ER26-1479-000 · 2026-03-16 · Eastman Chemical Company

Protest and Comments of Eastman Chemical Company on PJM Interconnection, L.L.C.'s 60- day compliance filing submitted on 02/23/2026

Text extracted from the eLibrary original (SHA-256 bb93bf17f8aa929a…). Download the original from the official source.

Contents · 5 sections
  1. I. BACKGROUND p. 1
  2. A. Eastman’s Kingsport Facility p. 1
  3. B. Commission Order p. 3
  4. C. PJM Compliance Filing p. 3
  5. II. PROTEST p. 4

Read topic-matched comments in ER26-1479

Topics in the text: Connecting load and generation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

ER26-1479-000 60-Day Compliance Filing for ) Co-Located Load Related Revisions to ) Open Access Transmission Tariff to ) Comply with Commission Order in ) Docket No.
Read this passage Filed comments: Connecting load and generation

I. BACKGROUND

printed heading

I.
Read this passage

A. Eastman’s Kingsport Facility

printed heading

Eastman’s Kingsport Facility Eastman is an industrial products manufacturer located in Kingsport, Tennessee, with significant on-site generation at its facilities in Kingsport (Kingsport facilities).
Read this passage

B. Commission Order

printed heading

Commission Order In the Order, the Commission required PJM to implement considerable changes to the “behind the meter generation” (BTMG) rules to eliminate the netting approach that allows BTMG network customers to pay for the services they use from PJM.
Read this passage

C. PJM Compliance Filing

printed heading · Topic match: Connecting load and generation

Any facility that qualifies as Retail Behind The Meter Generation shall be excluded from Co-Located Load configurations.
Read this passage Filed comments: Connecting load and generation

II. PROTEST

printed heading · Topic match: Reliability and curtailment

Second, if FERC and PJM do not maintain netting for BTMG facilities like the Kingsport facility because of their operating realities, FERC must require PJM to implement a threshold of at least 200 MW on a permanent basis.
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Dated at Arlington, Virginia, this 16th day of March 2026.
Read this passage