates.  The rule is applied automatically on a strict liability basis because of the significant reliability risk posed by necessary control technology or protection system scheme misoperations. This two-strike rule appropriately implements the two key principles, in that it properly balances the desire of these loads to obtain a transmission service lesser than NITS because they are willing and able to limit their energy withdrawals, against the need to

scheme in place that limits energy withdrawals from the Transmission System—and if the scheme has failed to operate or misoperates, it cannot be considered functional.

136 Illustrative Tariff, Part XI, Subpart A, section 705.6(b); id., Part XI, Subpart B, section 713.7(b).

PDF page 51

46
protect system reliability and maintain reliable service to the 67+ million customers in the PJM Region.  After the second time a necessary control technology or protection system misoperates, it is evident that the necessary control technology or protection system cannot adequately protect the system from the Co-Located Load’s unreserved (and unscheduled) energy withdrawals.137

Accordingly, under illustrative Tariff, Part XI, Subpart B, section 713.7, an Eligible Customer taking Non-Firm Contract Demand Transmission Service on behalf of a Co- Located Load is disqualified from taking Firm or Non-Firm Contract Demand Transmission Service if the Eligible Customer experiences more than one misoperation of a necessary control technology or protection system scheme.  Importantly, however, an Eligible Customer disqualified from taking Contract Demand Transmission Service (both Firm and Non-Firm) may continue taking transmission service on behalf of a Co-Located Load by either taking NITS or by qualifying for Interim NITS.

Under illustrative Tariff, Part XI, Subpart A, section 705.6, an Eligible Customer taking Interim NITS on behalf of a Co-Located Load is disqualified from taking Interim NITS, Firm Contract Demand Transmission Service, and Non-Firm Contract Demand Transmission Service if the Eligible Customer experiences more than one necessary control technology or protection system scheme misoperation.  Importantly, however, such an Eligible Customer may take NITS, which would begin after all necessary upgrades are placed into service.

137 With respect to RAS in particular, Mr. Wharton details the cascading adverse effects a RAS misoperation could have the Transmission System, particularly when RASs are clustered geographically and electrically. See Wharton Aff. ¶¶ 21-22.

PDF page 52

47
c. Option to take NITS following disqualification
Eligible Customers that have been disqualified from taking Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS on behalf of Co-Located Load nonetheless retain the option to take NITS on behalf of that Co-Located Load, as Network Load, or, if not already taking Interim NITS, to qualify to take Interim NITS prior to transitioning to NITS pursuant to illustrative Tariff, Part XI, Subpart A, section 705.6(c) and illustrative Tariff, Part XI, Subpart B, section 713.7(c). This rule recognizes that NITS, in and of itself, addresses Curtailment, Load Shed, and control technology or protection scheme misoperation risk.  In PJM, as Dr. Abdulsalam notes, “NITS is used for internal (non-border) transmission service in the PJM Region.”138 As Mr. Wharton testifies on behalf of PJM, “a reliable centrally dispatched Balancing Authority relies on [NITS] to ensure that generation is not ‘bottled’ and is deliverable to load[.]”139  Likewise, Dr. Abdulsalam testifies that, in PJM:

The NITS type of transmission service enables a high level of
reliability across the region under system normal and abnormal
operating conditions.  This type of service ensures the transmission network and the needed capacity to serve such load and allows PJM

to plan for and secure the requisite level of service needed to
accommodate changes in system conditions and the resource mix,
as it shifts with time.  NITS also ensures the system overall is
“proactively” planned to a forecasted level of service and the needed resource capacity to maintain the reliability of service is secured

ahead of time.  Given the level of reliability offered by the NITS to its transmission service loads, such loads rarely face situations of curtailments or load shedding, as they are usually limited to extreme transmission outage conditions or resource emergency conditions.

In addition, PJM serves a system load that is high in density
compared to its geographic footprint.  The high load density in the
PJM Region means that a higher load level is served from a single
point of service/delivery.  As a result, a higher number of customers

138 Abdulsalam Aff. ¶ 7. 139 Wharton Aff. ¶ 10 (footnote omitted).

PDF page 53

48
could be exposed to interruption risk under malfunction,
misoperation, or unplanned interaction between more than one
necessary control technologies and protection systems, which may
include [RAS].140
Since at least its establishment as an Independent System Operator in 1997, PJM’s processes have been built around the long-held practice and expectation that load internal to PJM will receive NITS.  This has significant implications for PJM’s planning, markets, and operations functions, which are focused on serving Network Load.

Within the existing PJM framework, transmission customers must elect one of two transmission services—NITS or Point-to-Point Transmission Service (“PTP Transmission Service”).  Load Serving Entities serving end-use load within PJM take NITS,141 while PTP Transmission Service is used for the transmission of capacity and/or energy into, out of, or through the PJM Region.  More specifically, PTP Transmission Service is the use of transmission facilities for the transmission of capacity and energy between a Point of Receipt and a Point of Delivery.  While all NITS is firm, PTP Transmission Service may be either firm or non-firm.  Unlike PTP Transmission Service, NITS is flexible, incorporated into PJM’s system planning studies and processes as well as PJM’s capacity market, and always firm.  Unlike customers with PTP Transmission Service, a Network Customer taking NITS must also obtain or provide Ancillary Services.

At bottom, NITS is not only the default transmission service taken by load internal to PJM, it is also significantly more comprehensive and a higher quality of service than PTP Transmission Service.  The choice to take NITS, in and of itself, decreases the

140 Abdulsalam Aff. ¶¶ 7-8.
141 Pa.-N.J.-Md. Interconnection, 81 FERC ¶ 61,257, at 62,272 (1997), order on reh’g, 82 FERC ¶ 61,047, order on clarification, 82 FERC ¶ 61,068, modified sub nom., Potomac Elec. Power Co., 83 FERC ¶ 61,068 (1998), order on reh’g & clarification, 92 FERC ¶ 61,282 (2000), vacated, in part, and remanded sub nom., Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002).

PDF page 54

49
likelihood of significant issues arising from failure to curtail, load shed, or misoperation of a necessary control technology or protection system.  Network Customers may “call upon the transmission provider to supply not just some, but all of their load at any given moment, when for instance they experience blackouts or brownouts.”142  Furthermore, NITS “allows [a] Network Customer to integrate, economically dispatch and regulate its current and planned Network Resources to serve its Network Load in a manner comparable to that in which each Transmission Owner utilizes the Transmission System to serve its Native Load Customers.  [NITS] also may be used by the Network Customer to deliver economy energy purchases to its Network Load from non-designated resources on an as-available basis without additional charge.”143

The split in PJM, in which NITS serves load within PJM and PTP Transmission Service serves load beyond PJM’s borders, is the natural outgrowth of PJM’s formation. In the 1997 order on PJM’s transition to an Independent System Operator, the Commission noted that it is important that:

[T]he [PJM] tariff was designed to replicate the network integration
service each utility had historically provided itself within the
confines of its individual service area.  By allowing transmission
service customers to integrate resources across eight utility systems, the PJM Transmission Tariff will permit customers to obtain a

transmission service that goes beyond the requirements of the Open
Access Rule. . . . We believe that . . . a single transmission service charge for multi-system use, in conjunction with its congestion

pricing proposal, will foster the creation of more competitive bulk
power markets, help to ration constrained capacity among
competing transactions on the basis of price, and simplify the

142 Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667, 725 (D.C. Cir. 2000).
143 Tariff, Part III, Preamble; Transmission Service Department, PJM Manual 2: Transmission Service Request, PJM Interconnection, L.L.C., section 1.1.2 (Jan. 22, 2026), https://www.pjm.com/- /media/DotCom/documents/manuals/m02.pdf.

PDF page 55

50
reassignment of transmission capacity.  This is consistent with our
policy goals in the Open Access Rule.144
PJM’s illustrative Tariff provision offers a balanced and conservative approach that enables Eligible Customers to take transmission service that is less than NITS on behalf of Co-Located Load, while also recognizing that permitting Eligible Customers to take non- NITS transmission services on behalf of Co-Located Load may pose additional reliability and operational risks to the PJM Region.

B. Financial Penalty for Unreserved Use of the PJM Transmission System PJM supports a penalty for unreserved use in addition to the disqualification and pause-in-service rules discussed above.  As PJM has previously noted, an operational penalty for unreserved use is “not intended to operate as a punishment for a tariff violation.”145  PJM expects that many, if not most, Eligible Customers taking service on behalf of a Co-Located Load could foreseeably elect to absorb financial penalties for unreserved use rather than follow Curtailment or Load Shed procedures or avoid misoperation of the protective technology or system.  Thus, in PJM’s view, financial penalties, alone, are not sufficient to incentivize Eligible Customers to comply with Load Shed, Curtailment, and control technology and protection system obligations.  As such, PJM has additionally proposed the disqualification and pause-in-service remedial actions discussed above.

With regard to the financial penalty, PJM intends to work with the PJM Transmission Owners to explore such a financial penalty. As such, PJM has “reserved” illustrative Tariff, Part XI, Subpart A, section 705.7 and illustrative Tariff, Part XI, Subpart

144 Pa.-N.J.-Md. Interconnection, 81 FERC ¶ 61,257, at 62,241 (footnote omitted).
145 PJM Interconnection, L.L.C., 134 FERC ¶ 61,040, at P 8 (2011) (footnote omitted).

PDF page 56

51
B, section 713.8 in anticipation of the development of financial penalty provisions. Unreserved use penalties should apply to Eligible Customers taking Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission Service, or Interim NITS on behalf of Co-Located Load.

PDF page 57

52
Question 6:
What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an Eligible Customer taking Non-Firm Contract Demand transmission service on behalf of a Co-Located Load?

Response to Question 6:

See Response to Question 5 above, which addresses penalty charges and remedial actions applicable to Non-Firm Contract Demand Transmission Service, Firm Contract Demand Transmission Service, and Interim NITS.

PDF page 58

53
Question 7:
What are the appropriate mechanisms for an anti-toggling feature for the Firm Contract Demand transmission service, including the appropriate minimum service period and minimum notice period for discontinuing or modifying the level of service?

Response to Question 7:

The Show Cause Order found that the terms and conditions for taking new Firm Contract Demand Transmission Service should include a mechanism that prevents a transmission customer from switching from Firm to Non-Firm Contract Demand Transmission Service so as to avoid charges associated with PJM’s capacity market.146  To implement this directive, PJM includes a two-pronged approach.  One, illustrative Tariff, Part XI, Subpart B, section 709.4 provides an anti-toggling mechanism to prevent transmission customers from switching between the Firm and Non-Firm Contract Demand Transmission Services, by providing that the portion of the Co-Located Load served by Firm Contract Demand Transmission Service is not eligible to be served by Non-Firm Contract Demand Transmission Service “for five years following the effective date of the Service Agreement for Contract Demand Transmission Service.”

Conversely, there is no prohibition on any portion of the Co-Located Load served by Non-Firm Contract Demand Transmission Service from being served by Firm Contract Demand Transmission Service in future years.  This is reasonable, as Firm Contract Demand Transmission Service is a higher quality of service and presents less risk to system

146 Show Cause Order at P 213 (“[W]e find that it is just and reasonable that the terms and conditions for taking the new Firm Contract Demand transmission service must prevent transmission customers from switching between the Firm Contract Demand and Non-Firm Contract Demand transmission services, i.e., must include an anti-toggling mechanism.  Otherwise, Eligible Customers taking transmission service on behalf of Co-Located Loads may attempt to switch between the two new transmission services based on expected capacity market conditions.”).

PDF page 59

54
reliability and fewer operational complexities for PJM’s dispatchers to manage.  That is, because PJM will plan the Transmission System to ensure the Firm Contract Demand Transmission Service MW quantity and PJM will consider such amount in resource

adequacy planning,147 the system will be designed to serve the Firm Contract Demand Transmission Service, minimizing much of the system reliability risks presented by Non- Firm Contract Demand Transmission Service.

However, the foregoing limitations will “not apply in the event of (i) a physical change to the Co-Located Generating Facility that would materially and permanently alter the [MW] level dedicated to the Co-Located Load; or (ii) a physical change to the Co-Located Load that would materially and permanently alter the [MW] level of its gross demand.”148  These exceptions are necessary to ensure that, should an Eligible Customer or Co-Located Load materially and permanently change either the generation capacity or the load on a gross demand basis, the Tariff provides flexibility to determine whether  Firm or Non-Firm Contract Demand Transmission Service should be taken for the new

incremental portion.
Two, the 42-month notice of termination also acts as an anti-toggling device in a manner similar to the five-year commitment period applicable to the Fixed Resource Requirement alternative in PJM’s capacity market.149  This notice period also is identical

147 Illustrative Tariff, Part XI, Subpart B, section 708(b) (“Firm Contract Demand Transmission Service is for the transfer of capacity and energy to an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, predetermined megawatt level of transmission service as requested by the Eligible Customer and confirmed by the Transmission Provider, using capacity and energy procured by the Transmission Provider[.]”).
148 Illustrative Tariff, Part XI, Subpart B, section 709.4.
149 See Reliability Assurance Agreement Among Load Serving Entities in the PJM Region, Schedule 8.1.C, section C.2 (“RA Agreement”) (“An FRR Entity may terminate its election of the FRR Alternative effective with the commencement of any Delivery Year following the minimum five Delivery Year commitment by providing written notice of such termination to the Office of the Interconnection no later than two months

PDF page 60

55
to the one used for NITS agreements,150 and recognizes that PJM is incorporating these loads in the capacity market, and has procured capacity on their behalf.  Allowing Co- Located Loads to avoid capacity charges that have been incurred on their behalf by

terminating their agreement prematurely would unreasonably shift those costs to other loads in the PJM Region and contrary to Commission precedent.151

prior to the Base Residual Auction for such Delivery Year.  An FRR Entity that has terminated its election of the FRR Alternative shall not be eligible to re-elect the FRR Alternative for a period of five consecutive Delivery Years following the effective date of such termination.”).

150 See Tariff, Part I, section 2.5(2) (“An incumbent Network Customer seeks to terminate its service and no successor Network Customer exists, in which case the incumbent must provide PJM with forty-two (42) months’ notice prior to the commencement of a Delivery Year, subject to receiving all necessary regulatory approvals for such termination, if any[.]”).
151 See Duquesne Light Co., 122 FERC ¶ 61,039, at P 86 (2008) (“[W]e conclude that Duquesne’s obligations to pay Locational Reliability Charges, under the RA Agreement, became set at such time as Duquesne’s loads were included by PJM in its auction parameters.”).

PDF page 61

56
Question 8:
What interconnection requirements and operational practices are necessary for special protection schemes to maintain system reliability (e.g. the need for full redundancy of such schemes) in the event that a Co-Located Load itself or its associated generator trips offline?

Response to Question 8:
PJM understands the “special protection schemes” referenced in Question 8 to mean the “necessary control technology and protection systems” that Eligible Customers taking Interim NITS and Non-Firm Contract Demand Transmission Service on behalf of Co-Located Load will need to outline in their respective Service Agreements. Similar to the current requirement to include any agreed upon “necessary control technologies and protection systems” in an executed, or requested to be filed, unexecuted GIA, Service Agreements for Interim NITS and Non-Firm Contract Demand Transmission Service will each outline the specific necessary control technology and protection schemes, including for example a RAS, required to ensure the reliability and stability of PJM’s Transmission System.

NERC has established various reliability standard requirements for the various forms of control technologies that may be relied upon for grid stability, which Eligible Customers are expected to adhere to.  For example, RAS, which PJM and NERC have also historically referred to as Special Protection Systems,152 is among the “control technology and protection systems” that PJM may deem necessary for an Eligible Customer to have. PJM includes an illustrative definition of RAS in Attachment A, which is explained in Section IV further below.

152 In 2014, NERC replaced references to Special Protection Systems with the term RAS.  “Remedial Action Scheme” Definition Development, North American Electric Reliability Corporation (June 2014), https://www.nerc.com/globalassets/standards/projects/2010-05.2/faq_ras_definition_0604_final.pdf.

PDF page 62

57
The interconnection requirements and operational practices necessary for necessary control technologies and protection systems to maintain system reliability in the event that a Co-Located Load or associated generator trips offline will be set forth in the PJM Manuals and, as applicable, NERC reliability standards.

The NERC reliability standards form baseline interconnection requirements and operational practices, while PJM, through its Manuals, provides additional details and, at times, more stringent standards for RAS.  The requirements set forth in NERC reliability standards and PJM Manuals are extensive.  An illustrative, non-exhaustive list of interconnection requirements and operational practices that ensure that RAS maintain system reliability includes, but is not limited to:

• Requirements and measures set forth in NERC PRC-012 associated with placing a new or functionally modified RAS in service to ensure that RAS do not introduce unintentional or unacceptable reliability risks to the Bulk Electric System, including the requirement that operational performance analyses are properly conducted and verify that RAS operation was

triggered correctly.  PJM Manual 3, section 1.7 expands on how PJM will review RAS to ensure that sufficient analysis, notice, documentation, and training on these RAS are established ahead of implementation and that NERC PRC-012-2 requirements are met.153

o RAS are evaluated to ensure, for example, full redundancy of critical components, multiple independent tripping paths, and that RAS settings and operation avoids adverse interactions with other RAS and

protection and control systems.
• PJM Manual 3, section 1.8 sets forth RAS operating criteria and the actions that PJM, the Transmission Owner, and the Generation Owner will take when PJM’s Energy Management System indicates that a simulated N-1

contingency will result in an overload on the facility that can be mitigated by an RAS.154  Due to the redundancy built into each RAS, PJM considers

153 Transmission Operations, PJM Manual 03: Transmission Operations, PJM Interconnection, L.L.C., § 1.7 (Rev. 69, Nov. 20, 2025), https://www.pjm.com/-/media/DotCom/documents/manuals/m03.pdf (“PJM Manual 3”).
154 PJM Manual 3, section 1.8..

PDF page 63

58
the loss of a facility and the subsequent failure of the associated RAS to be a double contingency.155

• PJM Manual 7, section 17.2 sets forth installation requirements that govern RAS, particularly in light of the complexity of the scheme and the

consequences of RAS misoperation.
• NERC PRC-017 requires RAS maintenance and testing to ensure that RAS are properly designed, meet performance requirements, and are coordinated with other protection systems, as well as to ensure that maintenance and testing programs are developed and that misoperations are analyzed and corrected.

Importantly, while interconnection requirements and operational practices are in place to decrease the risk of relying on necessary control technologies and protection systems, the decision to employ necessary control technologies and protection systems is not taken lightly and requires weighing the complexity of the scheme and the risk and consequences of misoperation against the potential benefits.  Necessary control technologies and protection systems, which may include RASs, should not be installed as a substitute for good system design or operating practices.  Their implementation is generally limited to temporary conditions involving the outage of critical equipment.156

155 PJM Manual 3, section 1.8.
156 System Planning Division Transmission Planning Department, PJM Manual 07: PJM Protection Standards, PJM Interconnection, L.L.C., § 17.2 (Rev. 05, Sep. 25, 2025), https://www.pjm.com/- /media/DotCom/documents/manuals/m07.pdf (“PJM Manual 7”).

PDF page 64

59
Question 9:
What communications, alarm, SCADA452 or other requirements are necessary for PJM to monitor Co-Located Load transmission system demand status; ensure that relay settings are consistent with special protection scheme design; and inform system operator action, in order to limit withdrawals from Eligible Customers on behalf of Co-Located Load that exceed the amount of Firm or Non-Firm Contract Demand transmission services?

Response to Question 9:
PJM understands this question to be focused on the requirements currently in place and that PJM will need to put into place in order to:

• Monitor Co-Located Load Transmission System demand status;
• Ensure relay settings are consistent with special protection scheme designs, as shown in illustrative Tariff, Part XI, Subpart A, section 705.6 and illustrative Tariff, Part XI, Subpart B, section 713.7; and

• Otherwise inform system operator action in order to limit withdrawals from Eligible Customers on behalf of Co-Located Load that exceed Contract Demand Transmission Services or Interim NITS.

First, to monitor the status of the demand placed on PJM’s Transmission System by Co-Located Load in order to ensure adequate reliability and stability of the Transmission System, PJM will need to develop telemetry requirements and require Co-Located Load to meet such requirements in order to monitor Co-Located Load’s use of the Transmission System.  PJM will need to develop data exchange and metering requirements for Co- Located Load that may be similar to those currently applicable to generation, as set forth in PJM Manual 14D, section 4.157  The kind of requirements PJM will need to develop include, for example, specific data paths, networking requirements, and measurement types and measurement points for any given topology or generation type.  Because the different

157 Operations Planning Division, PJM Manual 14D: Generator Operational Requirements, PJM Interconnection,

L.L.C.,
§
4
(Rev.
70,
Dec.
17,
2025),
https://www.pjm.com/-
/media/DotCom/documents/manuals/m14d.pdf.

PDF page 65

60
types of services being made available to Eligible Customers taking service on behalf of Co-Located Load are prioritized differently, PJM would need to develop the capability to more granularly differentiate, at a minimum, between NITS and Interim NITS, and between Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.  Eligible Customers, acting on behalf of Co-Located Load, would need to take these different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve the Co-Located Load.

Second, to adequately ensure that relay settings are consistent with the design of the necessary control technologies and protection systems (e.g., RAS), as agreed to by PJM and set forth in each Service Agreement for Interim NITS and Non-Firm Contract Demand Transmission Service put into place in order for an Eligible Customer to serve Co-Located Load, PJM will need to develop requirements and identify any relevant NERC rules.158 In addition, Transmission Owners will need to be heavily involved in ensuring that necessary control technology and/or protective system is properly designed and, where appropriates, operates as intended.

Given that the complexity introduced by the necessary control technology and protection systems (e.g., RAS) introduces significant risks,159 including possible failure to communicate material information about such protective technology or system, the illustrative Tariff includes technical requirements that must be in place prior to the commencement of service, including that the Eligible Customer “is staffed with PJM

158 NERC requirements already set forth requirements that ensure relay settings are consistent with the design of the RAS.  An RAS must comply with PJM Manual 3, sections 1.7 and 1.8; PJM Manual 7, section 17; and all applicable NERC requirements; and the new illustrative Tariff, sections 705.5 and 713.6.
159 See Wharton Aff. ¶¶ 16, 22 & 23.

PDF page 66

61
Certified Operators pursuant to PJM Manual 40” and has the “ability to receive voice and electronic signals from [PJM].”160

Third, as discussed above, PJM will need to rely on developing telemetry to remain informed of unreserved use by Eligible Customers taking Contract Demand Transmission Service or Interim NITS.  PJM is still determining the scope of the tools and requirements that will need to be developed in order to limit withdrawals that exceed reserved use. In addition to developing new requirements, as Senior Director of Forward Market Operations for PJM Mr. Horger testifies, PJM will need to make changes to core Markets and Operations systems in order to incorporate the information provided by Eligible Customers and Co-Located Load, as needed, to ensure reliability and stability of the PJM Transmission System.161  Changes to these systems will necessarily be dependent on vendor availability, the speed with which the system changes can be designed, and the interaction of these requested changes with other competing priorities, including system changes to implement other Commission-directed initiatives.162

160 See Illustrative Tariff, Part XI, Subpart A, section 702.4; id., Part XI, Subpart B, section 710.4.
161 Horger Aff. ¶ 16.
162 Horger Aff. ¶ 16.

PDF page 67

62
Question 10:
What other eligibility requirements, e.g., interconnection requirements or operational practices, are necessary for an Eligible Customer to take Firm Contract Demand or Non-Firm Contract Demand transmission service on behalf of Co-Located Load?

Response to Question 10:
Please see PJM’s above answers to Questions 1 and 2, as well as Section III below discussing Interim NITS, which, among other non-rate terms and conditions, discusses interconnection requirements or operational practices that PJM envisions would be necessary to implement these new transmission services.

PDF page 68

63
Question 11:
What are the appropriate procedures to govern the circumstances under which PJM curtails an Eligible Customer taking the interim, non-firm transmission service, Firm Contract Demand transmission service, or Non-Firm Contract Demand transmission service on behalf of a Co-Located Load during emergency procedures? In particular, can PJM shed all or a portion of a Co-Located Load on whose behalf an Eligible Customer takes Non-Firm Contract Demand transmission service while continuing to serve all or a portion of a Co-Located Load on whose behalf an Eligible Customer takes Firm Contract Demand transmission service? Response to Question 11:

Question 11 focuses on Curtailment of Eligible Customers taking transmission service on behalf of a Co-Located Load “during emergency procedures,” or to avoid the need to implement escalating emergency procedures, which PJM understands to mean “Emergency Operations,” as set forth in Tariff, Attachment K-Appendix, section 8 and PJM Manual 13.

PJM has included, in the illustrative Tariff provisions and Service Agreements, provisions that address Curtailment procedures during Emergency Operations.

A. New Curtailment Procedures Applicable to Eligible Customers Taking Service on Behalf of a Co-Located Load During Emergency Operations Under the illustrative Tariff provisions, Interim NITS and Non-Firm Contract Demand Transmission Service will be curtailed before Firm Contract Demand Transmission Service and NITS.  The Transmission Provider may also curtail Interim NITS or Non-Firm Contract Demand Transmission Service prior to dispatching the Pre- Emergency Load Response Program as further set forth in the PJM Manuals, or in response to a transfer capability shortage as a result of system reliability conditions.  This effectively means that Interim NITS and Non-Firm Contract Demand Transmission Service will be

PDF page 69

64
curtailed before Demand Response resources are called upon to reduce load.163  For purposes of Curtailment, Firm Contract Demand Transmission Service will be treated as the equivalent of NITS.164

To the extent that a system contingency exists on the Transmission Provider’s Transmission System and the Transmission Provider determines that it is necessary for the Transmission Owners and an Eligible Customer taking Interim NITS, Firm Contract Demand Transmission Service, or Non-Firm Contract Demand Transmission Service to shed load, the Eligible Customer and the affected Transmission Owner(s) must shed load in accordance with previously established procedures under the relevant Service Agreement for Interim NITS (Attachment F-3A) or for Contract Demand Transmission Service (Attachment F-4).

Consistent with PJM’s provision of NITS,165 PJM is reserving the right, consistent with Good Utility Practice and on a not unduly discriminatory basis, to curtail Interim NITS, Firm Contract Demand Transmission Service, and/or Non-Firm Contract Demand Transmission Service without liability on PJM’s part “for the purpose of making necessary adjustments to, changes in, or repairs on its lines, substations and facilities,” and in cases where the continuance of Interim NITS, Firm Contract Demand Transmission Service, and/or Non-Firm Contract Demand Transmission Service would endanger persons or property.166  PJM will give the Eligible Customer as much advance notice as is practicable in the event of such Curtailment.

163 Illustrative Tariff, Part XI, Subpart A, section 705.2; id., Part XI, Subpart B, section 713.4.
164 Illustrative Tariff, Part XI, Subpart A, section 713.3.
165 Tariff, section 33.7.
166 Illustrative Tariff, Part XI, Subpart A, section 705.4, id., Part XI, Subpart B, section 713.5.

PDF page 70

65
B. Curtailment of an Eligible Customer Taking Both Firm and Non-Firm Contract Demand Transmission Service on Behalf of a Co-Located Load

During Emergency Operations
Question 11 asks, “in particular, whether PJM can shed all or a portion of a Co- Located Load on whose behalf an Eligible Customer takes Non-Firm Contract Demand transmission service while continuing to serve all or a portion of a Co-Located Load on whose behalf an Eligible Customer takes Firm Contract Demand transmission service.” PJM understands the Commission to be asking whether PJM has the operational capability to appropriately prioritize Load Shed based on level of transmission service when an Eligible Customer serves a Co-Located Load under both a Firm Contract Demand Transmission Service Agreement and a Non-Firm Contract Demand Transmission Service Agreement.

For example, if a 15-MW Co-Located Load is served by an Eligible Customer with a Firm Contract Demand Transmission Service Agreement for 5 MWs and a Non-Firm Contract Demand Transmission Service for 10 MWs, can PJM operationally differentiate between and appropriately prioritize the 5 MWs of Firm Contract Demand Transmission Service and the 10 MWs of Non-Firm Contract Demand Transmission Service?  Currently, PJM’s core Markets and Operations Systems including modifying the Intermediate and Real-Time Security Constrained Economic Dispatch (IT SCED and RT SCED), Day-Ahead Market software, and PJM dispatch tools, do not automate Curtailment of Non- Firm Contract Demand Transmission Service (or Interim NITS) before Firm Contract Demand Transmission Service.  Currently, the system does not differentiate between different types of transmission service being used to serve load within PJM, because all

PDF page 71

66
load within PJM is currently served by NITS.167  Thus, as an initial matter, as Mr. Horger notes, core systems, including software changes, would need to be implemented to enable this level of granularity when shedding an Eligible Customer’s Co-Located Load being served by two different levels of transmission service.168  Assuming that these core system design changes can be and are implemented, Eligible Customers taking transmission service on behalf of Co-Located Load, would need to take these different forms of transmission service on different feeders, or cables leaving substations, to ultimately serve the Co-Located Load.169  PJM would need to develop these requirements, as outlined, above, in PJM’s response to Question 9.

III. INTERIM NETWORK INTEGRATION TRANSMISSION SERVICE
The Commission in the Show Cause Order recognized that Co-Located Loads desire a way to more rapidly interconnect to the PJM Transmission System and begin operation.170  The Commission ordered PJM to develop a new service transitional to obtaining NITS that would allow new Co-Located Load to withdraw electricity from the PJM Transmission System earlier than may be otherwise achievable if these loads were required to await completion of any necessary Network Upgrades for NITS.171  Therefore, PJM has developed a new, transitional Interim NITS that will accelerate the time needed for an Eligible Customer to start taking service on behalf of a Co-Located Load than otherwise would be required to provide a Co-Located Load with NITS equivalent to that a

167 See Abdulsalam Aff. ¶ 7.
168 See Horger Aff. ¶ 16.
169 See Abdulsalam Aff. ¶ 11.
170 Show Cause Order at P 200.
171 Id.

PDF page 72

67
Network Load would receive.  This service will be interim until such time that the necessary Network Upgrades, in order to serve the Co-Located Load as full Network Load, are placed in service and operational.  PJM has attached illustrative Tariff language setting forth non-rate terms and conditions for this service in Attachment A, Part XI, Subpart A, sections 700-707.

However, the Briefing Questions above do not specifically focus on the non-rate terms and conditions for Interim NITS.  Nonetheless, the record in this proceeding could benefit from PJM detailing non-rate terms and conditions applicable to this new transmission service type for Eligible Customers willing and able to limit energy withdrawals prior to their NITS being available (because the necessary transmission facilities are not completed).  Accordingly, PJM includes this additional section to describe those rules.

A. Provision of Interim NITS and Nature and Scope of Service
Generally speaking, the non-rate terms and conditions for Interim NITS are the same as for NITS,172 with modifications necessary to implement the interim and non-firm nature of the service.  As envisioned by the Show Cause Order, Interim NITS is designed to merely be a transition service until the system can support the customer’s NITS request. Thus, upon request to PJM and as determined through appropriate studies of the Transmission System by PJM and the affected Transmission Owner(s), Eligible Customers may take, on behalf of a Co-Located Load, Interim NITS—a non-firm, interruptible network transmission service until such time as the Network Upgrades necessary to provide

172 Compare illustrative Tariff, Part XI, Subpart A, sections 700-07, with Tariff, Part III.

PDF page 73

68
NITS are complete.173  Once the necessary Network Upgrades are completed, Interim NITS customers will automatically convert to NITS customers.174  An Eligible Customer receiving Interim NITS will receive non-firm interruptible transmission service for the delivery of energy to serve Co-Located Load.175

B. Initiating Service
Illustrative section 702 in Attachment A details how an Eligible Customer seeking Interim NITS on behalf of a Co-Located Load will initiate service requests.  Given that Interim NITS is transitory before full NITS is available, an Eligible Customer must also be requesting NITS176 and will need to pay an study fee “in addition to the study fee required under an Application for Network Integration Transmission Service under Tariff, Part III, section 32.2.”177  Upon receipt of the request and study fee, PJM, in consultation with the affected Transmission Owner(s) and based on the results of appropriate studies, will determine the amount of Interim NITS that can be reliably provided.178

As with NITS,179 prior to obtaining Interim NITS, the Eligible Customer must meet certain conditions precedent and meet the appropriate technical requirements.  Specifically, among several enumerated conditions precedent, the language would require the Eligible Customer to comply with the provisions of the “PJM Credit Policy” set forth in Tariff,

173 Illustrative Tariff, Part XI, Subpart A, sections 701.1, 701.4.
174 Illustrative Tariff, Part XI, Subpart A, section 701.1.
175 Illustrative Tariff, Part XI, Subpart A, section 701.2.  Similar restrictions on third-party sales as detailed in response to Question 1 above will also apply to Interim NITS.  See illustrative Tariff, Part XI, Subpart A, section 701.3; supra section II, Response to Question 1. 176 Illustrative Tariff, Part XI, Subpart A, section 702.2 (“[A]n Eligible Customer shall not apply for Interim Network Integration Service without applying for Network Integration Transmission Service.”). 177 Illustrative Tariff, Part XI, Subpart A, section 702.2.
178 Illustrative Tariff, Part XI, Subpart A, section 702.3.
179 See Tariff, Part III, sections 29.1, 29.3.

PDF page 74

69
Attachment Q; “certify[y] that it is willing and able to limit energy withdrawals from the Transmission System when requested by [PJM];” and “otherwise execute, if necessary, and comply with the PJM Governing Agreements.”180

As for the necessary technical requirements, the Eligible Customer must (i) install “necessary hardware and software to limit energy withdrawals, including metering equipment;” (ii) provide PJM an operational contact and backup contact that is to be available 24 hours a day and 7 days a week, (iii) certify that it “is staffed with PJM Certified Operators pursuant to PJM Manual 40;” (iv) demonstrate “its ability to receive voice and electronic signals from [PJM];” (v) demonstrate that it “has operational control to respond to operating instructions from [PJM] to reduce or disconnect the Co-Located Load within 5 minutes or as specified in PJM Manuals;” and (vi) demonstrate that it “has operational control of the necessary control technologies and protection systems set forth in Section 705, as applicable.”181  The illustrative Tariff also provides that the Eligible Customer “shall be solely responsible” for constructing, maintaining, and operating all facilities on its side of the Delivery Point.182

C. Designation of Co-Located Load
Illustrative Attachment A, section 703 would require that an Eligible Customer taking Interim NITS designate the individual Co-Located Load on behalf of which the Eligible Customer is taking Contract Demand Transmission Service, whether Firm, Non- Firm, or both.183  Given that the provision of Interim NITS is premised on how the

180 Illustrative Tariff, Part XI, Subpart A, section 702.1.
181 Illustrative Tariff, Part XI, Subpart A, section 702.4.
182 Illustrative Tariff, Part XI, Subpart A, section 702.5.
183 Illustrative Tariff, Part XI, Subpart A, section 703.1.

PDF page 75

70
Transmission System can handle the special circumstances of the Co-Located Load arrangement prior to the completion of necessary facilities, the Co-Located Load arrangement cannot change during the term of the Interim NITS without discussion and possible further studies with PJM.  Thus, section 703.2 provides that “[p]rior to the Service Commencement Date of Network Integration Transmission Service, if an Eligible Customer designates a new Co-Located Load, or increases the size of the designated Co- Located Load, the new Co-Located Load shall be studied pursuant to a new Application.” Further, in order to maintain operational visibility by PJM of the system and thus to ensure reliability, Eligible Customers shall have an ongoing obligation to provide the Transmission Provider with timely written or electronic notice of material changes in the demand characteristics of the Co-Located Load and the supply characteristics of the Co-Located Generating Facility.184  Given that each control technology or protection scheme will be designed based on the specific circumstances and technical arrangements of each Co-Located Load arrangement, such a material change could have deleterious effects on the efficacy of the necessary control technologies and protection schemes associated with a Service Agreement for Interim NITS and PJM’s ability to reliably operate the system.  Thus, failure to timely inform the PJM of such material changes “may constitute a breach of the Eligible Customer’s Service Agreement.”185

D. Study Procedures for Interim NITS
To assess whether the Transmission System can accommodate a request for Interim NITS, PJM will determine whether additional studies beyond what is required to evaluate

184 Illustrative Tariff, Part XI, Subpart A, section 703.3.
185 Illustrative, Part XI, Subpart A, section 703.3.

PDF page 76

71
the Eligible Customer’s request for NITS is needed for Interim NITS.186  If additional studies are deemed necessary, PJM will inform the Eligible Customer and will provide them with an Application and Studies Agreement in which the Eligible Customer will agree to reimburse PJM for the cost of the required studies.187  The Eligible Customer must execute the Application and Studies Agreement within fifteen days and provide the study fee, otherwise the Application will be deemed withdrawn and the study fee will be returned with interest.188

E. Load Shedding and Curtailments
As envisioned by the Show Cause Order, Interim NITS is premised on the notion that the Co-Located Load is willing and able to limit its energy withdrawals from the Transmission System prior to NITS being available.189  Accordingly, PJM developed Load Shedding and Curtailment provisions applicable to Interim NITS in illustrative Tariff, Part XI, Subpart A, section 705.  In addition, Load Shed and Curtailment procedures applicable to Interim NITS are described above, in response to Question 11.

Under the provisions set forth in the illustrative Tariff, prior to the Service Commencement Date, an Eligible Customer seeking to take Interim NITS on behalf of a Co-Located Load would need to demonstrate its ability to comply with Load Shedding and Curtailment procedures as directed by PJM.190  Whenever ordered by PJM, an Eligible Customer must implement any Load Shedding or Curtailment directive, including as

186 Illustrative Tariff, Part XI, Subpart A, section 704.1.
187 Illustrative Tariff, Part XI, Subpart A, section 704.1.
188 Illustrative Tariff, Part XI, Subpart A, sections 704.1, 704.2.
189 Show Cause Order at P 178.
190 Illustrative Tariff, Part XI, Subpart A, section 705.1.

PDF page 77

72
necessary responding to any real-time instruction to reduce or curtail load within five minutes of the directive.  PJM reserves the right to curtail Interim NITS to maintain system reliability,191 but any and all Curtailments will be on a non-discriminatory basis.192  Load Shed instructions will be directed toward Eligible Customers in a manner that is consistent with previously established procedures under the Service Agreement for Interim NITS, and Interim NITS will be curtailed before Firm Contract Demand Transmission Service and NITS and PJM may curtail Interim NITS prior to initiating a pre-emergency event.193  PJM may also instruct Eligible Customers taking Interim NITS to shed load in accordance with previously established procedures under the Service Agreement for Interim NITS (Attachment F-3A).194

As discussed, as part of implementing the key principles that (1) the services are designed to serve loads that are “willing and able to control their withdrawals from the transmission system;”195 and (2) the services are designed to allow PJM to maintain system reliability, PJM is requiring Eligible Customers taking Interim NITS to work with PJM and affected Transmission Owners to “establish necessary control technologies and protection systems, which may include a Remedial Action Scheme, for each Service Agreement for Interim [NITS].”196

PJM’s response to Question 5, above, discusses the processes and procedures for establishing these schemes for limiting the Co-Located Load’s withdrawal of energy from

191 Illustrative Tariff, Part XI, Subpart A, section 705.5.
192 Illustrative Tariff, Part XI, Subpart A, section 705.1.
193 Illustrative Tariff, Part XI, Subpart A, section 705.2.
194 Illustrative Tariff, Part XI, Subpart A, section 705.3. 195 Show Cause Order at P 204. 196 Illustrative Tariff, Part XI, Subpart A, section 705.5.

PDF page 78

73
the Transmission System and for protecting the Transmission System from the adverse operational effects of unscheduled energy withdrawals.  As discussed, above, in PJM’s response to Question 5, Eligible Customers may be temporarily paused and subsequently disqualified from taking Interim NITS following two misoperations of any necessary control technology or protection system.  Likewise, as explained, above, in response to Question 5, an Eligible Customer that fails to respond to established Load Shedding and Curtailment procedures on one occasion will be disqualified from taking Interim NITS.197 To the extent an Eligible Customer is disqualified from taking Interim NITS, the Eligible Customer—having demonstrated that it is not willing (because it did not follow instruction) or able (because the protection scheme failed twice) to limit energy withdrawals—must wait until the facilities necessary to provide NITS are completed before it can resume service to this Co-Located Load.198

F. Rates and Charges for Interim NITS
Consistent with the allocation of rights between PJM and PJM Transmission Owners,199 PJM expects the PJM Transmission Owners to brief a transmission rate appropriate for Interim NITS.

However, Eligible Customers will be assessed other rates in addition to transmission service rates, and PJM has authority to institute such non-transmission-related rates.  Thus, section 706 provides that PJM would assess:

• administrative services charges under Schedule 1A, Schedule 9, and Schedule 10 of the Tariff, consistent with the charges assessed to loads taking NITS;200

197 See supra section II, response to Question 5.
198 See illustrative Tariff, Part XI, Subpart A, section 705.6(c).
199 Illustrative Tariff, Part XI, Subpart A, section 706.4; see supra note 4.
200 Illustrative Tariff, Part XI, Subpart A, section 706.4.

PDF page 79

74
• Ancillary Services charges, except for Regulation, based on the net demand of the Co-Located Load in accordance with Part I, section 3;201

• Black Start Service charges based on the gross demand of the Co-Located Load in accordance with Tariff, Schedule 6A;202 and

• any redispatch costs as set forth in Tariff, Attachment K.203
These are standard charges associated with the use of the Transmission System over and above the transmission service rates.

Further, as with all settlements in PJM, PJMSettlement will be the Counterparty to the Firm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission Service transactions under this Tariff.204

G. Operating Agreement
PJM requires that the Eligible Customer plan, construct, operate, and maintain its facilities in conformance with the Operating Agreement.  Additionally, the terms and conditions under which the Eligible Customer will operate its facilities will be detailed in the Operating Agreement.205  Consistent with PJM’s requirements for NITS and the Commission’s pro forma Open Access Transmission Tariff,206 PJM requires that the Eligible Customer taking Interim NITS to plan, construct, operate, and maintain its facilities in conformance with the Operating Agreement.207  Additionally, the terms and

201 Illustrative Tariff, Part XI, Subpart A, section 706.4.
202 Illustrative Tariff, Part XI, Subpart A, section 706.4.
203 Illustrative Tariff, Part XI, Subpart A, section 706.2.
204 Illustrative Tariff, Part XI, Subpart A, section 700; id., Attachment F-3A, section 1.0.
205 Illustrative Tariff, Part XI, Subpart A, section 707.1
206Pro Forma Open Access Transmission Tariff, section 35.1.
207 See illustrative Tariff, Part XI, Subpart A, section 707.1.  The Commission’s pro forma Open Access Transmission Tariff uses the term “Network Operating Agreement.”  In PJM, the “Operating Agreement of the PJM Interconnection, L.L.C., as amended from time to time, shall constitute the Network Operating Agreement.”  Tariff, Attachment G.

PDF page 80

75
conditions under which the Eligible Customer will operate its facilities will be detailed in the Operating Agreement.208

H. Pro Forma Service Agreement Specific to Eligible Customers Serving
Co-Located Load Via NITS or Interim NITS
To facilitate the automatic transition from Interim NITS to NITS and to best administer the terms and conditions specific to serving Co-Located Loads, PJM has developed a single Service Agreement specific to Eligible Customers serving Co-Located Loads via Interim NITS or NITS.  PJM’s illustrative Service Agreement for NITS and Interim NITS is included in Attachment A to this initial brief and has been designated as Attachment F-3A.209  In addition to the NITS terms carried over from the pro forma NITS Service Agreement (Attachment F-3), PJM has added terms specific to Co-Located Load arrangements, including, for example, a description of Co-Located Generating Facility and its Maximum Facility Output, and a description of Co-Located Load and its gross demand.210

The Service Agreement provides the optionality of applying to full NITS only, or both full NITS and Interim NITS.211  The Eligible Customer is also required to submit a single-line diagram as a part of Attachment F-3A to show the Delivery Point between the Co-Located Load and Co-Located Generating Facility.

208 Illustrative Tariff, Part XI, Subpart A, section 707.1. 209 Illustrative Tariff, Attachment F-3A.  The existing pro forma NITS Service Agreement is located at Tariff, Attachment F-3.
210 Illustrative Tariff, Attachment F-3A.
211 Illustrative Tariff, Attachment F-3A, section 2.0.

PDF page 81

76
IV. OTHER ILLUSTRATIVE TARIFF REVISIONS

Other than the new illustrative Tariff, Part XI discussed above, PJM also provides illustrative Tariff revisions to other parts of its Tariff, including Part I (Definitions), Part III (Network Integration Transmission Service), and the pro forma GIA.  Because these revisions relate to the terms and conditions of transmission service for Co-Located Load, PJM has included them in the illustrative Tariff in Attachment A to this initial brief, rather than in the compliance filing being submitted concurrently with this initial brief.

First, PJM provides illustrative Tariff language to the definition of “Curtailment” in Part I, which refers to the specific Curtailment procedures provided in the new Tariff, Part XI applicable to Interim NITS or Non-Firm Contract Demand Transmission

Service.212  This definitional change distinguishes between ordinary Curtailment procedures and the ones that are specific to the new transmission services available to Co-Located Load arrangements.

Second, PJM includes a definition of “Remedial Action Scheme” in the illustrative language, which simply refers to the NERC Glossary of Terms.213

Third, PJM includes an additional set of Application Procedures for Eligible Customers taking service on behalf of Co-Located Load seeking NITS in Part III.214  This information is necessary for PJM to perform the relevant studies and analyses needed to

212 Illustrative Tariff, Part I (Definitions), Definitions – C – D.
213 Illustrative Tariff, Part I (Definitions), Definitions – R.  Other Regional Transmission Organizations and Independent System Operators have implemented RAS consistent with the NERC standards.  See, e.g., Cal. Indep. Sys. Operator Corp., 180 FERC ¶ 61,143, at PP 16, 40 (2022); Midcontinent Indep. Sys. Operator, Inc., 177 FERC ¶ 61,233, at P 4 n.8 (2021) (“MISO notes that the RAS was adopted pursuant to North American Electric Reliability Corporation standard PRC-012-1.”).
214 Illustrative Tariff, Part III (Network Integration Transmission Service), section 29.2(x).

PDF page 82

77
provide NITS for Eligible Customers taking transmission service on behalf of Co-Located Load.

Finally, PJM includes additional operational procedures and data exchange requirements for a Co-Located Generating Facility associated with Co-Located Load,215 in compliance with the Show Cause Order.216  As described in the Transmittal Letter,217 PJM is proposing in that filing a new Schedule O which will include required information for a Project Developer who intends to use its Generating Facility to serve Co-Located Load through the new Tariff, Part XI.  In Attachment A, the text that is marked in grey has been proposed by PJM in the Transmittal Letter.  However, the text that is marked in redline below the grey text includes additional illustrative Tariff language on operational procedures and data exchange requirements that PJM believes are necessary for a Project Developer who intends to use its Generating Facility to serve Co-Located Load.218  This includes:

• Reference to, and incorporation of, operational or administrative
requirements necessary for the Co-Located Generating Facility based on fuel type;

• Requirements relating to the revenue meter and necessary control
technologies and protection systems; and
• Requirements relating to communication about failure or malfunction of any equipment relating to such technologies and systems.219

215 Illustrative Tariff, Schedule O, pro forma GIA.
216 Show Cause Order at P 188.
217 PJM Transmittal Letter at 34-35.
218 Illustrative Tariff, Schedule O, pro forma GIA.
219 Illustrative Tariff, Schedule O, pro forma GIA.

PDF page 83

78
As discussed further in the following Section of the initial brief, PJM reserves its rights to supplement Schedule O to include additional operational procedures or data exchange requirements.

V. RESERVATION OF RIGHTS TO SUPPLEMENT FILING

As discussed throughout this brief and shown in the illustrative Tariff provisions, the addition of three new transmission services, and revisions to the NITS to accommodate Eligible Customers serving Co-Located Load, requires complex revisions to PJM’s transmission planning, interconnection, and operational procedures.  Indeed, the illustrative provisions represent most, but not all, of the potential tariff language and revisions that would be necessary to implement these new services from a planning, interconnection, and operational perspective.

However, further work is required to fully integrate these new services into PJM, including into PJM’s energy, ancillary services, and capacity markets.  PJM continues to review its Governing Documents to determine the additional revisions necessary to properly account for these new services.  For example, PJM anticipates that it will likely need to revise its existing Tariff provisions addressing Real-time and Day-ahead Energy Market settlements to account for the new transmission services—i.e., Firm and Non-Firm Contract Demand Transmission Service and Interim NITS, particularly given that such provisions often determine charges based on Network Load, and load served by Firm and Non-Firm Contract Demand Transmission Service cannot be Network Load.220  As another example, PJM may need to revise existing Tariff provisions to address the applicability to Auction Revenue Rights and Financial Transmission Rights to Eligible Customers serving

220 See Show Cause Order at P 205.

PDF page 84

79
load with Contract Demand Transmission Service.  PJM will continue to review its Governing Documents and reserves the right to supplement its filing with additional terms and conditions needed to effectuate these new transmission services to allow the paper hearing the benefit of such additional information.

VI. IMPLEMENTATION AND EFFECTIVE DATE
As explained by Mr. Horger, PJM believes an effective date of June 1, 2029, is necessary for the three new transmission services—Interim NITS, Non-Firm Contract Demand Transmission Service, and Firm Contract Demand Transmission Service.221  Mr. Horger explains that June 1, 2029, is a reasonable and appropriate effective date for these new transmission services because of the time required to:  (1) integrate these transmission services into PJM’s capacity market, the Reliability Pricing Model (“RPM”), so that PJM can procure capacity for those that are capacity-backed (e.g., Firm Contract Demand Transmission Service); and (2) make the necessary modifications to the PJM core Markets and Operations systems.  Regardless, it is unlikely that generation intended to serve Co-Located Load will be constructed and operational before June 1, 2029. First, Mr. Horger explains that the three new transmission services that will be available to Eligible Customers seeking to take transmission service on behalf of a Co-Located Load will significantly affect the PJM Load Forecast and expected demand, which will, in turn, have significant implications for the RPM, a three-year forward market.222  Given current tight conditions, it is of utmost importance that Eligible

221 PJM notes that NITS is already a service that is available to Eligible Customers electing to take NITS on behalf of Co-Located Load.
222 Horger Aff. ¶ 11 (Although the next few RPM Base Residual Auctions (“BRAs”) will be operating on a compressed auction schedule, “PJM has been on track to return to a normal three-year forward auction for its capacity market by May 2027 (for the 2030/2031 Delivery Year).”).

PDF page 85

80
Customers’ expected demand be reflected in the RPM to ensure that PJM procures needed capacity.

As a forward market, the RPM relies on PJM Load Forecasts to ensure that the RPM auctions procure sufficient capacity for future Delivery Years based on expected demand.  Each Delivery Year begins on June 1.  The RPM BRA for the 2027/2028 Delivery Year, for the Delivery Year beginning June 1, 2027, took place in December 2025.  While the BRA for the 2028/2029 Delivery Year, for the Delivery Year beginning June 1, 2028, has not yet taken place, “as of today, the PJM Load Forecast for the 2028/2029 Delivery Year BRA is already determined, and eligible capacity has already been determined for the 2028/2029 Delivery Year BRA.”223  As a result, “it is no longer possible to update the PJM Load Forecast, update the RPM auction input parameters (planning parameters), and implement necessary changes before the 2028/2029 RPM BRA is conducted, even if the Commission were to theoretically approve the proposed changes today.”224  The BRA for the 2029/2030 Delivery Year, starting June 1, 2029, is the first BRA in which the effects of these transmission services for Eligible Customers can be considered (including procuring necessary capacity for firm transmission services).

Inclusion of these transmission services for Eligible Customers taking transmission on behalf of Co-Located Load in Incremental Auctions, i.e., in the intervening period between the BRAs, would likewise be inappropriate.  As Mr. Horger testifies, “Incremental Auctions are conducted to allow for replacement resource procurement, along with increases and decreases in resource commitments due to reliability requirement

223 Horger Aff. ¶ 12.
224 Horger Aff. ¶ 13.

PDF page 86

81
adjustments.  These adjustments are typically small.”225  Thus, due to the interaction between the impact that Eligible Customers’ load will have on underlying Load Forecasts and expected demand, which in turn will significantly impact the RPM, PJM is proposing a June 1, 2029 implementation date for the three new transmission services applicable to Eligible Customers seeking service on behalf of Co-Located Load.

Second, Mr. Horger testifies that the addition of the three new transmission services will require significant changes to PJM’s core Markets and Operations systems.226 Changes to these systems will necessarily be dependent on vendor availability, the speed with which the system changes can be designed, and the interaction of these requested changes with other competing priorities, including system changes to implement other Commission-directed initiatives.227  In particular, PJM anticipates that, implementing the proposed Curtailment priorities applicable to Interim NITS and Non-Firm Contract Demand Transmission Service, which can affect prices and dispatch instructions, will require PJM to work with vendors to develop system automation that will avoid non-optimal, untimely, and inefficient outcomes.  Because the transmission services proposed herein are novel and subject to a paper hearing, efficient use of vendors to develop the requisite system updates, including software changes, cannot commence until the specific rates, terms, and conditions of these transmission services are correspondingly finalized.228

225 Horger Aff. ¶ 15.
226 Horger Aff. ¶ 16.
227 Horger Aff. ¶ 16.
228 Horger Aff. ¶ 16.

PDF page 87

82
Furthermore, PJM does not expect that Eligible Customers and associated
generation will be online and taking service under any of the proposed transmission services before June 1, 2029.  In other words, the implementation and effective date will not be a limiting factor.  Rather, the process of an Eligible Customer’s generation getting through the interconnection queue, being constructed, and becoming operational will likely take more than three years, particularly in light of current supply chain issues, Transmission Owner and PJM queue requirements, and RPM auction timelines.229  There is a known

challenge to procure equipment, such as turbines,230 and it is not currently expected that a generator could be physically built in less than three years.  The earliest expected Delivery Year a new generator can participate in an RPM BRA or an existing capacity resource can delist, which includes required interconnection modified studies, is for the 2029/2030 Delivery Year.  Thus, for the foregoing reasons, a June 1, 2029 implementation and effective date for the three new transmission services is just and reasonable.

VII. DOCUMENTS ENCLOSED

In addition to this initial brief, PJM encloses the following:
1. Attachment A: Illustrative Language for New Tariff, Part XI; Attachments
F-3A and F-4; and Other Illustrative Tariff Revisions;
2. Attachment B: Affidavit of
Dr.
Sami Abdulsalam, Director of
Transmission Planning;

229 Notably, however, as the Commission recently reiterated, for purposes of the RPM, “Capacity prices are intended to send longer-term investment signals to which developers respond over time[]” and “delays in the interconnection queue, compressed auction schedules, and supply chain issues” do not render RPM auction results unjust and unreasonable.  PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, at P 50 (2025) (citing PJM Interconnection, L.L.C., 126 FERC ¶ 61,275, at P 150 (2009) (“RPM was designed to provide long- term forward price signals . . . .”)).
230 Jared Anderson, US gas-fired turbine wait times as much as seven years; costs up sharply, S&P Global (May 20, 2025), https://www.spglobal.com/energy/en/news-research/latest-news/electric-power/052025-us- gas-fired-turbine-wait-times-as-much-as-seven-years-costs-up-sharply.

PDF page 88

83
3. Attachment C: Affidavit of Matthew Wharton, Manager, Reliability Engineering; and

4. Attachment D: Affidavit of Timothy Horger, Senior Director, Forward Market Operations.

VIII. CONCLUSION
PJM respectfully requests that the Commission find that the illustrative Tariff revisions included in Attachment A are part of a just and reasonable replacement rate in accordance with the requirements of the Show Cause Order.

Respectfully submitted,
/s/ Ryan J. Collins

Craig Glazer
Vice President – Federal
Government Policy
PJM Interconnection, L.L.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 423-4743
craig.glazer@pjm.com

Mark J. Stanisz
Associate General Counsel
Thomas DeVita
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd,
Audubon, PA  19403
(610) 666-8800
mark.stanisz@pjm.com
thomas.devita@pjm.com
Wendy B. Warren
Ryan J. Collins
Vivian W. Chum
Qingliu (Mary) Yang
Wright & Talisman, P.C.
1200 G Street, NW, Suite 600
Washington, DC  20005
(202) 393-1200
warren@wrightlaw.com
collins@wrightlaw.com
chum@wrightlaw.com
yang@wrightlaw.com

Counsel for PJM Interconnection, L.L.C.

February 23, 2026

PDF page 89

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, D.C., this 23rd day of February 2026.

/s/ Ryan J. Collins

Ryan J. Collins

Wright & Talisman, P.C.

1200 G Street, N.W., Suite 600

Washington, DC 20005-3802

(202) 393-1200

collins@wrightlaw.com