Exhibit No. PTO-0001 - Direct Joint Testimony of Blazunas, Shafer, & Hammer
Text extracted from the eLibrary original (SHA-256 0f308db2d97c18c5…). Download the original from the official source.
Contents · 11 sections
- I. INTRODUCTION
- II. BACKGROUND
- III. PURPOSE OF TESTIMONY
- IV. NEW TRANSMISSION SERVICE CATEGORIES AND RATE DESIGNS
- A. Firm Contract Demand Transmission Service
- B. Non-Firm Contract Demand Transmission Service
- C. Interim, Non-Firm Transmission Service
- V. GRID RELIANCE CHARGE
- VI. EXAMPLE OF RATE DESIGNS FOR NEW SERVICES
- VII. PENALTY CHARGE
- VIII. INTERCONNECTION REQUIREMENTS AND OPERATIONAL PRACTICES
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword. Pages with no text layer: 41.
Opening text
opening text
PTO-0001 Page 1 of 39 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C., et al. ) Docket No.Read this passage
I. INTRODUCTION
printed heading · Topic match: Cost allocation
I am a Senior Project Manager with Concentric. 12 In my current role, I advise regulators, utilities, grid operators, and developers on complex 13 regulatory and market issues, including wholesale market participation, compliance with 14 FERC directives, transmission planning and cost allocation,…Read this passage Filed comments: Cost allocation
II. BACKGROUND
printed heading · Topic match: Connecting load and generation
What is the background for this proceeding? 2 A. [Blazunas, Schafer, and Hammer] On December 18, 2025, the Commission issued its 3 order in PJM Interconnection.Read this passage Filed comments: Connecting load and generation
III. PURPOSE OF TESTIMONY
printed heading
These proposals have not yet been submitted to the TOAAC for approval. 4 For purposes of this testimony and the accompanying responses to the Commission’s paper hearing questions, the PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian…Read this passage
IV. NEW TRANSMISSION SERVICE CATEGORIES AND RATE DESIGNS
printed heading
NEW TRANSMISSION SERVICE CATEGORIES AND RATE DESIGNS 1Read this passage
A. Firm Contract Demand Transmission Service
printed heading · Topic match: Connecting load and generation
What is Firm Contract Demand transmission service? 3 A. [Blazunas] Pursuant to the Order, under the new Firm Contract Demand transmission 4 service (“Firm Contract Demand Service”), Eligible Customers will have the right to 5 request transmission service on behalf of a Co-Located Load up to a…Read this passage Filed comments: Connecting load and generation
B. Non-Firm Contract Demand Transmission Service
printed heading · Topic match: Connecting load and generation
See Order No. 888 at 31,780. 17 Schedules 7 and 8 of the PJM Tariff state: [t]hree principal requirements apply to discounts for transmission service as follows: (1) any offer of a discount made by the Transmission Provider must be announced to all Eligible Customers solely by posting on the OASIS,…Read this passage Filed comments: Connecting load and generation
C. Interim, Non-Firm Transmission Service
printed heading · Topic match: Connecting load and generation
What is interim, non-firm transmission service? 19 A. [Blazunas] Under the Order, interim, non-firm transmission service, also sometimes 20 referred to as “Interim NITS,” allows an Eligible Customer that has requested NITS on 21 behalf of a Co-Located Load to take non-firm transmission service that…Read this passage Filed comments: Connecting load and generation
V. GRID RELIANCE CHARGE
printed heading · Topic match: Connecting load and generation
Second, this initial Grid 1 Reliance Charge rate must be adjusted to account for the difference between the measure 2 of demand used to calculate the NITS rate (i.e., NITS customer load at zonal peak plus 3 contract demand for Firm Contract Demand Service) and the appropriate measure of 4 demand…Read this passage Filed comments: Connecting load and generation
VI. EXAMPLE OF RATE DESIGNS FOR NEW SERVICES
printed heading
Above you described the rate designs for Firm Contract Demand Service, Non-Firm 2 Contract Demand Service, and interim, non-firm transmission service.Read this passage
VII. PENALTY CHARGE
printed heading · Topic match: Connecting load and generation
Although operational penalties 10 will likely serve as the primary deterrent against Co-Located Load customers exceeding 11 their reserved use, financial penalties could still play a valuable role in enhancing this 12 deterrent as well as ensuring the market and other ratepayers are made whole if a…Read this passage Filed comments: Connecting load and generation
VIII. INTERCONNECTION REQUIREMENTS AND OPERATIONAL PRACTICES
printed heading · Topic match: Reliability and curtailment
Does the Order’s proposal to rely on SPS/RAS to accommodate Co-Located Load 17 transmission service requests present any reliability or planning concerns? 18 A. [Hammer] Yes.Read this passage Filed comments: Reliability and curtailment