ER26-1479-000 · 2026-03-16 · Eastman Chemical Company
Protest and Comments of Eastman Chemical Company on PJM Interconnection, L.L.C.'s 60- day compliance filing submitted on 02/23/2026
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.,
)
Docket No. ER26-1479-000
60-Day Compliance Filing for
)
Co-Located Load Related Revisions to
)
Open Access Transmission Tariff to
)
Comply with Commission Order in
)
Docket No. EL25-49, et al.
)
PROTEST AND COMMENTS OF EASTMAN CHEMICAL COMPANY
Pursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (FERC or Commission), 18 C.F.R. § 385.211 (2025), Eastman Chemical Company (Eastman) submits this protest and comments on the 60- day compliance filing that PJM Interconnection, L.L.C. (PJM) submitted to FERC on February 23, 2026 (Compliance Filing). For the reasons set forth herein, the Commission should deny portions of the Compliance Filing because they do not comport with the Commission’s specific directives in the Order1 and would result in economic harm to Eastman.
I. BACKGROUND
A. Eastman’s Kingsport Facility
Eastman is an industrial products manufacturer located in Kingsport, Tennessee, with significant on-site generation at its facilities in Kingsport (Kingsport facilities). The on-site generation facilities carry a name-plate capacity of 194 MW, with
1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (Order).
PDF page 2
2
generation facilities installed in phases from 1929 through 1994. Eastman has had an interconnection to the grid through Kingsport Power Company d/b/a American Electric Power Company (Kingsport Power) since the mid-1970s.
While the Kingsport facility requires a significant amount of energy to fulfill its production targets, the bulk of the electricity and steam for industrial processes are produced onsite at the Kingsport facility, on an as needed basis, by relying on a tightly coupled generator-steam network. Eastman purchases only a relatively small amount of electricity (9 MWe on average) from Kingsport Power.2
Eastman has been operating under its current service agreement with Kingsport Power since July 1, 1998. This service agreement was subject to a one-year term and has rolled over year to year under the terms of the agreement. As part of this service agreement, Kingsport Power has agreed to provide Eastman back-up power and surplus power. Eastman pays charges for both of these services. For almost 50 years, Eastman has relied on its interconnection with Kingsport Power, and for at least the past 28 years on this service agreement and the commensurate netting provisions to ensure that its energy costs remain economically reasonable at the Kingsport facility.
Additionally, due to the configuration of its tightly coupled generator-steam combined heat and power network (comprised of 17 boilers—6 coal and 11 natural gas—and 19 turbine generators), Eastman is never able to pull the full load of power
2 See “Integrated Energy System Investigation for the Eastman Chemical Company,” Oak Ridge National Laboratory, at 9, https://www.osti.gov/servlets/purl/1643929 (May 2020).
PDF page 3
3
from the grid.3 Approximately 90 percent of the energy produced by Eastman’s network is in the form of steam to satisfy the thermal demand of the facility’s chemical manufacturing units. If Eastman’s on-site generation of steam and electricity is substantially reduced, Eastman’s chemical manufacturing units are derated and shut down due to a lack of steam, and Eastman’s electric load is reduced proportionally.
B. Commission Order
In the Order, the Commission required PJM to implement considerable changes to the “behind the meter generation” (BTMG) rules to eliminate the netting approach that allows BTMG network customers to pay for the services they use from PJM. As relevant to this protest, FERC directed PJM “to propose a new MW threshold for the amount of load at a particular electrical location that Network Customers may net by using BTMG.”4 In addition, FERC directed PJM to revise its Tariff to “grandfather entities with existing contracts for the specific purpose of effectuating a BTMG arrangement for the current term remaining under the existing contract.”5 FERC also directed PJM to allow for a three-year transition period for those retail BTMG facilities to shift to the new services that FERC directed PJM to create.
C. PJM Compliance Filing
In the Compliance Filing, PJM proposed the following definition for “Retail Behind The Meter Generation”:
3 Id.4 Order at P 221.5 Id. at P 224.
PDF page 4
4
Behind The Meter Generation that is used to serve a retail load served by a Network Customer located at the same electrical location, where such generation has a cumulative nameplate rating of no greater than 50 MW (not including back-up generation at the same electrical location as the retail load that can only be used to serve such retail load during conditions that may threaten the integrity or reliability of the PJM Region or the regional power system). Notwithstanding the foregoing and for a transition period through December 18, 2028, Retail Behind The Meter Generation includes any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load prior to December 18, 2025. Provided further, Retail Behind The Meter Generation includes any generation used to serve a retail load served by a Network Customer to net load if it is the subject of a contractual arrangement (including but not limited to a bilateral agreement or interconnection agreement) that was in effect as of December 18, 2025 through the end of the term of such agreement, which may be renewed or extended per the terms of such agreement. Further, Retail Behind The Meter Generation also includes any generation with a cumulative nameplate rating greater than 50 MW used to serve a retail load served by a Network Customer to net load that, as of December 18, 2025, was a Qualifying Facility consistent with the requirements of the Public Utility Regulatory Policies Act of 1978, as amended, and its implementing regulations. Any facility that qualifies as Retail Behind The Meter Generation shall be excluded from Co-Located Load
configurations.
Under PJM’s proposed definition of “retail behind the meter generation,” Eastman’s Kingsport facility would likely qualify under the three-year transition period, and thereafter, under the grandfathering provision.
II. PROTEST
Eastman protests the Compliance Filing because the proposed threshold ignores the operational realities of industrial plant BTMG facilities; the proposed threshold is too low; and because the proposed threshold is “all or nothing.” In addition, Eastman comments on the proposed grandfathering and seeks clarification that grandfathering should apply to the facilities that are operating under a currently effective BTMG
PDF page 5
5
service agreement, rather than simply the existing service agreement (as renewed or extended).
First, the proposed BTMG changes ignore the operational realities of a facility like Eastman’s Kingsport facility. The Commission acknowledged that not all loads using BTMG are large loads that create reliability and resource adequacy risks that the Commission described in the Order.6 The Kingsport facility is a BTMG load that does not create reliability and resources adequacy risks because the Kingsport facility uses the electric generation at its facilities not only to provide electric power to the facilities, but also to generate steam necessary for the industrial processes that take place within the facilities. If the Kingsport facility is unable to generate power, it is unable to generate steam, which reduces the industrial output at the facility along with reducing the need for additive power from the grid. Thus, the limited times when the Kingsport facility would have the greatest need for additional power (i.e., when its generators are running at full capacity) are the times when the grid is most likely able to provide additional power – which Eastman pays for through its service agreement with Kingsport power. In contrast, in periods of grid distress, the Kingsport facility is more likely to support the grid through using its own BTMG to power the Kingsport facility than it is to create operational constraints for the grid. Accordingly, PJM and FERC should recognize the importance that industrial BTMG facilities have in maintaining
6 Order at P 221.
PDF page 6
6
the stability of the grid by maintaining BTMG netting for facilities like the Eastman Kingsport facility, not through punishing them to make uneconomic choices.
Second, if FERC and PJM do not maintain netting for BTMG facilities like the Kingsport facility because of their operating realities, FERC must require PJM to implement a threshold of at least 200 MW on a permanent basis. The nameplate capacity of the generation at the Kingsport facility is 194 MW. However, the Kingsport facility cannot pull that amount through its interconnection with Kingsport Power, nor could it operate solely on electrical power delivered from the grid. Yet the Kingsport facility has been able to operate its BTMG facilities reliably and without creating reliability and resource adequacy risks on the grid. This is largely due to the incentives that BTMG netting provides to industrial facilities like the Kingsport facility to operate their generation in a manner that ensures that BTMG is available when the grid is constrained (e.g., maintenance is planned for non-critical periods). Imposing an arbitrarily low threshold eliminates the netting benefits for those BTMG facilities that exceed the threshold and eliminates the grid benefits that those BTMG facilities have provided. In addition, the proposed threshold would remove the economic benefits that Eastman has relied on to continue operating its BTMG at the Kingsport facilities – i.e., the arbitrarily low threshold renders Eastman’s BTMG uneconomic after almost 28 years of operations. By implementing a 200 MW threshold, FERC and PJM will ensure that BTMG facilities, like the Kingsport facility, which has supported the grid for many decades, are able to operate economically.
PDF page 7
7
Third, the Commission must reject PJM’s proposed “all or nothing” approach to the MW threshold. In the Order, FERC directed PJM to create a MW threshold for the amount of load that Network Customers may net by using BTMG.7 Said differently, FERC directed PJM to allow for netting up to a certain level, such that all BTMG facilities would continue to receive some benefits of BTMG. There is nothing just and reasonable regarding PJM’s proposal to allow a facility with nameplate generation capacity of 50 MW to net all of its BTMG, but a facility with nameplate generation capacity of 51 MW to net none of its BTMG. FERC should deny the proposed threshold limitations that PJM has proposed and require PJM to submit a revised compliance filing that allows for all BTMG to net up to the threshold level.
Finally, Eastman requests the Commission to clarify that the PJM grandfathering provision would apply to the facilities rather than simply the service agreement. As crafted, the PJM proposal would unnecessarily impede the ability of the BTMG operator to amend or modify an existing agreement to better reflect the then-current operational realities of BTMG facilities. For example, facilities could be modified to become more efficient such that an existing agreement should be modified to reflect lower electrical energy needs. As drafted, the PJM proposal would no longer allow for those BTMG facilities to be grandfathered because the existing service agreement had been modified. In short, attaching grandfathering to the BTMG facilities (and capping their ability to net at the current nameplate capacity) would ensure that BTMG operators
7 Order at P 221.
PDF page 8
8
can continue to operate their facilities in the most economically efficient manner possible without concern over losing grandfathering rights.
For the foregoing reasons, the Commission should require PJM to continue to allow BTMG facilities like the Kingsport facility to net. Alternatively, the Commission should require PJM to increase the MW threshold to 200 MW on a permanent basis and allow for netting at any BTMG facility up to the MW threshold. Finally, the Commission should require PJM to attach grandfathering to the BTMG facility with a currently effective service agreement rather than the term of the existing service agreement as extended.
Respectfully submitted,
By: /s/ John Paul Floom
John Paul Floom
(571) 842-8185
jpf@floomenergylaw.com
Kaci W. Poor
(571) 842-8189
kwp@floomenergylaw.com
Emma M. Ross
(571) 842-8187
emr@floomenergylaw.com
Floom Energy Law PLLC
3100 Clarendon Blvd.
Suite 920
Arlington, VA 22201
Attorneys for
Dated: March 16, 2026
Eastman Chemical Company
PDF page 9
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2025), I hereby certify that I have this day served a copy of the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Arlington, Virginia, this 16th day of March 2026.
By: /s/ John Paul Floom
John Paul Floom
Floom Energy Law PLLC
3100 Clarendon Blvd., Suite 920
Arlington, VA 22201
(571) 842-8185
jpf@floomenergylaw.com