Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper Hearing Questions
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
)
Docket No. EL25-49-001
)
Large Loads Co-Located at Generating Facilities )
Docket No. AD24-11-000
)
Constellation Energy Generation, LLC
)
Docket No. EL25-20-000
v.
)
PJM Interconnection, L.L.C.
)
(Consolidated)
INITIAL BRIEF AND JOINT RESPONSES
OF THE INDICATED PJM TRANSMISSION OWNERS
TO
PAPER HEARING QUESTIONS
Pursuant to the Commission’s December 18, 2025 order in PJM Interconnection, L.L.C.,
193 FERC ¶ 61,217, at P 193 (2025) (“Order”), the Indicated PJM Transmission Owners
(collectively the “PJM Transmission Owners”)1 submit this initial brief and joint responses to the paper hearing questions that the Commission presented in the Order. These paper hearing questions involve the rates, terms and conditions of service for the new transmission services that
1 For the purpose of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service Corporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, AEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company (“PECO”), and Potomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas Company (“PSE&G”); Rockland Electric Company; and the Southern Maryland Electric Cooperative (“SMECO”).
PDF page 2
2
the Commission directed to be added to the PJM Open Access Transmission Tariff (“Tariff”) for Eligible Customers2 serving co-located load in PJM.
I. INTRODUCTION
In the Order, the Commission found that PJM’s Tariff “is unjust and unreasonable because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to generators serving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-Located Load.”3 Specifically, the Commission found PJM’s Tariff “unjust and unreasonable because it does not include types of transmission service that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing and able to limit their use of the transmission system under certain conditions.”4
The Commission ordered PJM to offer three new forms of transmission service under its Tariff: (i) Firm Contract Demand transmission service; (ii) Non-Firm Contract Demand transmission service and (iii) interim, non-firm transmission service.5 The Commission also established a paper hearing to determine the just and reasonable rates, terms, and conditions for these new transmission services.6
The PJM Transmission Owners are submitting joint responses to the paper hearing questions in this initial round of briefing because, pursuant to the Consolidated Transmission
2 All capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Tariff or Amended and Restated Operating Agreement of PJM Interconnection, L.L.C.3 Order at P 2. The Commission defines Co-Located Load as a “configuration [that] refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection to the PJM Transmission System.” Id. at P 164.4 Id. at P 2.5 Id. at P 160.6 Id. at PP 2, 194.
PDF page 3
3
Owners Agreement (“CTOA”), between the PJM Transmission Owners and PJM, the PJM
Transmission Owners have the rights and obligation to develop and file the rates for these new services.7 As the Commission has recognized, the PJM Transmission Owners have exclusive
and unilateral rights regarding regional rates and rate design under the PJM Tariff and the cost allocation provisions of Schedule 12 of the PJM Tariff.8 Accordingly, these responses are required consistent with the CTOA and related precedent.9
The Commission’s review of the proposed rates and terms for the new services required
in the Order should be primarily guided by two principles: (1) rates for the new services must be consistent with longstanding cost allocation principles, and (2) the new services must be implemented in a manner that does not compromise system reliability.10 In the context of the
7 See Pa.-N.J.-Md. Interconnection, 105 FERC ¶ 61,294 (2003), order on compliance, 108 FERC ¶ 61,033 (2004) (approving Settlement Agreement, Docket No. OA97-261-006 et al. (filed Oct. 3, 2003), as modified, Modification of Settlement Agreement, Docket No. OA97-261-009 et al., §§ 3.2, 4.2(B); 4.3, 4.5 (filed Jan. 20, 2004 and corrected Jan. 23, 2004)). The Settlement Agreement is incorporated into PJM OATT, § 9 and the CTOA at § 7.3.1, PJM Interconnection, L.L.C., Rate Schedules, TOA, TOA-42 Rate Schedule FERC No. 42 (1.0.0). Moreover, the PJM Transmission Owners have contractual rights and obligations to engage in coordination and consultation with PJM and the PJM Members Committee with respect to changes to other terms and conditions of the PJM OATT. See CTOA, at § 7.5.1. The PJM Transmission Owners are submitting joint responses to the paper hearing questions and expressing views herein in light of the current status of the proceeding and reserve all rights, including the right to revise or supplement these responses. With respect to Exelon and FirstEnergy, nothing herein waives or limits any arguments made on rehearing or appeal by Exelon or FirstEnergy.8 See, e.g., Neptune Reg’l Transmission Sys., LLC v. PJM Interconnection, L.L.C., 175 FERC ¶ 61,247, at P 47 (2021); PPL Elec. Utils. Corp., 177 FERC ¶ 61,123, at PP 34 and 36 (2021). See also Am. Mun. Power, Inc. v. FERC, 86 F.4th 922, 927 (D.C. Cir. 2023) (“PJM’s authority to oversee and operate the electrical grid is limited to that granted to it by transmission owners in the Owners Agreement.”).9 The PJM Transmission Owners have developed the rate design proposals reflected in these responses through the Section 205 Working Group, established under the authority of the Transmission Owner Agreement Administrative Committee (“TOAAC”). See CTOA § 8.1. These proposals have not yet been submitted to the TOAAC for approval.10 See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Policy Study Grp., v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002); Preventing Undue Discrimination & Preference in Transmission Serv., Order No. 890, 118 FERC ¶ 61,119, order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh’g, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009); Transmission Plan. & Cost Allocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051 (2011), order on
PDF page 4
4
new services designed to accommodate Co-Located Load arrangements, these principles
manifest as follows. First, the rates and terms for the new transmission services must ensure that Co-Located Load customers11 pay their appropriate share of transmission system costs, including those related to the benefits of being connected and synchronized with the extensive PJM Transmission System, which reliably serves 67 million customers. Absent this sharing, existing ratepayers, including network customers, will be forced to unfairly subsidize Co-Located Load customers, a result that would be unjust, unreasonable, unduly discriminatory, or preferential.12 Second, the new transmission services required in the Order must be subject to
appropriate terms and conditions to ensure that the implementation of these new services does not compromise system reliability. Co-Located Loads, as well as any on-site generators used to serve those loads, are not islanded. They are fully connected and synchronized with the transmission system, like all other loads and generators. As such, the full amounts of on-site load and generation have the ability to impact the system. Because PJM proposes that it will not identify network upgrades to accommodate transmission service requests for Co-Located Load beyond those amounts that an Eligible Customer designates for Network Integration
Transmission Service (“NITS”) or Firm Contract Demand Service, the continued reliability of the system will necessarily depend on the utilization of protection schemes. Thus, these protection schemes must be subject to comprehensive and rigorous testing and inspection, reh’g, Order No. 1000-A, 139 FERC ¶ 61,132, order on reh’g & clarification, Order No. 1000-B, 141 FERC ¶ 61,044 (2012), aff’d sub. nom. S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. 2014); Bldg. for the Future Through Elec. Reg’l Transmission Planning & Cost Allocation, Order No. 1920, 89 FR 49280 (June 11, 2024), 187 FERC ¶ 61,068, order on reh’g, Order No. 1920-A, 89 FR 97174 (Dec. 6, 2024), 189 FERC ¶ 61,126 (2024), order on reh’g, Order No. 1920-B, 191 FERC ¶ 61,026 (2025); see also 16 U.S.C. § 824o(b).
11 All references to Co-Located Load customers throughout should be read to mean an Eligible Customer taking service under the PJM Tariff on behalf of one or more co-located loads.12 See 16 U.S.C. §§ 824d, 824e (requiring that all rates subject to the Commission’s jurisdiction be just and reasonable, and prohibiting rates that are unjust, unreasonable, unduly discriminatory or preferential).
PDF page 5
5
including well-designed implementation and operational requirements to protect the PJM Transmission System and the network customers that rely on that system from unacceptable reliability risk.
Guided by these principles and as detailed below and in the testimony supporting these responses, the PJM Transmission Owners have developed rate design proposals in response to the Order for the three new transmission services required in the Order.13 The PJM Transmission Owners also have developed rate design proposals for a new Grid Reliance Charge related to the new services. Whereas PJM has responsibility for proposing tariff terms and conditions, as the owners of the PJM Transmission System, the PJM Transmission Owners have a significant interest in certain planning and operational issues relating to Eligible Customers that choose to take one or more of these new services. Accordingly, the PJM Transmission Owners offer their suggestions for appropriate practices and requirements relating to the protection schemes that will be necessary to ensure ongoing system reliability.1413 Although the Commission’s paper hearing questions do not address rates for the interim, non-firm transmission service, consistent with the Order, the PJM Transmission Owners propose to apply the NITS rate to Eligible Customers taking interim, non-firm transmission service. See Prepared Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer, Exhibit No. PTO-0001 at Section IV.C. (“Blazunas, Schafer, and Hammer Direct Joint Testimony”). See also Order at P 200 (“Eligible Customers taking this interim, non-firm transmission service on behalf of Co-Located Loads would pay the NITS rate for the new service . . . .”).14 Because the primary purpose of this initial response is to set out the PJM Transmission Owners’ rate design proposals, the PJM Transmission Owners reserve their rights to supplement their responses in subsequent briefing rounds, particularly as it relates to the questions that do not directly relate to rate design issues.
PDF page 6
6
II. RESPONSES TO PAPER HEARING QUESTIONS
1. What are the appropriate rates, terms, and conditions for the new Firm Contract Demand transmission service, including whether it would be just and reasonable to apply the current zonal firm PTPS charges to this new service and whether it would be just and reasonable and consistent with cost causation to include charges for any of PJM’s administrative services?
The PJM Transmission Owners propose that the rate for Firm Contract Demand Service be based on the zonal NITS rates and the underlying NITS revenue requirements. Under this approach, Eligible Customers taking Firm Contract Demand Service will pay the same base charge per megawatt (“MW”) as NITS customers, except that unlike NITS customers their demand will be their specified firm contract demand equal to the firm contract demand amount (in MWs) multiplied by a single zonal rate for both NITS and Firm Contract Demand Service customers. Eligible Customers taking Firm Contract Demand Service will also pay a Grid Reliance Charge for their remaining on-site load, which is not covered by Firm Contract Demand Service. The design of the Grid Reliance Charge is discussed in response to Question 3 below. Additional details regarding the PJM Transmission Owners’ proposal for calculating Firm Contract Demand Service rates are set forth in the accompanying Direct Joint Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer of Concentric Energy Advisors, Inc.15 As explained therein, in Zones with formula transmission rates, the single annual rate applicable to both NITS and Firm Contract Demand Service rates will be established in the same basic manner as NITS rates are today.16 This rate will be calculated based on each transmission owner’s annual net revenue requirement, as determined pursuant to the formula rates contained in
15 Blazunas, Schafer, and Hammer Direct Joint Testimony at Section IV.A.16 Id. at 6. A handful of PJM transmission owners continue to utilize stated rates, which in some cases are based on black-box settlements and may need to be accounted for in specific stated rates for the new firm and non- firm contract demand services.
PDF page 7
7
Attachment H to the PJM Tariff. That annual net revenue requirement will then be divided by the single coincident peak load, which will include both NITS customer load (including interim non-firm transmission service customers) and the total contract demand for all Firm Contract Demand Service customers.17 This will result in a single $/MW-year rate that will apply to both NITS and Firm Contract Demand Service customers. A simple example of this rate calculation is set forth below, with a more detailed example contained in the Blazunas, Schafer, and Hammer Direct Joint Testimony.18
Example 1 – Firm Contract Demand Service Rate Calculation
Transmission Owner “ABC”
1 ABC Net Revenue Requirement – $5,000,000
2 ABC NITS Customer Coincident Peak Demand – 400 MW
3 ABC Firm Contract Demand Service Customer Demand – 100 MW
4 ABC Total Demand – 500 MW
5 ABC NITS and Firm Contract Demand Service Rate [Line 1 / Line 4] =
$10,000/MW/Year
As discussed in further detail below, both NITS and Firm Contract Demand Service customers will receive bill credits for revenues associated with the Grid Reliance Charge as well as revenues from Non-Firm Contract Demand Service customers, based on their share of the coincident peak load, to ensure that there is no double-recovery of any revenue requirement amounts. The procedures for establishing zonal NITS/Firm Contract Demand Service rates and updating the underlying annual revenue requirements will remain unchanged, and Firm Contract Demand Service customers will be treated the same as NITS customers under each PJM Transmission Owner’s formula rate protocols.
17 Id. at 6.18 Blazunas, Schafer, and Hammer Direct Joint Testimony at Exhibit No. PTO-0004.
PDF page 8
8
The PJM Transmission Owners are proposing to charge the same rate for Firm Contract Demand Service and NITS because the level of service provided to both customers is, for all relevant purposes, the same. Both NITS and Firm Contract Demand Service are firm services for which network upgrades will be planned and constructed as necessary, with the only difference being that upgrades for NITS customers are identified based on existing and anticipated load growth while upgrades for Firm Contract Demand Service customers will be identified based on their contracted demand level. Firm Contract Demand Service customers will be able to serve their contracted demand through capacity procured by PJM just like NITS customers and will not be required to designate specific points of receipt and delivery. There is no need or benefit to developing a separate Firm Contract Demand Service rate or utilizing the existing Firm Point-to-Point Service (“PTPS”) rates.19 Firm PTPS rates are generally based on the same revenue requirement as the NITS rate, and the nature of Firm Contract Demand Service, as contemplated in the Order, is essentially a variation of NITS with a specified contract demand level. Consequently, PJM will need to treat and plan for Firm Contract Demand Service load in the same manner that it plans for load using NITS, thus providing service to the Firm Contract Demand Service load on a comparable basis with NITS load. Because NITS and Firm Contract Demand customers receive comparable benefits, using the same rate for NITS and Firm Contract Demand Service is consistent with the Commission’s cost allocation principles, particularly the requirement that transmission customers be allocated costs roughly commensurate with the estimated benefits they receive.20 On the other hand, it would be unjust and unreasonable and unduly discriminatory to charge Firm Contract Demand
19 Id. at 7-8.20 See, e.g., Order No. 1000 at P 622.
PDF page 9
9
Service customers a rate that is lower than one based on the NITS rate, as doing so would subsidize Firm Contract Demand Service customers at the expense of NITS customers.21 Moreover, in PJM, PTPS is only utilized for purposes of service at the PJM border. That will not be the case for Co-Located Load customers taking Firm Contract Demand Service to serve their contract demand within PJM.
Basing the rate for Firm Contract Demand Service on the NITS rate also has the advantage of minimizing changes to current PJM billing and settlements practices. As for NITS today, the PJM Transmission Owners anticipate that PJM will perform the billing function for transmission, capacity, and energy charges for customers taking Firm Contract Demand Service, while load serving entities (“LSEs”) will perform their current roles of submitting the metrics that PJM uses to calculate those charges, such as a customer’s peak load share information. This will permit PJM to provide the credits to NITS and Firm Contract Demand Service customers directly in their monthly invoices outside of the formula rate calculation of zonal NITS charges.22
It is also appropriate to use the single coincident peak to calculate the Firm Contract Demand Service rate just like the NITS rate, because the Order establishes Firm Contract Demand Service as an annual service.23
Finally, the PJM Transmission Owners understand that PJM will include administrative service charges to Eligible Customers taking Firm Contract Demand Service, which is just and reasonable and consistent with cost causation. The PJM Transmission Owners understand that
21 Blazunas, Schafer, and Hammer Direct Joint Testimony at 7-8.22 This process is discussed in further detail in the Blazunas, Schafer, and Hammer Direct Joint Testimony at
8. 23 Order at P 213 (“We find that the new Firm Contract Demand transmission service must have a minimum term of one year, similar to NITS.”).
PDF page 10
10
PJM will impose these charges on Firm Contract Demand Service customers on the same basis it charges all transmission customers currently, which is based on actual measured demand.
2. What are the appropriate rates, terms, and conditions for the new Non-Firm Contract Demand transmission service, including whether it would be just and reasonable to apply the current zonal non-firm PTPS charges to this new
transmission service and whether it would be just and reasonable and consistent with cost causation to include charges for any of PJM’s administrative services? The PJM Transmission Owners propose that Non-Firm Contract Demand Service
customers pay a charge for their as-reserved contract demand amount (in MWs) multiplied by a zonal Non-Firm Contract Demand Service rate determined based on the specific term of service. The PJM Transmission Owners propose to use the same Firm Contract Demand Service rate for purposes of establishing the maximum rate for Non-Firm Contract Demand Service. Eligible Customers taking Non-Firm Contract Demand Service will also pay a Grid Reliance Charge for their on-site load that is not covered by Firm Contract Demand Service. However, in order to protect against double-charging Non-Firm Contract Demand Service customers, the Grid Reliance Charge will be subtracted from the Non-Firm Contract Demand Service charge on a MWh basis for each MWh of Non-Firm Contract Demand Service included in a transmission service reservation request.
Non-Firm Contract Demand Service customers will take service and pay for their reserved amount of demand based on system availability, and Non-Firm Contract Demand Service will be available for terms ranging from one hour to one month.24 As discussed in the Blazunas, Schafer, and Hammer Direct Joint Testimony, in other respects the Non-Firm Contract Demand Service rate will be computed in the same manner as the Firm Contract Demand Service
24 Daily and hourly rates will be distinguished based on on-peak days (Monday–Friday, except for certain holidays) and off-peak days (Saturday and Sunday, including the applicable holidays that fall on a weekday).
PDF page 11
11
rate.25 To ensure against double recovery, all revenues received from Non-Firm Contract Demand Service charges will be credited to NITS and Firm Contract Demand Service customers based on their share of the coincident peak load. The example contained in the Blazunas, Schafer, and Hammer Direct Joint Testimony also shows the proposed methodology for calculating and crediting Non-Firm Contract Demand Service rates.26 A simplified example of the maximum Non-Firm Contract Demand Service rate is set forth below, building off of Example 1 in the discussion of the Firm Contract Demand Service rate above: Example 2 – Non-Firm Contract Demand Service Rate Calculation
Transmission Owner “ABC”
1 ABC NITS and Firm Contract Demand Service Rate – $10,000/MW/Year27
2 ABC Grid Reliance Charge – $2,580/MW/Year28
3 ABC Non-Firm Contract Demand – 50 MW
4 ABC Non-Firm Contract Demand Maximum Rate [Line 1 - Line 2] = $7,420/MW/Year 5 ABC Non-Firm Contract Demand Revenues [Line 3 * Line 4] = $371,000 annual revenues returned as bill credits to NITS and Firm Contract Demand Service customers Using the same maximum rate for Firm Contract Demand Service and Non-Firm
Contract Demand Service is just and reasonable. The Commission has traditionally permitted non-firm PTPS to be priced at (but not above) the rate used for firm PTPS,29 and many transmission owners have set the same maximum rates for firm and non-firm service, including in PJM.30 Because pursuant to PJM’s proposed operational procedures, Non-Firm Contract
25 Blazunas, Schafer, and Hammer Direct Joint Testimony at 11-12.26 Id. at 26-31.27 Refer to Example 1 in the discussion of the Firm Contract Demand Service charge above for the derivation of the $10,000/MW/Year rate.28 Refer to Example 3 below for the calculation of the Grid Reliance Charge.29 See Order No. 888 at 31,780 (noting the importance of allowing pricing flexibility and indicating that the non-firm rate is capped at the firm rate).30 See Schedules 7 and 8 of the PJM Tariff. The PJM Transmission Owners recognize that non-firm PTPS customers in PJM are currently subject to a discounted rate of $0.67/kWh. Currently, the only customers that utilize PTPS in PJM are those entities taking service at the PJM border. However, requiring this discount be extended to a broader class of customers taking service throughout PJM rather than simply at the PJM border would not be just and
PDF page 12
12
Demand Service customers will have the benefit of PJM re-dispatching generation prior to curtailing Non-Firm Contract Demand Service where applicable, Non-Firm Contract Demand Service will represent a superior level of service compared to non-firm PTPS. Combined with the additional flexibility that Non-Firm Contract Demand Service customers will have with respect to arranging and scheduling Non-Firm Contract Demand Service, and given that Non- Firm Contract Demand Service customers will not pay for generation capacity,31 it is just and reasonable to set the maximum Non-Firm Contract Demand Service rate equal to the rate for Firm Contract Demand Service customers on a $/MWh basis.32
Currently, PJM has the ability to offer discounts for Non-Firm Point-to-Point Service subject to certain requirements, and based on criteria established by the PJM Transmission Owners.33 The PJM Transmission Owners propose similar flexibility for Non-Firm Contract Demand Service. The Commission directed the implementation of a Non-Firm Contract Demand Service to act as a limited supplemental service that may be needed for the benefit of Firm Contract Demand Service customers to ensure that such customers can serve on-site load, reasonable. As discussed above, the PJM Transmission Owners will consider on a going-forward basis whether a discount is appropriate and just and reasonable for Non-Firm Contract Demand Service, based on system conditions and use patterns.
31 See Order at P 218 (“The new Non-Firm Contract Demand transmission service will not include a charge for generation capacity.”).32 This would be comparable to the rules the Commission established in Order No. 888 with respect to the relationship between firm and non-firm point-to-point transmission service rates. See Order No. 888 at 31,780.33 Schedules 7 and 8 of the PJM Tariff state: [t]hree principal requirements apply to discounts for transmission service as follows: (1) any offer of a discount made by the Transmission Provider must be announced to all Eligible Customers solely by posting on the OASIS, (2) any customer-initiated requests for discounts (including requests for use by one’s wholesale merchant or an Affiliate’s use) must occur solely by posting on OASIS, and
(3) once a discount is negotiated, details must be immediately posted on the OASIS. For any discount agreed upon for service on a path, from point(s) of receipt to point(s) of delivery, the Transmission Provider must offer the same discounted transmission service rate for the same time period to all Eligible Customers on all unconstrained transmission paths that go to the same point(s) of delivery on the Transmission System.
PDF page 13
13
for instance, when its on-site generator is experiencing an outage, but not as a substitute for Firm Contract Demand Service. Also relevant is the fact that the historical purpose of a discount on non-firm transmission service is to encourage the efficient use of the transmission system – i.e., to ensure that the system is being utilized optimally. Before determining whether a discount is appropriate for Non-Firm Contract Demand Service, and if so what level it should be set at, it is necessary for the PJM Transmission Owners to gather data on how Non-Firm Contract Demand Service customers are utilizing the service, taking into account the intended purpose of the service, and the effect of that utilization on the system. Accordingly, the PJM Transmission Owners will consider on a going-forward basis whether a discount is appropriate for Non-Firm Contract Demand Service based on system conditions and use patterns and, if so, the criteria and limits under which PJM will apply the discount. Any discount offered for Non-Firm Contract Demand Service would be offered by PJM based on rules and criteria established by the PJM Transmission Owners designed to incentivize the efficient use of Non-Firm Contract Demand Service and the transmission system.
Finally, as with Firm Contract Demand Service, the PJM Transmission Owners
understand that PJM proposes to charge Non-Firm Contract Demand Service customers for applicable PJM administrative charges based on actual demand, in the same manner as it does with respect to transmission service customers currently. The PJM Transmission Owners agree that this proposal is just and reasonable and consistent with cost causation principles.
PDF page 14
14
3. As noted above, a Co-Location Arrangement is synchronized to the transmission system. Should the rate paid by an Eligible Customer on behalf of a Co-Located load taking only the new Non-Firm Contract Demand transmission service that elects to not reserve any amount of that service for a period of time (e.g., one month) reflect not only charges for regulation and black start services, but also an additional charge given that regulation and black start services could not be provided without the transmission system? If so, how should that additional charge be determined?
The PJM Transmission Owners are proposing to charge a Grid Reliance Charge to Eligible Customers taking the new Contract Demand services based on the difference between the amount of their firm contract demand for Firm Contract Demand Service or, in the case of Non-Firm Contract Demand Service customers, the amount of their reserved service, and their total (gross) on-site load.34 The proposed Grid Reliance Charge is designed to reflect the costs of using the transmission system to deliver black start and regulation services, as well as providing the inherent benefits that all customers, including Contract Demand customers, receive as a result of their synchronization to and reliance on the grid.35 The Grid Reliance Charge also recognizes the costs associated with the operations, maintenance, and other activities that PJM Transmission Owners will need to perform for the grid and to accommodate the increased number of protection schemes that will be required for Co-Located Load customers. As discussed further below, and in the Blazunas, Schafer, and Hammer Direct Joint Testimony, the PJM Transmission Owners initially propose to calculate this charge for each zone based on an average fixed percentage of the portion of transmission depreciation and operations and maintenance (“O&M”) expense associated with providing grid reliance services, and then applying that percentage to each PJM Transmission Owner’s Attachment H annual transmission
34 Order at P 216.35 Compensation for providing black start and regulation services, as distinct from delivery of those services, will be received by the providers of those services.
PDF page 15
15
revenue requirement.36 The initial percentage is 25.8 percent, subject to adjustment every five years as discussed below.
As Commissioner Chang stated in her concurrence to the Order, a minimum charge such as the Grid Reliance Charge is “particularly essential to protecting customers against transmission cost shifts under the new framework established through [the Order].”37 Commissioner Chang went on to explain that all Co-Located Loads are synchronized with the grid through their generators, and rely on the PJM grid.38 The PJM Transmission Owners agree. The Grid Reliance Charge is necessary and appropriate to ensure that Co-Located Load customers pay their appropriate share of transmission system costs. Co-Located Load and its associated generation is electrically connected to the transmission system (not islanded) and therefore benefits from the existence and reliable operation of the transmission system and should contribute to paying the costs of continuing to reliably operate the system regardless of the amount of energy withdrawn. Even with a zero MW contract demand, a large Co‑Located Load and generation arrangement will still depend on the grid for the delivery of various ancillary services and a suite of synchronization support services, such as stable frequency, inertia, stability services (damping, angle stability), fault current capability, and ride-through and protection coordination. In short, a Co-Located Load’s net withdrawals do not fully reflect its actual reliance on the grid.
Although the proliferation of large Co-Located Load arrangements is a relatively recent phenomenon, the Commission has long recognized that an integrated transmission system
36 As noted above, a handful of PJM transmission owners continue to utilize stated rates, which in some cases are based on black-box settlements and may need to be accounted for in specific stated rates for the new firm and non- firm contract demand services. This also applies to the Grid Reliance Charge. 37 Order, Chang, Comm’r, concurring at P 5.38 Id. at P 6.
PDF page 16
16
provides broad reliability benefits to all customers of the system.39 This recognition has guided Commission decisions relating to issues such as ratemaking and cost allocations.40 Consistent with this longstanding policy, as well as cost allocation rules,41 it is appropriate to require Co- Located Load customers to pay their appropriate share of costs of relying on the system to deliver necessary ancillary services and grid support to reliably connect their on-site load and generation.
The Grid Reliance Charge methodology proposed by the PJM Transmission Owners represents a just and reasonable means of estimating the grid reliance benefits to Co-Located Load with an appropriate level of precision, while ensuring that the Grid Reliance Charge can be fairly and efficiently implemented.42 Pursuant to this methodology, the Grid Reliance Charge will be determined on an annual basis by multiplying an average fixed percentage of the portion of transmission costs associated with providing grid reliance services by each PJM Transmission Owner’s Attachment H annual transmission revenue requirement. Using annual depreciation and O&M expenses to establish the Grid Reliance Charge is appropriate because these expenses best capture the portions of a transmission owner’s revenue requirement relating to the ongoing reliable operation of the grid.
A detailed discussion of the methodology for calculating the Grid Reliance Charge is set forth in the Blazunas, Schafer, and Hammer Direct Joint Testimony.43 As explained by Mr. Schafer, the fixed percentage allocator is based on costs included in transmission plant and
39 See, e.g., W. Mass. Elec. Co. v. FERC, 165 F.3d 922, 927 (D.C. Cir. 1999).40 See, e.g., Order No. 890-B at PP 61, 62 (citing Niagara Mohawk Power Corp., 42 FERC ¶ 61,143, at 61,531 (1988)); see also Order No. 1000 and Order No. 1920.41 See supra note 10.42 See Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009).43 Blazunas, Schafer, and Hammer Direct Joint Testimony at Section V.
PDF page 17
17
transmission O&M FERC accounts, derived from FERC Form No. 1 Reports of the PJM Transmission Owners, that provide grid reliance capability.44 Mr. Schafer adopted a conservative approach in a number of respects, such as by excluding amortization and general plant depreciation, as well as administrative and general (A&G) expenses.45 The allocator will be multiplied by each PJM Transmission Owner’s rate for NITS and Firm Contract Demand Service to arrive at an “unadjusted” Grid Reliance Charge rate. This unadjusted rate will then be multiplied by a ratio that accounts for the difference between the demand used to account for the NITS and Firm Contract Demand Service rate (NITS customer load plus Firm Contract Demand Service load) and Co-Located Load customers’ gross load, to arrive at the final Grid Reliance Charge for each Zone.46
The Grid Reliance Charge will be calculated on a zonal basis, as opposed to a blended, PJM-wide basis. Because black start service is procured zonally, delivery obligations are inherently local. Likewise, most synchronization support is provided at the local rather than regional level. These factors support calculating the Grid Reliance Charge on a zone-by-zone basis, just like the Firm Contract Demand Service and Non-Firm Contract Demand Service rates. The PJM Transmission Owners also propose to recalculate and update the allocation percentages used to establish the Grid Reliance Charge every five years, using the same averaging approach. This will ensure a reasonable level of year-to-year rate stability while ensuring that the allocators do not become overly stale over time.
Finally, the PJM Transmission Owners propose to treat the revenues from the Grid Reliance Charge by applying them as a dollar-for-dollar credit to NITS and Firm Contract
44 Id. at 19-24.45 Id. at 22.46 Id. at 24-25.
PDF page 18
18
Demand Service customers located in the relevant Zone based on their share of the coincident peak load. This will ensure that the Grid Reliance Charge does not result in a double recovery for the PJM Transmission Owners or inappropriate cost shifts.
A detailed example showing the calculation and crediting of the Grid Reliance Charge is set forth in the Blazunas, Schafer and Hammer Direct Joint Testimony.47 However, a simplified example showing the determination and application of the Grid Reliance Charge is set forth below, using the same assumptions as Examples 1 and 2 above:
Example 3 – Grid Reliance Charge Calculation
Transmission Owner “ABC”
1 ABC NITS and Firm Contract Demand Service Rate – $10,000/MW/Year48 2 Fixed Grid Reliance Percentage Allocator – 25.8% (applicable to all TOs) 3 ABC Grid Reliance Charge (Unadjusted) [Line 1 * Line 2] = $2,580/MW/Year 4 ABC Grid Reliance Charge Demand Adjustment Ratio – .9
5 ABC Final Grid Reliance Charge [Line 3 * Line 4] = $2,322/MW/Year 6 ABC Firm Contract Demand Service Demand – 100 MW
7 ABC on-site Load in Excess of Firm Contract Demand Load – 300 MW 8 ABC Grid Reliance Charge Revenues [Line 5 * Line 7] = $696,600 annual revenues, returned as bill credits to NITS and Firm Contract Demand Service customers
4. As noted above, a Co-Location Arrangement is synchronized to the transmission system. Should the rate paid by an Eligible Customer on behalf of a Co-Located load taking only a de minimis amount of the new Firm or Non-Firm Contract Demand transmission services reflect not only (i) charges for regulation and black start service and (ii) the transmission service charges for that de minimis amount of service, but also an additional charge reflecting that the Co-Location Arrangement is physically connected and synchronized to the PJM transmission system? If so, how should that additional charge be determined?
See response to Question 3.
47 Id. at 27-28.48 Refer to Example 1 in the discussion of the Firm Contract Demand Service charge above for the derivation of the $10,000/MW/Year rate.
PDF page 19
19
5. What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an Eligible Customer taking Firm Contract Demand transmission service on behalf of a Co- Located load?
Robust penalty provisions are a necessary component of the new services required by the Commission. First, and most importantly, any penalties must be sufficient to meaningfully deter Co-Located Load customers from exceeding their contract demand and making unreserved use of the transmission system. Because network upgrades are planned and built only to accommodate load covered by Firm Contract Demand Service or NITS, it is of the utmost importance that Co-Located Loads respect their contractual limits, including any related curtailment or other instructions from PJM. This concern is particularly acute because many of these arrangements will likely involve substantial amounts of load—hundreds, if not thousands of MWs—being served by on-site generation but still connected to the grid. If these limits are not respected, the reliability consequences to the system could be severe. Therefore, operational penalties must be structured to meaningfully deter load customers that exceed reserved service amounts. Financial penalties alone are insufficient.
The PJM Transmission Owners understand that PJM intends to propose operational penalties, and agree with PJM that the imposition of such penalties is appropriate. The PJM Transmission Owners believe that any penalty regime should rely on both operational consequences and complementary financial penalties. The PJM Transmission Owners understand that, at a high level, PJM’s proposal would be to refer to FERC enforcement or applicable reliability organizations any failure to comply with PJM operating instructions. In addition, PJM is proposing a “two-strike” approach, pursuant to which if a customer’s protective systems fail to operate as required, PJM would first determine whether to impose a 120-day “pause” in service and, with the second failure, would terminate the customer’s Contract
PDF page 20
20
Demand Service contract and the customer would be required to become a NITS customer if it wished to resume service. The PJM Transmission Owners believe this proposal is a good starting point conceptually, but recognize that additional details will need to be developed as to how these operational consequences would be applied. As such, the PJM Transmission Owners reserve the right to provide further input as part of this paper hearing process when further information becomes available.
The PJM Transmission Owners also believe that a financial penalty structure is appropriate to complement and supplement operational penalties implemented by PJM. Although the PJM Transmission Owners anticipate that operational penalties will provide a significant deterrent against Co-Located Load customers exceeding their reserved transmission service use, financial penalties could still play a valuable role in enhancing this deterrent as well as ensuring the market and other ratepayers are made whole if a Co-Located Load customer exceeds its contract demand. In addition, it may also be appropriate to impose financial penalties when a Co-Located Load customer deviates from its contract demand even if such deviations are mitigated by a Special Protection Scheme (“SPS”) or Remedial Action Scheme (“RAS”) installed on the Transmission Owner side of the point of interconnection. The PJM Transmission Owners intend to work with PJM in continuing to explore the penalty options and will, if appropriate, offer a proposal at a subsequent stage of this paper hearing process.
6. What is the appropriate penalty charge or other remedial action that PJM should take to address any unreserved use of the PJM transmission system for an Eligible Customer taking Non-Firm Contract Demand transmission service on behalf of a Co-Located load?
See response to Question 5.
PDF page 21
21
7. What are the appropriate mechanisms for an anti-toggling feature for the Firm Contract Demand transmission service, including the appropriate minimum
service period and minimum notice period for discontinuing or modifying the
level of service?
The Order indicates that Firm Contract Demand Service should have a minimum term of one year. However, as the Commission recognized, there are concerns regarding a customer’s ability to toggle between firm and non-firm service levels.49 One of the primary concerns with permitting Firm Contract Demand Service customers to take service for a single-year term is that PJM will be required to procure capacity for these customers, and one-year commitments will not encourage the appropriate price signals necessary to incent additional needed capacity. There also is a potential concern that Firm Contract Demand Service customers will cause the need for network upgrades to accommodate their Firm Contract Demand Service and then exit the system, thereby potentially shifting costs to other customers.50 To partially address these concerns, the PJM Transmission Owners propose a five-year minimum commitment period for Firm Contract Demand Service. A five-year minimum commitment period is appropriate because, as noted by the Commission in the Order, it mirrors the commitment period for loads seeking to procure their own capacity.51
With respect to minimum notice obligations, the PJM Transmission Owners recommend the Commission adopt the same requirements for Firm Contract Demand Service that currently apply to notices of termination for NITS under Section 2.5 of the PJM Tariff.52 This is
49 Order at P 213.50 Id. at P 213. If network upgrades are attributable to the Firm Contract Demand Service, these may require separate payment guarantees to prevent NITS customers from being left “holding the bag” if a Firm Contract Demand Service customer leaves before the costs of the upgrades are fully paid.51 Id. (“PJM’s capacity market includes anti-toggling measures, including the ‘must offer’ requirement for existing Capacity Resources and the five-year minimum commitment for loads seeking to procure their own capacity through the Fixed Resource Requirement alternative.”).52 PJM Tariff, Section 2.5 (“Although Regional Network Integration Service is presumed to continue without expiration, it may be terminated where:
PDF page 22
22
appropriate given the concerns regarding toggling and the resulting potential for cost shifting discussed above.
8. What interconnection requirements and operational practices are necessary for special protection schemes to maintain system reliability (e.g., the need for full redundancy of such schemes) in the event that a Co-Located load itself or its associated generator trips offline?
The PJM Transmission Owners are not offering a specific proposal at this time relating to these issues, but highlight a number of concerns and key elements relating to interconnection, planning and operational practices for Co-Located Load customers taking Firm Contract Demand Service, Non-Firm Contract Demand Service, or interim, non-firm transmission service. Significant ink has been spilled already in this proceeding regarding the appropriateness of relying on protection schemes such as RAS in lieu of requiring Co-Located Load customers to take NITS for their full on-site load. The PJM Transmission Owners will not repeat those arguments here. However, there are certain key facts that the Commission should take into consideration in order to allow the new transmission services to be implemented in a safe and reliable manner. Without network upgrades being planned to serve the entire amount of a customer’s on-site load, the reliability of the PJM system will necessarily depend on the adequate deployment and effective operation of SPS or RAS to ensure that Co-Located Load customers respect their contractual limitations. This will result in the PJM system relying on
1) An incumbent Network Customer will be replaced by a successor Network Customer, in which case the incumbent’s service shall only terminate if the successor agrees to commence the taking of service, the appropriate service agreement is executed, and all other applicable terms and conditions of the PJM Governing Agreements are satisfied;
2) An incumbent Network Customer seeks to terminate its service and no successor Network Customer exists, in which case the incumbent must provide PJM with forty-two (42) months’ notice prior to the commencement of a Delivery Year, subject to receiving all necessary regulatory approvals for such termination, if any; or
3) On such other date mutually agreed upon by the parties.”).
PDF page 23
23
SPS or RAS, potentially including customer-operated systems, to secure reliable operations.53 Although SPS/RAS are already employed in PJM, the use of multiple SPS/RAS to protect the grid from large amounts of on-site load exceeding their contractual withdrawal limitations rather than more permanent solutions is novel. To address issues arising from this novel approach, the PJM Transmission Owners suggest the following:
The Commission should adopt rigorous and comprehensive requirements to ensure that this novel reliance on SPS/RAS does not result in adverse reliability impacts, including potential violations of North American Electric Reliability Corporation (“NERC”) criteria. To that end, the PJM Transmission Owners recommend the following: All SPS and RAS should be fully redundant. Although failures of protection schemes are relatively rare, they do occur, and given the large amount of on-site load and generation potentially involved in these arrangements, it is crucially important to protect against such failures.
The Commission should require the Co-Located Load customer to pay for PJM and PJM Transmission Owner-administered studies to ensure any SPS or RAS can effectively mitigate the risks of potential failure modes.
The PJM Transmission Owners should have the option to review and agree to any customer load curtailment procedures or operational control mechanisms.
All SPS and RAS must fully meet PJM and PJM Transmission Owner technical criteria.
The Commission should consider requiring more frequent testing of SPS and RAS than is currently required by NERC Reliability Standards, with particular attention to
53 Examples of potential approaches as to how these SPS/RAS might be implemented are discussed in the accompanying testimony. See Blazunas, Schafer and Hammer Direct Joint Testimony at 39.
PDF page 24
24
protection equipment installed on the customer side of the point of interconnection. Results from tests of customer-side protection schemes should be submitted to both PJM and the interconnected PJM Transmission Owner, and any SPS or RAS found to be inadequate/insufficient should be updated accordingly.
The Commission should permit PJM and the PJM Transmission Owners to
implement and enforce reasonable limits on the total amount of load that can be covered by SPS or RAS, particularly for customers in relatively close proximity to one another or in a transmission-constrained area.
The Commission should permit PJM Transmission Owners the option to require the implementation of SPS or RAS on the Transmission Owner’s side of the point of interconnection and to require that the costs associated with such SPS or RAS be fully recoverable.
The Commission should permit the PJM Transmission Owners to exercise an option to own, maintain, and operate any SPS or RAS installed on the customer’s side of the point of interconnection, at the customer’s expense.
The Commission should direct NERC to establish requirements that Co-Located Load customers register with NERC so that those customers may be responsible for meeting NERC’s reliability standards, including NERC Reliability Standard PRC- 012-2.
Additionally, the Commission must strictly enforce compliance with NERC Reliability Standard PRC-012-2, which includes nine requirements to address all aspects of RAS.54 The PJM Transmission Owners emphasize particularly the importance of requirements 3, 4, and 8 of
54 North American Electric Reliability Corporation, PRC-012-2 – Remedial Action Schemes (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012-2.pdf.
PDF page 25
25
PRC-012-2. Requirement R3 outlines the RAS component of Dependability, which is a measure of certainty of a device to operate when required. For instance, if a RAS is installed to meet system performance requirements, the RAS’s failure to operate when intended would put the system at risk. This risk can be mitigated by designing the RAS so that it will accomplish its intended purpose while experiencing a single RAS component failure. Such a design is typically achieved through redundancy. Other strategies include “over-tripping” load or generation, or alternative backup schemes. Requirement R4 of PRC-012-2 requires the reliability planning coordinator to perform a periodic evaluation of each RAS within its planning area, at least once every five years. These evaluations must determine whether each RAS: (1) mitigates the system conditions or contingencies for which it was designated; and (2) avoids adverse interactions with other RAS and special protection systems. The Commission must ensure that any new requirements or flexibility provided to Co-Located Load customers do not hinder the planning coordinator’s ability to complete these evaluations and comply with the reliability standards devised to protect the system from catastrophic failure. Similarly, Requirement R8 of PRC-012- 2 requires periodic testing of RAS performance, i.e., every six years for normal RAS and every 12 years for limited impact RAS. The Commission should consider whether more frequent testing is advisable, particularly for protection installed on the customer side of the point of interconnection.
With respect to interconnection requirements, the PJM Transmission Owners emphasize that they will still need to perform load integration studies for any Co-Located Load arrangements, just as they do today with respect to any large load customers. These studies could involve some or all of the following analyses: (i) what, if any, upgrades are needed to accommodate the physical gross load amount behind the point of interconnection; (ii) the request
PDF page 26
26
for firm contract demand amount in front of the point of interconnection; (iii) the impacts that would result from additional load located on-site (behind the point of interconnection) but being served by on-site (behind the point of interconnection) generation and how those impacts need to be addressed, including appropriate protection schemes; and (iv) what additional measures are necessary to accommodate non-firm contract demand service requests in front of the point of interconnection.
III. CONCLUSION
The PJM Transmission Owners appreciate the opportunity to submit their initial responses to the paper hearing questions posed by the Commission in the Order. The PJM Transmission Owners respectfully request that any subsequent Commission orders addressing these issues adopt the proposals and recommendations set forth herein.
Respectfully Submitted,
/s/ Michael Kunselman
Michael Kunselman
Richard P. Sparling
Nicholas J. Cicale
Jonathan A. Namazi
Davis Wright Tremaine LLP
1301 K Street NW
Suite 500 East
Washington, DC 20005
Counsel for the FirstEnergy
Companies
On behalf of the PJM
Transmission Owners
Dated: February 23, 2026