ER26-1479-000 · 2026-03-16 · EDF Power Solutions, Inc.
Comments of EDF Power Solutions, Inc. in response to the 60-Day Compliance Filing by PJM Interconnection, L.L.C. on 02/23/2026
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Docket No. ER26-1479-000
COMMENTS OF EDF POWER SOLUTIONS, INC.
Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (Commission or FERC),1 EDF power solutions, Inc. (EDFps) respectfully submits these comments in response to the 60-Day Compliance Filing2 filed by PJM Interconnection, L.L.C. (PJM) on February 23, 2026 (PJM Compliance Filing). The PJM Compliance Filing was submitted in response to the Commission’s December 18, 2025 Order on Show Cause Proceeding,3 regarding the co-location of large loads in PJM.
I. SUMMARY OF COMMENTS
PJM’s proposed framework for new transmission services presents an important opportunity to support the reliable and flexible integration of large load resources. PJM’s proposed three new transmission service options will allow large loads to combine Firm and Non-Firm Contract Demand services, facilitating flexible co-location arrangements and efficient interconnection.
PJM’s proposed 50 MW Retail Behind the Meter Generation (BTMG) threshold, on the other hand, is arbitrary and too low. It will disincentivize large loads from installing their own generation and thereby stifle innovation. The Retail BTMG threshold should instead be based on
1 18 C.F.R. §§ 385.212, 385.213 (2025).2 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related to Revisions to Open Access Transmission Tariff to Comply with Commission Order in Docket No. EL25-49, Feb. 23, 2026.3 PJM Interconnection, L.L.C., et al., 193 FERC ¶ 61,217 (2025) (December 18 Order).
PDF page 2
2
percentage of the load size. EDFps suggests 100% of the load size, at the electrical location, combined with operational safeguards and appropriate transmission charges. There are significant benefits of BTMG co-location that should be encouraged. BTMG can reduce grid congestion, avoid queue delays, lower network upgrade needs, and provide economic and community benefits. EDFps suggests a “bifurcated netting” approach, which allows netting of generation up to the Retail BTMG size while charging the full load for transmission service. Finally, PJM’s proposed BTMG changes require modifications to ensure that (1) a Retail BTMG resource that exceeds the established threshold can still be netted up to the threshold amount; and (2) a BTMG resource can continue to serve load (provide ride-through capacity) during a grid curtailment event, similar to backup generation.
II. BACKGROUND
EDFps develops, builds, operates, and manages renewable energy projects throughout North America, including in PJM, MISO, SPP, and ERCOT. As a market-leading independent power producer and service provider for over 35 years, EDFps delivers grid-scale power, including wind (onshore and offshore), solar photovoltaic, and storage projects; distribution- scale power, including solar and storage; and asset optimization. The company also provides technical, operational, and commercial expertise to maximize performance of generating projects. EDFps is an active participant in interconnection and large load-related policy discussions, rulemaking proceedings, and reform efforts.
On February 23, 2026, PJM submitted the 60-Day Compliance Filing in response to the Commission’s December 18 Order. Among other things, PJM proposes to adopt a revised definition of Retail BTMG to include a new 50 MW materiality threshold and to establish three new transmission service options for large loads.
PDF page 3
3
III. COMMENTS
A. PJM’s Proposed 50 MW Materiality Threshold for New Retail BTMG is
Arbitrarily Too Low: The Threshold Should Vary Based on the Size of the
Load.
PJM proposes a materiality threshold of up to 50 MW for a new generator at the same electrical location as the Network Load to qualify for Retail BTMG.4 According to PJM, its proposed 50 MW threshold corresponds with the PJM Board’s definition of large load additions, which are individual loads of 50 MW or greater at a single point of interconnection.5 However, the 50 MW Retail BTMG threshold is arbitrary and could disincentivize retail customers from installing their own generation. The benefits of “bring your own generation” to the grid has been recognized as an essential element of the drive to meet the demand of new large loads.6 To meet this goal, the Retail BTMG threshold should be established based on 100% of the size of the large load it serves at that electrical location, coupled with operational safeguards and a requirement that the appropriate transmission service charges are paid.
Large loads come in all sizes and co-location arrangements can vary significantly. The Retail BTMG threshold should be flexible and non-discriminatory to account for these differences. For example, with a 50 MW Retail BTMG threshold, a 50 MW large load could theoretically cover 100% of its load with Retail BTMG. A large load of 200 MW, on the other hand, could only cover 25% of its load with the 50 MW threshold. PJM’s proposed 50 MW threshold will stifle innovation and arbitrarily incentivize the development of smaller loads rather
4 PJM Compliance Filing at p. 6-7.5 Id. at p. 11-12.6 December 18 Order, Rosner concurring at P 8. See also Energy Secretary Encourages Data Centers to Bring Their Own Generation, The Ohio Mfrs.’ Ass’n (Oct. 10, 2025), available at: https://www.ohiomfg.com/our-communities/energy-secretary-encourages-data-centers-to-bring-their- own-generation/; “Behind-the-Meter” AI Projects Surge in the U.S., Nam News Room (Feb. 6, 2026), available at: https://nam.org/behind-the-meter-ai-projects-surge-in-u-s-35696/.
PDF page 4
4
than designing the loads to meet the needs of the large load customer. It may also incentivize large loads to be segmented in close but separate electrical locations, resulting in inefficient and redundant construction of interconnection facilities.
The optimal sizing of Retail BTMG, such as solar plus battery energy storage systems (BESS) or some other combination, to support an AI data center would most certainly exceed 50 MW. An arbitrary 50 MW limit will require that these new large loads develop new grid- connected resources instead of BTMG resources. This would force new generation resources – which are solely intended to serve new large loads – into the generation interconnection queue with full wholesale interconnection studies that would otherwise be unnecessary. It may also call for network upgrades that would also otherwise be unnecessary.
Stripping the new large load with BTMG of netting rights penalizes the very co-located configurations that can ease grid congestion. BTMG arrangements can benefit the transmission system in many ways, such as by serving load on a streamlined basis, avoiding queue delays in the generator interconnection process, and reducing the need for expensive grid upgrades. BTMG co-locating with large loads can also reduce congestion costs and allow the load to provide demand response services if the power demands are flexible. Finally, BTMG resources will provide benefits to states and communities by facilitating new large load facilities that can provide a host of benefits to local communities in the form of tax revenues, construction jobs, and employment.
EDFps understands that there could be impacts to operation of the transmission system if the Retail BTMG is not available. This possibility can be managed to preserve the benefits of BTMG to the new load and to the grid while also protecting the grid from negative impacts if the BTMG is unavailable. For example, PJM could establish a “bifurcated netting” approach:
PDF page 5
5
• If a Retail BTMG system exceeds 50 MW, the large load should still be permitted to net its generation against its load for the purposes of energy and capacity market settlements.
• To satisfy concerns regarding transmission cost shifting, PJM could establish a framework where facilities with BTMG that exceeds 50 MW pay transmission and/or distribution network charges without the benefit of netting (i.e., paying transmission and/or distribution charges based on the gross load or agreed-upon contract demand). This bifurcated netting approach is beneficial in that it preserves the economic incentive to build various resources with storage configurations directly at the load center (such as large- scale renewables plus storage, or natural gas resources plus storage). Setting the Retail BTMG threshold at 100% of the load it serves at that electrical location is consistent with the Commission’s “beneficiary pays” principle when it is coupled with transmission charges that appropriately reflect the full loads potential usage of the transmission system.7
B. For Retail BTMG Resources that Exceed the Materiality Threshold Size,
PJM Should Allow Netting Up to the Threshold Amount.
PJM states that going forward any new large Retail BTMG that is greater than the proposed threshold would not qualify as Retail BTMG and that “a Retail BTMG cannot both net up to a certain threshold but still potentially have generation and load above that threshold which
7 Under the “beneficiary pays” cost causation principle, rates must “reflect to some degree the costs actually caused by the customer who must pay them.” Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004). Costs must be allocated in a manner that is at least roughly commensurate with the benefits an entity receives. Ill. Com. Comm’n v. FERC, 576 F.3d 470, 474-78 (7th Cir. 2009) (remanding Commission order for further proceedings in light of Commission’s failure to provide substantial evidence supporting Commission’s approval of cost allocation method as complying with “beneficiary pays” principle).
PDF page 6
6
cannot be netted.”8 PJM claims that this provision is consistent with its interpretation of the Commission’s directive in the December 18 Order.9
In the December 18 Order, the Commission found that PJM’s existing Retail BTMG rules were no longer just and reasonable for use by large loads because large loads do not carry reserves and such loads must nevertheless be served, which would allow them to “lean on the PJM system when the co-located generation is on a full or partial outage or if the load exceeds the rating of the co-located generation.”10
PJM’s filing in response to the December 18 Order, however, makes significant changes to the transmission service requirements that alleviate the ability of large loads with Retail BTMG to lean on the system. PJM states that its proposed contract demand service (consisting of Firm and Non-Firm Contract Demand Transmission Service) provides “an alternative to NITS for those Co-Located Loads willing and able to limit energy withdrawals from the Transmission System.”11 PJM states that “there can be no ‘unstudied’ and/or ‘unknown’ portion of the Co- Located Load that is not covered by either Firm Contract Demand Transmission Service or dedicated generation from the Co-Located Generating Facility (as backed up by Non-Firm Contract Demand Transmission Service).”12
Thus, in the case of a Retail BTMG resource, the load being served would be required to purchase Non-Firm Contract Demand up to the amount covered by the Retail BTMG and Firm
8 PJM Compliance Filing at p. 10-11.9 Id. at p. 11.10 December 18 Order at P 186, citing PJM Interconnection, L.L.C., Answer in Docket No. EL25-49, Mar. 24, 2025 at P 13 n. 5.11 PJM Interconnection, L.L.C., Initial Brief in Docket No. EL25-49, Feb. 23, 2026 at p. 5 (emphasis added) (PJM Brief).12 Id. at p. 7.
PDF page 7
7
Contract Demand for the remainder of the load. If the Retail BTMG was equal to the size of the load and the load is fully covered by Non-Firm Contract Demand, the load would be limited to taking energy “on an as-needed and as-available basis,”13 for its entire load and could not lean on the system.
PJM indicates that a “hybrid approach,” where a Retail BTMG can both net up to a certain threshold and have generation and load above the threshold that cannot be netted, would
(1) impose significant metering costs all Retail BTMG that would have to install previously unnecessary equipment; and (2) amplify compliance risks in monitoring and reporting different generator and load thresholds.14
PJM’s rejection of a hybrid approach is unwarranted. First, grandfathered Retail BTMG would not face any additional metering costs, nor would entities that installed Retail BTMG that did not exceed the threshold. Only entities choosing to install larger Retail BTMG resources would have to install the appropriate metering. These entities can decide whether the costs and compliance risks (if any) are cost-effective for their business. Rejecting a hybrid approach altogether would discourage investment in BTMG.
C. Co-Located Retail BTMG Resources Must Be Permitted to Provide Ride-
Through Capacity During Curtailments.
PJM proposes that the Retail BTMG threshold excludes backup generation “at the same electrical location as the retail load that can only be used to serve such retail load during conditions that may threaten the integrity or reliability of the PJM Region or the regional power system.”15 EDFps interprets this to mean that backup generation can be used during a grid
13 PJM Compliance Filing at p. 21.
14 Id. at p. 11.15 Id. at p. 7.
PDF page 8
8
curtailment event. However, it is not clear whether the Retail BTMG itself can operate during a grid curtailment event.
Large loads electing to take “Interim NITS” accept the risk of grid curtailment but they should not have to accept a complete operational downtime during a grid curtailment. Like backup generation, discharging a BTMG BESS (or a BESS charged by BTM solar) directly to the data center load during a grid curtailment event is a necessary self-supply function. The Commission should direct PJM to explicitly clarify that BESS and hybrid systems functioning in a load-following, non-exporting capacity manner during a curtailment event qualify under the “backup generation” exemption, and can continue to serve the load, regardless of their size.
D. PJM’s Proposed Three New Transmission Services Should Be Accepted.
EDFps supports PJM’s proposal to add three new transmission service options to benefit large load customers. According to PJM, large load customers will have the option to take a combination of Firm and Non-Firm Contract Demand service as long as the combined service fully covers the co-located loads total load.16 The Non-Firm Contract Demand service provides a useful option for large loads that do not necessarily intend to withdraw energy from the grid on a regular basis and instead plan to rely on Retail BTMG for all or a portion of its load. The new transmission service options will encourage flexible co-location structures that will enable speedy and reliable interconnection for large loads. Standardized yet flexible rules to accommodate different co-location structures with varying operational needs and capabilities are needed to meet the challenges of serving the power needs of new large loads.
16 PJM Brief at p. 11.
PDF page 9
9
IV. CONCLUSION
PJM’s proposed framework for Retail BTMG thresholds and new transmission service options presents an important opportunity to support the reliable and flexible integration of large load resources. To ensure the effectiveness and fairness of these proposals, PJM should (1) set a Retail BTMG materiality threshold that is based on 100% of the load; (2) allow a hybrid approach to netting of Retail BTMG resources that exceed the threshold; and (3) expressly permit co-located Retail BTMG and backup generation—including BESS and hybrid systems— to operate during grid curtailment events. These clarifications will preserve incentives for investment in innovative on-site generation and storage, enhance reliability, and provide large load customers with the operational flexibility they require. Adoption of the three new transmission service options will further promote efficient interconnection and accommodate the evolving needs of large energy users. For these reasons, the Commission should approve PJM’s proposed changes, with the recommended modifications/clarifications.
Respectfully submitted,
/s/ Linda Walsh_____
Temujin Roach
Linda Walsh
Emma Nix Simon
Michael Blackwell
EDF power solutions, Inc.
Husch Blackwell LLP
15445 Innovation Dr.
1801 Pennsylvania Ave., NW, Suite 1000
San Diego, CA 92128
Washington, DC 20006
Tel: (612) 486-4498
Tel: (202) 378-2308
Temujin.Roach@edf-re.com
linda.walsh@huschblackwell.com
EmmaNix.Simon@edf-re.com
michael.blackwell@huschblackwell.com
Counsel to EDF power solutions, Inc.
Dated: March 16, 2026
PDF page 10
CERTIFICATE OF SERVICE
Pursuant to Rule 2010 of the Federal Energy Regulatory Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.2010, I certify that I served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, D.C. this 16th day of March 2026.
/s/ Emily Starobin
Emily Starobin
Husch Blackwell LLP
1801 Pennsylvania Ave. NW, Suite 1000
Washington, D.C. 20006
Tel: (202) 378-2319
emily.starobin@huschblackwell.com