Exhibit No. PTO-0001 - Direct Joint Testimony of Blazunas, Shafer, & Hammer
PDF page 1
Exhibit No. PTO-0001Page 1 of 39
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
DIRECT JOINT TESTIMONY
OF
PETER BLAZUNAS, LANCE SCHAFER
AND
HANHAN HAMMER
I. INTRODUCTION
1
Q.
Please state your name, title, business address, and provide your professional 2
background and relevant experience.
3
A. [Blazunas] My name is Peter Blazunas, and my business address is 293 Boston Post Road 4
West, Marlborough, MA 01752. I am a Vice President with Concentric Energy Advisors, 5
Inc. (“Concentric”). I joined Concentric in 2021, and I provide regulatory strategy and rate 6
case expertise to regulated electric and gas utilities, especially with respect to the topics of 7
cost of service and rate design. Prior to Concentric, I managed a team overseeing the cost 8
of service, rate design, and rate administration functions for Potomac Electric Power 9
Company’s (“Pepco”) Maryland and District of Columbia jurisdictions. Prior to Pepco, I 10
worked as an analyst in the FirstEnergy Rates and Regulatory Affairs department. I have 11
PDF page 2
Exhibit No. PTO-0001Page 2 of 39
testified before regulatory commissions in Delaware, the District of Columbia, Maryland, 1
Ohio, and Rhode Island.
2
[Schafer] My name is Lance Schafer, and my business address is 293 Boston Post 3
Road West, Marlborough, MA 01752. I am a Senior Project Manager with Concentric. I 4
specialize in regulatory strategy, rate design, and cost of service for regulated electric and 5
gas utilities. Prior to joining Concentric in 2024, I was the Manager of Rate Administration 6
at Pepco, where I was responsible for overseeing the cost of service, rate design, and rate 7
administration functions for Pepco’s Maryland and District of Columbia jurisdictions. I 8
have testified before regulatory commissions in Delaware, the District of Columbia, 9
Kentucky, Maryland, Missouri, and Rhode Island.
10
[Hammer] My name is Hanhan Hammer, and my business address is 293 Boston 11
Post Road West, Marlborough, MA 01752. I am a Senior Project Manager with Concentric. 12
In my current role, I advise regulators, utilities, grid operators, and developers on complex 13
regulatory and market issues, including wholesale market participation, compliance with 14
FERC directives, transmission planning and cost allocation, large load tariffs, and 15
integrated resource planning. Prior to joining Concentric in 2024, I spent approximately 15 16
years working at various Independent System Operators and Regional Transmission 17
Organizations. My experience includes designing wholesale market rules at ISO New 18
England (“ISO-NE”) and overseeing competitive market performance monitoring at the 19
Midcontinent Independent System Operator (“MISO”) and the Southwest Power Pool 20
(“SPP”). I have provided expert testimony before FERC.
21
[Blazunas, Schafer, and Hammer] Our professional background and relevant 22
experience are also shown in Exhibit No. PTO-0002.
23
PDF page 3
Exhibit No. PTO-0001Page 3 of 39
II. BACKGROUND
1
Q.
What is the background for this proceeding?
2
A. [Blazunas, Schafer, and Hammer] On December 18, 2025, the Commission issued its 3
order in PJM Interconnection. L.L.C., 193 FERC ¶ 61,217, at P 193 (2025) (“Order”). In 4
the Order, the Commission found that PJM’s Open Access Transmission Tariff (“Tariff”) 5
“is unjust and unreasonable because it does not contain provisions addressing with 6
sufficient clarity or consistency the rates, terms, and conditions of service that apply to 7
generators serving Co-Located Load and Eligible Customers taking transmission service 8
on behalf of Co-Located Load.”1 Specifically, the Commission found PJM’s Tariff “unjust 9
and unreasonable because it does not include types of transmission service that reflect 10
Eligible Customers taking service on behalf of Co-Located Loads that are willing and able 11
to limit their use of the transmission system under certain conditions.”2 12
The Commission ordered PJM to offer three new forms of transmission service 13
under its Tariff, and identified these three new forms of transmission service as: (i) Firm 14
Contract Demand transmission service; (ii) Non-Firm Contract Demand transmission 15
service; and (iii) interim, non-firm transmission service. The Commission also established 16
a paper hearing to determine the just and reasonable rates, terms, and conditions for these 17
new transmission services. The paper hearing process provides for initial briefs, responses 18
to initial briefs, and replies to those responses.
19
20
21
1 Order at P 2.2 Id.
PDF page 4
Exhibit No. PTO-0001Page 4 of 39
III. PURPOSE OF TESTIMONY
1
Q.
What is the purpose of your testimony?
2
A. [Blazunas, Schafer, and Hammer] The PJM Transmission Owners, acting through the
3
Section 205 Working Group,3 have developed rate design proposals in response to the
4
Order’s requirement that PJM implement new transmission services and for submission in 5
the paper hearing process.4 The purpose of this testimony is to describe and support the 6
PJM Transmission Owners’ rate design proposals for the three new transmission services 7
the Commission required in the Order. We also support the PJM Transmission Owners’
8
rate design proposals for a new Grid Reliance Charge. We also address penalty provisions 9
and planning and operational issues relating to Eligible Customers5 that choose to take one 10
or more of these new services. In particular, we discuss appropriate practices and
11
requirements relating to protective systems and other components that will be necessary to 12
ensure ongoing system reliability.
13
3 The Section 205 Working Group is established under the authority of the Transmission Owner Agreement Administrative Committee (“TOAAC”) pursuant to the Consolidated Transmission Owners Agreement (“CTOA”). See CTOA § 8.1. These proposals have not yet been submitted to the TOAAC for approval.4 For purposes of this testimony and the accompanying responses to the Commission’s paper hearing questions, the PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Duquesne Light Company; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company (“PECO”), and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans- Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company (“PSE&G”); Rockland Electric Company; and the Southern Maryland Electric Cooperative (“SMECO”).5 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff or Amended and Restated Operating Agreement of PJM Interconnection, L.L.C.
PDF page 5
Exhibit No. PTO-0001Page 5 of 39
IV. NEW TRANSMISSION SERVICE CATEGORIES AND RATE DESIGNS
1
A. Firm Contract Demand Transmission Service
2
Q.
What is Firm Contract Demand transmission service?
3
A. [Blazunas] Pursuant to the Order, under the new Firm Contract Demand transmission 4
service (“Firm Contract Demand Service”), Eligible Customers will have the right to 5
request transmission service on behalf of a Co-Located Load up to a specified megawatt 6
(“MW”) quantity (“Firm Contract Demand”). The Firm Contract Demand Service will 7
have the same reservation and curtailment priority as existing firm transmission services at 8
the level of the contract demand. However, unlike Network Integration Transmission 9
Service (“NITS”) customers, the Eligible Customer taking Firm Contract Demand Service 10
on behalf of the Co-Located Load is not permitted to withdraw energy from the PJM 11
transmission system beyond the firm contract demand level under this service. 12
Q.
What is the PJM Transmission Owners’ proposed rate design for the new Firm 13
Contract Demand Service?
14
A. [Blazunas] The PJM Transmission Owners propose that the rate for Firm Contract 15
Demand Service be based on zonal NITS rates and the underlying NITS revenue 16
requirements. Under this approach, Eligible Customers taking Firm Contract Demand 17
Service will pay the same base charge per MW as NITS customers, except that, unlike 18
NITS customers, their applicable billing determinant will be their specified firm contract 19
demand. The transmission charge for a Firm Contract Demand Service customer will be 20
calculated by multiplying: (i) the customer’s firm contract demand amount (in MWs) by 21
(ii) the applicable zonal NITS rate.
22
PDF page 6
Exhibit No. PTO-0001Page 6 of 39
In zones with formula transmission rates, the single annual rate applicable to both 1
NITS and Firm Contract Demand Service customers will be established in the same manner 2
as NITS rates are today.6 This rate will be calculated based on each transmission owner’s 3
annual net revenue requirement, as determined pursuant to the formula rates contained in 4
Attachment H to the PJM Tariff, divided by the single zonal coincident peak load, which 5
will include NITS customer load, the total contract demand for all Firm Contract Demand 6
Service customers, and load associated with interim, non-firm transmission service.7 This 7
will result in a single $/MW-year rate that will apply to both NITS and Firm Contract 8
Demand Service customers.
9
Eligible Customers will also pay a Grid Reliance Charge for the portion of their 10
remaining on-site load not covered by Firm Contract Demand Service. The Grid Reliance 11
Charge is discussed in further detail below.
12
The procedures for establishing zonal NITS/Firm Contract Demand transmission 13
service rates and updating the underlying annual revenue requirements will remain 14
unchanged, and Firm Contract Demand Service customers will be treated the same as NITS 15
customers under each PJM Transmission Owner’s formula rate protocols.
16
A detailed example showing how the Firm Contract Demand Service rate and other 17
charges associated with the new services will be calculated is set forth below. 18
6 A handful of PJM transmission owners continue to utilize stated rates, which in some cases are based on black-box settlements, which may need to be accounted for in specific stated rates for the new firm and non-firm contract demand services.7 Any changes to a transmission owner’s procedure for assigning a Network Service Peak Load (“NSPL”) tag to a Load Serving Entity (“LSE”) may need to be addressed in a future filing.
PDF page 7
Exhibit No. PTO-0001Page 7 of 39
Q.
Why are the PJM Transmission Owners proposing to base the rate for Firm Contract 1
Demand Service on the NITS rate, as opposed to the firm Point-to-Point rate or some 2
other rate?
3
A. [Blazunas] The PJM Transmission Owners are proposing to charge the same rate for Firm 4
Contract Demand Service and NITS because the level of service provided to both 5
customers is, for all relevant purposes, the same. Both NITS and Firm Contract Demand 6
Service are firm services for which Network Upgrades will be planned and constructed as 7
necessary, with the only difference being that upgrades for NITS customers are identified 8
based on anticipated load growth while upgrades for Firm Contract Demand Service 9
customers will be identified based on their contracted demand level. Firm Contract 10
Demand Service customers will be able to serve their contracted demand through capacity 11
procured by PJM just like NITS customers and will not be required to designate specific 12
points of receipt and delivery.
13
There is no need or benefit to utilizing existing Firm Point-to-Point Service 14
(“PTPS”) rates. Firm PTPS rates are generally based on the same revenue requirement as 15
the NITS rate, and the nature of Firm Contract Demand Service as contemplated in the 16
Order is essentially a variation of NITS service with a specified contract demand level. The 17
Firm Contract Demand Service customer will be serving its full contract demand from all 18
resources on the grid, not on a point-to-point basis. Consequently, PJM will treat Firm 19
Contract Demand Service load during system emergencies in the same manner as load 20
using NITS, thus providing service to the Firm Contract Demand Service load on a 21
comparable basis with NITS load. Furthermore, Firm Contract Demand transmission 22
Service will enjoy the same firmness as NITS load, as well as the same ability to make use 23
PDF page 8
Exhibit No. PTO-0001Page 8 of 39
of PJM resources to serve their full contract demand and ensure guaranteed grid energy 1
delivery. Given the similarities between NITS and Firm Contract Demand Service, it would 2
be inappropriate to charge Firm Contract Demand Service customers a rate lower than one 3
based on the NITS rate because doing so would result in subsidizing these customers at the 4
expense of other ratepayers.
5
Finally, in PJM, PTPS is generally only utilized for purposes of service at the PJM 6
border. That will not be the case for Co-Located Load customers taking Firm Contract 7
Demand Service to serve their on-site, contract demand within PJM. Basing the rate for 8
Firm Contract Demand Service on the zonal NITS rate also has the advantage of 9
minimizing changes to current PJM billing and settlements practices. As it does for NITS 10
now, for Firm Contract Demand Service, PJM will perform the billing function for 11
transmission, capacity, and energy charges, while electric distribution companies will 12
perform their current roles of submitting the metrics that PJM uses to calculate those 13
charges, such as customers’ peak load share information.
14
Q.
Do the PJM Transmission Owners have suggestions regarding interconnection 15
requirements or operational practices that are necessary for an Eligible Customer to 16
take Firm Contract Demand Service on behalf of Co-Located Load?
17
A. [Hammer] Yes. The PJM Transmission Owners have identified several requirements and 18
operational considerations that are necessary to ensure the reliable operation of the Bulk 19
Electric System and consistency with established planning and operational practices. In 20
particular, the provision of Firm Contract Demand Service on behalf of Co‑Located Load 21
should be conditioned on demonstrating that such load is physically and operationally 22
capable of being managed in a manner consistent with its firm service designation. 23
PDF page 9
Exhibit No. PTO-0001Page 9 of 39
Accordingly, the PJM Transmission Owners recommend the Commission adopt 1
requirements that may include, among other things: (1) compliance with applicable 2
interconnection requirements, including the ability to control and measure load consistent 3
with PJM operating needs; (2) demonstrated capability to respond to curtailment or 4
operational instructions, including the ability to reduce or interrupt loads as necessary to 5
support system reliability; and (3) adherence to defined operating practices, including 6
telemetry, metering, and communications requirements necessary for real‑time monitoring 7
and control.
8
In addition, further consideration may also be warranted in a transmission 9
constrained area where a significant amount of Co-Located Load taking Firm Contract 10
Demand Service relies on operational controls, such as Special Protection Schemes 11
(“SPS”) and Remedial Action Schemes (“RAS”), to curtail load back to the level of 12
contract demand following the loss of on-site generation. In such circumstances, customers 13
may be required to either take a higher level of contract demand or to take NITS for their 14
gross load, because the risk of simultaneous SPS/RAS failure in the local area may be 15
elevated and could result in cascading grid failure.
16
Q.
What are appropriate mechanisms for an anti-toggling feature for Firm Contract 17
Demand Service?
18
A. [Blazunas] Pursuant to the Order, Firm Contract Demand Service will have a minimum 19
term of one year. However, as the Commission recognized, there are concerns regarding a 20
customer’s ability to toggle between firm and non-firm service levels.8 There also is a 21
concern that Firm Contract Demand Service customers will cause the need for transmission 22
8 Order at P 213.
PDF page 10
Exhibit No. PTO-0001Page 10 of 39
upgrades and capacity resource procurement to accommodate their Firm Contract Demand 1
Service and then exit the system, thereby shifting costs to other customers.9 To partially 2
address these concerns, the PJM Transmission Owners recommend a five-year minimum 3
commitment period for Firm Contract Demand Service, consistent with the five-year 4
minimum commitment noted by the Commission for loads seeking to procure their own 5
capacity.10
6
Q.
Do the PJM Transmission Owners have a proposal with respect to notice obligations? 7
A. [Blazunas] Yes. With respect to notice obligations, the PJM Transmission Owners suggest 8
that the Commission adopt the same requirements that currently apply to notices of 9
termination for NITS under Section 2.5 of the PJM Tariff.11
10
B. Non-Firm Contract Demand Transmission Service
11
Q.
What is Non-Firm Contract Demand transmission service?
12
A. [Blazunas] Under the Order, the Commission established a new Non-Firm Contract 13
Demand transmission service (“Non-Firm Contract Demand Service”) to be offered to 14
Eligible Customers taking service on behalf of Co-Located Loads. This new service will 15
permit Eligible Customers taking service on behalf of such loads to seek to withdraw 16
9 Id. at P 213.10 Id.11 PJM Tariff, Section 2.5 (“Although Regional Network Integration Service is presumed to continue without expiration, it may be terminated where:
1) An incumbent Network Customer will be replaced by a successor Network Customer, in which case the incumbent’s service shall only terminate if the successor agrees to commence the taking of service, the appropriate service agreement is executed, and all other applicable terms and conditions of the PJM Governing Agreements are satisfied;
2) An incumbent Network Customer seeks to terminate its service and no successor Network Customer exists, in which case the incumbent must provide PJM with forty-two (42) months’ notice prior to the commencement of a Delivery Year, subject to receiving all necessary regulatory approvals for such termination, if any; or
3) On such other date mutually agreed upon by the parties.”).
PDF page 11
Exhibit No. PTO-0001Page 11 of 39
energy from the transmission system from time to time when transmission capacity is 1
available and not needed by firm customers.12
2
Pursuant to the Order, the new Non-Firm Contract Demand Service will be 3
available during normal operations and curtailed during emergency operations (i.e., it will 4
be curtailed before existing firm transmission services and the new Firm Contract Demand 5
Service). Under this service, Eligible Customers may reserve transmission service on 6
behalf of a Co-Located Load as needed during normal, non-emergency system operating 7
conditions.
8
As specified in the Order, reservations for Non-Firm Contract Demand Service will 9
be permitted only when there is available transmission capacity, similar to existing non- 10
firm transmission service options in the PJM Tariff. Moreover, reservations will be 11
available for terms ranging from one hour to one month, consistent with the terms available 12
for non-firm PTPS currently in the PJM Tariff. Finally, Eligible Customers may use Non- 13
Firm Contract Demand Service to make use of the transmission system above their Firm 14
Contract Demand Service level, if transmission capacity is available.13 15
Q.
What is the PJM Transmission Owners’ proposed rate design for the new Non-Firm 16
Contract Demand Service?
17
A. [Blazunas] As with Firm Contract Demand Service, the PJM Transmission Owners 18
propose that the rate design for Non-Firm Contract Demand Service be based on zonal 19
NITS rates in PJM. Under this approach, the maximum rate for Non-Firm Contract 20
Demand Service on behalf of Co-Located Load will be calculated by multiplying (i) their 21
12 Order at P 214.13 Id. at P 215.
PDF page 12
Exhibit No. PTO-0001Page 12 of 39
reserved, non-firm contract demand amount (in MWs) by (ii) the applicable zonal NITS 1
rate. In the same manner as non-firm PTPS today, PJM will have the ability to offer a 2
discount off of this maximum rate based on rules and criteria established by the PJM 3
Transmission Owners.
4
Finally, as with Firm Contract Demand transmission service, Eligible Customers 5
taking Non-Firm Contract Demand Service also will pay a Grid Reliance Charge 6
representing the remaining on-site load not covered by either Firm Contract Demand 7
Service or Non-Firm Contract Demand Service. The base rate for Non-Firm Contract 8
Demand Service is adjusted to reflect the impact of the Grid Reliance Charge in order to 9
prevent double-recovery. The Grid Reliance Charge is discussed in further detail below. 10
A detailed example of the calculation of the Non-Firm Contract Demand Service 11
rate and other new service charges is set forth below.
12
Q.
Why is it appropriate to use the same rate for Firm Contract Demand Service to 13
establish the maximum rate for the Non-Firm Contract Demand Service?
14
A. [Blazunas] For the reasons outlined above with respect to Firm Contract Demand Service, 15
using the applicable zonal NITS rate to establish the base rate for Non-Firm Contract 16
Demand Service is appropriate. In addition, using the same maximum base rate for Firm 17
Contract Demand Service and Non-Firm Contract Demand Service is just and reasonable. 18
The Commission has traditionally permitted non-firm PTPS to be priced up to (but not 19
above) the rate used for firm PTPS,14 and many transmission owners have identical 20
14 See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, at 31,780 (1996) (cross-referenced at 75 FERC ¶ 61,080) (noting the importance of allowing pricing flexibility and indicating that the non-firm rate is capped at the firm rate), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on
PDF page 13
Exhibit No. PTO-0001Page 13 of 39
maximum base rates for firm and non-firm service, including in PJM. Also, Non-Firm 1
Contract Demand Service will represent a superior level of service compared to non-firm 2
PTPS because pursuant to PJM’s proposed operational procedures, Non-Firm Contract 3
Demand Service customers will have the benefit of PJM re-dispatching generation prior to 4
curtailing Non-Firm Contract Demand Service. Combined with the additional flexibility 5
that Non-Firm Contract Demand Service customers will have with respect to arranging and 6
scheduling Non-Firm Contract Demand Service, and the fact that Non-Firm Contract 7
Demand Service customers will not pay for generation capacity,15 it is just and reasonable 8
to set the maximum Non-Firm Contract Demand Service rate equal to the rate for Firm 9
Contract Demand Service customers on a $/MWh basis.16
10
Q.
Under what circumstances would the PJM Transmission Owners offer a discount for 11
Non-Firm Contract Demand Service?
12
A. [Blazunas] First, under the current PJM Tariff, maximum rates for non-firm PTPS are set 13
equal to rates for firm PTPS, although PJM has the ability to offer discounts for Non-Firm 14
PTPS subject to certain requirements, and based on rules and criteria established by the 15
PJM Transmission Owners.17 The PJM Transmission Owners propose a similar flexibility 16
reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Pol’y Study Grp., v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002).
15 See Order at P 218 (“The new Non-Firm Contract Demand transmission service will not include a charge for generation capacity.”).16 This would be comparable to the rules the Commission established in Order No. 888 with respect to the relationship between firm and non-firm point-to-point transmission service rate. See Order No. 888 at 31,780.17 Schedules 7 and 8 of the PJM Tariff state: [t]hree principal requirements apply to discounts for transmission service as follows: (1) any offer of a discount made by the Transmission Provider must be announced to all Eligible Customers solely by posting on the OASIS, (2) any customer-initiated requests for discounts (including requests for use by one’s wholesale merchant or an Affiliate’s use) must occur solely by posting on OASIS, and
(3) once a discount is negotiated, details must be immediately posted on the OASIS. For any discount agreed upon for service on a path, from point(s) of receipt to point(s) of delivery, the
PDF page 14
Exhibit No. PTO-0001Page 14 of 39
for Non-Firm Contract Demand Service. The Commission directed the implementation of 1
a Non-Firm Contract Demand Service to act as a limited supplemental service that may be 2
needed for the benefit of Firm Contract Demand Service customers to ensure that such 3
customers can serve on-site load, for instance, when its on-site generator is on outage, but 4
not as a substitute for Firm Contract Demand Service. Also relevant is the fact that the 5
historical purpose of a discount on non-firm transmission service is to encourage the 6
efficient use of the transmission system – i.e., to ensure that the system is being utilized 7
optimally. Before determining whether a discount is appropriate, and at what level it should 8
be set, it is necessary for the PJM Transmission Owners to gather data on how Non-Firm 9
Contract Demand Service customers are utilizing the service, taking into account the 10
intended purposes of the service, and the effect of that utilization on the system. 11
Accordingly, the PJM Transmission Owners will consider on a going-forward basis 12
whether a discount is appropriate for Non-Firm Contract Demand Service based on system 13
conditions and use patterns and, if so, the criteria and limits under which PJM will apply 14
the discount.
15
It is worth re-emphasizing that Non-Firm Contract Demand Service will represent 16
a superior level of service compared to non-firm PTPS because Non-Firm Contract 17
Demand Service customers will have the benefit of PJM re-dispatching generation prior to 18
their curtailment based on PJM’s proposed operational procedures. Non-Firm Contract 19
Demand Service customers will also have additional flexibility with respect to arranging 20
and scheduling their service and will not pay for generation capacity.
21
Transmission Provider must offer the same discounted transmission service rate for the same time period to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) of delivery on the Transmission System.
PDF page 15
Exhibit No. PTO-0001Page 15 of 39
Any discount offered for Non-Firm Contract Demand Service would be offered by 1
PJM based on rules and criteria established by the PJM Transmission Owners designed to 2
incentivize the efficient use of Non-Firm Contract Demand Service and the transmission 3
system.
4
Q.
How do the PJM Transmission Owners propose to treat the revenues received from 5
Non-Firm Contract Demand Service charges?
6
A. [Blazunas] To ensure against double recovery, all revenues received from Non-Firm 7
Contract Demand Service charges will be credited to NITS and Firm Contract Demand 8
Service customers based on their share of the coincident peak load, inclusive of the contract 9
demand associated with Firm Contract Demand Service, of the zone where the Co-Located 10
Load is physically located. These credits will reduce the total transmission costs for these 11
customers, and ensure that these customers, who pay rates based on all of the costs of the 12
transmission system, receive the credits associated with Non-Firm Contract Demand 13
Service customers’ use of excess capacity on that system. The credits will be applied to 14
NITS and Firm Contract Demand Service customers through their PJM bills. This will 15
minimize or eliminate the need for the PJM Transmission Owners to modify their formula 16
rates.
17
C. Interim, Non-Firm Transmission Service
18
Q.
What is interim, non-firm transmission service?
19
A. [Blazunas] Under the Order, interim, non-firm transmission service, also sometimes 20
referred to as “Interim NITS,” allows an Eligible Customer that has requested NITS on 21
behalf of a Co-Located Load to take non-firm transmission service that can be interrupted 22
until the network upgrades necessary to provide NITS are complete and the Co-Located 23
PDF page 16
Exhibit No. PTO-0001Page 16 of 39
Load can be designated as network load. Interim, non-firm transmission service is 1
temporary. That is, it is only available to Eligible Customers that have requested NITS on 2
behalf of Co-Located Loads that cannot yet be reliably served with NITS, and it is available 3
only until the necessary network upgrades are completed and the Co-Located Load is 4
designated as network load. Moreover, this new service is optional for an Eligible 5
Customer seeking NITS on behalf of a Co-Located Load and is available only to the extent 6
PJM determines that it can provide some level of interim service reliably.18 7
Q.
What is the PJM Transmission Owners’ proposed rate design for the new interim, 8
non-firm transmission service?
9
A. [Blazunas] The PJM Transmission Owners propose that the rate design for interim, non- 10
firm transmission service be based on the full, zonal NITS rates, as permitted under the 11
Order.19 Under this approach, Eligible Customers taking interim, non-firm transmission 12
service will pay a transmission service charge calculated by multiplying: (i) their measured 13
demand amount (in MWs) multiplied by (ii) the applicable zonal NITS rate. The measured 14
demand amount will be the MW level that PJM determines the transmission system can 15
reliably support under all pre-upgrade operating conditions.
16
Charging the full, zonal NITS rate is consistent with the Order, which stated that 17
interim, non-firm transmission service would be charged the NITS rate.20 Essentially, 18
interim, non-firm transmission service is a temporary, “speed-to-market” tool that allows 19
18 Order at P 200.19 Id. at P 200.20 Id.
PDF page 17
Exhibit No. PTO-0001Page 17 of 39
a Co-Located Load project to energize on an as-available basis while permanent, necessary 1
transmission upgrades are in the PJM queue.
2
V. GRID RELIANCE CHARGE
3
Q.
Above, you explained that Eligible Customers taking Firm Contract Demand Service 4
and Non-Firm Contract Demand Service also will pay a Grid Reliance Charge. Please 5
explain that charge.
6
A. [Schafer] As contemplated under the Order, the PJM Transmission Owners are proposing 7
to include a Grid Reliance Charge as part of the charges associated with the new Co- 8
Located Load terms and conditions under the PJM Tariff. The intent of the Grid Reliance 9
Charge is to reflect the inherent benefits that Firm Contract Demand Service and Non-Firm 10
Contract Demand Service customers receive as a result of their reliance upon the grid. It is 11
designed to recover the costs of delivering ancillary services, including the delivery of 12
black start and regulation, and providing synchronization and grid reliance support, thereby 13
ensuring Co‑Located Loads pay their appropriate share of the transmission system that they 14
rely on regardless of whether they withdraw energy from the grid. The Grid Reliance 15
Charge also recognizes the benefits associated with monitoring and other activities that 16
transmission owners will need to perform associated with the increased number of 17
protective systems that will be required for Co-Located Load customers.
18
As the Commission recognized, Co-Located Loads are electrically connected to the 19
transmission system (not islanded) and therefore benefit from the system and should 20
contribute to the ongoing operation and maintenance of the transmission system, consistent 21
with foundational cost causation principles. Commissioner Chang’s concurrence to the 22
Order stressed the need for a minimum charge for the two new contract demand services. 23
PDF page 18
Exhibit No. PTO-0001Page 18 of 39
The Commissioner noted that a customer selecting a de minimis contract demand could 1
pay almost nothing despite its continuous reliance on the grid.
2
Even with a zero MW contract demand, a large Co‑Located Load still depends on 3
the grid for the delivery of various ancillary services and a suite of synchronization support 4
services, such as a stable frequency, inertia, stability services (damping, angle stability), 5
fault current capability, and ride-through and protection coordination. For example, adding 6
a 1,000 MW load to the transmission system inherently imposes electrical impacts at the 7
point of interconnection and beyond. In summary, zero net withdrawals are not indicative 8
of a load’s actual reliance on the grid. And, of course, a large Co-Located Load, such as a 9
data center, would not be interested in locating in PJM if the system did not also support 10
an extensive network of customers and communications infrastructure.
11
Q.
What is the PJM Transmission Owners’ proposed rate design for the new Grid 12
Reliance Charge?
13
A. [Schafer] The PJM Transmission Owners propose to apply a new Grid Reliance Charge 14
rate to an Eligible Customer’s gross on-site load not covered by Firm Contract Demand 15
Service.21 Practically speaking, this means that Firm Contract Demand Service customers 16
will pay the full zonal NITS/Firm Contract Demand rate on their Firm Contract Demand 17
and the Grid Reliance Charge rate on the difference between their gross load and their Firm 18
Contract Demand. This approach is reasonable because it recognizes the fact that Firm 19
Contract Demand Service customers are already paying for the services recovered via the 20
Grid Reliance Charge through the full zonal NITS rate assessed on their Firm Contract 21
21 A handful of PJM transmission owners continue to utilize stated rates, which in some cases are based on black-box settlements and may need to be accounted for in specific stated rates for the new firm and non-firm contract demand services. This also applies to the Grid Reliance Charge.
PDF page 19
Exhibit No. PTO-0001Page 19 of 39
Demand. Consequently, the Grid Reliance Charge rate only needs to be assessed on any 1
incremental gross load in excess of their Firm Contract Demand. Eligible Customers taking 2
only Non-Firm Contract Demand Service would pay the Grid Reliance Charge on their 3
entire load, but as noted above, the Non-Firm Contract Demand Service rate is calculated 4
so as to remove the Grid Reliance Charge, so there will be no double-charging of Non- 5
Firm Contract Demand Service customers.
6
Q.
How do the PJM Transmission Owners propose to calculate the new Grid Reliance 7
Charge rate?
8
A. [Schafer] The PJM Transmission Owners propose to calculate the Grid Reliance Charge 9
rate using a standardized, percentage-based methodology that relies on publicly available 10
FERC Form No. 1 (“FERC Form 1”) data for PJM Transmission Owners22 to determine 11
the portion of transmission depreciation and operation and maintenance (“O&M”) expense 12
associated with grid reliance capability, and then applies that portion (expressed as a 13
percentage) to each transmission owner’s Attachment H annual transmission revenue 14
requirement (“TRR”).
15
The first step in the proposed methodology is to identify transmission plant 16
accounts and transmission O&M FERC accounts that provide grid reliance capability, 17
described above as related to: (1) supporting the delivery of ancillary services; and (2) 18
providing synchronization support required to accommodate the load’s electrical 19
characteristics. Tables 1 and 2 below summarize the FERC accounts identified as 20
supporting grid reliance capability:
21
22
FERC Form 1 data is publicly available for PJM Transmission Owners, representing approximately 95 percent of the total transmission assets in PJM.
PDF page 20
Exhibit No. PTO-0001Page 20 of 391
Table 1: FERC Accounts Identified as Supporting Grid Reliance Capabilities - Depreciation FERC
Account
Account Description
Basis for Retention
Supported Grid Reliance Charge
Functions
(A)
(B)
(C)
(D)
Depreciation Expense Related to the Following Accounts 350
Land and Land Rights
Physical footprint required for
substations and transmission
facilities.
352
Structures and
Improvements
Houses essential transmission and
control equipment.
Control center housing, restoration facilities, AS control rooms, black-start interfaces
353
Station Equipment
Core equipment required to energize,
synchronize, and control the grid.
Synchronization, protection, voltage
stability, AS interfaces, regulation &
reactive delivery
354
Towers and Fixtures
Physical support of energized
transmission facilities.
Baseline transmission support, AS signal
routing, restoration paths
355
Poles and Fixtures
Physical support of energized
transmission facilities.
Baseline transmission support, AS signal
routing, restoration paths
356
Overhead Conductors
and Devices
Primary electrical pathways required
for synchronization.
Baseline connectivity, control, telemetry, AS signal paths
357
Underground Conduit
Primary electrical pathways required
for synchronization.
Baseline connectivity, control, telemetry, AS signal paths
358
Underground
Conductors and
Devices
Primary electrical pathways required
for synchronization.
Baseline connectivity, control, telemetry, AS signal paths
359
Roads and Trails
Allows access to the infrastructure in
the above accounts.
Supports the above-listed functions
2
3
4
5
6
7
8
9
10
11
12
PDF page 21
Exhibit No. PTO-0001Page 21 of 391
Table 2: FERC Accounts Identified as Supporting Grid Reliance Capabilities - O&M FERC
Account
Account
Description
Basis for Retention
Supported Grid Reliance
Charge Functions
(A)
(B)
(C)
(D)
Operation and Maintenance Expense From the Following Accounts
561
Load Dispatch
The cost of labor, materials, and expenses incurred in
directing the operation of the electric transmission system
and dispatching loads.
[O&M accounts support the
functions identified for the plant
accounts]
562
Station Expenses
Operation expense required to keep substations energized,
protected, and operational.
563
Overhead Line
Expenses
Operation necessary to maintain synchronized transmission
paths.
564
Underground Line
Expenses
Operation expense related to Primary electrical pathways
required for synchronization.
570
Maintenance of
Station Equipment
Maintenance of Core equipment required to energize,
synchronize, and control the grid.
571
Maintenance of
Overhead Lines
Maintenance of Primary electrical pathways required for
synchronization.
572
Maintenance of
Underground Lines
Maintenance of Primary electrical pathways required for
synchronization.
2
In the second step, for the identified transmission plant accounts and transmission 3
O&M accounts, FERC Form 1 data is used to calculate the percentage of Grid Reliance 4
Charge-related depreciation and O&M expenses by summing 100 percent of the expense 5
associated with each identified account and then dividing by the category total. FERC 6
accounts 561-564 and 570-572 are identified as Grid Reliance Charge-related O&M 7
accounts, and the amounts in those accounts will be summed and then divided by the total 8
Transmission O&M amount from the FERC Form 1 to derive the percentage of Grid 9
Reliance Charge-related O&M.23 FERC accounts 350-359 are identified as Grid Reliance 10
Charge-related plant accounts. These accounts constitute 100 percent of the transmission 11
23
Note that the O&M percentage calculations will include the removal of Account 565 – Transmission of Electricity by Others, consistent with the treatment of this account in Attachment H.
PDF page 22
Exhibit No. PTO-0001Page 22 of 39
depreciation category. Therefore, 100 percent is used as the appropriate percentage of 1
transmission depreciation to include in the calculation.
2
These percentages are developed exclusively from FERC Form 1 account-level 3
data. Account balances are either included in full or excluded in full. This ensures that the 4
percentage calculations are transparent, replicable, and based entirely on recorded 5
accounting data.
6
In the third step, the FERC Form 1-developed percentages are applied to the 7
transmission depreciation expense and transmission O&M expense reported in the 8
transmission owner’s annual TRR filing, Attachment H. The sum of the resulting Grid 9
Reliance Charge-related depreciation and O&M amounts constitutes the Grid Reliance 10
Charge revenue requirement. Note that only amounts directly related to the transmission 11
portions of depreciation and O&M are included in this calculation. Amortization and 12
general-plant depreciation are not included in the depreciation calculation. Likewise, 13
Administrative and General expenses are not included in the O&M calculation. 14
In the fourth step, the Grid Reliance Charge revenue requirement is divided by the 15
net revenue requirement from the transmission owner’s TRR, Attachment H to derive a 16
Grid Reliance Charge percentage of the net revenue requirement. This Grid Reliance 17
Charge percentage is calculated as described above for all PJM Transmission Owners. 18
Finally, the average of all the PJM Transmission Owners’ calculated Grid Reliance 19
Charge percentages is taken. This average Grid Reliance Charge percentage will be used 20
in the calculation of all the PJM Transmission Owners’ Grid Reliance Charge calculations 21
and employed in the following manner to derive the final Grid Reliance Charge rate. First, 22
the average Grid Reliance Charge percentage will be applied to a transmission owner’s 23
PDF page 23
Exhibit No. PTO-0001Page 23 of 39
NITS rate to determine the initial Grid Reliance Charge rate. Second, this initial Grid 1
Reliance Charge rate must be adjusted to account for the difference between the measure 2
of demand used to calculate the NITS rate (i.e., NITS customer load at zonal peak plus 3
contract demand for Firm Contract Demand Service) and the appropriate measure of 4
demand used to design the final Grid Reliance Charge rate.
5
The Grid Reliance Charge will apply to the difference between the customers’ gross 6
load and firm contract demand for Firm Contract Demand Service and Non-Firm Contract 7
Demand Service customers. Consequently, the appropriate measure of demand to use to 8
design the Grid Reliance Charge should include this additional load above Firm Contract 9
Demand. Therefore, the final step in the development of the Grid Reliance Charge rate is 10
to multiply the initial Grid Reliance Charge rate by a ratio equal to the demand used to 11
calculate NITS divided by the demand equal to that used to calculate NITS plus the 12
additional load above Firm Contract Demand. This will reduce the initial Grid Reliance 13
Charge rate and ensure that the Grid Reliance Charge does not over-recover from Firm 14
Contract Demand and Non-Firm Contract Demand Service customers.
15
In summary, the proposed methodology for the calculation of the Grid Reliance 16
Charge rate uses FERC Form 1 data to identify the relative share of depreciation and O&M 17
that supports grid reliance, translates that share to the Attachment H revenue-requirement 18
framework, and expresses it as a standardized percentage of the total transmission revenue 19
requirement. That percentage is then applied consistently across transmission owners to 20
develop the Grid Reliance Charge rate.
21
An exhibit that calculates the Grid Reliance Charge percentage for a single 22
transmission owner according to the methodology described above is provided as Exhibit 23
PDF page 24
Exhibit No. PTO-0001Page 24 of 39
No. PTO-0003. Furthermore, the exhibit provides the average Grid Reliance Charge 1
percentage for all PJM Transmission Owners, which will be applied to their respective 2
NITS rates in order to calculate their individual Grid Reliance Charges. The initial 3
percentage is 25.8 percent, subject to adjustment as discussed below.
4
Q.
Do the PJM Transmission Owners recommend that the Grid Reliance Charge be 5
updated and if so, how frequently?
6
A. [Schafer] Yes. The PJM Transmission Owners propose that the resulting average Grid 7
Reliance Charge percentage be updated approximately every five years. A five-year term 8
is reasonable for several reasons. Transmission depreciation rates and O&M structures 9
change gradually over time; they do not generally fluctuate greatly from year to year. A 10
multi-year period therefore avoids unnecessary annual recalculations while maintaining 11
alignment with underlying cost structures. In addition, leaving the percentage in place for 12
five years promotes rate stability, reduces administrative burden for both utilities and 13
regulators, and provides customers with predictable charges.
14
Q.
Why is the PJM Transmission Owners proposed Grid Reliance Charge methodology 15
just and reasonable?
16
[Schafer] The proposed Grid Reliance Charge methodology is just and reasonable for a 17
number of reasons. First, the Grid Reliance Charge is intentionally limited to depreciation 18
and O&M. Depreciation reflects the annualized consumption of the transmission 19
infrastructure that enables customers to rely on the grid, while O&M reflects the ongoing 20
expense required to keep that infrastructure functional. By excluding return on rate base 21
and associated income taxes, the methodology produces a conservative result focused on 22
cost recovery rather than investment return. This provides transparency, administrative 23
PDF page 25
Exhibit No. PTO-0001Page 25 of 39
simplicity, and stability. Second, it relies on publicly reported and audited accounting data 1
from those PJM Transmission Owners with formula rates that have reported O&M and 2
depreciation balances associated with assets in service. This covers the vast majority 3
(approximately 95 percent) of transmission facilities in PJM. Third, it avoids re-litigating 4
or recalculating each utility’s rate base, return, or tax components. Fourth, it eliminates the 5
need for company-specific engineering allocations. Fifth, by expressing the Grid Reliance 6
Charge as a percentage of the total transmission revenue requirement, it scales 7
proportionally with each utility’s size and cost structure. Finally, the Grid Reliance Charge- 8
percentage averaging component further promotes administrative efficiency and rate 9
stability. Individual transmission owners may exhibit modest year-to-year variations in 10
account structure or expense classification. Averaging the calculated Grid Reliance Charge 11
percentages across all PJM Transmission Owners smooths those variations, reduces 12
volatility, and produces a reasonable proxy for the portion of transmission costs attributable 13
to grid reliance on a regional basis.
14
Q.
How do the PJM Transmission Owners propose to treat the revenues received from 15
the Grid Reliance Charge?
16
A. [Schafer] Revenues from the Grid Reliance Charge will be applied as bill credits to 17
customers receiving service via NITS (including interim, non-firm transmission service) 18
and Firm Contract Demand Service, thereby reducing total transmission costs for these 19
customers. This will ensure that the Grid Reliance Charge does not result in a double 20
recovery for the PJM Transmission Owners or inappropriate cost shifts. The credit will be 21
applied to the bills of these customers in the zone where the Co-Located Load is physically 22
connected.
23
PDF page 26
Exhibit No. PTO-0001Page 26 of 39
VI. EXAMPLE OF RATE DESIGNS FOR NEW SERVICES
1
Q.
Above you described the rate designs for Firm Contract Demand Service, Non-Firm 2
Contract Demand Service, and interim, non-firm transmission service. Please provide 3
an example of how each of these services will be calculated.
4
A. [Blazunas] An example of the rate designs for each of these three services is provided as 5
Exhibit No. PTO-0004 and is described below.24
6
First, the transmission rate for Firm Contract Demand Service will be the same rate 7
as the rate for NITS and interim, non-firm transmission service. Practically speaking, the 8
calculation of the transmission rate for NITS, interim, non-firm transmission service, and 9
Firm Contract Demand Service, will be the same as the calculation for NITS currently 10
except that the divisor in the calculation of the rate will necessarily need to include, in 11
addition to the measure of the single coincident peak (“CP”) for NITS and interim, non- 12
firm transmission service customers, the firm contract demand associated with Firm 13
Contract Demand Service. Hence, the rate for NITS, Firm Contract Demand Service, and 14
interim, non-firm transmission service will be calculated using the net revenue requirement 15
from the PJM Transmission Owner’s Attachment H divided by the CP, taking into account 16
all NITS, interim, non-firm transmission service, and Firm Contract Demand Service 17
demand. Table 3 below shows an example calculation of the transmission rates for NITS, 18
interim, non-firm transmission service, and Firm Contract Demand Service: 19
20
21
24 The example calculates a maximum rate for Non-Firm Contract Demand Service although, as discussed above, this rate may be discounted, if appropriate.
PDF page 27
Exhibit No. PTO-0001Page 27 of 391
Table 3: Example Calculation of Transmission Rate for NITS, interim, non-firm transmission service, and Firm Contract Demand Service
Component
Source/Calculation
Amount
(a) Gross Revenue Requirement
$1,000,000,000
(b) Revenue Credits
($50,000,000)
(c) True-Up Adjustment
($50,000,000)
(d) Net Revenue Requirement
= (a) + (b) + (c)
$900,000,000
(e) 1 CP – NITS (MW/Year)
7,250
(f) 1 CP – interim, non-firm transmission service
(MW/Year)
500
(g) Firm Contract Demand – Firm Contract Demand
Service (MW/Year)
2,000
(h) Total MW/Year
= (e) + (f) + (g)
9,750
(i) Transmission Rate ($/MW/Year)
= (d) ÷ (h)
$92,308
2
As discussed above, the PJM Transmission Owners propose to calculate the Grid 3
Reliance Charge rate using a standardized, percentage-based methodology that relies on 4
publicly available FERC Form 1 data to determine the portion of transmission depreciation 5
and O&M expense associated with grid reliance capability, and then applies that portion 6
(expressed as a percentage) to each transmission owner’s calculated transmission rate for 7
NITS, interim, non-firm transmission service, and Firm Contract Demand Service. The 8
Grid Reliance Charge rate is also adjusted to account for the difference between the 9
measure of demand used to calculate the transmission rates for NITS, interim, non-firm 10
transmission service, and Firm Contract Demand Service, and the appropriate measure of 11
demand used to design the final Grid Reliance Charge rate. Table 4 below shows an 12
example of the calculation of the Grid Reliance Charge rate:
13
14
15
16
17
PDF page 28
Exhibit No. PTO-0001Page 28 of 391
Table 4: Example Calculation of the Grid Reliance Charge
Component
Source/Calculation
Amount
(i) Transmission Rate ($/MW/Year) – NITS,
interim, non-firm transmission service, and Firm
Contract Demand Service
Table 3, (i)
$92,308
(j) Grid Reliance Charge Percentage
25.8%
(k) Grid Reliance Charge ($/MW/Year)
(Unadjusted)
= (i) x (j)
$23,815
(l) Total MW/Year (Transmission Service)
Table 3, (h)
9,750
(m) Contract Demand Gross Load in Excess of
Firm Contract Demand (MW/Year)
522
(n) Total MW/Year (Transmission Service Plus
Contract Demand Gross Load in Excess of Firm
Contract Demand)
= (l) + (m)
10,272
(o) Ratio of Total MW/Year (Transmission
Service) to Total MW/Year (Transmission
Service Plus Contract Demand Gross Load in
Excess of Firm Contract Demand)
= (l) ÷ (n)
0.9492
(p) Grid Reliance Charge ($/MW/Year)
= (k) x (o)
$22,605
2
The revenues received from Firm Contract Demand Service and Non-Firm Contract 3
Demand Service customers will consequently be returned to NITS, interim, non-firm 4
transmission service, and Firm Contract Demand Service customers as bill credits on the 5
basis of the same billing determinants used to design the transmission rate for NITS, 6
interim, non-firm transmission service, and Firm Contract Demand Service, as shown in 7
Table 5 below:
8
9
10
11
12
13
14
PDF page 29
Exhibit No. PTO-0001Page 29 of 391
Table 5: Example Calculation of Bill Credits (Grid Reliance Charge) Component
Source/Calculation
Amount
(p) Grid Reliance Charge ($/MW/Year)
Table 4, (p)
$22,605
(q) Contract Demand (Firm Contract Demand
transmission service and Non-Firm Contract
Demand Service) Gross Load (MW/Year)
Table 3, (g) + Table 4, (m)
2,522
(r) Firm Contract Demand (MW/Year)
2,000
(s) Contract Demand Gross Load in Excess of
Firm Contract Demand (MW/Year)
= (q) – (r)
522
(t) Grid Reliance Charge Revenue
= (p) x (s)
$11,799,810
(u) Total MW/Year
Table 3, (h)
9,750
(v) Bill Credit ($/MW/Year)
= (t) ÷ (u)
($1,210)
2
The maximum rate for Non-Firm Contract Demand Service is calculated as the 3
same rate for NITS, interim, non-firm transmission service, and Firm Contract Demand 4
Service exclusive of the Grid Reliance Charge itself, as shown in Table 6 below. As 5
discussed above, the PJM Transmission Owners will consider whether a discount to the 6
Non-Firm Contract Demand Service is appropriate upon implementation: 7
8
Table 6: Example Calculation of Transmission Maximum Rate for Non-Firm Contract Demand Service Component
Source/Calculation
Amount
(w) Transmission Rate ($/MW/Year) – NITS,
interim, non-firm transmission service, and Firm
Contract Demand Service
Table 3, (i)
$92,308
(x) Grid Reliance Charge ($/MW/Year)
Table 4, (p)
$22,605
(y) Transmission Maximum Rate
($/MW/Year) – Non-Firm Contract Demand
Service
= (w) – (x)
$69,703
9
The revenues received from Non-Firm Contract Demand Service customers will 10
consequently be returned to NITS, interim, non-firm transmission service, and Firm 11
Contract Demand Service customers as bill credits on the basis of the same billing 12
PDF page 30
Exhibit No. PTO-0001Page 30 of 39
determinants used to design the transmission rate for NITS, interim, non-firm transmission 1
service, and Firm Contract Demand Service, as shown in Table 7 below:
2
3
Table 7: Example Calculation of Bill Credits (Non-Firm Contract Demand Service) Component
Source/Calculation
Amount
(y) Transmission Maximum Rate ($/MW/Year) –
Non-Firm Contract Demand Service
Table 6, (y)
$69,703
(z) Non-Firm Contract Demand (MW/Year)
275
(aa) Non-Firm Contract Demand Service
Revenue
= (y) x (z)
$19,168,325
(bb) Total MW/Year
Table 3, (h)
9,750
(cc) Bill Credit ($/MW/Year)
= (aa) ÷ (bb)
($1,966)
4
Based on the above, NITS, interim, non-firm transmission service, Firm Contract 5
Demand Service, and Non-Firm Contract Demand Service customers would pay rates for 6
transmission service as shown in Table 8 below:
7
8
Table 8: Example Rates for NITS, interim, non-firm transmission service, Firm Contract Demand Service, and Non-Firm Contract Demand Service
Component
Source/Calculation
Billing Determinant
Amount
(dd) NITS – Transmission Service
($/MW/Year)
Table 3, (i)
Per MW/Year (1CP)
$92,308
(ee) Grid Reliance Charge Bill
Credit ($/MW/Year)
Table 5, (v)
Per MW/Year (1CP)
($1,210)
(ff) Non-Firm Contract Demand
Service Bill Credit ($/MW/Year)
Table 7, (cc)
Per MW/Year (1CP)
($1,966)
(gg) NITS - Transmission Service
($/MW/Year) (Effective Rate)
= (dd) + (ee) + (ff)
Per MW/Year (1CP)
$89,132
(hh) interim, non-firm transmission
service – Transmission Service
($/MW/Year)
Table 3, (i)
Per MW/Year (1CP)
$92,308
(ii) Grid Reliance Charge Bill
Credit ($/MW/Year)
Table 5, (v)
Per MW/Year (1CP)
($1,210)
(jj) Non-Firm Contract Demand
Service Bill Credit ($/MW/Year)
Table 7, (cc)
Per MW/Year (1CP)
($1,966)
(kk) interim, non-firm
transmission service –
Transmission Service
($/MW/Year) (Effective Rate)
= (hh) + (ii) + (jj)
Per MW/Year (1CP)
$89,132
PDF page 31
Exhibit No. PTO-0001Page 31 of 39
(ll) Firm Contract Demand Service
– Transmission Service
($/MW/Year)
Table 3, (i)
Per MW/Year (Firm
Contract Demand)
$92,308
(mm) Grid Reliance Charge Bill
Credit ($/MW/Year)
Table 5, (v)
Per MW/Year (Firm
Contract Demand)
($1,210)
(nn) Non-Firm Contract Demand
Service Bill Credit ($/MW/Year)
Table 7, (cc)
Per MW/Year (Firm
Contract Demand)
($1,966)
(pp) Firm Contract Demand
transmission service –
Transmission Service
($/MW/Year) (Effective Rate)
= (ll) + (mm) + (nn)
Per MW/Year (Firm
Contract Demand)
$89,132
(oo) Firm Contract Demand Service
– Grid Reliance Charge
($/MW/Year)
Table 4, (p)
Per MW/Year (Gross Load
in Excess of Firm Contract
Demand)
$22,605
(pp) Non-Firm Contract Demand
Service – Transmission Service
($/MW/Year)25
Table 6, (y)
MW/Year (Non-Firm
Contract Demand)
$69,703
(qq) Non-Firm Contract Demand
Service – Grid Reliance Charge
($/MW/Year)
Table 4, (p)
Per MW/Year (Gross Load
in Excess of Firm Contract
Demand)
$22,605
1
As demonstrated above, based on the proposed rate designs, customers taking NITS, 2
interim, non-firm transmission service, and Firm Contract Demand Service pay the same effective 3
base rates for transmission service. Firm Contract Demand Service customers only pay the Grid 4
Reliance Charge on their gross load in excess of their firm contract demand. 5
VII. PENALTY CHARGE
6
Q.
Are the PJM Transmission Owners proposing new penalty charges?
7
A. [Hammer] No, not at this time. I understand that PJM intends to propose operational 8
penalties, and I agree the imposition of such penalties is appropriate. The PJM 9
Transmission Owners believe that any penalty regime should rely on both operational 10
consequences as well as complementary financial penalties. The PJM Transmission 11
Owners understand that, at a high level, PJM’s proposal would be to refer to FERC 12
enforcement or applicable reliability organizations any failure to comply with PJM 13
25 Consistent with the Order, Non-Firm Contract Demand Service would be available for terms from one hour to one month, and rates for these terms would be calculated based on the annual rate. Id. at P 215.
PDF page 32
Exhibit No. PTO-0001Page 32 of 39
operating instructions. In addition, PJM is proposing a “Two Strike, You’re NITS” 1
approach pursuant to which if a customer’s protective systems fail to operate as required, 2
PJM would first determine whether to impose a 120-day “pause” in service and, with the 3
second failure, PJM would terminate the customer’s service under contract demand and the 4
customer would be required to become a NITS customer if it wished to resume service. 5
The PJM Transmission Owners believe this proposal is a good starting point conceptually 6
but recognize that additional details will need to be developed as to how these operational 7
consequences would be applied.
8
I believe that a financial penalty structure is appropriate to complement and 9
supplement operational penalties implemented by PJM. Although operational penalties 10
will likely serve as the primary deterrent against Co-Located Load customers exceeding 11
their reserved use, financial penalties could still play a valuable role in enhancing this 12
deterrent as well as ensuring the market and other ratepayers are made whole if a Co- 13
Located Load customer exceeds its contract demand. In addition, it may also be appropriate 14
to impose financial penalties when a Co-Located Load customer exceeds its contract 15
demand even if such exceedances are mitigated by an SPS or RAS installed on the 16
Transmission Owner side of the point of interconnection. The PJM Transmission Owners 17
intend to work with PJM in continuing to explore penalty options and will, if appropriate, 18
offer a proposal at a subsequent stage of this paper hearing process.
19
20
21
22
23
PDF page 33
Exhibit No. PTO-0001Page 33 of 39
VIII. INTERCONNECTION REQUIREMENTS AND OPERATIONAL PRACTICES
1
Q.
What are NERC’s transmission planning standards and why is transmission owner 2
and transmission provider compliance with those standards important?
3
A. [Hammer] The North American Electric Reliability Corporation’s (“NERC”) 4
Transmission Planning (“TPL”) standards establish mandatory planning requirements to 5
ensure the Bulk Electric System can reliably withstand credible contingencies over 6
planning horizons. TPL-001 Transmission System Planning Performance Requirements is 7
the foundational and currently enforceable transmission planning standard. Its purpose is 8
to ensure that the Bulk Electric System is planned so it will operate reliably across a broad 9
range of system conditions and contingencies, from normal conditions to extreme events. 10
Compliance with the NERC TPL-001 requirements is important because they
11
ensure the transmission system is planned to reliably withstand credible outages and system 12
stresses, reducing the risk of cascading failures and large-scale blackouts. For transmission 13
owners and providers, TPL-001 compliance also minimizes regulatory and financial risk, 14
supports coordinated regional planning, and provides a defensible technical basis for 15
transmission investments needed to maintain long-term grid reliability.
16
Q.
Does the Order’s proposal to rely on SPS/RAS to accommodate Co-Located Load 17
transmission service requests present any reliability or planning concerns? 18
A. [Hammer] Yes. Under the principle of TPL-001, transmission planners must plan for load 19
that has the ability to draw power from the transmission system, not merely for load that is 20
expected or intended to do so under normal operating conditions. Reliance on SPS/RAS as 21
a substitute for timely network upgrades raises significant concerns under established good 22
utility practices and applicable NERC reliability standards. SPS/RAS are generally 23
PDF page 34
Exhibit No. PTO-0001Page 34 of 39
intended as supplemental or last-resort reliability measures, not a primary tool to 1
accommodate incremental transmission services on a routine or ongoing basis. In 2
particular, substituting SPS/RAS for network upgrade identification, design, coordination, 3
testing, and commissioning risks undermining the transparency and predictability of the 4
transmission planning process. Transmission Owners must ensure that all applicable 5
performance requirements under NERC Standard TPL‑001 remain satisfied, including 6
under stressed system conditions and under reasonable worst‑case assumptions such as 7
SPS/RAS failure, mis-operation, or unavailability.
8
Accordingly, any planning assumptions that rely on SPS/RAS must demonstrate 9
acceptable system performance both with and without successful SPS/RAS operation. 10
Absent such demonstrations, reliance on SPS/RAS to accommodate Co‑Located Load 11
transmission service requests could defer necessary upgrades, increase operational risk, 12
and impede prudent transmission planning and reliable operation of the Bulk Electric 13
System.
14
Q.
Are there any other grid challenges associated with utilizing SPS/RAS to ensure 15
reliability in connection with Co-Located Load taking contract demand transmission 16
service?
17
A. [Hammer] Yes. SPS/RAS are operational tools rather than transmission facilities. While 18
they can be effective when properly designed and operated, they introduce dependencies 19
related to system protection performance, communications, and coordination during 20
stressed system conditions. Individual SPS/RAS-backed Firm Contract Demand Service 21
requests may appear manageable in isolation; however, the cumulative impact of multiple 22
large Firm Contract Demand Service loads relying on SPS/RAS – particularly within the 23
PDF page 35
Exhibit No. PTO-0001Page 35 of 39
same transmission constrained area – may present risks that are not fully reflected in 1
existing planning models.
2
There is also a broader planning precedent concern. If major reliability drivers 3
identified in planning are routinely mitigated through SPS/RAS in lieu of network 4
upgrades, clarification is needed regarding the boundaries of this approach. Specifically, 5
stakeholders should understand when infrastructure investment becomes necessary 6
regardless of a customer’s willingness to curtail, particularly as load magnitude, geographic 7
concentration, and/or system stress increases.
8
Q.
Given these grid challenges, what steps can PJM and the PJM Transmission Owners 9
take to ensure grid reliability while relying on SPS/RAS to provide contract demand 10
transmission service?
11
A. [Hammer] To ensure that any reliance on SPS/RAS remains consistent with transmission 12
planning practices and applicable reliability standards, the Commission should permit PJM 13
and the PJM Transmission Owners to implement necessary guardrails in several areas, 14
including:
15
Clearly defined eligibility criteria for Firm Contract Demand Service supported by 16
SPS/RAS;
17
Full redundancy of SPS/RAS, which could include permitting PJM Transmission 18
Owners to require the implementation of SPS or RAS on the Transmission Owner’s 19
side of the point of interconnection;
20
Established reasonable limits on the size, aggregation, and geographic concentration of 21
the use of SPS/RAS;
22
PDF page 36
Exhibit No. PTO-0001Page 36 of 39
Defined thresholds under which network upgrades are required notwithstanding the 1
availability of operational curtailment; and
2
Appropriate rules as to how SPS/RAS supported contract demand service is evaluated 3
in PJM’s transmission planning study and PJM Transmission Owners’ interconnection 4
facilities studies.
5
Implementation of contract demand transmission services must preserve the integrity of 6
the transmission planning process and continued compliance with NERC reliability 7
standards. From the transmission owners’ perspective, the central implementation issue is 8
how reliance on SPS/RAS is appropriately bounded, monitored, and integrated into 9
planning and study analyses to ensure that firm transmission service obligations do not 10
increasingly depend on operational controls in lieu of durable network infrastructure 11
solutions.
12
Q.
Please explain the above-mentioned “full redundancy of SPS/RAS” in more detail. 13
A. [Hammer] In this context, “full redundancy of SPS/RAS” refers to a layered protection 14
framework under which reliability risks associated with Co‑Located Load taking the new 15
contract demand transmission services are addressed through both primary, 16
customer‑owned protection and an optional, transmission‑owner‑owned backstop, rather 17
than reliance on a single protection scheme.
18
Under this framework, the primary responsibility for limiting withdrawals from the 19
transmission system remains with the interconnection customer or Co‑Located Load, 20
typically through customer-owned SPS/RAS that are designed, operated, and maintained 21
in accordance with applicable NERC standards and reviewed by PJM. To help accomplish 22
this, the Commission should direct NERC to establish requirements that Co-Located Load 23
PDF page 37
Exhibit No. PTO-0001Page 37 of 39
Customers register with NERC so that those customers may be responsible for meeting 1
NERC’s reliability standards. These customer‑owned schemes serve as the first line of 2
defense and are expected to operate under normal and reasonably foreseeable contingency 3
conditions.
4
“Full redundancy” does not mean duplicative or parallel protection for every 5
contingency, nor does it imply that transmission owners must install SPS/RAS in all cases. 6
Rather, it means that, where system studies identify elevated reliability risk, transmission 7
owners should have the option to implement a transmission-owner-owned SPS/RAS as a 8
secondary backstop to protect the Bulk Electric System in the event of customer‑owned 9
scheme failure, mis-operation, or unavailability.
10
Q.
How does this concept of redundancy align with NERC reliability standards, 11
including PRC-012?
12
A. [Hammer] This approach is fully consistent with NERC Reliability Standard PRC‑012, 13
which expressly contemplates that SPS/RAS may be owned by Transmission Owners, 14
Generator Owners, or Distribution Providers, provided that ownership and accountability 15
are clearly defined. Importantly, PRC‑012 does not prohibit multiple SPS/RAS acting on 16
the same system condition, nor does it require exclusive reliance on a single owner’s 17
protection scheme. Allowing a Transmission Owner to own and operate a backstop 18
SPS/RAS therefore fits within the PRC‑012 framework.
19
Q.
Why is reliance on a single, customer‑owned SPS/RAS insufficient in some cases? 20
A. [Hammer] Transmission planning and operating standards, including TPL‑001, require 21
planners to account for credible contingencies and protection system failures, including 22
single points of failure and mis-operations. In configurations where Co‑Located Load 23
PDF page 38
Exhibit No. PTO-0001Page 38 of 39
depends on SPS/RAS to limit transmission system withdrawals, exclusive reliance on a 1
single, customer‑controlled protection scheme can introduce reliability risk, particularly if 2
the equipment is unavailable due to outage or maintenance. In high‑impact scenarios, 3
failure of the primary SPS/RAS could result in unexpected load appearing on the 4
transmission system, potentially leading to overloads, stability concerns, or emergency 5
operating actions. A transmission-owner‑owned backstop SPS/RAS provides an additional 6
layer of assurance that these risks can be mitigated before they affect other transmission 7
customers or system reliability.
8
Q.
Does “full redundancy” shift responsibility or cost from customers to Transmission 9
Owners?
10
A. [Hammer] No. The concept of full redundancy does not shift responsibility away from 11
customers. The presence of a transmission-owner‑owned backstop does not relieve 12
customers of compliance obligations, nor does it entitle customers to rely on transmission- 13
owner‑owned protection in lieu of their own facilities.
14
Q.
Why is the ability to selectively curtail load essential to the contract demand 15
transmission service framework adopted by the Commission, and how is that 16
capability implemented in practice at the point of interconnection?
17
A. [Hammer] The Commission directed PJM to create contract demand transmission service 18
to reflect loads that are willing and able to limit their withdrawals from the transmission 19
system. Load taking contract demand transmission service is granted access to the 20
transmission system without corresponding reliability reinforcements to support the full 21
gross load, therefore, the reliability condition is curtailment.
22
PDF page 39
Exhibit No. PTO-0001Page 39 of 39
Under certain system conditions, PJM and the PJM Transmission Owners have the 1
authority to shed the non‑firm portion of load, either preemptively or immediately 2
following a contingency. For example, PJM may arm a SPS/RAS to instantaneously drop 3
a large block of load upon the trip of the on-site generator, thereby preventing a thermal or 4
stability overload.
5
Where a point of interconnection serves both firm and non‑firm contract demand, 6
the interconnection must be designed to allow selective curtailment. Operationally, this 7
typically requires that firm and non‑firm load be served through separate breakers, feeders, 8
or other independently controllable facilities. The Transmission Owner may structure the 9
interconnection so that the non‑firm portion can be shed without interrupting firm service. 10
Examples could include:
11
Separate feeder lines or breakers dedicated to firm versus non‑firm load; 12
Partial load‑shedding schemes that trip only designated non‑firm MW; or
13
For large facilities such as data centers, multiple transformer banks, with some 14
designated as “firm service” and others as “non‑firm service,” allowing independent 15
tripping.
16
Critically, the ability to distinguish and shed the non‑firm portion of load 17
independently is a prerequisite for a contract demand service model. Curtailment cannot 18
be all‑or‑nothing; the firm portion of load is expected to remain in service except under 19
last‑resort system conditions. As a result, compliance may require the installation of special 20
protection or control equipment at the substation or within the customer’s facilities. 21
Q.
Does this complete your testimony at this time?
22
A. [Blazunas, Schafer, and Hammer] Yes.
23
PDF page 40
UNITED STATES OF AMERICA
BETORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
Docket No. EL25-49-000
Docket No. EL25-49-001
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection. L.L.C.
Docket No. AD24-11-000
Docket No. EL25-20-000
(Consolidated)
DECLARATION OF PETER BLAZUNAS
I depose and state under penalty of perjury that the foregoing exhibits were prepared or assembled by me or under my direction, and that I have read the foregoing questions and answers labeled as my testimony: that if asked the same questions my answ'ers in response would be as shown; and that the facts contained in my answers are true to the best of my knowledge, information, and belief.
F
)
)
)
)
)
)
)
)
PDF page 41
[No extractable text on this page.]
PDF page 42
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities
)
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
DECLARATION OF HANHAN HAMMER
I depose and state under penalty of perjury that the foregoing exhibits were prepared or assembled by me or under my direction, and that I have read the foregoing questions and answers labeled as my testimony: that if asked the same questions my answers in response would be as shown; and that the facts contained in my answers are true to the best of my knowledge, information, and belief.